Combined Notice of Filings #2, 2206-2207 [2016-00702]
Download as PDF
2206
Federal Register / Vol. 81, No. 10 / Friday, January 15, 2016 / Notices
Milestone
Target date
Notice of Acceptance/Notice of Ready for Environmental Analysis.
Filing of recommendations,
preliminary terms and
conditions, and fishway
prescriptions.
Commission issues EA ......
Comments on EA ..............
February 2016.
Modified Terms and Conditions.
Commission Issues Final
EA, if necessary.
April 2016.
August 2016.
September
2016.
November 2016.
Issuance of EA—February 12, 2016
90-day Federal Authorization Decision
Deadline—May 12, 2016
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
February 2017.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
[FR Doc. 2016–00710 Filed 1–14–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–560–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Cameron LNG, LLC; Notice of
Schedule for Environmental Review of
the Cameron LNG Terminal Expansion
Project
On September 28, 2015, Cameron
LNG, LLC filed an application in Docket
No. CP15–560–000 requesting
Authorization pursuant to section 3 of
the Natural Gas Act to construct and
operate certain liquefied natural gas
(LNG) facilities at the existing Cameron
LNG Terminal. The proposed project is
known as the Cameron LNG Terminal
Expansion Project (Project), and would
increase the terminal’s capability to
liquefy natural gas for export by 515
billion cubic feet per year.
On October 13, 2015, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
20:01 Jan 14, 2016
Cameron LNG, LLC’s Project would
add an additional LNG storage tank
(Tank 5) and two new systems to liquefy
natural gas (Trains 4 and 5) to its
existing LNG Terminal in Cameron and
Calcasieu Parishes, Louisiana. No
construction would occur outside of the
existing terminal and no new shipping
is proposed as a result of this Project.
site (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP15–560), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Web site also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: January 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–00703 Filed 1–14–16; 8:45 am]
BILLING CODE 6717–01–P
Background
Dated: January 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
VerDate Sep<11>2014
Schedule for Environmental Review
Jkt 238001
On June 18, 2015, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Planned Cameron LNG Expansion
Project and Request for Comments on
Environmental Issues (NOI). The NOI
was issued during the pre-filing review
of the Project in Docket No. PF15–13–
000 and was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers. In response to the NOI,
the Commission received comments
from the U.S. Environmental Protection
Agency (EPA). The primary issues
raised by the EPA are alternatives,
groundwater and water impacts,
wildlife and habitat impacts, air quality,
hazardous materials, tribal and state
historic preservation office consultation,
and environmental justice.
The U.S. Department of
Transportation and U.S. Department of
Energy are cooperating agencies in the
preparation of the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #2
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG16–36–000.
Applicants: Kingbird Solar A, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Kingbird Solar A,
LLC.
Filed Date: 1/11/16.
Accession Number: 20160111–5267.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: EG16–37–000.
Applicants: Kingbird Solar B, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Kingbird Solar B,
LLC.
Filed Date: 1/11/16.
Accession Number: 20160111–5271.
Comments Due: 5 p.m. ET 2/1/16.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER16–38–001.
Applicants: Kingbird Solar A, LLC.
Description: Compliance filing:
Application for Initial Market-Based
Rate Tariff and Granting Certain
Waivers to be effective 1/12/2016.
Filed Date: 1/11/16.
Accession Number: 20160111–5265.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: ER16–705–001.
Applicants: RE Garland LLC.
Description: Tariff Amendment:
Amendment to Application and Initial
Tariff Filing to be effective 2/12/2016.
Filed Date: 1/11/16.
E:\FR\FM\15JAN1.SGM
15JAN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 81, No. 10 / Friday, January 15, 2016 / Notices
Accession Number: 20160111–5311.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: ER16–706–001.
Applicants: RE Garland A LLC.
Description: Tariff Amendment:
Amendment to Application and Initial
Tariff Filing to be effective 2/12/2016.
Filed Date: 1/11/16.
Accession Number: 20160111–5312.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: ER16–708–000.
Applicants: Calpine Energy Services,
L.P.
Description: Request for Limited
Waiver and Shortened Comment Period
of Calpine Energy Services, L.P.
Filed Date: 1/8/16.
Accession Number: 20160108–5278.
Comments Due: 5 p.m. ET 1/19/16.
Docket Numbers: ER16–710–000.
Applicants: Arizona Public Service
Company.
Description: Section 205(d) Rate
Filing: Service Agreement No. 219—
Amendment 2 to be effective 1/1/2016.
Filed Date: 1/11/16.
Accession Number: 20160111–5297.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: ER16–711–000.
Applicants: Pio Pico Energy Center,
LLC.
Description: Baseline eTariff Filing:
Application for MBR to be effective
3/1/2016.
Filed Date: 1/11/16.
Accession Number: 20160111–5304.
Comments Due: 5 p.m. ET 2/1/16.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: January 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016–00702 Filed 1–14–16; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
20:01 Jan 14, 2016
Jkt 238001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2512–075]
Hawks Nest Hydro, LLC; Notice of
Application Tendered for Filing With
the Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2512–075.
c. Date Filed: December 29, 2015.
d. Applicant: Hawks Nest Hydro, LLC
(Hawks Nest Hydro).
e. Name of Project: Hawks Nest
Hydroelectric Project.
f. Location: The existing project is
located on the New River, in Fayette
County, West Virginia. The project does
not occupy any federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Steven Murphy,
Manager, Licensing, Brookfield
Renewable Energy Group, 33 West 1st
Street South, Fulton, New York 13069;
Telephone (315) 598–6130.
i. FERC Contact: Monir Chowdhury,
(202) 502–6736 or monir.chowdhury@
ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The existing
Hawks Nest Hydroelectric Project
consists of: (1) A 948-foot-long concrete
gravity dam with a crest elevation of
795.0 feet National Geodetic Vertical
Datum of 1929 (NGVD29); (2) 14 ogeetype spillway bays extending almost the
entire length of the dam, each with a 25foot-high by 50-foot-wide Stoney-type
steel lift gate and separated by a 9-footwide concrete pier; (3) a 243-acre
reservoir with a gross storage capacity of
7,323 acre-feet at a normal pool
elevation of 819.9 feet NGVD29; (4) an
intake structure located at the right
shoreline (looking downstream) of the
reservoir just upstream of the dam and
consisting of a 110-foot-wide by 50-foothigh trashrack structure and a Stoneytype 42-foot-high by 50-foot-wide
bulkhead intake gate that sits back
approximately 50 feet from the opening
where the trashrack is located; (5) a
16,240-foot-long tunnel that runs along
the right side of the river to convey
water from the intake to the powerhouse
downstream of the New River; (6) a 600foot-long by 170-foot-wide surge basin
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
2207
located at a point on the tunnel
approximately 60 percent of the
distance from the intake to the
powerhouse; (7) a 116-foot-diameter and
56-foot-high differential surge tank
located at the downstream end of the
tunnel and before the powerhouse; (8) a
210-foot-long by 74.5-foot-wide
powerhouse containing four turbinegenerator units, each with a rated
capacity of approximately 25.5
megawatts; (9) two parallel
approximately 5.5-mile-long, 69-kilovolt
transmission lines; and (10) appurtenant
facilities.
Hawks Nest Hydro operates the
project in a run-of-river mode. The
existing license (Article 402) requires
that the project release a continuous
minimum flow of 100 cubic feet per
second into the bypassed reach between
the dam and the powerhouse. Hawks
Nest Hydro proposes to continue run-ofriver operation and a modified
minimum flow schedule for the
bypassed reach. The project generates
an annual average of 544,253 megawatthours.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or toll-free at 1–866–208–3676,
or for TTY, (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item (h)
above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Notice of Acceptance/Notice of Ready for Environmental Analysis.
Filing of recommendations,
preliminary terms and
conditions, and fishway
prescriptions.
Commission issues EA ......
Comments on EA ..............
February 2016.
E:\FR\FM\15JAN1.SGM
15JAN1
April 2016.
August 2016.
September
2016.
Agencies
[Federal Register Volume 81, Number 10 (Friday, January 15, 2016)]
[Notices]
[Pages 2206-2207]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-00702]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #2
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG16-36-000.
Applicants: Kingbird Solar A, LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status of Kingbird Solar A, LLC.
Filed Date: 1/11/16.
Accession Number: 20160111-5267.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: EG16-37-000.
Applicants: Kingbird Solar B, LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status of Kingbird Solar B, LLC.
Filed Date: 1/11/16.
Accession Number: 20160111-5271.
Comments Due: 5 p.m. ET 2/1/16.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER16-38-001.
Applicants: Kingbird Solar A, LLC.
Description: Compliance filing: Application for Initial Market-
Based Rate Tariff and Granting Certain Waivers to be effective 1/12/
2016.
Filed Date: 1/11/16.
Accession Number: 20160111-5265.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: ER16-705-001.
Applicants: RE Garland LLC.
Description: Tariff Amendment: Amendment to Application and Initial
Tariff Filing to be effective 2/12/2016.
Filed Date: 1/11/16.
[[Page 2207]]
Accession Number: 20160111-5311.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: ER16-706-001.
Applicants: RE Garland A LLC.
Description: Tariff Amendment: Amendment to Application and Initial
Tariff Filing to be effective 2/12/2016.
Filed Date: 1/11/16.
Accession Number: 20160111-5312.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: ER16-708-000.
Applicants: Calpine Energy Services, L.P.
Description: Request for Limited Waiver and Shortened Comment
Period of Calpine Energy Services, L.P.
Filed Date: 1/8/16.
Accession Number: 20160108-5278.
Comments Due: 5 p.m. ET 1/19/16.
Docket Numbers: ER16-710-000.
Applicants: Arizona Public Service Company.
Description: Section 205(d) Rate Filing: Service Agreement No.
219--Amendment 2 to be effective 1/1/2016.
Filed Date: 1/11/16.
Accession Number: 20160111-5297.
Comments Due: 5 p.m. ET 2/1/16.
Docket Numbers: ER16-711-000.
Applicants: Pio Pico Energy Center, LLC.
Description: Baseline eTariff Filing: Application for MBR to be
effective 3/1/2016.
Filed Date: 1/11/16.
Accession Number: 20160111-5304.
Comments Due: 5 p.m. ET 2/1/16.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: January 11, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-00702 Filed 1-14-16; 8:45 am]
BILLING CODE 6717-01-P