PE Hydro Generation, LLC; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 2857-2858 [2016-00819]
Download as PDF
Federal Register / Vol. 81, No. 11 / Tuesday, January 19, 2016 / Notices
CFR 1501.6, made under 18 CFR
385.2201(e) (1) (v).
The following is a list of off-therecord communications recently
received by the Secretary of the
Commission. The communications
listed are grouped by docket numbers in
ascending order. These filings are
available for electronic review at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the eLibrary link.
Enter the docket number, excluding the
Docket No.
2.
3.
4.
5.
6.
CP15–558–000 ...........................................................
CP16–21–000 .............................................................
CP16–21–000 .............................................................
CP16–9–000 ...............................................................
CP16–21–000 .............................................................
1 Memo
last three digits, in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202)502–8659.
File date
Prohibited:
1. CP15–554–000 ...........................................................
2. CP–15–554–000 .........................................................
3. CP15–554–000 ...........................................................
4. CP16–21–000 .............................................................
5. EL15–623–000, EL15–29–000, EL15–70–000, EL15–
71–000, EL15–72–000, EL15–82–000.
6. CP16–21–000 .............................................................
7. CP15–520–000 ...........................................................
Exempt:
1. CP15–558–000 ...........................................................
12–28–2015
12–28–2015
12–28–2015
1–4–2016
1–5–2016
1–5–2016
1–8–2016
12–28–2015
12–28–2015
1–4–2016
1–4–2016
1–4–2016
1–5–2016
2857
Presenter or requester
William Long.
Bobby Albrite.
James Lee.
Peter Stasiowski.
FERC Staff.1
Christine Dudley-Marling.
FERC Staff.2
Delaware Township, New Jersey Municipal Clerk Judith
Allen.
Township of Hopewell, New Jersey Mayor Harvey Lester.
U.S. House Representative Paul D. Tonko.
State of Massachusetts Senate President Stan Rosenberg.
U.S. House Representative Stephen F. Lynch.
U.S. Senator Kirsten Gillibrand.
forwarding post conference notes and transcript for PJM Interconnection, LLM Capacity Performance filing.
Summary from January 8, 2016 conference call with Shannon Miller and Jacqueline Rocan of Tennessee Gas Pipeline Company,
2 Meeting
LLC.
Dated: January 12, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–00817 Filed 1–15–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2343–086]
asabaliauskas on DSK5VPTVN1PROD with NOTICES
PE Hydro Generation, LLC; Notice of
Application Tendered for Filing With
the Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2343–086.
c. Date Filed: December 30, 2015.
d. Applicant: PE Hydro Generation,
LLC (PE Hydro).
e. Name of Project: Millville
Hydroelectric Project.
f. Location: The existing project is
located on the Shenandoah River, near
the town of Harpers Ferry in Jefferson
County, West Virginia. No federal lands
are occupied by project works or located
within the project boundary.
VerDate Sep<11>2014
18:44 Jan 15, 2016
Jkt 238001
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Juan Kimble,
President, PE Hydro Generation, LLC,
5425 Wisconsin Avenue, 6th Floor,
Chevy Chase, MD 20815; Telephone—
(301) 718–4496.
i. FERC Contact: Michael Spencer,
(202) 502–6093, or michael.spencer@
ferc.gov.
j. This application is not ready for
environmental analysis (EA) at this
time.
k. Project Description: The Millville
project consists of: (1) A 14.0-foot-high
concrete and stone dam consisting of
three sections: a 36-foot-long nonoverflow abutment on the east bank; an
813-foot long, non-gated spillway
section; and a 122-foot-long intake
structure, equipped with four vertical
lift gates and one canal gate, and
extending to the west riverbank; (2) a
100 acre reservoir with gross storage
capacity of 900 acre-feet at elevation
324.0 mean sea level; (3) a 1,600-footlong, 30-foot-wide, 12-foot-high
masonry and concrete sided headrace
canal; (4) a 125-foot-long, 40-foot-wide
brick powerhouse containing 3 turbinegenerating units with a combined
capacity of 2.84 megawatts; (5) a 550foot-long tailrace, excavated in bedrock
and returning flow to the river channel;
and (6) a 1,006-foot-long, 2.4 kilovolt
(kV) transmission line to a transformer,
with a 794-foot-long, 34.5 kV
transmission line to the interconnection
with the local grid.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
PE Hydro operates the project in a
run-of-river mode, with a minimum
flow of 200 cfs, or inflow, whichever is
less. Under an agreement with the US
Fish and Wildlife Service the licensee
shuts down Project nightly from
September 15 to December 15 in an
effort to reduce entrainment of
downstream-migrating American eels.
The project generates an annual average
of 10,159.431 MWh.
l. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov, using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). A copy is also available for
inspection and reproduction at the
address in item (h) above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
m. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule will be made as appropriate.
E:\FR\FM\19JAN1.SGM
19JAN1
2858
Federal Register / Vol. 81, No. 11 / Tuesday, January 19, 2016 / Notices
Notice of Acceptance/Notice of Ready
for Environmental Analysis.
Filing of recommendations, preliminary terms and conditions, and
fishway prescriptions.
Commission issues EA .......................
Comments on EA ................................
Modified Terms and Conditions ..........
Commission Issues Final EA, if necessary.
February
2016.
April 2016.
August
2016.
September
2016.
November
2016.
February
2017.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: January 12, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–00819 Filed 1–15–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP16–368–000.
Applicants: Guardian Pipeline, L.L.C.
Description: § 4(d) Rate Filing:
Negotiated Rate PAL Agreement—
Exelon Generation Comp., LLC to be
effective 1/8/2016.
Filed Date: 1/7/16.
Accession Number: 20160107–5157.
Comments Due: 5 p.m. ET 1/19/16.
Docket Numbers: RP16–369–000.
Applicants: Columbia Gas
Transmission, LLC.
Description: § 4(d) Rate Filing: Penalty
Clean Up Filing to be effective 2/1/2016.
Filed Date: 1/7/16.
Accession Number: 20160107–5193.
Comments Due: 5 p.m. ET 1/19/16.
Docket Numbers: RP16–370–000.
Applicants: Enable Mississippi River
Transmission, L.
Description: § 4(d) Rate Filing:
Negotiated Rate Filing to Amend LER
5680’s Attachment A_1_7_16 to be
effective 1/7/2016.
Filed Date: 1/7/16.
Accession Number: 20160107–5222.
Comments Due: 5 p.m. ET 1/19/16.
Docket Numbers: RP16–371–000.
Applicants: Millennium Pipeline
Company, L.L.C.
Description: Penalty Revenue
Crediting Report of under RP16–371.
VerDate Sep<11>2014
17:50 Jan 15, 2016
Jkt 238001
Filed Date: 1/8/16.
Accession Number: 20160108–5149.
Comments Due: 5 p.m. ET 1/20/16.
Docket Numbers: RP16–372–000.
Applicants: Texas Eastern OFO.
Description: Compliance filing Report
of Refund—S–2 Customer Share of
Texas Eastern OFO Penalty
Disbursement to be effective N/A.
Filed Date: 1/8/16.
Accession Number: 20160108–5179.
Comments Due: 5 p.m. ET 1/20/16.
Docket Numbers: RP16–373–000.
Applicants: Southwest Energy, L.P.
Description: § 4(d) Rate Filing:
Negotiated Rate PAL Agreement—
Southwest Energy, L.P. to be effective 1/
10/2016.
Filed Date: 1/8/16.
Accession Number: 20160108–5203.
Comments Due: 5 p.m. ET 1/20/16.
Docket Numbers: RP16–374–000.
Applicants: Trailblazer Pipeline
Company LLC.
Description: § 4(d) Rate Filing: Neg
Rate 2016–01–08 Mieco to be effective
1/9/2016.
Filed Date: 1/8/16.
Accession Number: 20160108–5224.
Comments Due: 5 p.m. ET 1/20/16.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
§ 385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
Filings in Existing Proceedings
Docket Numbers: RP16–233–001.
Applicants: No Applicants listed for
this docket/subdocket.
Description: Compliance filing SG
Resources Mississippi, L.L.C.—
Compliance Filing to be effective 12/31/
2015.
Filed Date: 1/8/16.
Accession Number: 20160108–5057.
Comments Due: 5 p.m. ET 1/20/16.
Any person desiring to protest in any
of the above proceedings must file in
accordance with Rule 211 of the
Commission’s Regulations (18 CFR
385.211) on or before 5:00 p.m. Eastern
time on the specified comment date.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: January 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–00809 Filed 1–15–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER16–701–000]
CPV Valley, LLC; Supplemental Notice
That Initial Market-Based Rate Filing
Includes Request for Blanket Section
204 Authorization
This is a supplemental notice in the
above-referenced proceeding of CPV
Valley, LLC’s application for marketbased rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is February 1,
2016.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
E:\FR\FM\19JAN1.SGM
19JAN1
Agencies
[Federal Register Volume 81, Number 11 (Tuesday, January 19, 2016)]
[Notices]
[Pages 2857-2858]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-00819]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2343-086]
PE Hydro Generation, LLC; Notice of Application Tendered for
Filing With the Commission and Establishing Procedural Schedule for
Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2343-086.
c. Date Filed: December 30, 2015.
d. Applicant: PE Hydro Generation, LLC (PE Hydro).
e. Name of Project: Millville Hydroelectric Project.
f. Location: The existing project is located on the Shenandoah
River, near the town of Harpers Ferry in Jefferson County, West
Virginia. No federal lands are occupied by project works or located
within the project boundary.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Juan Kimble, President, PE Hydro Generation,
LLC, 5425 Wisconsin Avenue, 6th Floor, Chevy Chase, MD 20815;
Telephone--(301) 718-4496.
i. FERC Contact: Michael Spencer, (202) 502-6093, or
michael.spencer@ferc.gov.
j. This application is not ready for environmental analysis (EA) at
this time.
k. Project Description: The Millville project consists of: (1) A
14.0-foot-high concrete and stone dam consisting of three sections: a
36-foot-long non-overflow abutment on the east bank; an 813-foot long,
non-gated spillway section; and a 122-foot-long intake structure,
equipped with four vertical lift gates and one canal gate, and
extending to the west riverbank; (2) a 100 acre reservoir with gross
storage capacity of 900 acre-feet at elevation 324.0 mean sea level;
(3) a 1,600-foot-long, 30-foot-wide, 12-foot-high masonry and concrete
sided headrace canal; (4) a 125-foot-long, 40-foot-wide brick
powerhouse containing 3 turbine-generating units with a combined
capacity of 2.84 megawatts; (5) a 550-foot-long tailrace, excavated in
bedrock and returning flow to the river channel; and (6) a 1,006-foot-
long, 2.4 kilovolt (kV) transmission line to a transformer, with a 794-
foot-long, 34.5 kV transmission line to the interconnection with the
local grid.
PE Hydro operates the project in a run-of-river mode, with a
minimum flow of 200 cfs, or inflow, whichever is less. Under an
agreement with the US Fish and Wildlife Service the licensee shuts down
Project nightly from September 15 to December 15 in an effort to reduce
entrainment of downstream-migrating American eels. The project
generates an annual average of 10,159.431 MWh.
l. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov, using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). A copy is also available for inspection
and reproduction at the address in item (h) above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
m. Procedural Schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule will be made as appropriate.
[[Page 2858]]
------------------------------------------------------------------------
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready for February 2016.
Environmental Analysis.
Filing of recommendations, preliminary April 2016.
terms and conditions, and fishway
prescriptions.
Commission issues EA...................... August 2016.
Comments on EA............................ September 2016.
Modified Terms and Conditions............. November 2016.
Commission Issues Final EA, if necessary.. February 2017.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: January 12, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-00819 Filed 1-15-16; 8:45 am]