Tennessee Gas Pipeline Company, L.L.C.; Notice of Intent To Prepare an Environmental Assessment for the Proposed Southwest Louisiana Supply Project and Request for Comments on Environmental Issues, 77621-77623 [2015-31473]
Download as PDF
Federal Register / Vol. 80, No. 240 / Tuesday, December 15, 2015 / Notices
77621
1022ST—MEETING, REGULAR MEETING—Continued
[December 17, 2015, 10 a.m.]
Item No.
Docket No.
Company
HYDRO
H–1 ........
H–2 ........
P–349–173 ..................................................
P–2210–252 ................................................
Alabama Power Company.
Appalachian Power Company.
CERTIFICATES
C–1 ........
C–2
C–3
C–4
C–5
........
........
........
........
CP14–119–000 ............................................
CP14–120–000 ............................................
CP14–122–000 ............................................
CP15–523–000 ............................................
CP14–501–000 ............................................
CP15–90–000 ..............................................
CP15–132–000 ............................................
A free webcast of this event is
available through www.ferc.gov. Anyone
with Internet access who desires to view
this event can do so by navigating to
www.ferc.gov’s Calendar of Events and
locating this event in the Calendar. The
event will contain a link to its webcast.
The Capitol Connection provides
technical support for the free webcasts.
It also offers access to this event via
television in the DC area and via phone
bridge for a fee. If you have any
questions, visit
www.CapitolConnection.org or contact
Danelle Springer or David Reininger at
703–993–3100.
Immediately following the conclusion
of the Commission Meeting, a press
briefing will be held in the Commission
Meeting Room. Members of the public
may view this briefing in the designated
overflow room. This statement is
intended to notify the public that the
press briefings that follow Commission
meetings may now be viewed remotely
at Commission headquarters, but will
not be telecast through the Capitol
Connection service.
Issued: December 10, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–31605 Filed 12–11–15; 4:15 pm]
asabaliauskas on DSK5VPTVN1PROD with NOTICES
BILLING CODE 6717–01–P
VerDate Sep<11>2014
17:08 Dec 14, 2015
Jkt 238001
Trunkline Gas Company, LLC.
Lake Charles LNG Export Company, LLC and Lake Charles LNG Company, LLC.
Lake Charles LNG Company, LLC.
American Midstream (Midla), LLC.
National Fuel Gas Supply Corporation.
Texas Eastern Transmission, LP.
Kern River Gas Transmission Company.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–12–000]
Tennessee Gas Pipeline Company,
L.L.C.; Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Southwest Louisiana Supply
Project and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Southwest Louisiana Supply Project
(Project) involving construction and
operation of facilities by Tennessee Gas
Pipeline Company, L.L.C. (Tennessee)
in Madison, Franklin, Richland, and
Rapides Parishes, Louisiana. The
Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before January 11,
2016.
If you sent comments on this project
to the Commission before the opening of
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
this docket on October 26, 2015, you
will need to file those comments in
Docket No. CP16–12–000 to ensure they
are considered as part of this
proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
Tennessee provided landowners with
a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
E:\FR\FM\15DEN1.SGM
15DEN1
77622
Federal Register / Vol. 80, No. 240 / Tuesday, December 15, 2015 / Notices
asabaliauskas on DSK5VPTVN1PROD with NOTICES
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (CP16–12–
000) with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Room 1A, Washington, DC 20426.
Summary of the Proposed Project
The purpose of the Southwest
Louisiana Supply Project is to provide
295,000 dekatherms per day of firm
natural gas capacity to Tennessee’s 800
Line. The Southwest Louisiana Supply
Project would consist of construction
and modification of the following
facilities:
• Construction of a new 2.4-milelong, 30-inch-diameter lateral pipeline
to be known as the Delhi North Lateral
and two new meter station
interconnects to be known as the
Midcontinent Express Pipeline Meter
Station (MEP Meter Station) and the
Gulf Crossing Pipeline Meter Station
(Gulf Crossing Meter Station) in
Madison Parish, Louisiana;
• construction of a new 1.4-mile-long30-inch-diameter lateral pipeline to be
known as the Delhi South Latera, three
new meter station interconnects to be
known as the Enable Midstream
Partners Meter Station (Enable Meter
Station), the Gulf South Pipeline Meter
Station (Gulf South Meter Station), and
the Tiger Pipeline Meter Station (Tiger
Meter Station) in Franklin and Richland
Parishes, Louisiana;
• construction of a new compressor
station to be known as the Delhi
Compressor Station 836A in Franklin,
Parish, Louisiana; and
• modifications at the Alexandria
Compressor Station, including turbine
replacement in Rapides Parish,
Louisiana.
VerDate Sep<11>2014
17:08 Dec 14, 2015
Jkt 238001
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would disturb approximately 108.4
acres of land for the aboveground
facilities and the pipeline. Following
construction, Tennessee would
maintain about 76.5 acres for permanent
operation of the project’s facilities; the
remaining acreage would be restored
and revert to former uses.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.4 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
E:\FR\FM\15DEN1.SGM
15DEN1
Federal Register / Vol. 80, No. 240 / Tuesday, December 15, 2015 / Notices
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
the mailing list, please return the
attached Information Request (appendix
2).
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP16–12–000). Be sure you
have selected an appropriate date range.
For assistance, please contact FERC
Online Support at FercOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
VerDate Sep<11>2014
17:08 Dec 14, 2015
Jkt 238001
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: December 9, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–31473 Filed 12–14–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. OR16–7–000]
Chicap Pipe Line Company; Notice Of
Petiton For Declaratory Order
Take notice that on December 8, 2015,
pursuant to Rule 207(a)(2) of the
Commission’s Rules of Practice and
Procedure, 18 CFR 385.207(a)(2)(2015),
Chicap Pipe Line Company (Chicap)
filed a petition requesting a declaratory
order approving the overall tariff and
rate structure, prorationing provisions,
and other terms of service for the
expansion of Chicap’s existing Blue
Island Lateral crude oil pipeline
(Project). The Project is intended to
increase flow rates and add new bidirectional capability between Blue
Island, Illinois to Mokena, Illinois, as
more fully explained in the petition.
Any person desiring to intervene or to
protest in this proceeding must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Petitioner.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
77623
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
The filings in the above proceeding
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive email
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please
email FERCOnlineSupport@ferc.gov or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Comment Date: 5:00 p.m. Eastern time
on January 8, 2016.
Dated: December 9, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–31477 Filed 12–14–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2633–022; ER10–
2570–022; ER10–2717–022; ER10–3140–
021;ER13–55–012.
Applicants: Birchwood Power
Partners, L.P., Shady Hills Power
Company, L.L.C., EFS Parlin Holdings,
LLC, Inland Empire Energy Center, LLC,
Homer City Generation, L.P.
Description: Notice of Non-Material
Change in Status of the GE Companies.
Filed Date: 12/8/15.
Accession Number: 20151208–5217.
Comments Due: 5 p.m. ET 12/29/15.
Docket Numbers: ER15–192–002.
Applicants: Arizona Public Service
Company.
Description: Compliance filing:
Service Agreement Nos. 338, 339, 349,
E:\FR\FM\15DEN1.SGM
15DEN1
Agencies
[Federal Register Volume 80, Number 240 (Tuesday, December 15, 2015)]
[Notices]
[Pages 77621-77623]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-31473]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP16-12-000]
Tennessee Gas Pipeline Company, L.L.C.; Notice of Intent To
Prepare an Environmental Assessment for the Proposed Southwest
Louisiana Supply Project and Request for Comments on Environmental
Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Southwest Louisiana Supply
Project (Project) involving construction and operation of facilities by
Tennessee Gas Pipeline Company, L.L.C. (Tennessee) in Madison,
Franklin, Richland, and Rapides Parishes, Louisiana. The Commission
will use this EA in its decision-making process to determine whether
the project is in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before January 11, 2016.
If you sent comments on this project to the Commission before the
opening of this docket on October 26, 2015, you will need to file those
comments in Docket No. CP16-12-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
Tennessee provided landowners with a fact sheet prepared by the
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do
I Need To Know?'' This fact sheet addresses a number of typically asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or efiling@ferc.gov. Please carefully
[[Page 77622]]
follow these instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(CP16-12-000) with your submission: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A,
Washington, DC 20426.
Summary of the Proposed Project
The purpose of the Southwest Louisiana Supply Project is to provide
295,000 dekatherms per day of firm natural gas capacity to Tennessee's
800 Line. The Southwest Louisiana Supply Project would consist of
construction and modification of the following facilities:
Construction of a new 2.4-mile-long, 30-inch-diameter
lateral pipeline to be known as the Delhi North Lateral and two new
meter station interconnects to be known as the Midcontinent Express
Pipeline Meter Station (MEP Meter Station) and the Gulf Crossing
Pipeline Meter Station (Gulf Crossing Meter Station) in Madison Parish,
Louisiana;
construction of a new 1.4-mile-long-30-inch-diameter
lateral pipeline to be known as the Delhi South Latera, three new meter
station interconnects to be known as the Enable Midstream Partners
Meter Station (Enable Meter Station), the Gulf South Pipeline Meter
Station (Gulf South Meter Station), and the Tiger Pipeline Meter
Station (Tiger Meter Station) in Franklin and Richland Parishes,
Louisiana;
construction of a new compressor station to be known as
the Delhi Compressor Station 836A in Franklin, Parish, Louisiana; and
modifications at the Alexandria Compressor Station,
including turbine replacement in Rapides Parish, Louisiana.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb approximately
108.4 acres of land for the aboveground facilities and the pipeline.
Following construction, Tennessee would maintain about 76.5 acres for
permanent operation of the project's facilities; the remaining acreage
would be restored and revert to former uses.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries
[[Page 77623]]
and newspapers. This list also includes all affected landowners (as
defined in the Commission's regulations) who are potential right-of-way
grantors, whose property may be used temporarily for project purposes,
or who own homes within certain distances of aboveground facilities,
and anyone who submits comments on the project. We will update the
environmental mailing list as the analysis proceeds to ensure that we
send the information related to this environmental review to all
individuals, organizations, and government entities interested in and/
or potentially affected by the proposed project.
If we publish and distribute the EA, copies of the EA will be sent
to the environmental mailing list for public review and comment. If you
would prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the ``Document-less Intervention Guide'' under the ``e-filing'' link on
the Commission's Web site. Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP16-
12-000). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: December 9, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-31473 Filed 12-14-15; 8:45 am]
BILLING CODE 6717-01-P