Aquenergy Systems, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 2853 [2016-00820]
Download as PDF
Federal Register / Vol. 81, No. 11 / Tuesday, January 19, 2016 / Notices
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: January 12, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–00810 Filed 1–15–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2428–007]
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Aquenergy Systems, LLC; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests and
Establishing Procedural Schedule for
Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Minor New
License.
b. Project No.: P–2428–007.
c. Date filed: December 31, 2015.
d. Applicant: Aquenergy Systems,
LLC.
e. Name of Project: Piedmont
Hydroelectric Project.
f. Location: On the Saluda River, in
Anderson and Greenville Counties,
South Carolina. The project does not
occupy lands of the United States.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Beth E. Harris,
P.E., Regional Operations Manager, Enel
Green Power North America, Inc., 11
Anderson St., Piedmont, SC 29674;
(864) 846–0042; Beth.Harris@Enel.com.
i. FERC Contact: Sean Murphy, (202)
502–6145 or sean.murphy@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
VerDate Sep<11>2014
17:50 Jan 15, 2016
Jkt 238001
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: February 29, 2016
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first
page of any filing should include docket
number P–2428–007.
m. The application is not ready for
environmental analysis at this time.
n. The Piedmont Hydroelectric Project
consists of: (a) A 25-foot-high, 600-footlong stone masonry dam with a 200foot-long overflow spillway section
fitted with 16-inch-high flashboards; (b)
a reservoir with a surface area of 22
acres at the normal water surface
elevation of 774.0 feet mean sea level;
(c) an open flume intake canal, about
144 feet long and 81 feet wide; (d) a
powerhouse containing a single
generating unit with a rated capacity of
1,000 kW; (e) a tailrace, about 180 feet
long and 38 feet wide; (f) a 600 volt
transmission line, about 263 feet long;
and (g) appurtenant facilities.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
2853
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary Hydro Licensing Schedule.
Revisions to the schedule will be made
as appropriate.
Issue Notice of Acceptance ................
Issue Scoping Document 1 for comments.
Comments on Scoping Document 1
due.
Issue Scoping Document 2 .................
Issue notice of ready for environmental analysis.
Commission issues EA .......................
Comments on EA due ........................
Commission issues final EA ...............
August
2016.
October
2016.
December
2016.
February
2017.
March 2017.
October
2017.
November
2017.
January
2018.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: January 12, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–00820 Filed 1–15–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER16–700–000]
CPV Towantic, LLC; Supplemental
Notice That Initial Market-Based Rate
Filing Includes Request for Blanket
Section 204 Authorization
This is a supplemental notice in the
above-referenced proceeding of CPV
Towantic, LLC’s application for marketbased rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
E:\FR\FM\19JAN1.SGM
19JAN1
Agencies
[Federal Register Volume 81, Number 11 (Tuesday, January 19, 2016)]
[Notices]
[Page 2853]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-00820]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2428-007]
Aquenergy Systems, LLC; Notice of Application Tendered for Filing
With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Minor New License.
b. Project No.: P-2428-007.
c. Date filed: December 31, 2015.
d. Applicant: Aquenergy Systems, LLC.
e. Name of Project: Piedmont Hydroelectric Project.
f. Location: On the Saluda River, in Anderson and Greenville
Counties, South Carolina. The project does not occupy lands of the
United States.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Beth E. Harris, P.E., Regional Operations
Manager, Enel Green Power North America, Inc., 11 Anderson St.,
Piedmont, SC 29674; (864) 846-0042; Beth.Harris@Enel.com.
i. FERC Contact: Sean Murphy, (202) 502-6145 or
sean.murphy@ferc.gov.
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: February 29, 2016
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, please send a paper copy
to: Secretary, Federal Energy Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first page of any filing should include
docket number P-2428-007.
m. The application is not ready for environmental analysis at this
time.
n. The Piedmont Hydroelectric Project consists of: (a) A 25-foot-
high, 600-foot-long stone masonry dam with a 200-foot-long overflow
spillway section fitted with 16-inch-high flashboards; (b) a reservoir
with a surface area of 22 acres at the normal water surface elevation
of 774.0 feet mean sea level; (c) an open flume intake canal, about 144
feet long and 81 feet wide; (d) a powerhouse containing a single
generating unit with a rated capacity of 1,000 kW; (e) a tailrace,
about 180 feet long and 38 feet wide; (f) a 600 volt transmission line,
about 263 feet long; and (g) appurtenant facilities.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary Hydro Licensing
Schedule. Revisions to the schedule will be made as appropriate.
------------------------------------------------------------------------
------------------------------------------------------------------------
Issue Notice of Acceptance................ August 2016.
Issue Scoping Document 1 for comments..... October 2016.
Comments on Scoping Document 1 due........ December 2016.
Issue Scoping Document 2.................. February 2017.
Issue notice of ready for environmental March 2017.
analysis.
Commission issues EA...................... October 2017.
Comments on EA due........................ November 2017.
Commission issues final EA................ January 2018.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: January 12, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-00820 Filed 1-15-16; 8:45 am]