KC Lake Hydro LLC; Notice of Surrender of Preliminary Permit, 3408 [2016-01122]
Download as PDF
3408
Federal Register / Vol. 81, No. 13 / Thursday, January 21, 2016 / Notices
Triennial MBR Update in Docket No.
ER10–3063 to be effective 3/14/2016.
Filed Date: 1/14/16.
Accession Number: 20160114–5363.
Comments Due: 5 p.m. ET 3/14/16.
Docket Numbers: ER16–732–000.
Applicants: Consolidated Edison
Company of New York, Inc.
Description: § 205(d) Rate Filing:
Surcharge—Targeted Demand
Management Program and Demo
Projects to be effective 1/15/2016.
Filed Date: 1/14/16.
Accession Number: 20160114–5378.
Comments Due: 5 p.m. ET 2/4/16.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: January 14, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–01114 Filed 1–20–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14558–001]
asabaliauskas on DSK9F6TC42PROD with NOTICES
KC Lake Hydro LLC; Notice of
Surrender of Preliminary Permit
Take notice that KC Lake Hydro LLC
(KC Hydro) filed a letter on January 7,
2016, describing its decision to abandon
the preliminary permit for the proposed
North Hadley Lake Warner Dam
Hydropower Project.1 The permit was
issued on June 26, 2014, and would
have expired on May 31, 2017.2 The
project would have been located at the
outlet of Lake Warner, on the Mill River,
1 While not explicitly stated, KC Hydro’s filing
constitutes a request to surrender its preliminary
permit.
2 147 FERC ¶ 62,236 (2014).
VerDate Sep<11>2014
18:26 Jan 20, 2016
Jkt 238001
near the Town of North Hadley,
Hampshire County, Massachusetts.
The preliminary permit for Project
No. 14558 will remain in effect until the
close of business, February 13, 2016.
But, if the Commission is closed on this
day, then the permit remains in effect
until the close of business on the next
day in which the Commission is open.3
New applications for this site may not
be submitted until after the permit
surrender is effective.
Dated: January 14, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–01122 Filed 1–20–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14702–000]
Twain Resources, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On August 25, 2015, Twain
Resources, LLC, filed an application for
a preliminary permit, pursuant to
section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of the Scheelite Water Power Project
(Scheelite Project or project) to be
located along Pine Creek, near the City
of Bishop, in Inyo County, California.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed project would consist of
the following: (1) An intake receiving
the water discharge from the Tungstar
Redux Water Power Project; (2) an18inch-diameter, approximately 6,500foot-long steel penstock, conveying
water to; (3) a powerhouse containing a
single 810-kilowatt impulse turbine and
an 840 kilovolt-ampere generator; (4) a
new substation at the powerhouse; (5)
an approximately 600-foot-long, 12kilovolt (kV) transmission line
connecting the substation to a 12-kV
California Edison-owned transmission
line; and (6) appurtenant facilities. The
estimated annual generation of the
3 18
PO 00000
CFR 385.2007(a)(2) (2015).
Frm 00032
Fmt 4703
Sfmt 4703
Scheelite Project would be 4,860
megawatt-hours.
Applicant Contact: Mr. Doug Hicks,
280 Floreca Way, Reno, Nevada 89511,
phone (775) 997–3429.
FERC Contact: Joseph Hassell; phone:
(202) 502–8079.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14702–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14702) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: January 14, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–01123 Filed 1–20–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2533–059]
City of Brainerd Public Utility
Commission; Notice of Application
Accepted for Filing, Soliciting
Comments, Motions To Intervene, and
Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
E:\FR\FM\21JAN1.SGM
21JAN1
Agencies
[Federal Register Volume 81, Number 13 (Thursday, January 21, 2016)]
[Notices]
[Page 3408]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-01122]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14558-001]
KC Lake Hydro LLC; Notice of Surrender of Preliminary Permit
Take notice that KC Lake Hydro LLC (KC Hydro) filed a letter on
January 7, 2016, describing its decision to abandon the preliminary
permit for the proposed North Hadley Lake Warner Dam Hydropower
Project.\1\ The permit was issued on June 26, 2014, and would have
expired on May 31, 2017.\2\ The project would have been located at the
outlet of Lake Warner, on the Mill River, near the Town of North
Hadley, Hampshire County, Massachusetts.
---------------------------------------------------------------------------
\1\ While not explicitly stated, KC Hydro's filing constitutes a
request to surrender its preliminary permit.
\2\ 147 FERC ] 62,236 (2014).
---------------------------------------------------------------------------
The preliminary permit for Project No. 14558 will remain in effect
until the close of business, February 13, 2016. But, if the Commission
is closed on this day, then the permit remains in effect until the
close of business on the next day in which the Commission is open.\3\
New applications for this site may not be submitted until after the
permit surrender is effective.
---------------------------------------------------------------------------
\3\ 18 CFR 385.2007(a)(2) (2015).
Dated: January 14, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.