Notice of Effectiveness of Exempt Wholesale Generator Status, 9836 [2016-04151]
Download as PDF
9836
Federal Register / Vol. 81, No. 38 / Friday, February 26, 2016 / Notices
As ‘‘non-decisional’’ staff, Mr. Hansen
and Ms. Liberty will not participate in
an advisory capacity in the
Commission’s review of any offer of
settlement or settlement agreement, or
deliberations concerning the disposition
of the relicense application.
Different Commission ‘‘advisory staff’’
will be assigned to review any offer of
settlement or settlement agreement, and
to process the relicense application,
including providing advice to the
Commission with respect to the
agreement and the application. Nondecisional staff and advisory staff are
prohibited from communicating with
one another concerning the settlement
and the relicense application.
Dated: February 22, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–04154 Filed 2–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Effectiveness of Exempt
Wholesale Generator Status
Docket No.
Pavant Solar, LLC .................
Campbell County Wind Farm,
LLC.
OCI Alamo 6 LLC ..................
OCI Alamo 7 LLC ..................
OCI Solar TRE LLC ...............
BIF III Holtwood LLC .............
Black Oak Wind, LLC ............
Central Antelope Dry Ranch
C LLC.
Shelby County Energy Center, LLC.
Golden Hills Interconnection,
LLC.
Blythe Solar 110, LLC ...........
NextEra Blythe Solar Energy
Center, LLC.
EG15–115–000
EG16–15–000
EG16–16–000
EG16–17–000
EG16–18–000
EG16–19–000
EG16–20–000
EG16–21–000
EG16–23–000
EG16–24–000
EG16–25–000
mstockstill on DSK4VPTVN1PROD with NOTICES
Take notice that during the months of
November 2015 and January 2016, the
status of the above-captioned entities as
Exempt Wholesale Generators became
effective by operation of the
Commission’s regulations. 18 CFR
366.7(a).
[FR Doc. 2016–04151 Filed 2–25–16; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
20:41 Feb 25, 2016
Jkt 238001
Federal Energy Regulatory
Commission
[Docket No. CP16–17–000]
Millennium Pipeline Company, L.L.C.;
Notice of Schedule for Environmental
Review of the Valley Lateral Project
On November 13, 2015, Millennium
Pipeline Company, L.L.C. (Millennium)
filed an application in Docket No.
CP16–17–000 requesting a Certificate of
Public Convenience and Necessity
pursuant to Section 7(c) of the Natural
Gas Act to construct and operate certain
natural gas pipeline facilities. The
proposed project is known as the Valley
Lateral Project (Project), and would
provide approximately 130,000
dekatherms per day (Dth/d) of firm
transportation service to CPV Valley,
LLC to serve a new natural gas
combined-cycle electric generator in the
Town of Wawayanda, New York (CPV
Valley Energy Center).
On November 30, 2015, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
EG16–22–000
Dated: February 22, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
DEPARTMENT OF ENERGY
Issuance of EA—May 9, 2016
90-day Federal Authorization Decision
Deadline—August 7, 2016
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
Millennium proposes to construct,
install, own, and maintain the proposed
Valley Lateral Project, which would
involve construction of an
approximately 7.9-mile, 16-inch
diameter lateral pipeline from
Millennium’s existing mainline in
Orange County, New York to the CPV
Valley Energy Center. The Project would
also involve construction of a new meter
station within the CPV Valley Energy
Center property, and pig launcher and
receiver facilities.
PO 00000
Frm 00033
Fmt 4703
Sfmt 9990
Background
On July 6, 2015, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Proposed Valley Lateral Project and
Request for Comments on
Environmental Issues (NOI). The NOI
was issued during the pre-filing review
of the Project in Docket No. PF15–23–
000 and was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers. In response to the NOI,
the Commission received comments
from the U.S. Environmental Protection
Agency (EPA) and 48 comments from
individual stakeholders. The primary
issues raised by commentors are
purpose and need, land use, visual
impacts, vegetation and wildlife,
cumulative impacts, alternatives, air
quality and climate change, safety, and
socioeconomic impacts.
The EPA and New York State
Department of Agriculture and Markets
are cooperating agencies in the
preparation of the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP16–17), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Web site also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: February 19, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–04144 Filed 2–25–16; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\26FEN1.SGM
26FEN1
Agencies
[Federal Register Volume 81, Number 38 (Friday, February 26, 2016)]
[Notices]
[Page 9836]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-04151]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Effectiveness of Exempt Wholesale Generator Status
Docket No.
Pavant Solar, LLC..................... EG15-115-000
Campbell County Wind Farm, LLC........ EG16-15-000
OCI Alamo 6 LLC....................... EG16-16-000
OCI Alamo 7 LLC....................... EG16-17-000
OCI Solar TRE LLC..................... EG16-18-000
BIF III Holtwood LLC.................. EG16-19-000
Black Oak Wind, LLC................... EG16-20-000
Central Antelope Dry Ranch C LLC...... EG16-21-000
Shelby County Energy Center, LLC...... EG16-22-000
Golden Hills Interconnection, LLC..... EG16-23-000
Blythe Solar 110, LLC................. EG16-24-000
NextEra Blythe Solar Energy Center, EG16-25-000
LLC.
Take notice that during the months of November 2015 and January
2016, the status of the above-captioned entities as Exempt Wholesale
Generators became effective by operation of the Commission's
regulations. 18 CFR 366.7(a).
Dated: February 22, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-04151 Filed 2-25-16; 8:45 am]
BILLING CODE 6717-01-P