National Fuel Gas Supply Corporation; Notice of Intent To Prepare an Environmental Assessment for the Proposed Line QP, Line Q, and Queen Storage Project Request for Comments on Environmental Issues, 4276-4278 [2016-01464]
Download as PDF
4276
Federal Register / Vol. 81, No. 16 / Tuesday, January 26, 2016 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14731–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Energy Resources USA, Inc.; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On November 27, 2015, Energy
Resources USA, Inc. filed an application
for a preliminary permit, pursuant to
section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of a hydropower project located at the
U.S. Army Corps of Engineers’ (Corps)
Green River Lock and Dam No. 5,
located on the Green River in Warren
County, Kentucky. The sole purpose of
a preliminary permit, if issued, is to
grant the permit holder priority to file
a license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following: (1) a 770-foot-long, 300foot-wide intake channel with a 85-footlong retaining wall; (2) a 98-foot-long,
66-foot-wide powerhouse containing
two generating units with a total
capacity of 7 megawatts; (3) a 1000-footlong, 220-foot-wide tailrace with a 40foot-long retaining wall; (4) a 4.16/69
kilo-Volt (kV) substation; and (5) a 11.5mile-long, 69 kV transmission line. The
proposed project would have an average
annual generation of 39,800 megawatthours, and operate utilizing surplus
water from the Green River Lock and
Dam No. 5, as directed by the Corps.
Applicant Contact: Mr. Ander
Gonzalez, Energy Resources USA, Inc.,
2655 Le Jeune Road, Suite 804, Coral
Gables, Florida 33134. (954) 248–8425.
FERC Contact: Dustin Wilson,
Dustin.Wilson@ferc.gov, (202) 502–
6528.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
VerDate Sep<11>2014
21:57 Jan 25, 2016
Jkt 238001
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://www.ferc.
gov/docs-filing/ecomment.asp. You
must include your name and contact
information at the end of your
comments. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14731–000)
in the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: January 19, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–01459 Filed 1–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–28–000]
National Fuel Gas Supply Corporation;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Line QP, Line Q, and Queen
Storage Project Request for Comments
on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Line QP, Line Q, and Queen Storage
Project involving construction and
operation of facilities by National Fuel
Gas Supply Corporation (National Fuel)
in Forest and Warren Counties,
Pennsylvania. National Fuel indicates
the project would abandon capacity by
sale a natural gas storage system and
associated pipeline that is no longer
needed by the company and would
provide that capacity to other gathering
system suppliers in Pennsylvania.
Additionally, National Fuel proposes to
replace a compromised portion of the
pipeline associated with the storage
system and install new pipeline to
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
maintain National Fuel’s distribution
capability. The Commission will use
this EA in its decision-making process
to determine whether the project is in
the public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before February
19, 2016.
If you sent comments on this project
to the Commission before the opening of
this docket on December 3, 2015, you
will need to file those comments in
Docket No. CP16–028–000 to ensure
they are considered as part of this
proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
National Fuel provided landowners
with a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
E:\FR\FM\26JAN1.SGM
26JAN1
Federal Register / Vol. 81, No. 16 / Tuesday, January 26, 2016 / Notices
Public Participation
Land Requirements for Construction
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (CP16–028–
000) with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Room 1A, Washington, DC 20426.
Construction of the proposed facilities
would disturb about 45.3 acres of land
for the pipeline. Following construction,
National Fuel would maintain about
20.5 acres for permanent operation of
the project’s facilities; the remaining
acreage would be restored and revert to
former uses.
National Fuel seeks authorization to
abandon by sale all of its facilities
comprising its Queen Storage Field,
including the base gas in the field, its
Queen Compressor Station, and a
segment of its Line Q, approximately 5.5
miles in length, beginning at the Queen
Compressor Station and traversing
northwest to a location just south of the
Allegheny River (the ‘‘Line Q
Segment’’). Also, National Fuel seeks
authorization to construct and operate
approximately 5 miles of new 4-inchdiameter plastic pipeline (‘‘Line QP’’)
beginning at a point just north of the
Allegheny River, and traversing
southeast along or adjacent to the
existing Line Q right-of-way, to a point
approximately 2,000 feet west of the
Queen Compressor Station.
The general location of the project
facilities is shown in appendix 1.1
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts.
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
Summary of the Proposed Project
mstockstill on DSK4VPTVN1PROD with NOTICES
The EA Process
VerDate Sep<11>2014
21:57 Jan 25, 2016
Jkt 238001
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
4277
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.4 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Currently Identified Environmental
Issues
We have already identified an issue
we think deserves attention based on a
preliminary review of the proposed
facilities and the environmental
information provided by National Fuel.
The proposed replacement of Line Q
and installation of Line QP would
involve an open cut crossing of the
Allegheny River in segments that may
contain sensitive freshwater mussels.
We encourage comments on this issue
as well as other issues you feel should
be addressed in the EA.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
E:\FR\FM\26JAN1.SGM
26JAN1
4278
Federal Register / Vol. 81, No. 16 / Tuesday, January 26, 2016 / Notices
Environmental Mailing List
The environmental mailing list
federal, state, and local government
representatives and agencies; elected
officials; environmental and public
interest groups; Native American Tribes;
other interested parties; and local
libraries and newspapers. This list also
includes all affected landowners (as
defined in the Commission’s
regulations) who are potential right-ofway grantors, whose property may be
used temporarily for project purposes,
or who own homes within certain
distances of aboveground facilities, and
anyone who submits comments on the
project. We will update the
environmental mailing list as the
analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
the mailing list, please return the
attached Information Request (appendix
2).
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: January 20, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–01464 Filed 1–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
mstockstill on DSK4VPTVN1PROD with NOTICES
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP16–28). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
VerDate Sep<11>2014
21:57 Jan 25, 2016
Jkt 238001
Filings Instituting Proceedings
Docket Numbers: RP16–381–000.
Applicants: Transcontinental Gas
Pipe Line Company.
Description: Section 4(d) Rate Filing:
LSS and SS–2 Tracker Effective
November 1, 2015 to be effective 11/1/
2015.
Filed Date: 1/13/16.
Accession Number: 20160113–5104.
Comments Due: 5 p.m. ET 1/25/16.
Docket Numbers: RP16–382–000.
Applicants: Alliance Pipeline L.P.
Description: Section 4(d) Rate Filing:
Contract 1000591 Correction & Others to
be effective 12/1/2015.
Filed Date: 1/13/16.
Accession Number: 20160113–5246.
Comments Due: 5 p.m. ET 1/25/16.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
Dated: January 14, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–01454 Filed 1–25–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CD16–5–000]
Becoming an Intervenor
Additional Information
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Thoreson Family Ranch, LLC; Notice
of Preliminary Determination of a
Qualifying Conduit Hydropower
Facility and Soliciting Comments and
Motions To Intervene
On January 5, 2016, as supplemented
on January 14 and 15, 2016, Thoreson
Family Ranch, LLC, filed a notice of
intent to construct a qualifying conduit
hydropower facility, pursuant to section
30 of the Federal Power Act (FPA), as
amended by section 4 of the
Hydropower Regulatory Efficiency Act
of 2013 (HREA). The proposed Thoreson
Family Ranch Project would have an
installed capacity of 2 kilowatts (kW),
and would be located at the end of an
existing 6-inch-diameter irrigation
pipeline. The project would be located
near Cottage Grove, in Lane County,
Oregon.
Applicant Contact: Stephen Joel
Thoreson, 319 North 20th Street,
Cottage Grove, Oregon 97424, Phone No.
(541) 942–7407.
FERC Contact: Christopher Chaney,
Phone No. (202) 502–6778, email:
christopher.chaney@ferc.gov.
Qualifying Conduit Hydropower
Facility Description: The proposed
project would consist of: (1) An existing
pump house, approximately 8 feet by 10
feet, at the end of an existing 6-inchdiameter irrigation pipeline; (2) one
turbine/generator unit with an installed
capacity of 2 kW; (3) an approximately
5-foot-long tailrace, discharging to
Damewood Creek; and (4) appurtenant
facilities.
The proposed project would have a
total installed capacity of 2 kW.
E:\FR\FM\26JAN1.SGM
26JAN1
Agencies
[Federal Register Volume 81, Number 16 (Tuesday, January 26, 2016)]
[Notices]
[Pages 4276-4278]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-01464]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP16-28-000]
National Fuel Gas Supply Corporation; Notice of Intent To Prepare
an Environmental Assessment for the Proposed Line QP, Line Q, and Queen
Storage Project Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Line QP, Line Q, and Queen
Storage Project involving construction and operation of facilities by
National Fuel Gas Supply Corporation (National Fuel) in Forest and
Warren Counties, Pennsylvania. National Fuel indicates the project
would abandon capacity by sale a natural gas storage system and
associated pipeline that is no longer needed by the company and would
provide that capacity to other gathering system suppliers in
Pennsylvania. Additionally, National Fuel proposes to replace a
compromised portion of the pipeline associated with the storage system
and install new pipeline to maintain National Fuel's distribution
capability. The Commission will use this EA in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before February 19, 2016.
If you sent comments on this project to the Commission before the
opening of this docket on December 3, 2015, you will need to file those
comments in Docket No. CP16-028-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
National Fuel provided landowners with a fact sheet prepared by the
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do
I Need To Know?'' This fact sheet addresses a number of typically asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
[[Page 4277]]
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(CP16-028-000) with your submission: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A,
Washington, DC 20426.
Summary of the Proposed Project
National Fuel seeks authorization to abandon by sale all of its
facilities comprising its Queen Storage Field, including the base gas
in the field, its Queen Compressor Station, and a segment of its Line
Q, approximately 5.5 miles in length, beginning at the Queen Compressor
Station and traversing northwest to a location just south of the
Allegheny River (the ``Line Q Segment''). Also, National Fuel seeks
authorization to construct and operate approximately 5 miles of new 4-
inch-diameter plastic pipeline (``Line QP'') beginning at a point just
north of the Allegheny River, and traversing southeast along or
adjacent to the existing Line Q right-of-way, to a point approximately
2,000 feet west of the Queen Compressor Station.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 45.3
acres of land for the pipeline. Following construction, National Fuel
would maintain about 20.5 acres for permanent operation of the
project's facilities; the remaining acreage would be restored and
revert to former uses.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified an issue we think deserves attention
based on a preliminary review of the proposed facilities and the
environmental information provided by National Fuel. The proposed
replacement of Line Q and installation of Line QP would involve an open
cut crossing of the Allegheny River in segments that may contain
sensitive freshwater mussels. We encourage comments on this issue as
well as other issues you feel should be addressed in the EA.
[[Page 4278]]
Environmental Mailing List
The environmental mailing list federal, state, and local government
representatives and agencies; elected officials; environmental and
public interest groups; Native American Tribes; other interested
parties; and local libraries and newspapers. This list also includes
all affected landowners (as defined in the Commission's regulations)
who are potential right-of-way grantors, whose property may be used
temporarily for project purposes, or who own homes within certain
distances of aboveground facilities, and anyone who submits comments on
the project. We will update the environmental mailing list as the
analysis proceeds to ensure that we send the information related to
this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies of the EA will be sent
to the environmental mailing list for public review and comment. If you
would prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the ``Document-less Intervention Guide'' under the ``e-filing'' link on
the Commission's Web site. Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP16-
28). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: January 20, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-01464 Filed 1-25-16; 8:45 am]