License Renewal for Davis-Besse Nuclear Power Station, Unit 1, 77380-77381 [2015-31418]
Download as PDF
77380
Federal Register / Vol. 80, No. 239 / Monday, December 14, 2015 / Notices
All meetings are Eastern time
and ending times are approximate:
Design (review of applications): This
meeting will be closed. Date and time:
January 11, 2016; 11:00 a.m. to 1:30 p.m.
Design (review of applications): This
meeting will be closed. Date and time:
January 11, 2016; 2:30 p.m. to 5:00 p.m.
Design (review of applications): This
meeting will be closed. Date and time:
January 12, 2016; 11:00 a.m. to 1:30 p.m.
Design (review of applications): This
meeting will be closed. Date and time:
January 12, 2016; 2:30 p.m. to 5:00 p.m.
State Partnerships (review of
applications): This meeting will be
open. Date and time: January 12, 2016;
3:00 p.m. to 5:00 p.m.
State Partnerships (review of
partnership agreements): This meeting
will be open. Date and time: January 13,
2016; 3:00 p.m. to 5:00 p.m.
State Partnerships (review of
applications): This meeting will be
open. Date and time: January 14, 2016;
3:00 p.m. to 5:00 p.m.
Design (review of applications): This
meeting will be closed. Date and time:
January 19, 2016; 11:00 a.m. to 1:30 p.m.
Design (review of applications): This
meeting will be closed. Date and time:
January 19, 2016; 2:30 p.m. to 5:00 p.m.
Folk & Traditional Arts (review of
nominations): This meeting will be
closed. Date and time: January 19, 2016;
2:00 p.m. to 4:00 p.m.
Folk & Traditional Arts (review of
nominations): This meeting will be
closed. Date and time: January 22, 2016;
2:00 p.m. to 4:00 p.m.
Research (review of applications):
This meeting will be closed. Date and
time: January 25, 2016; 2:00 p.m. to 4:30
p.m.
Research (review of applications):
This meeting will be closed. Date and
time: January 26, 2016; 2:00 p.m. to 4:30
p.m.
Regional Partnerships (review of
partnership agreements): This meeting
will be open. Date and time: January 27,
2016; 3:00 p.m. to 4:00 p.m.
Folk and Traditional Arts (review of
applications): This meeting will be
closed. Date and time: January 28, 2016;
2:00 p.m. to 4:00 p.m.
ADDRESSES: National Endowment for the
Arts, Constitution Center, 400 7th St.
SW., Washington, DC, 20506.
FOR FURTHER INFORMATION CONTACT:
Further information with reference to
these meetings can be obtained from Ms.
Kathy Plowitz-Worden, Office of
Guidelines & Panel Operations, National
Endowment for the Arts, Washington,
DC, 20506; plowitzk@arts.gov, or call
202/682–5691.
SUPPLEMENTARY INFORMATION: The
closed portions of meetings are for the
mstockstill on DSK4VPTVN1PROD with NOTICES
DATES:
VerDate Sep<11>2014
17:36 Dec 11, 2015
Jkt 238001
purpose of Panel review, discussion,
evaluation, and recommendations on
financial assistance under the National
Foundation on the Arts and the
Humanities Act of 1965, as amended,
including information given in
confidence to the agency. In accordance
with the determination of the Chairman
of February 15, 2012, these sessions will
be closed to the public pursuant to
subsection (c)(6) of section 552b of title
5, United States Code.
Dated: December 9, 2015.
Kathy Plowitz-Worden,
Panel Coordinator, National Endowment for
the Arts.
[FR Doc. 2015–31345 Filed 12–11–15; 8:45 am]
BILLING CODE 7537–01–P
NATIONAL SCIENCE FOUNDATION
Notice of Permits Issued Under the
Antarctic Conservation Act of 1978
National Science Foundation.
ACTION: Notice of permits issued under
the Antarctic Conservation of 1978.
AGENCY:
The National Science
Foundation (NSF) is required to publish
notice of permits issued under the
Antarctic Conservation Act of 1978.
This is the required notice.
FOR FURTHER INFORMATION CONTACT:
Nature McGinn, ACA Permit Officer,
Division of Polar Programs, Rm. 755,
National Science Foundation, 4201
Wilson Boulevard, Arlington, VA 22230.
Or by email: ACApermits@nsf.gov.
SUPPLEMENTARY INFORMATION: On August
18, 2015 the National Science
Foundation published a notice in the
Federal Register of a permit application
received. The permit was issued on
December 8, 2015 to:
Angela L. Sremba Permit No. 2016–
006
SUMMARY:
Nadene G. Kennedy,
Polar Coordination Specialist, Division of
Polar Programs.
[FR Doc. 2015–31335 Filed 12–11–15; 8:45 am]
BILLING CODE 7555–01–P
NATIONAL SCIENCE FOUNDATION
Notice of Permits Issued Under the
Antarctic Conservation Act of 1978
National Science Foundation.
Notice of permits issued under
the Antarctic Conservation of 1978,
Public Law 95–541.
AGENCY:
ACTION:
The National Science
Foundation (NSF) is required to publish
notice of permits issued under the
SUMMARY:
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
Antarctic Conservation Act of 1978.
This is the required notice.
FOR FURTHER INFORMATION CONTACT:
Nature McGinn, ACA Permit Officer,
Division of Polar Programs, Rm. 755,
National Science Foundation, 4201
Wilson Boulevard, Arlington, VA 22230.
Or by email: ACApermits@nsf.gov.
SUPPLEMENTARY INFORMATION: On
November 6, 2015 the National Science
Foundation published a notice in the
Federal Register of a permit
modification application received. The
permit was issued on December 8, 2015
to:
Joseph A. Covi Permit No. 2015–015
Nadene G. Kennedy,
Polar Coordination Specialist, Division of
Polar Programs.
[FR Doc. 2015–31337 Filed 12–11–15; 8:45 am]
BILLING CODE 7555–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–346; NRC–2010–0298]
License Renewal for Davis-Besse
Nuclear Power Station, Unit 1
Nuclear Regulatory
Commission.
ACTION: License renewal and record of
decision; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has issued renewed
facility operating license No. NPF–3 to
FirstEnergy Nuclear Operating Company
(FENOC or the licensee), the operator of
the Davis-Besse Nuclear Power Station,
Unit 1. Renewed facility operating
license No. NPF–3 authorizes operation
of Davis-Besse by the licensee at reactor
core power levels not in excess of 2817
megawatts thermal, in accordance with
the provisions of the Davis-Besse
renewed license and technical
specifications. In addition, the NRC has
prepared a record of decision (ROD) that
supports the NRC’s decision to renew
facility operating license No. NPF–3.
DATES: The license renewal of facility
operating license No. NPF–3 was
effective on December 8, 2015.
ADDRESSES: Please refer to Docket ID
NRC–2010–0298 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2010–0298. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
SUMMARY:
E:\FR\FM\14DEN1.SGM
14DEN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 239 / Monday, December 14, 2015 / Notices
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS):You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if that document
is available in ADAMS) is provided the
first time that a document is referenced.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Richard Plasse, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555; telephone: 301–415–1427;
email: Richard.Plasse@nrc.gov.
SUPPLEMENTARY INFORMATION: Notice is
hereby given that the NRC has issued
renewed facility operating license No.
NPF–3 to FirstEnergy Nuclear Operating
Company, the operator of Davis-Besse.
Renewed facility operating license No.
NPF–3 authorizes operation of DavisBesse by the licensee at reactor core
power levels not in excess of 2817
megawatts thermal, in accordance with
the provisions of the Davis-Besse
renewed license and technical
specifications. The NRC’s ROD that
supports the NRC’s decision to renew
facility operating license No. NPF–3 is
available in ADAMS under Accession
No. ML15295A319. As discussed in the
ROD and the final supplemental
environmental impact statement (FSEIS)
for Davis-Besse, Supplement 52 to
NUREG–1437, ‘‘Generic Environmental
Impact Statement for License Renewal
of Nuclear Plants Regarding Davis-Besse
Nuclear Power Station’’ dated April
2015 (ADAMS Accession No.
ML15112A098 for Volume 1 and
ML15113A187 for Volume 2), the NRC
has considered a range of reasonable
alternatives that included natural gas
combined-cycle (NGCC), supercritical
pulverized coal, combination of wind,
solar, and NGCC, and the no action
alternative. The ROD and FSEIS
document the NRC decision for the
VerDate Sep<11>2014
17:36 Dec 11, 2015
Jkt 238001
environmental review that the adverse
environmental impacts of license
renewal for Davis-Besse are not so great
that preserving the option of license
renewal for energy planning
decisionmakers would be unreasonable.
Davis-Besse, is a pressurized water
reactor located in Carroll Township,
Ottawa County, Ohio. The application
for the renewed license, ‘‘License
Renewal Application, Davis-Besse
Nuclear Power Station,’’ dated August
30, 2010, as supplemented by letters
dated through June 29, 2015 (ADAMS
Accession No. ML15180A252),
complied with the standards and
requirements of the Atomic Energy Act
of 1954, as amended (the Act), and the
NRC’s regulations. As required by the
Act and the NRC’s regulations in
Chapter 1 of title 10 of the Code of
Federal Regulations (10 CFR), the NRC
has made appropriate findings, which
are set forth in the license. A public
notice of the proposed issuance of the
renewed license and an opportunity for
a hearing was published in the Federal
Register on October 25, 2010 (75 FR
65528).
For further details with respect to this
action, see: (1) FirstEnergy Nuclear
Operating Company license renewal
application for Davis-Besse Nuclear
Power Station, Unit 1 dated August 20,
1010, as supplemented by letters dated
through June 29, 2015; (2) the NRC’s
safety evaluation report published on
September 3, 2013 (ADAMS Accession
No. ML13248A267); (3) the NRC’s
supplemental safety evaluation report
published on August 10, 2015 (ADAMS
Accession No. ML15196A429); (4) the
NRC’s final environmental impact
statement (NUREG–1437, Supplement
52), for Davis-Besse published in April
2014; and (5) the NRC’s ROD.
Dated at Rockville, Maryland, this 8th day
of December 2015.
For the Nuclear Regulatory Commission.
Christopher G. Miller,
Director, Division of License Renewal, Office
of Nuclear Reactor Regulation.
[FR Doc. 2015–31418 Filed 12–11–15; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2015–0001]
Sunshine Act Meeting Notice
December 14, 21, 28, 2015,
January 4, 11, 18, 2016.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public and Closed.
DATE:
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
77381
Week of December 14, 2015
Tuesday, December 15, 2015
9:00 a.m. Hearing on Construction
Permit for SHINE Medical Isotope
Production Facility: Section 189a.
of the Atomic Energy Act
Proceeding (Public Meeting);
(Contact: Steven Lynch: 301–415–
1524).
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Thursday, December 17, 2015
9:30 a.m. Briefing on Project AIM 2020
(Public Meeting); (Contact: John
Jolicoeur: 301–415–1642).
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Thursday, December 17, 2015
1:00 p.m. Briefing on Digital
Instrumentation and Control (Public
Meeting); (Contact: Daniel Doyle:
301–415–3748).
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Week of December 21, 2015—Tentative
There are no meetings scheduled for
the week of December 21, 2015.
Week of December 28, 2015—Tentative
There are no meetings scheduled for
the week of December 28, 2015.
Week of January 4, 2016—Tentative
There are no meetings scheduled for
the week of January 4, 2016.
Week of January 11, 2016—Tentative
There are no meetings scheduled for
the week of January 11, 2016.
Week of January 18, 2016—Tentative
There are no meetings scheduled for
the week of January 18, 2016.
*
*
*
*
*
The schedule for Commission
meetings is subject to change on short
notice. For more information or to verify
the status of meetings, contact Denise
McGovern at 301–415–0681 or via email
at Denise.McGovern@nrc.gov.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.
E:\FR\FM\14DEN1.SGM
14DEN1
Agencies
[Federal Register Volume 80, Number 239 (Monday, December 14, 2015)]
[Notices]
[Pages 77380-77381]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-31418]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-346; NRC-2010-0298]
License Renewal for Davis-Besse Nuclear Power Station, Unit 1
AGENCY: Nuclear Regulatory Commission.
ACTION: License renewal and record of decision; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued
renewed facility operating license No. NPF-3 to FirstEnergy Nuclear
Operating Company (FENOC or the licensee), the operator of the Davis-
Besse Nuclear Power Station, Unit 1. Renewed facility operating license
No. NPF-3 authorizes operation of Davis-Besse by the licensee at
reactor core power levels not in excess of 2817 megawatts thermal, in
accordance with the provisions of the Davis-Besse renewed license and
technical specifications. In addition, the NRC has prepared a record of
decision (ROD) that supports the NRC's decision to renew facility
operating license No. NPF-3.
DATES: The license renewal of facility operating license No. NPF-3 was
effective on December 8, 2015.
ADDRESSES: Please refer to Docket ID NRC-2010-0298 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2010-0298. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463;
[[Page 77381]]
email: Carol.Gallagher@nrc.gov. For technical questions, contact the
individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS):You may obtain publicly-available documents online in the ADAMS
Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if that document
is available in ADAMS) is provided the first time that a document is
referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Richard Plasse, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555; telephone: 301-415-1427; email: Richard.Plasse@nrc.gov.
SUPPLEMENTARY INFORMATION: Notice is hereby given that the NRC has
issued renewed facility operating license No. NPF-3 to FirstEnergy
Nuclear Operating Company, the operator of Davis-Besse. Renewed
facility operating license No. NPF-3 authorizes operation of Davis-
Besse by the licensee at reactor core power levels not in excess of
2817 megawatts thermal, in accordance with the provisions of the Davis-
Besse renewed license and technical specifications. The NRC's ROD that
supports the NRC's decision to renew facility operating license No.
NPF-3 is available in ADAMS under Accession No. ML15295A319. As
discussed in the ROD and the final supplemental environmental impact
statement (FSEIS) for Davis-Besse, Supplement 52 to NUREG-1437,
``Generic Environmental Impact Statement for License Renewal of Nuclear
Plants Regarding Davis-Besse Nuclear Power Station'' dated April 2015
(ADAMS Accession No. ML15112A098 for Volume 1 and ML15113A187 for
Volume 2), the NRC has considered a range of reasonable alternatives
that included natural gas combined-cycle (NGCC), supercritical
pulverized coal, combination of wind, solar, and NGCC, and the no
action alternative. The ROD and FSEIS document the NRC decision for the
environmental review that the adverse environmental impacts of license
renewal for Davis-Besse are not so great that preserving the option of
license renewal for energy planning decisionmakers would be
unreasonable.
Davis-Besse, is a pressurized water reactor located in Carroll
Township, Ottawa County, Ohio. The application for the renewed license,
``License Renewal Application, Davis-Besse Nuclear Power Station,''
dated August 30, 2010, as supplemented by letters dated through June
29, 2015 (ADAMS Accession No. ML15180A252), complied with the standards
and requirements of the Atomic Energy Act of 1954, as amended (the
Act), and the NRC's regulations. As required by the Act and the NRC's
regulations in Chapter 1 of title 10 of the Code of Federal Regulations
(10 CFR), the NRC has made appropriate findings, which are set forth in
the license. A public notice of the proposed issuance of the renewed
license and an opportunity for a hearing was published in the Federal
Register on October 25, 2010 (75 FR 65528).
For further details with respect to this action, see: (1)
FirstEnergy Nuclear Operating Company license renewal application for
Davis-Besse Nuclear Power Station, Unit 1 dated August 20, 1010, as
supplemented by letters dated through June 29, 2015; (2) the NRC's
safety evaluation report published on September 3, 2013 (ADAMS
Accession No. ML13248A267); (3) the NRC's supplemental safety
evaluation report published on August 10, 2015 (ADAMS Accession No.
ML15196A429); (4) the NRC's final environmental impact statement
(NUREG-1437, Supplement 52), for Davis-Besse published in April 2014;
and (5) the NRC's ROD.
Dated at Rockville, Maryland, this 8th day of December 2015.
For the Nuclear Regulatory Commission.
Christopher G. Miller,
Director, Division of License Renewal, Office of Nuclear Reactor
Regulation.
[FR Doc. 2015-31418 Filed 12-11-15; 8:45 am]
BILLING CODE 7590-01-P