Texas Gas Transmission, LLC; Revised Notice of Schedule for Environmental Review of the Northern Supply Access Project, 3789-3790 [2016-01234]

Download as PDF mstockstill on DSK4VPTVN1PROD with NOTICES Federal Register / Vol. 81, No. 14 / Friday, January 22, 2016 / Notices ER10–2461–010; ER12–2159–006; ER12–682–011; ER10–2463–010; ER15– 1672–004; ER11–2201–014; ER10–2464– 007; ER10–1821–011; ER13–1139–013; ER13–1585–007; ER12–2205–007; ER10–2465–006; ER11–2657–007; ER13–17–008; ER14–2630–006; ER12– 919–005; ER12–1311–010; ER10–2466– 011; ER11–4029–010. Applicants: Blue Sky East, LLC, Blue Sky West, LLC, Canandaigua Power Partners, LLC, Canandaigua Power Partners II, LLC, Canadian Hills Wind, LLC, Erie Wind, LLC, Evergreen Wind Power, LLC, Evergreen Wind Power II, LLC, Evergreen Wind Power III, LLC, First Wind Energy Marketing, LLC, Goshen Phase II LLC, Imperial Valley Solar 1, LLC, Longfellow Wind, LLC, Meadow Creek Project Company LLC, Milford Wind Corridor Phase I, LLC, Milford Wind Corridor Phase II, LLC, Niagara Wind Power, LLC, Regulus Solar, LLC, Rockland Wind Farm LLC, Stetson Holdings, LLC, Stetson Wind II, LLC, Vermont Wind, LLC. Description: Notice of Change in Status of Blue Sky East, LLC, et al. Filed Date: 1/14/16. Accession Number: 20160114–5449. Comments Due: 5 p.m. ET 2/4/16. Docket Numbers: ER15–2483–002. Applicants: Emerald City Renewables LLC. Description: Notification of NonMaterial Change in Status of Emerald City Renewables LLC. Filed Date: 1/15/16. Accession Number: 20160115–5157. Comments Due: 5 p.m. ET 2/5/16. Docket Numbers: ER16–91–001. Applicants: Blythe Solar 110, LLC. Description: Amendment to December 18, 2015 Notification of Change in Status of Blythe Solar 110, LLC. Filed Date: 1/14/16. Accession Number: 20160114–5447. Comments Due: 5 p.m. ET 2/4/16. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For VerDate Sep<11>2014 16:59 Jan 21, 2016 Jkt 238001 other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: January 15, 2016. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–01231 Filed 1–21–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #2 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC16–61–000. Applicants: American Transmission Company LLC, Wisconsin Power and Light Company. Description: Application of American Transmission Company LLC, et al. for Authority to Acquire Certain Facilities under Section 203 of the FPA. Filed Date: 1/15/16. Accession Number: 20160115–5395. Comments Due: 5 p.m. ET 2/5/16. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER15–303–002. Applicants: PJM Interconnection, L.L.C., American Transmission Systems, Incorporated. Description: Compliance filing: ATSI submits superseding compliance filing re revisions to Attach. H–21A & H–21B to be effective 1/1/2015. Filed Date: 1/15/16. Accession Number: 20160115–5266. Comments Due: 5 p.m. ET 2/5/16. Docket Numbers: ER16–733–000. Applicants: LQA, LLC. Description: Baseline eTariff Filing: Application for Market-Based Rate Authorization and Request for Waivers to be effective 1/16/2016. Filed Date: 1/15/16. Accession Number: 20160115–5289. Comments Due: 5 p.m. ET 2/5/16. Docket Numbers: ER16–734–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Service Agreement Nos. 4372–4390; Queue Nos. AB1–035–AB1–052 and AB1–071 (WMPAs) to be effective 12/ 21/2015. Filed Date: 1/15/16. Accession Number: 20160115–5307. Comments Due: 5 p.m. ET 2/5/16. Docket Numbers: ER16–735–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2016–01–15 FTR Market Data Posting Filing to be effective 3/15/2016. PO 00000 Frm 00014 Fmt 4703 Sfmt 4703 3789 Filed Date: 1/15/16. Accession Number: 20160115–5336. Comments Due: 5 p.m. ET 2/5/16. Docket Numbers: ER16–736–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Revisions to OATT Schedule 12 Appdx A–RTEP Approved by the PJM Board Dec 2015 to be effective 2/11/2016. Filed Date: 1/15/16. Accession Number: 20160115–5385. Comments Due: 5 p.m. ET 2/5/16. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: January 15, 2016. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–01232 Filed 1–21–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–513–000] Texas Gas Transmission, LLC; Revised Notice of Schedule for Environmental Review of the Northern Supply Access Project This notice identifies the Federal Energy Regulatory Commission (Commission or FERC) staff’s revised schedule for the completion of the environmental assessment (EA) for Texas Gas Transmission, LLC’s Northern Supply Access Project. The previous notice of schedule, issued on December 23, 2015, identified February 4, 2016 as the issuance date. Schedule for Environmental Review Issuance of EA, January 26, 2016 90-day Federal Authorization Decision Deadline, April 25, 2016 E:\FR\FM\22JAN1.SGM 22JAN1 3790 Federal Register / Vol. 81, No. 14 / Friday, January 22, 2016 / Notices If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. Go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: January 15, 2016. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2016–01234 Filed 1–21–16; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–144–000] mstockstill on DSK4VPTVN1PROD with NOTICES Florida Gas Transmission Company, LLC: Notice of Availability of the Environmental Assessment for the Proposed Jacksonville Expansion Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the Jacksonville Expansion Project, proposed by the Florida Gas Transmission Company, LLC (FGT) in the above-referenced docket. FGT requests authorization to construct about 8.7 miles of natural gas pipeline and associated aboveground facilities in Suwannee, Columbia, Bradford, and Clay Counties, Florida. The purpose is to provide a total of approximately 75,000 MMBtu/d of natural gas capacity to be delivered at various amounts at several points throughout Florida. The EA assesses the potential environmental effects of constructing and operating the Jacksonville Expansion Project in accordance with the requirements of the National Environmental Policy Act (NEPA). The FERC staff concludes that approval of the proposed project, with appropriate mitigating measures, would not constitute a major federal action significantly affecting the quality of the human environment. The proposed Jacksonville Expansion Project includes the following facilities: • Approximately 3.0 miles of 30-inchdiameter looping pipeline and VerDate Sep<11>2014 16:59 Jan 21, 2016 Jkt 238001 associated facilities 1 in Suwannee and Columbia Counties; • one new compressor unit, re-wheel an existing turbine compressor unit, and construct and modify piping and valves at Compressor Station 16 in Bradford County; • approximately 5.7 miles of 20-inchdiameter looping pipeline and associated facilities in Bradford and Clay Counties; and • a new regulation station in Bradford County. The FERC staff mailed copies of the EA to federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; newspapers and libraries in the project area; and parties to this proceeding. In addition, the EA is available for public viewing on the FERC’s Web site (www.ferc.gov) using the eLibrary link. A limited number of copies of the EA are available for distribution and public inspection at: Federal Energy Regulatory Commission, Public Reference Room, 888 First Street NE., Room 2A, Washington, DC 20426, (202) 502–8371. Any person wishing to comment on the EA may do so. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that the Commission has the opportunity to consider your comments prior to making its decision on this project, it is important that we receive your comments in Washington, DC on or before February 15, 2016. For your convenience, there are three methods you can use to file your comments to the Commission. In all instances, please reference the project docket number (CP15–144–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can also file your comments electronically using the eFiling feature 1 Associated facilities include new or relocated pig launchers and receivers, valves, and cathodic protection equipment. PO 00000 Frm 00015 Fmt 4703 Sfmt 4703 on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission’s Rules of Practice and Procedures (18 CFR 385.214).2 Only intervenors have the right to seek rehearing of the Commission’s decision. The Commission grants affected landowners and others with environmental concerns intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which no other party can adequately represent. Simply filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search,’’ and enter the docket number excluding the last three digits in the Docket Number field (i.e., CP15– 144). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. 2 See the previous discussion on the methods for filing comments. E:\FR\FM\22JAN1.SGM 22JAN1

Agencies

[Federal Register Volume 81, Number 14 (Friday, January 22, 2016)]
[Notices]
[Pages 3789-3790]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-01234]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-513-000]


Texas Gas Transmission, LLC; Revised Notice of Schedule for 
Environmental Review of the Northern Supply Access Project

    This notice identifies the Federal Energy Regulatory Commission 
(Commission or FERC) staff's revised schedule for the completion of the 
environmental assessment (EA) for Texas Gas Transmission, LLC's 
Northern Supply Access Project. The previous notice of schedule, issued 
on December 23, 2015, identified February 4, 2016 as the issuance date.

Schedule for Environmental Review

Issuance of EA, January 26, 2016
90-day Federal Authorization Decision Deadline, April 25, 2016


[[Page 3790]]


    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. Go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: January 15, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-01234 Filed 1-21-16; 8:45 am]