Download as PDF mstockstill on DSK4VPTVN1PROD with NOTICES Federal Register / Vol. 80, No. 234 / Monday, December 7, 2015 / Notices County Wind, LLC, FPL Energy Cabazon Wind, LLC, FPL Energy Cape, LLC, FPL Energy Cowboy Wind, LLC, FPL Energy Green Power Wind, LLC, FPL Energy Hancock County Wind, LLC, FPL Energy Illinois Wind, LLC, FPL Energy Marcus Hook, L.P., FPL Energy MH50 L.P., FPL Energy Montezuma Wind, LLC, FPL Energy Mower County, LLC, FPL Energy New Mexico Wind, LLC, FPL Energy North Dakota Wind, LLC, FPL Energy North Dakota Wind II, LLC, FPL Energy Oklahoma Wind, LLC, FPL Energy Oliver Wind I, LLC, FPL Energy Oliver Wind II, LLC, FPL Energy Sooner Wind, LLC, FPL Energy South Dakota Wind, LLC, FPL Energy Stateline II, Inc., FPL Energy Vansycle, L.L.C, FPL Energy Wyman, LLC, FPL Energy Wyman IV, LLC, Garden Wind, LLC, Genesis Solar, LLC, Golden West Power Partners, LLC, Gray County Wind Energy, LLC, Green Mountain Storage, LLC, Hatch Solar Energy Center I, LLC, Hawkeye Power Partners, LLC, High Majestic Wind Energy Center, LLC, High Majestic Wind II, LLC, High Winds, LLC, Jamaica Bay Peaking Facility, LLC, Lake Benton Power Partners II, LLC, Langdon Wind, LLC, Limon Wind, LLC, Limon Wind II, LLC, Limon Wind III, LLC, Logan Wind Energy LLC, Mammoth Plains Wind Project, LLC. Description: Supplement to October 28, 2015 Notice of Change in Status of the NextEra Energy Companies [Part 1 of 2]. Filed Date: 11/25/15. Accession Number: 20151125–5220. Comments Due: 5 p.m. ET 12/16/15. Docket Numbers: ER16–414–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Revised Service Agreement No. 1135; Queue K4 (ISA—Assignment Agreement) to be effective 6/4/2004. Filed Date: 11/30/15. Accession Number: 20151130–5047. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–415–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Revised Service Agreement No. 1791; Queue R74 (WMPA—Assignment Agreement) to be effective 10/30/2007. Filed Date: 11/30/15. Accession Number: 20151130–5057. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–416–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original Service Agreement No. 4312; Queue No. AA2–058 to be effective 10/29/2015. Filed Date: 11/30/15. VerDate Sep<11>2014 18:36 Dec 04, 2015 Jkt 238001 Accession Number: 20151130–5083. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–417–000. Applicants: Southern California Edison Company. Description: § 205(d) Rate Filing: Distribution Service Agreement Mirasol Development, LLC Ivanhoe Land 1A Project to be effective 1/30/2016. Filed Date: 11/30/15. Accession Number: 20151130–5092. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–418–000. Applicants: Southern California Edison Company. Description: § 205(d) Rate Filing: Distribution Service Agreement Mirasol Development, LLC Ivanhoe Land 1B Project to be effective 1/30/2016. Filed Date: 11/30/15. Accession Number: 20151130–5093. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–419–000. Applicants: Dominion Energy Marketing, Inc. Description: Compliance filing: Compliance Filing—DEMI Removal of Affiliate Waiver to be effective 11/1/2015. Filed Date: 11/30/15. Accession Number: 20151130–5124. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–420–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 3103 Plains and Eastern Clean Line Oklahoma & SPS Inter Agr to be effective 11/6/2015. Filed Date: 11/30/15. Accession Number: 20151130–5152. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–421–000. Applicants: Dominion Nuclear Connecticut, Inc. Description: Compliance filing: Compliance Filing—DNCI Removal of Affiliate Waiver to be effective 11/1/2015. Filed Date: 11/30/15. Accession Number: 20151130–5153. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–422–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original Service Agreement No. 4300; Queue No. Z1–079 to be effective 10/30/2015. Filed Date: 11/30/15. Accession Number: 20151130–5163. Comments Due: 5 p.m. ET 12/21/15. Docket Numbers: ER16–423–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Second Revised Service Agreement No. PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 76003 2775; Queue No. Y3–045/Y3–052/Y3– 107 to be effective 10/29/2015. Filed Date: 11/30/15. Accession Number: 20151130–5172. Comments Due: 5 p.m. ET 12/21/15. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: November 30, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–30705 Filed 12–4–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–490–001] Delfin LNG LLC; Notice of Amendment to Application Take notice that on November 19, 2015 Delfin LNG LLC (Delfin LNG), 1100 Louisiana Street, Houston, Texas 77002, filed in Docket No. CP15–490– 001, an amendment to its May 8, 2015 application pursuant to section 7(c) of the Natural Gas Act and Part 157 of the Commission’s regulations requesting authorization to reactivate, construct, own, operate and maintain certain pipeline and compression facilities that comprise the onshore portion of Delfin LNG’s proposed Deepwater Port (DWP), an offshore liquefied natural gas facility located off the coast of Louisiana in the Gulf of Mexico. The Amendment increases the amount of compression and capacity previously proposed, all as more fully set forth in the application which is on file with the Commission and open to public inspection. This filing may be viewed on the web at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in E:\FR\FM\07DEN1.SGM 07DEN1 mstockstill on DSK4VPTVN1PROD with NOTICES 76004 Federal Register / Vol. 80, No. 234 / Monday, December 7, 2015 / Notices the docket number field to access the document. For assistance, please contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions regarding this Application should be directed to Daniel P. Werner, Delfin LNG LLC, 1100 Louisiana Street, Suite 3550, Houston, Texas 77002; phone: 346–240–2574, or J. Patrick Nevins, Hogan Lovells US LLP, 555 Thirteenth Street NW., Washington, DC 20004; phone: 202– 637–6441. Delfin LNG’s onshore facilities will connect with the DWP facilities that are subject to jurisdiction of the Maritime Authority (MARAD) and the United States Coast Guard (USCG). Additionally, as part of Delfin LNG’s DWP, Delfin LNG proposes to utilize a segment of pipeline abandoned by High Island Offshore System, LLC (HIOS) that extends from the terminus of the UTOS pipeline offshore. HIOS filed to abandon certain pipeline facilities on November 19, 2015 in Docket No. CP16–20–000. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the VerDate Sep<11>2014 18:36 Dec 04, 2015 Jkt 238001 Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 7 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and ill not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. Comment Date: December 22, 2015. PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 Dated: December 1, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–30736 Filed 12–4–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Effectiveness of Exempt Wholesale Generator Status Willey Battery Utility, LLC ............................... Little Elk Wind Project, LLC ............................... Patriot Wind Farm, LLC .. Chapman Ranch Wind I, LLC ............................... Silver State Solar Power South, LLC ................... RE Garland LLC ............... RE Garland A LLC ........... Latigo Wind Park, LLC .... Parrey, LLC ...................... South Plains Wind Energy, LLC ...................... PHR Holdings LLC .......... Golden West Power Partners, LLC ...................... EG15–108–000 EG15–109–000 EG15–110–000 EG15–111–000 EG15–112–000 EG15–113–000 EG15–114–000 EG15–116–000 EG15–117–000 EG15–118–000 EG15–119–000 EG15–120–000 Take notice that during the month of October 2015, the status of the abovecaptioned entities as Exempt Wholesale Generators became effective by operation of the Commission’s regulations. 18 CFR 366.7(a). Dated: November 30, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–30699 Filed 12–4–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Staff Attendance The Federal Energy Regulatory Commission (Commission) hereby gives notice that members of the Commission’s staff may attend the following meeting related to the transmission planning activities of the South Carolina Regional Planning (SCRTP) Stakeholder Group. South Carolina Regional Transmission Planning Meeting, December 9, 2015 (10:00 a.m.–1:00 p.m.) The above-referenced meeting will be held at: Hilton Garden Inn—Charleston Airport, Cypress I Room, 5265 International Blvd., North Charleston, SC 29418. (843) 308–9330 The meeting is open to the public. E:\FR\FM\07DEN1.SGM 07DEN1

Agencies

[Federal Register Volume 80, Number 234 (Monday, December 7, 2015)]
[Notices]
[Pages 76003-76004]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-30736]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-490-001]


Delfin LNG LLC; Notice of Amendment to Application

    Take notice that on November 19, 2015 Delfin LNG LLC (Delfin LNG), 
1100 Louisiana Street, Houston, Texas 77002, filed in Docket No. CP15-
490-001, an amendment to its May 8, 2015 application pursuant to 
section 7(c) of the Natural Gas Act and Part 157 of the Commission's 
regulations requesting authorization to reactivate, construct, own, 
operate and maintain certain pipeline and compression facilities that 
comprise the onshore portion of Delfin LNG's proposed Deepwater Port 
(DWP), an offshore liquefied natural gas facility located off the coast 
of Louisiana in the Gulf of Mexico. The Amendment increases the amount 
of compression and capacity previously proposed, all as more fully set 
forth in the application which is on file with the Commission and open 
to public inspection. This filing may be viewed on the web at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in

[[Page 76004]]

the docket number field to access the document. For assistance, please 
contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 
208-3676 or TYY, (202) 502-8659.
    Any questions regarding this Application should be directed to 
Daniel P. Werner, Delfin LNG LLC, 1100 Louisiana Street, Suite 3550, 
Houston, Texas 77002; phone: 346-240-2574, or J. Patrick Nevins, Hogan 
Lovells US LLP, 555 Thirteenth Street NW., Washington, DC 20004; phone: 
202-637-6441.
    Delfin LNG's onshore facilities will connect with the DWP 
facilities that are subject to jurisdiction of the Maritime Authority 
(MARAD) and the United States Coast Guard (USCG). Additionally, as part 
of Delfin LNG's DWP, Delfin LNG proposes to utilize a segment of 
pipeline abandoned by High Island Offshore System, LLC (HIOS) that 
extends from the terminus of the UTOS pipeline offshore. HIOS filed to 
abandon certain pipeline facilities on November 19, 2015 in Docket No. 
CP16-20-000.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 7 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenter's will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenter's will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentary, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and ill not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link.
    Comment Date: December 22, 2015.

    Dated: December 1, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.