Federal Register / Vol. 80, No. 238 / Friday, December 11, 2015 / Notices
https://www.ferc.gov. Persons unable to
file electronically should submit an
original and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: January 6, 2016.
Dated: December 7, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–31213 Filed 12–10–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP16–22–000; PF15–10–000;
CP16–23–000; PF15–11–000; CP16–24–000]
jstallworth on DSK7TPTVN1PROD with NOTICES
NEXUS Gas Transmission, LLC; Texas
Eastern Transmission, LP; DTE Gas
Company; Notice of Applications
Take notice that on November 20,
2015, NEXUS Gas Transmission, LLC
(NEXUS), 5400 Westheimer Court,
Houston, Texas 77056, filed in Docket
No. CP16–22–000 an application
pursuant to section 7(c) of the Natural
Gas Act (NGA) for authorization: (i) To
construct approximately 255.9 miles of
new, 36-inch-diameter interstate
pipeline in Ohio and Michigan; (ii) to
construct four compressor stations,
totaling 130,000 horsepower (HP); (iii)
to construct various appurtenances
(collectively, the NEXUS Project); (iv) of
its proposed pro forma tariff; (v) for a
Part 157, Subpart F construction
certificate; (vi) for a Part 284, Subpart G
blanket certificate; and (vii) for any
waivers the Commission deems
necessary for the NEXUS Project.
NEXUS states that the proposed
pipeline will have a capacity of 1.5
million dekatherms per day (Dth/d) and
estimates the cost of the NEXUS Project
to be approximately $2,095,267,444.
Additionally, on November 20, 2015,
Texas Eastern Transmission, LP (Texas
Eastern), 5400 Westheimer Court,
Houston, Texas 77056, filed in Docket
No. CP16–23–000 an application
pursuant to sections 7(b) and 7(c) of the
NGA for authorization: (i) To construct
approximately 4.4 miles of 36-inchdiameter pipeline loop in Monroe
County, Ohio; (ii) to construct 1,790 feet
of connecting pipeline to the NEXUS
Project in Columbiana County, Ohio;
(iii) to construct a new 18,800 HP
compressor station in Columbiana
County, Ohio; (iv) to construct a new
9,400 HP compressor unit at its existing
Colerain Compressor Station in Belmont
County, Ohio; (v) to modify Line 73 to
VerDate Sep<11>2014
18:51 Dec 10, 2015
Jkt 238001
allow for bi-directional flow; (vi) to
construct various appurtenances
(collectively, the TEAL Project); (vii) to
abandon by lease to NEXUS 950,155
Dth/d; and (vii) for any waivers the
Commission deems necessary for the
TEAL Project. Texas Eastern estimates
the cost of the TEAL Project to be
approximately $183,519,668.
These applications will be reviewed
contemporaneously with the application
for an operating lease filed by DTE Gas
Company in Docket No. CP16–24–000
on November 24, 2015.
All of the applications are on file with
the Commission and open to public
inspection. The filing is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site Web at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions concerning the
application in Docket No. CP16–22–000
may be directed to Berk Donaldson or
Leanne Sidorkewicz, NEXUS Gas
Transmission LLC, 5400 Westheimer
Court, Houston, Texas 77056, by
telephone at (713) 627–4488, or by
email at bdonaldson@
spectraenergy.com or lsidorkewicz@
spectraenergy.com.
Any questions concerning the
application in Docket No. CP16–23–000
may be directed to Berk Donaldson,
General Manger, Rates and Certificates,
Texas Eastern Transmission, LP, PO Box
1642, Houston, Texas 77251–1642, by
telephone at (713) 624–4488, or by
facsimile at (713) 627–5947.
On December 30, 2014, the
Commission staff granted NEXUS’
request to utilize the Pre-Filing Process
and assigned Docket No. PF15–10–000
to staff’s activities involved in the
NEXUS Project. Now, as of the
November 20, 2015 application, the PreFiling Process for the NEXUS Project
has ended. From this time forward, this
proceeding will be conducted in Docket
No. CP16–22–000, as noted in the
caption of this Notice.
On January 16, 2015, the Commission
staff granted Texas Eastern’s request to
utilize the Pre-Filing Process and
assigned Docket No. PF15–11–000 to
staff’s activities involved in the TEAL
Project. Now, as of the November 20,
2015 application, the Pre-Filing Process
for the TEAL Project has ended. From
this time forward, this proceeding will
be conducted in Docket No. CP16–23–
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
000, as noted in the caption of this
Notice.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice, the
Commission staff will issue a Notice of
Schedule for Environmental Review. If
a Notice of Schedule for Environmental
Review is issued, it will indicate, among
other milestones, the anticipated date
for the Commission staff’s issuance of
the final environmental impact
statement (FEIS) for this proposal. The
issuance of a Notice of Schedule for
Environmental Review will serve to
notify federal and state agencies of the
timing for the completion of all
necessary reviews, and the subsequent
need to complete all federal
authorizations within 90 days of the
date of issuance of the Commission
staff’s FEIS.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
seven copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
E:\FR\FM\11DEN1.SGM
11DEN1
Federal Register / Vol. 80, No. 238 / Friday, December 11, 2015 / Notices
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 7 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time on December 28, 2015.
Dated: December 7, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–31214 Filed 12–10–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
jstallworth on DSK7TPTVN1PROD with NOTICES
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC15–210–000.
Applicants: Dominion Solar Projects
A, Inc., Dominion Solar Projects I, Inc.
Description: Second Clarification to
September 24, 2015 Application for
Authorization Under Section 203 of the
Federal Power Act of Dominion Solar
Projects A, Inc., et al.
Filed Date: 12/4/15.
Accession Number: 20151204–5299.
Comments Due: 5 p.m. ET 12/14/15.
Docket Numbers: EC16–21–000.
Applicants: Sandstone Solar LLC.
Description: Clarification to October
29, 2015 Application for Authorization
Under Section 203 of the Federal Power
Act, Request for Expedited
Consideration and Confidential
Treatment of Sandstone Solar LLC.
Filed Date: 12/3/15.
VerDate Sep<11>2014
14:55 Dec 10, 2015
Jkt 238001
Accession Number: 20151203–5147.
Comments Due: 5 p.m. ET 12/14/15.
Docket Numbers: EC16–46–000.
Applicants: Bicent (California)
Malburg LLC.
Description: Application for
Authorization for Disposition of
Jurisdictional Facilities and Request for
Expedited Action of Bicent (California)
Malburg LLC.
Filed Date: 12/4/15.
Accession Number: 20151204–5293.
Comments Due: 5 p.m. ET 12/28/15.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER16–468–000.
Applicants: FTS Master Tenant 1,
LLC.
Description: Baseline eTariff Filing:
FTS Master Tenant 1 LLC MBR Tariff to
be effective 2/1/2016.
Filed Date: 12/4/15.
Accession Number: 20151204–5249.
Comments Due: 5 p.m. ET 12/28/15.
Docket Numbers: ER16–469–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2015–12–04_Order 1000 CTDS Variance
Analysis Filing to be effective 2/2/2016.
Filed Date: 12/4/15.
Accession Number: 20151204–5257.
Comments Due: 5 p.m. ET 12/28/15.
Docket Numbers: ER16–470–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2015–12–04_Order 1000 (TOA) CTDS
Variance Analysis Filing to be effective
2/2/2016.
Filed Date: 12/4/15.
Accession Number: 20151204–5259.
Comments Due: 5 p.m. ET 12/28/15.
Docket Numbers: ER16–471–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Notice of Termination of
the Generator Interconnection
Agreement designated as Project No.
G359 of Midcontinent Independent
System Operator, Inc.
Filed Date: 12/4/15.
Accession Number: 20151204–5286.
Comments Due: 5 p.m. ET 12/28/15.
Take notice that the Commission
received the following open access
transmission tariff filings:
Docket Numbers: OA08–14–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Compliance Filing of
Midcontinent Independent System
Operator, Inc.
Filed Date: 12/4/15.
Accession Number: 20151204–5292.
Comments Due: 5 p.m. ET 12/28/15.
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
76971
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
§ 385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: December 7, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–31211 Filed 12–10–15; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OAR–2014–0535; FRL 9939–94–
OAR]
California State Nonroad Engine
Pollution Control Standards; Small OffRoad Engines Regulations; Tier 4 OffRoad Compression-Ignition
Regulations; Exhaust Emission
Certification Test Fuel for Off-Road
Spark-Ignition Engines, Equipment,
and Vehicles Regulations; Notice of
Decision
Environmental Protection
Agency.
ACTION: Notice of Decision.
AGENCY:
The Environmental Protection
Agency (EPA) is confirming that the
California Air Resources Board’s
(CARB’s) 2011 amendments to its Small
Off-Road Engines (SORE) regulations
(2011 SORE amendments), Tier 4 OffRoad Compression-Ignition (CI)
regulations (2011 Tier 4 amendments),
and Exhaust Emission Certification Test
Fuel for Off-Road Spark-Ignition (SI)
Engines, Equipment, and Vehicles
regulations (2011 Certification Test Fuel
amendments) are within the scope of
previous EPA authorizations. The 2011
SORE amendments modify California’s
existing SORE test procedures by
aligning California procedures to be
consistent with recent amendments by
EPA to the federal certification and
exhaust emission testing requirements.
SUMMARY:
E:\FR\FM\11DEN1.SGM
11DEN1
Agencies
[Federal Register Volume 80, Number 238 (Friday, December 11, 2015)]
[Notices]
[Pages 76970-76971]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-31214]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP16-22-000; PF15-10-000; CP16-23-000; PF15-11-000; CP16-
24-000]
NEXUS Gas Transmission, LLC; Texas Eastern Transmission, LP; DTE
Gas Company; Notice of Applications
Take notice that on November 20, 2015, NEXUS Gas Transmission, LLC
(NEXUS), 5400 Westheimer Court, Houston, Texas 77056, filed in Docket
No. CP16-22-000 an application pursuant to section 7(c) of the Natural
Gas Act (NGA) for authorization: (i) To construct approximately 255.9
miles of new, 36-inch-diameter interstate pipeline in Ohio and
Michigan; (ii) to construct four compressor stations, totaling 130,000
horsepower (HP); (iii) to construct various appurtenances
(collectively, the NEXUS Project); (iv) of its proposed pro forma
tariff; (v) for a Part 157, Subpart F construction certificate; (vi)
for a Part 284, Subpart G blanket certificate; and (vii) for any
waivers the Commission deems necessary for the NEXUS Project. NEXUS
states that the proposed pipeline will have a capacity of 1.5 million
dekatherms per day (Dth/d) and estimates the cost of the NEXUS Project
to be approximately $2,095,267,444.
Additionally, on November 20, 2015, Texas Eastern Transmission, LP
(Texas Eastern), 5400 Westheimer Court, Houston, Texas 77056, filed in
Docket No. CP16-23-000 an application pursuant to sections 7(b) and
7(c) of the NGA for authorization: (i) To construct approximately 4.4
miles of 36-inch-diameter pipeline loop in Monroe County, Ohio; (ii) to
construct 1,790 feet of connecting pipeline to the NEXUS Project in
Columbiana County, Ohio; (iii) to construct a new 18,800 HP compressor
station in Columbiana County, Ohio; (iv) to construct a new 9,400 HP
compressor unit at its existing Colerain Compressor Station in Belmont
County, Ohio; (v) to modify Line 73 to allow for bi-directional flow;
(vi) to construct various appurtenances (collectively, the TEAL
Project); (vii) to abandon by lease to NEXUS 950,155 Dth/d; and (vii)
for any waivers the Commission deems necessary for the TEAL Project.
Texas Eastern estimates the cost of the TEAL Project to be
approximately $183,519,668.
These applications will be reviewed contemporaneously with the
application for an operating lease filed by DTE Gas Company in Docket
No. CP16-24-000 on November 24, 2015.
All of the applications are on file with the Commission and open to
public inspection. The filing is available for review at the Commission
in the Public Reference Room or may be viewed on the Commission's Web
site Web at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
Any questions concerning the application in Docket No. CP16-22-000
may be directed to Berk Donaldson or Leanne Sidorkewicz, NEXUS Gas
Transmission LLC, 5400 Westheimer Court, Houston, Texas 77056, by
telephone at (713) 627-4488, or by email at
bdonaldson@spectraenergy.com or lsidorkewicz@spectraenergy.com.
Any questions concerning the application in Docket No. CP16-23-000
may be directed to Berk Donaldson, General Manger, Rates and
Certificates, Texas Eastern Transmission, LP, PO Box 1642, Houston,
Texas 77251-1642, by telephone at (713) 624-4488, or by facsimile at
(713) 627-5947.
On December 30, 2014, the Commission staff granted NEXUS' request
to utilize the Pre-Filing Process and assigned Docket No. PF15-10-000
to staff's activities involved in the NEXUS Project. Now, as of the
November 20, 2015 application, the Pre-Filing Process for the NEXUS
Project has ended. From this time forward, this proceeding will be
conducted in Docket No. CP16-22-000, as noted in the caption of this
Notice.
On January 16, 2015, the Commission staff granted Texas Eastern's
request to utilize the Pre-Filing Process and assigned Docket No. PF15-
11-000 to staff's activities involved in the TEAL Project. Now, as of
the November 20, 2015 application, the Pre-Filing Process for the TEAL
Project has ended. From this time forward, this proceeding will be
conducted in Docket No. CP16-23-000, as noted in the caption of this
Notice.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice, the Commission staff will issue a Notice
of Schedule for Environmental Review. If a Notice of Schedule for
Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) for this proposal. The
issuance of a Notice of Schedule for Environmental Review will serve to
notify federal and state agencies of the timing for the completion of
all necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of the date of issuance of the Commission
staff's FEIS.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit seven copies of filings made in the proceeding with the
Commission and must mail a copy to the applicant and to every other
party. Only parties to the proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and
[[Page 76971]]
two copies of their comments to the Secretary of the Commission.
Environmental commentors will be placed on the Commission's
environmental mailing list, will receive copies of the environmental
documents, and will be notified of meetings associated with the
Commission's environmental review process. Environmental commentors
will not be required to serve copies of filed documents on all other
parties. However, the non-party commentors will not receive copies of
all documents filed by other parties or issued by the Commission
(except for the mailing of environmental documents issued by the
Commission) and will not have the right to seek court review of the
Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 7 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426.
Comment Date: 5:00 p.m. Eastern Time on December 28, 2015.
Dated: December 7, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-31214 Filed 12-10-15; 8:45 am]