Columbia Gas Transmission, LLC;, 80760-80761 [2015-32572]

Download as PDF 80760 Federal Register / Vol. 80, No. 248 / Monday, December 28, 2015 / Notices (5) Annual Estimated Number of Respondents: 1,004; (6) Annual Estimated Number of Total Responses: 79,634; (7) Response Obligation: Required, except for Noncompliance Tracking System (see Statutory Authority section below); (8) Annual Estimated Number of Burden Hours: 41,733; (9) Annual Estimated Reporting and Recordkeeping Cost Burden: $0 Statutory Authority: Section 641 of the Department of Energy Organization Act, codified at 42 U.S.C. 7251, and the following additional authorities: Computerized Accident/Incident Reporting System (CAIRS): DOE Order 231.1B (June 27, 2011). Occurrence Reporting and Processing System (ORPS): DOE Order 232.2 (August 30, 2011). Noncompliance Tracking System (NTS): 10 CFR part 820; 10 CFR part 851. Radiation Exposure Monitoring System (REMS): 10 CFR part 835; DOE Order 231.1B (June 27, 2011). Annual Fire Protection Summary Application: DOE Order 231.1B (June 27, 2011). Safety Basis Information System: 10 CFR part 830; DOE O 231.1B (June 27, 2011). Lessons Learned System: DOE Order 210.2A (April 8, 2011). Issued in Washington, DC, on December 11, 2015. Stephanie K. Martin, Acting Director, Office of Resource Management, Office of Environment, Health, Safety and Security. [FR Doc. 2015–32588 Filed 12–24–15; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER16–517–000] Dated: December 21, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. mstockstill on DSK4VPTVN1PROD with NOTICES Shelby County Energy Center, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization [FR Doc. 2015–32574 Filed 12–24–15; 8:45 am] BILLING CODE 6717–01–P This is a supplemental notice in the above-referenced proceeding Shelby County Energy Center, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice VerDate Sep<11>2014 13:31 Dec 24, 2015 Jkt 238001 and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is January 11, 2016. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 5 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The filings in the above-referenced proceeding are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for electronic review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP16–31–000] Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization Take notice that on December 10, 2015 Columbia Gas Transmission, LLC (Columbia Gas), 5151 San Felipe, Suite 2500, Houston, Texas 77056 filed a prior PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 notice request pursuant to sections 157.205 and 157.210 of the Commission’s regulations under the Natural Gas Act for authorization to convert existing compressor units from base load to standby mode at the Cleveland Compressor Station, located in Upshur County, WV and the Files Creek Compressor Station, located in Randolph County, WV. Columbia Gas states that there will be no impact on Columbia’s overall capacity and certified horsepower, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this Application should be directed to Tyler R. Brown, Senior Counsel, Columbia Gas Transmission, LLC, 5151 San Felipe, Suite 2500, Houston, Texas 77056, by calling (713) 386–3797, or by email at tbrown@cpg.com. Any person may, within 60 days after the issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention. Any person filing to intervene or the Commission’s staff may, pursuant to section 157.205 of the Commission’s Regulations under the NGA (18 CFR 157.205) file a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record E:\FR\FM\28DEN1.SGM 28DEN1 Federal Register / Vol. 80, No. 248 / Monday, December 28, 2015 / Notices for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a) (1) (iii) and the instructions on the Commission’s Web site (www.ferc.gov) under the ‘‘e-Filing’’ link. Persons unable to file electronically should submit original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Dated: December 21, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–32572 Filed 12–24–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission mstockstill on DSK4VPTVN1PROD with NOTICES Combined Notice of Filings #2 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER11–1881–007; ER11–1894–007; ER11–1893–007; ER11–1892–007; ER11–1890–007; ER11–1889–007; ER11–1887–007; ER11–1886–007; ER11–1885–007; ER11–1883–007; ER11–1882–007. Applicants: Burley Butte Wind Park, LLC, Golden Valley Wind Park, LLC, VerDate Sep<11>2014 13:31 Dec 24, 2015 Jkt 238001 Milner Dam Wind Park, LLC, Oregon Trail Wind Park, LLC, Pilgrim Stage Station Wind Park, LLC, Thousand Springs Wind Park, LLC, Tuana Gulch Wind Park, LLC, Camp Reed Wind Park, LLC, Payne’s Ferry Wind Park, LLC, Salmon Falls Wind Park, LLC, Yahoo Creek Wind Park, LLC. Description: Supplement to August 7, 2015 Notice of Non-Material Change in Status of the IWP Sellers. Filed Date: 12/21/15. Accession Number: 20151221–5141. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER15–1883–002; ER16–91–002; ER16–90–001; ER15– 2477–001; ER15–1418–002; ER15–1375– 002; ER15–1016–002; ER13–2112–004; ER13–1992–006; ER13–1991–006; ER12–631–009; ER12–2444–008; ER11– 4678–009; ER11–4677–009; ER11–4462– 014; ER11–2160–008; ER10–1989–008; ER10–1971–023; ER10–1962–008; ER10–1890–008 ER10–1856–008; ER10– 1847–008. Applicants: Adelanto Solar, LLC, Adelanto Solar II, LLC, Blythe Solar 110, LLC, Desert Sunlight 250, LLC, Desert Sunlight 300, LLC, Diablo Winds, LLC, FPL Energy Cabazon Wind, LLC, FPL Energy Green Power Wind, LLC, FPL Energy Montezuma Wind, LLC, Genesis Solar, LLC, Golden Hills Wind, LLC, Golden Hills Interconnection, LLC, High Winds, LLC, McCoy Solar, LLC, NEPM II, LLC, NextEra Energy Montezuma II Wind, LLC, NextEra Energy Power Marketing, LLC, North Sky River Energy, LLC, Shafter Solar, LLC, Sky River LLC, Vasco Winds, LLC, Windpower Partners 1993, LLC Description: Notification of Change in Status of the NextEra Resources Entities. Filed Date: 12/18/15. Accession Number: 20151218–5311. Comments Due: 5 p.m. ET 1/8/16. Docket Numbers: ER16–149–001. Applicants: Midcontinent Independent System Operator, Inc. Description: Tariff Amendment: 2015–12–21_SA 2854 MDU–MDU Amended FCA (F109) to be effective 10/ 28/2015. Filed Date: 12/21/15. Accession Number: 20151221–5162. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER16–587–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original WMPA SA No. 4324, Queue No. Z2–115 to be effective 12/8/2015. Filed Date: 12/21/15. Accession Number: 20151221–5091. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER16–588–000. Applicants: PJM Interconnection, L.L.C. PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 80761 Description: § 205(d) Rate Filing: Service Agreement No. 2975; Queue No. W1–082 to be effective 12/2/2015. Filed Date: 12/21/15. Accession Number: 20151221–5092. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER16–589–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amendment to Florence Solar WMPA SA No. 3482, Queue No. W3–080 to be effective 5/8/2014. Filed Date: 12/21/15. Accession Number: 20151221–5104. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER16–590–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Cancellation: Notice of Cancellation of WMPA SA No. 3248, Queue No. W2–083 to be effective 2/5/2016. Filed Date: 12/21/15. Accession Number: 20151221–5110. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER16–591–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Cancellation: Notice of Cancellation of WMPA SA No. 3249, Queue No. W2–088 to be effective 2/5/2016. Filed Date: 12/21/15. Accession Number: 20151221–5133. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER16–592–000. Applicants: Wisconsin Electric Power Company. Description: Application of Wisconsin Electric Power Company of Depreciation Study and Change in Depreciation Rates. Filed Date: 12/18/15. Accession Number: 20151218–5300. Comments Due: 5 p.m. ET 1/8/16. Docket Numbers: ER16–593–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Cancellation: Notice of Cancellation of WMPA SA No. 4159, Queue No. AA1–131 to be effective 2/8/2016. Filed Date: 12/21/15. Accession Number: 20151221–5135. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER16–594–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Assignment of WMPA SA No. 3859, Queue No. Z1–082 to HD Project One, LLC to be effective 5/19/2014. Filed Date: 12/21/15. Accession Number: 20151221–5138. Comments Due: 5 p.m. ET 1/11/16. Docket Numbers: ER16–595–000. E:\FR\FM\28DEN1.SGM 28DEN1

Agencies

[Federal Register Volume 80, Number 248 (Monday, December 28, 2015)]
[Notices]
[Pages 80760-80761]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-32572]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-31-000]


Columbia Gas Transmission, LLC;

Notice of Request Under Blanket Authorization

    Take notice that on December 10, 2015 Columbia Gas Transmission, 
LLC (Columbia Gas), 5151 San Felipe, Suite 2500, Houston, Texas 77056 
filed a prior notice request pursuant to sections 157.205 and 157.210 
of the Commission's regulations under the Natural Gas Act for 
authorization to convert existing compressor units from base load to 
standby mode at the Cleveland Compressor Station, located in Upshur 
County, WV and the Files Creek Compressor Station, located in Randolph 
County, WV. Columbia Gas states that there will be no impact on 
Columbia's overall capacity and certified horsepower, all as more fully 
set forth in the application which is on file with the Commission and 
open to public inspection. The filing may also be viewed on the web at 
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC at 
FERCOnlineSupport@ferc.gov or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Any questions regarding this Application should be directed to 
Tyler R. Brown, Senior Counsel, Columbia Gas Transmission, LLC, 5151 
San Felipe, Suite 2500, Houston, Texas 77056, by calling (713) 386-
3797, or by email at tbrown@cpg.com.
    Any person may, within 60 days after the issuance of the instant 
notice by the Commission, file pursuant to Rule 214 of the Commission's 
Procedural Rules (18 CFR 385.214) a motion to intervene or notice of 
intervention. Any person filing to intervene or the Commission's staff 
may, pursuant to section 157.205 of the Commission's Regulations under 
the NGA (18 CFR 157.205) file a protest to the request. If no protest 
is filed within the time allowed therefore, the proposed activity shall 
be deemed to be authorized effective the day after the time allowed for 
protest. If a protest is filed and not withdrawn within 30 days after 
the time allowed for filing a protest, the instant request shall be 
treated as an application for authorization pursuant to section 7 of 
the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record

[[Page 80761]]

for this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenter's will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenter's will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentary, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the internet in lieu of paper. See 18 
CFR 385.2001(a) (1) (iii) and the instructions on the Commission's Web 
site (www.ferc.gov) under the ``e-Filing'' link. Persons unable to file 
electronically should submit original and 5 copies of the protest or 
intervention to the Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426.

    Dated: December 21, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-32572 Filed 12-24-15; 8:45 am]
 BILLING CODE 6717-01-P