Florida Southeast Connection, LLC; Transcontinental Gas Pipe Line Company, LLC; Sabal Trail Transmission, LLC; Notice of Availability of the Final Environmental Impact Statement for the Proposed Southeast Market Pipelines Project, 80354-80355 [2015-32402]
Download as PDF
80354
Federal Register / Vol. 80, No. 247 / Thursday, December 24, 2015 / Notices
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Dated: December 18, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–32398 Filed 12–23–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–77–000]
Tennessee Gas Pipeline Company,
L.L.C.; Notice of Schedule for
Environmental Review of the Broad
Run Expansion Project
mstockstill on DSK4VPTVN1PROD with NOTICES
On January 30, 2015, Tennessee Gas
Pipeline Company, L.L.C. (Tennessee)
filed an application in Docket No.
CP15–77–000 pursuant to sections 7(b)
and 7(c) of the Natural Gas Act,
requesting a certificate of public
convenience and necessity to construct,
operate, and maintain certain natural
gas pipeline facilities, and authorization
to abandon certain facilities, collectively
known as the Broad Run Expansion
Project (Project). The Project purpose is
to provide an additional 200,000
dekatherms per day of firm incremental
transportation service through
construction of new compressor stations
and replacement of compression
facilities in West Virginia, Kentucky;
and Tennessee.
On February 12, 2015, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. The
notice alerted agencies responsible for
issuing federal authorizations of the
requirement to complete necessary
reviews and reach a final decision on a
request for a federal authorization
within 90 days of the date of issuance
of the Environmental Assessment (EA)
prepared by Commission staff. This
Notice of Schedule identifies the
Commission staff’s planned schedule for
the completion of the EA for the Project.
Schedule for Environmental Review
Issuance of EA
March 11, 2016
90-day Federal Authorization Decision
Deadline
June 9, 2016
If a schedule change becomes
necessary, additional notice will be
provided so the relevant agencies are
kept informed of the Project’s progress.
VerDate Sep<11>2014
17:57 Dec 23, 2015
Jkt 238001
Project Description
Tennessee proposes to build four new
compressor stations and add
compression at two existing compressor
stations. Tennessee also proposes to
improve efficiency and reduce certain
emissions by replacing older existing
compression facilities on its system
with newer compressor units.
The Project would include
construction and operation of the
following facilities:
• Two new compressor stations in
Kanawha County, West Virginia, to be
known as the Tyler Mountain
Compressor Station (CS 118A) and the
Rocky Fork Compressor Station (CS
119A);
• a new compressor station in
Madison County, Kentucky, to be
known as the Richmond Compressor
Station (CS 875);
• a new compressor station in
Davidson County, Tennessee, to be
known as the Pinnacle Compressor
Station (CS 563); and
• modifications (including
abandonment and replacement of
certain compression units, system
components, and associated facilities) at
the existing Clay City Compressor
Station in Powell County, Kentucky (CS
106), and the existing Catlettsburg
Compressor Station in Boyd County,
Kentucky (CS 114).
Background
On May 1, 2015, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Proposed Broad Run Expansion Project
and Request for Comments on
Environmental Issues (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
Tennessee’s application and the NOI,
the Commission received comments
from many affected landowners,
interested individuals and
organizations, elected officials, and
agencies. Commentors included U.S.
Representative Andy Barr, Kentucky
State Representative Terry Mills, U.S.
Fish and Wildlife Service, Kentucky
Department for Environmental
Protection, Madison County Fiscal
Court, Allegheny Defense Project,
Concerned Citizens for a Safe
Environment, Freshwater
Accountability Project, Heartwood,
Ohio Valley Environmental Coalition,
Tennessee Valley Authority, ByFaith
Farm LLC, and Walden’s Puddle
Wildlife Rehabilitation Center.
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
The primary issues raised by the
commentors included concerns about
potential impacts on organic farms and
wildlife, including Walden’s Puddle
Wildlife Rehabilitation Center; air
quality and noise impacts; public safety;
and aspects of the FERC process.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time spent
researching proceedings by
automatically providing notification of
these filings, document summaries, and
direct links to the documents. Go to
www.ferc.gov/docs-filing/
esubscription.asp.
The FERC’s eLibrary system can also
be used to search formal issuances and
submittals from the public docket. To
use, select the ‘‘eLibrary’’ link, select
‘‘General Search’’ from the eLibrary
menu located at www.ferc.gov/docsfiling/elibrary.asp, enter the selected
date range and ‘‘Docket Number’’
excluding the last three digits (i.e.,
CP15–77), and follow the instructions.
For assistance with access to eLibrary,
the helpline can be reached at (866)
208–3676, TTY (202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Web site also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov).
Dated: December 18, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–32403 Filed 12–23–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP14–554–000; CP15–16–000;
CP15–17–000]
Florida Southeast Connection, LLC;
Transcontinental Gas Pipe Line
Company, LLC; Sabal Trail
Transmission, LLC; Notice of
Availability of the Final Environmental
Impact Statement for the Proposed
Southeast Market Pipelines Project
The staff of the Federal Energy
Regulatory Commission (FERC or
E:\FR\FM\24DEN1.SGM
24DEN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 247 / Thursday, December 24, 2015 / Notices
Commission) has prepared a final
environmental impact statement (EIS)
for the Hillabee Expansion, Sabal Trail,
and Florida Southeast Connection (FSC)
Projects as proposed by
Transcontinental Gas Pipe Line
Company, LLC (Transco), Sabal Trail
Transmission, LLC (Sabal Trail), and
Florida Southeast Connection, LLC
(FSC), respectively, in the abovereferenced dockets. These are separate,
but connected, natural gas transmission
pipeline projects collectively referred to
as the Southeast Market Pipelines (SMP)
Project. The applicants request
authorization to construct and operate a
total of about 686.0 miles of natural gas
transmission pipeline and associated
facilities, six new natural gas-fired
compressor stations, and modify
existing compressor stations in
Alabama, Georgia, and Florida. The
SMP Project would provide about 1.1
billion cubic feet per day of natural gas
to meet growing demands by the electric
generation, distribution, and end use
markets in Florida and the southeast
United States.
The final EIS assesses the potential
environmental effects of the
construction and operation of the SMP
Project in accordance with the
requirements of the National
Environmental Policy Act (NEPA). The
FERC staff concludes that approval of
the SMP Project would have some
adverse environmental impacts;
however, these impacts would be
reduced to less-than-significant levels
with the implementation of the
applicants’ proposed mitigation and the
additional measures recommended in
the final EIS.
The U.S. Army Corps of Engineers
(USACE) participated as a cooperating
agency in the preparation of the final
EIS. The USACE has jurisdiction by law
or special expertise with respect to
resources potentially affected by the
proposals and participate in the NEPA
analysis. The USACE may adopt and
use the EIS as it has jurisdictional
authority pursuant to section 404 of the
Clean Water Act, which governs the
discharge of dredged or fill material into
waters of the United States; section 10
of the Rivers and Harbors Act, which
regulates any work or structures that
potentially affect the navigable capacity
of navigable waters of the United States;
and section 14 of the Rivers and Harbors
Act which regulates the temporary
occupation of water-related structures
constructed by the United States.
Although the cooperating agency
provides input to the conclusions and
recommendations presented in the final
EIS, the agency will present its own
VerDate Sep<11>2014
17:57 Dec 23, 2015
Jkt 238001
conclusions and recommendations in its
Record of Decision for the project.
The final EIS of the SMP Project
addresses the potential environmental
effects of the construction and operation
of the following project facilities:
The Hillabee Expansion Project would
include:
• Approximately 43.5 miles of new
42- and 48-inch-diameter natural gas
pipeline loop 1 in Alabama;
• one new compressor station in
Choctaw County, Alabama and
modifications to three existing
compressor stations in Dallas, Chilton,
and Coosa Counties, Alabama; and
• installation of pig 2 launchers/
receivers and mainline valves (MLVs).
The Sabal Trail Project would
include:
• approximately 516.2 miles of new
natural gas pipeline in Alabama,
Georgia, and Florida, including:
Æ 481.6 miles of 36-inch-diameter
mainline pipeline in Alabama, Georgia,
and Florida;
Æ the 21.5-mile-long, 24-inchdiameter Citrus County Line in Florida;
and
Æ the 13.1-mile-long, 36-inchdiameter Hunters Creek Line in Florida;
• five new compressor stations in
Tallapoosa County, Alabama; Dougherty
County, Georgia; and Suwannee,
Marion, and Osceola Counties, Florida;
• subsequent modifications to two of
the new compressor stations in
Dougherty County, Georgia and
Suwannee County, Florida; and
• installation of pig launchers/
receivers, MLVs, and meter and
regulating stations.
The FSC Project would include:
• approximately 126.3 miles of new
30- and 36-inch-diameter natural gas
pipeline in Florida; and
• installation of pig launchers/
receivers, MLVs, and meter and
regulating stations.
The FERC staff mailed copies of the
final EIS to federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American tribes;
potentially affected landowners and
other interested individuals and groups;
newspapers and libraries in the project
area; and parties to this proceeding.
Paper copy versions of the final EIS
were mailed to those specifically
requesting them; all others received a
1 A loop is a segment of pipe that is installed
adjacent to an existing pipeline and connected to
it at both ends. A loop generally allows more gas
to move through the system.
2 A pig is an internal tool that can be used to
clean and dry a pipeline and/or to inspect it for
damage or corrosion.
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
80355
CD version. In addition, the final EIS is
available for public viewing on the
FERC’s Web site (www.ferc.gov) using
the eLibrary link. A limited number of
copies are available for distribution and
public inspection at: Federal Energy
Regulatory Commission, Public
Reference Room, 888 First Street NE.,
Room 2A, Washington, DC 20426, (202)
502–8371.
Additional information about the
SMP Project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search,’’ and enter the docket
number excluding the last three digits in
the Docket Number field (i.e., CP14–
554, CP15–16, and CP15–17). Be sure
you have selected an appropriate date
range. For assistance, please contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676; for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription that
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Dated: December 18, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–32402 Filed 12–23–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. IC16–5–000]
Commission Information Collection
Activities; Consolidated Comment
Request; Extension
Federal Energy Regulatory
Commission.
ACTION: Notice of information
collections and request for comments.
AGENCY:
In compliance with the
requirements of the Paperwork
Reduction Act of 1995, 44 U.S.C.
3506(c)(2)(A), the Federal Energy
Regulatory Commission (Commission or
SUMMARY:
E:\FR\FM\24DEN1.SGM
24DEN1
Agencies
[Federal Register Volume 80, Number 247 (Thursday, December 24, 2015)]
[Notices]
[Pages 80354-80355]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-32402]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP14-554-000; CP15-16-000; CP15-17-000]
Florida Southeast Connection, LLC; Transcontinental Gas Pipe Line
Company, LLC; Sabal Trail Transmission, LLC; Notice of Availability of
the Final Environmental Impact Statement for the Proposed Southeast
Market Pipelines Project
The staff of the Federal Energy Regulatory Commission (FERC or
[[Page 80355]]
Commission) has prepared a final environmental impact statement (EIS)
for the Hillabee Expansion, Sabal Trail, and Florida Southeast
Connection (FSC) Projects as proposed by Transcontinental Gas Pipe Line
Company, LLC (Transco), Sabal Trail Transmission, LLC (Sabal Trail),
and Florida Southeast Connection, LLC (FSC), respectively, in the
above-referenced dockets. These are separate, but connected, natural
gas transmission pipeline projects collectively referred to as the
Southeast Market Pipelines (SMP) Project. The applicants request
authorization to construct and operate a total of about 686.0 miles of
natural gas transmission pipeline and associated facilities, six new
natural gas-fired compressor stations, and modify existing compressor
stations in Alabama, Georgia, and Florida. The SMP Project would
provide about 1.1 billion cubic feet per day of natural gas to meet
growing demands by the electric generation, distribution, and end use
markets in Florida and the southeast United States.
The final EIS assesses the potential environmental effects of the
construction and operation of the SMP Project in accordance with the
requirements of the National Environmental Policy Act (NEPA). The FERC
staff concludes that approval of the SMP Project would have some
adverse environmental impacts; however, these impacts would be reduced
to less-than-significant levels with the implementation of the
applicants' proposed mitigation and the additional measures recommended
in the final EIS.
The U.S. Army Corps of Engineers (USACE) participated as a
cooperating agency in the preparation of the final EIS. The USACE has
jurisdiction by law or special expertise with respect to resources
potentially affected by the proposals and participate in the NEPA
analysis. The USACE may adopt and use the EIS as it has jurisdictional
authority pursuant to section 404 of the Clean Water Act, which governs
the discharge of dredged or fill material into waters of the United
States; section 10 of the Rivers and Harbors Act, which regulates any
work or structures that potentially affect the navigable capacity of
navigable waters of the United States; and section 14 of the Rivers and
Harbors Act which regulates the temporary occupation of water-related
structures constructed by the United States. Although the cooperating
agency provides input to the conclusions and recommendations presented
in the final EIS, the agency will present its own conclusions and
recommendations in its Record of Decision for the project.
The final EIS of the SMP Project addresses the potential
environmental effects of the construction and operation of the
following project facilities:
The Hillabee Expansion Project would include:
Approximately 43.5 miles of new 42- and 48-inch-diameter
natural gas pipeline loop \1\ in Alabama;
---------------------------------------------------------------------------
\1\ A loop is a segment of pipe that is installed adjacent to an
existing pipeline and connected to it at both ends. A loop generally
allows more gas to move through the system.
---------------------------------------------------------------------------
one new compressor station in Choctaw County, Alabama and
modifications to three existing compressor stations in Dallas, Chilton,
and Coosa Counties, Alabama; and
installation of pig \2\ launchers/receivers and mainline
valves (MLVs).
---------------------------------------------------------------------------
\2\ A pig is an internal tool that can be used to clean and dry
a pipeline and/or to inspect it for damage or corrosion.
---------------------------------------------------------------------------
The Sabal Trail Project would include:
approximately 516.2 miles of new natural gas pipeline in
Alabama, Georgia, and Florida, including:
[cir] 481.6 miles of 36-inch-diameter mainline pipeline in Alabama,
Georgia, and Florida;
[cir] the 21.5-mile-long, 24-inch-diameter Citrus County Line in
Florida; and
[cir] the 13.1-mile-long, 36-inch-diameter Hunters Creek Line in
Florida;
five new compressor stations in Tallapoosa County,
Alabama; Dougherty County, Georgia; and Suwannee, Marion, and Osceola
Counties, Florida;
subsequent modifications to two of the new compressor
stations in Dougherty County, Georgia and Suwannee County, Florida; and
installation of pig launchers/receivers, MLVs, and meter
and regulating stations.
The FSC Project would include:
approximately 126.3 miles of new 30- and 36-inch-diameter
natural gas pipeline in Florida; and
installation of pig launchers/receivers, MLVs, and meter
and regulating stations.
The FERC staff mailed copies of the final EIS to federal, state,
and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American tribes;
potentially affected landowners and other interested individuals and
groups; newspapers and libraries in the project area; and parties to
this proceeding. Paper copy versions of the final EIS were mailed to
those specifically requesting them; all others received a CD version.
In addition, the final EIS is available for public viewing on the
FERC's Web site (www.ferc.gov) using the eLibrary link. A limited
number of copies are available for distribution and public inspection
at: Federal Energy Regulatory Commission, Public Reference Room, 888
First Street NE., Room 2A, Washington, DC 20426, (202) 502-8371.
Additional information about the SMP Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search,'' and enter the docket number
excluding the last three digits in the Docket Number field (i.e., CP14-
554, CP15-16, and CP15-17). Be sure you have selected an appropriate
date range. For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676; for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription that allows you to keep track of all formal issuances and
submittals in specific dockets. This can reduce the amount of time you
spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Dated: December 18, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-32402 Filed 12-23-15; 8:45 am]
BILLING CODE 6717-01-P