Marshall Wind Energy LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization, 76281 [2015-30848]
Download as PDF
Federal Register / Vol. 80, No. 235 / Tuesday, December 8, 2015 / Notices
FERC) issued its Notice of Application
for the Project. Among other things, that
notice alerted agencies issuing federal
authorizations of the requirement to
complete all necessary reviews and to
reach a final decision on a request for
a federal authorization within 90 days of
the date of issuance of the Commission
staff’s Environmental Assessment (EA)
for the Project. This instant notice
identifies the FERC staff’s planned
schedule for the completion of the EA
for the Project.
SCHEDULE FOR ENVIRONMENTAL
REVIEW
Issuance of EA ...............
90-day Federal Authorization Decision Deadline.
January 11, 2016.
April 11, 2016.
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP15–505), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC Web site also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: December 2, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–30847 Filed 12–7–15; 8:45 am]
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Project Description
The proposed Project would construct
a new 30,000 horsepower natural gasfired compressor station with suction
and discharge piping and ancillary
equipment in Livingston County,
Illinois.
Lhorne on DSK9F6TC42PROD with NOTICES
Background
On July 9, 2015, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Proposed Chicago Market Expansion
Project and Request for Comments on
Environmental Issues (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
the NOI, the Commission received a
consultation letter from United States
Department of Agriculture regarding
impacts of farmland conversion.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
VerDate Sep<11>2014
14:17 Dec 07, 2015
Jkt 238001
Federal Energy Regulatory
Commission
[Docket No. ER16–438–000]
Marshall Wind Energy LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding Marshall
Wind Energy LLC’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is December 22,
2015.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
76281
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: December 2, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–30848 Filed 12–7–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14715–000]
Lock+TM Hydro Friends Fund XII;
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On September 14, 2015, Lock+TM
Hydro Friends Fund XII filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the Hepburn Street Dam
Hydroelectric Project (Hepburn Project
or project) to be located on West Branch
of the Susquehanna River, near
Williamsport, Lycoming County,
Pennsylvania. The Hepburn Street Dam
is owned by the state of Pennsylvania.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
E:\FR\FM\08DEN1.SGM
08DEN1
Agencies
[Federal Register Volume 80, Number 235 (Tuesday, December 8, 2015)]
[Notices]
[Page 76281]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-30848]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER16-438-000]
Marshall Wind Energy LLC; Supplemental Notice That Initial
Market-Based Rate Filing Includes Request for Blanket Section 204
Authorization
This is a supplemental notice in the above-referenced proceeding
Marshall Wind Energy LLC's application for market-based rate authority,
with an accompanying rate tariff, noting that such application includes
a request for blanket authorization, under 18 CFR part 34, of future
issuances of securities and assumptions of liability.
Any person desiring to intervene or to protest should file with the
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426, in accordance with Rules 211 and 214 of the Commission's
Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone
filing a motion to intervene or protest must serve a copy of that
document on the Applicant.
Notice is hereby given that the deadline for filing protests with
regard to the applicant's request for blanket authorization, under 18
CFR part 34, of future issuances of securities and assumptions of
liability, is December 22, 2015.
The Commission encourages electronic submission of protests and
interventions in lieu of paper, using the FERC Online links at https://www.ferc.gov. To facilitate electronic service, persons with Internet
access who will eFile a document and/or be listed as a contact for an
intervenor must create and validate an eRegistration account using the
eRegistration link. Select the eFiling link to log on and submit the
intervention or protests.
Persons unable to file electronically should submit an original and
5 copies of the intervention or protest to the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426.
The filings in the above-referenced proceeding are accessible in
the Commission's eLibrary system by clicking on the appropriate link in
the above list. They are also available for electronic review in the
Commission's Public Reference Room in Washington, DC. There is an
eSubscription link on the Web site that enables subscribers to receive
email notification when a document is added to a subscribed docket(s).
For assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov. or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Dated: December 2, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-30848 Filed 12-7-15; 8:45 am]