Williams Field Services-Gulf Coast Company LP; Notice of Petition for Declaratory Order, 79880-79881 [2015-32269]
Download as PDF
tkelley on DSK3SPTVN1PROD with NOTICES
79880
Federal Register / Vol. 80, No. 246 / Wednesday, December 23, 2015 / Notices
and consist of the following new
facilities: (1) A 140-foot-long, 90-footwide intake channel located
immediately downstream of the Corps’
5th spillway gate on the west side of the
river; (2) a pair of spill gates totaling 84
feet wide located within the proposed
intake channel; (3) a 100-foot-long, 65foot-high, 90-foot-wide intake structure
with 3-inch bar spacing trash racks; (4)
a 150-foot-long, 70-foot-high, 90-footwide reinforced concrete powerhouse;
(5) two turbine-generator units with a
combined capacity of 12.0 MW; (6) a
210-foot-long, 130-foot-wide tailrace; (7)
a 40-foot-long by 40-foot-wide
substation; (8) a 45-foot-long, 69-kV,
overhead transmission line to connect
the project substation to an existing
distribution line; and (9) appurtenant
facilities.
The proposed Allegheny Lock and
Dam Number Two Hydroelectric Project
would be located at RM 6.7 on the
Allegheny River and consist of the
following new facilities: (1) A 170-footwide, 120-foot-long, 70-foot-high intake
structure with two 5-inch bar spacing
trash racks; (2) two 45-foot-wide, 40foot-high spillway bays; (3) an 1,100foot-long, 2.5-foot-high adjustable crest
gate on top of the existing dam crest; (4)
a 170-foot-wide by 180-foot-long
powerhouse along the east side of the
river; (5) three Kaplan turbine-generator
units with a combined installed
capacity of 17.0 MW; (6) a 50-foot-wide
by 60-foot-long substation; (7) a 1,265foot-long, single overhead, 69-kV,
overhead transmission line to connect
the project substation to an existing
distribution line owned by Duquesne
Light Company; and (8) appurtenant
facilities. The average annual generation
would be 81,950 MWh annually.
The proposed Emsworth Locks and
Dam Hydroelectric Project would be
located at RM 6.2 on the Ohio River and
would consist of the following new
facilities: (1) A 205-foot-long, 180-footwide intake channel directing flow to a
30-foot-long, 63.5-foot-high, 180-footwide intake structure with 5-inch bar
spacing trash racks; (2) a 180-foot-long,
77-foot-high, 180-foot-wide reinforced
concrete powerhouse on the south bank
of the river; (3) four turbine-generator
units with a combined capacity of 24
MW; (4) a 380-foot-long, 280-foot-wide
tailrace; (5) a 50-foot-long by 60-footwide substation; (6) a 1,893-foot-long,
69-kV, overhead transmission line to
connect the project substation to an
existing substation; and (7) appurtenant
facilities. The average annual generation
would be 101,300 MWh.
The proposed Emsworth Back
Channel Dam Hydroelectric Project
would be located at RM 6.8 on the Ohio
VerDate Sep<11>2014
18:05 Dec 22, 2015
Jkt 238001
River and consist of the following new
facilities: (1) A 100-foot-long, 165-footwide intake channel directing flow to a
32-foot-long, 63.5-foot-high, 90-footwide intake structure with 5-inch bar
spacing trash racks; (2) a 150-foot-long,
77-foot-high, 90-foot-wide reinforced
concrete powerhouse on the north bank
of the river; (3) two turbine-generator
units with a combined capacity of 12.0
MW; (4) a 190-foot-long, 105-foot-wide
tailrace; (5) a 50-foot-long by 60-footwide substation; (6) a 3,758-foot-long,
69-kV, overhead transmission line to
connect the project substation to an
existing substation; and (7) appurtenant
facilities. The average annual generation
would be 53,500 MWh.
The proposed Montgomery Locks and
Dam Hydroelectric Project would be
located at RM 31.7 on the Ohio River
and consist of the following new
facilities: (1) A 340-foot-long, 205-footwide intake channel directing flow to a
150-foot-long, 90-foot-high, 205-footwide intake structure with 5-inch bar
spacing trash racks; (2) a 315-foot-long,
105-foot-high, 205-foot-wide reinforced
concrete powerhouse on the north bank
of the river; (3) three turbine-generator
units with a combined capacity of 42
MW; (4) a 280-foot-long, 210-foot-wide
tailrace; (5) a 50-foot-long by 60-footwide substation; (6) a 392-foot-long, 69kV, overhead transmission line to
connect the project substation to an
existing distribution line; and (7)
appurtenant facilities. The average
annual generation would be 194,370
MWh.
The applicants propose to operate
each of the ten projects in a ‘‘run-ofriver’’ mode using flows made available
by the Corps. The proposed projects
would not change existing flow releases
or water surface elevations upstream or
downstream of the proposed projects.
m. A copy of each application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. Copies are also
available for inspection and
reproduction at the address in item h
above.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS,’’ ‘‘REPLY
COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
PO 00000
Frm 00064
Fmt 4703
Sfmt 4703
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to these or other pending
projects. For assistance, contact FERC
Online Support.
n. Public notice of the filing of the
initial development applications, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: December 17, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–32272 Filed 12–22–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–32–000]
Williams Field Services—Gulf Coast
Company LP; Notice of Petition for
Declaratory Order
Take notice that on December 11,
2015, and supplemented on December
16, 2015, pursuant to section 207(a)(2)
of the Federal Energy Regulatory
Commission’s (Commission) Rules of
E:\FR\FM\23DEN1.SGM
23DEN1
tkelley on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 246 / Wednesday, December 23, 2015 / Notices
Practice and Procedure, 18 CFR
385.207(a)(2) (2014), Williams Field
Services—Gulf Coast Company LP
(Williams Gulf Coast) submitted a
petition for declaratory order seeking a
ruling that certain natural gas pipeline
and appurtenant facilities (WGC
Lateral), to be constructed in support of
a new ultra-deep water oil and gas
production project, will perform a
gathering function and therefore will be
exempt from the Commission’s
jurisdiction pursuant to section l(b) of
the Natural Gas Act, 15 U.S.C. 717, et
seq.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Petitioner.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on January 7, 2016.
Dated: December 17, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–32269 Filed 12–22–15; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
18:05 Dec 22, 2015
Jkt 238001
DEPARTMENT OF ENERGY
Southwestern Power Administration
Sam Rayburn Dam Project Power Rate
Southwestern Power
Administration, DOE.
ACTION: Notice of Rate Order.
AGENCY:
Pursuant to Delegation Order
Nos. 00–037.00A, effective October 25,
2013, and 00–001.00F, effective
November 17, 2014, the Deputy
Secretary has approved and placed into
effect on an interim basis Rate Order No.
SWPA–69, which increases the power
rate for the Sam Rayburn Dam Project
(Rayburn) pursuant to the Rayburn Rate
Schedule (SRD–15) to supersede the
existing rate schedule.
DATES: The effective period for the rate
schedule specified in Rate Order No.
SWPA–69 is January 1, 2016, through
September 30, 2019.
FOR FURTHER INFORMATION CONTACT: Mr.
Marshall Boyken, Senior Vice President,
Chief Operating Officer, Southwestern
Power Administration, U.S. Department
of Energy, Williams Center Tower I, One
West Third Street, Tulsa, Oklahoma
74103, (918) 595–6646,
marshall.boyken@swpa.gov.
SUPPLEMENTARY INFORMATION: Rate Order
No. SWPA–69, which has been
approved and placed into effect on an
interim basis, increases the power rate
for Rayburn pursuant to the following
rate schedule:
SUMMARY:
Rate Schedule SRD–15, Wholesale Rates
for Hydro Power and Energy Sold to Sam
Rayburn Dam Electric Cooperative, Inc.
(Contract No. DE–PM75–92SW00215)
The rate schedule supersedes the
existing rate schedule shown below:
Rate Schedule SRD–13, Wholesale Rates
for Hydro Power and Energy Sold to Sam
Rayburn Dam Electric Cooperative, Inc.
(Contract No. DE–PM75–92SW00215)
(superseded by SRD–15)
Southwestern Power Administration’s
(Southwestern) Administrator has
determined, based on the 2015 Rayburn
Current Power Repayment Study, that
the existing power rate will not satisfy
cost recovery criteria specified in
Department of Energy Order No. RA
6120.2 and Section 5 of the Flood
Control Act of 1944. The finalized 2015
Rayburn Power Repayment Studies
indicate that an increase in annual
revenue of $333,672, or 7.9 percent,
beginning January 1, 2016, will satisfy
cost recovery criteria for Rayburn. The
proposed Rayburn rate schedule would
increase annual revenues from
$4,230,120 to $4,563,792, to recover the
costs associated with increased
PO 00000
Frm 00065
Fmt 4703
Sfmt 4703
79881
operations and maintenance costs as
well as increased interest expense
associated with investments and
replacements in the hydroelectric
generating facilities.
The Administrator has followed title
10, part 903 subpart A, of the Code of
Federal Regulations (10 CFR part 903),
‘‘Procedures for Public Participation in
Power and Transmission Rate
Adjustments and Extensions’’ in
connection with the proposed rate
schedule. On October 9, 2015,
Southwestern published notice in the
Federal Register, (80 FR 61206), of the
proposed power rate increase for
Rayburn. Southwestern provided a 30day comment period as an opportunity
for customers and other interested
members of the public to review and
comment on the proposed power rate
increase with written comments due by
November 9, 2015. Southwestern did
not hold the combined Public
Information and Comment Forum
(Forum) because Southwestern did not
receive any requests to hold the Forum.
One comment was received from Gillis,
Borchardt and Barthel, LLP, on behalf of
the Sam Rayburn Dam Electric
Cooperative, Inc., which stated they had
no objection to the proposed rate
adjustment.
Information regarding this rate
proposal, including studies and other
supporting material, is available for
public review and comment in the
offices of Southwestern Power
Administration, Williams Center Tower
I, One West Third Street, Tulsa,
Oklahoma 74103. Following review of
Southwestern’s proposal within the
Department of Energy, I approved Rate
Order No. SWPA–69 which increases
the existing Rayburn power rate to
$4,563,792 per year for the period
January 1, 2016 through September 30,
2019.
Dated: December 17, 2015.
Elizabeth Sherwood-Randall,
Deputy Secretary.
DEPARTMENT OF ENERGY
DEPUTY SECRETARY OF ENERGY
In the matter of: Southwestern Power
Administration Sam Rayburn Dam Project
Rate
Rate Order No. SWPA–69
Order Confirming, Approving and
Placing Increased Power Rate Schedule
in Effect on an Interim Basis
Pursuant to Sections 302(a) and
301(b) of the Department of Energy
Organization Act, Public Law 95–91, the
functions of the Secretary of the Interior
and the Federal Power Commission
under Section 5 of the Flood Control
E:\FR\FM\23DEN1.SGM
23DEN1
Agencies
[Federal Register Volume 80, Number 246 (Wednesday, December 23, 2015)]
[Notices]
[Pages 79880-79881]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-32269]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP16-32-000]
Williams Field Services--Gulf Coast Company LP; Notice of
Petition for Declaratory Order
Take notice that on December 11, 2015, and supplemented on December
16, 2015, pursuant to section 207(a)(2) of the Federal Energy
Regulatory Commission's (Commission) Rules of
[[Page 79881]]
Practice and Procedure, 18 CFR 385.207(a)(2) (2014), Williams Field
Services--Gulf Coast Company LP (Williams Gulf Coast) submitted a
petition for declaratory order seeking a ruling that certain natural
gas pipeline and appurtenant facilities (WGC Lateral), to be
constructed in support of a new ultra-deep water oil and gas production
project, will perform a gathering function and therefore will be exempt
from the Commission's jurisdiction pursuant to section l(b) of the
Natural Gas Act, 15 U.S.C. 717, et seq.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date.
Anyone filing a motion to intervene or protest must serve a copy of
that document on the Petitioner.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 5 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive email
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5:00 p.m. Eastern Time on January 7, 2016.
Dated: December 17, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-32269 Filed 12-22-15; 8:45 am]
BILLING CODE 6717-01-P