NUCLEAR REGULATORY
COMMISSION
[Docket No. 52–043; NRC–2014–0149]
Early Site Permit for the PSEG Site
Nuclear Regulatory
Commission.
ACTION: Final environmental impact
statement; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) and the U.S. Army
Corps of Engineers (USACE),
Philadelphia District, have completed
the final environmental impact
statement (EIS), NUREG–2168,
‘‘Environmental Impact Statement for an
Early Site Permit (ESP) at the PSEG Site:
Final Report’’ for the PSEG Site ESP
application in accordance with the
National Environmental Policy Act of
1969, as amended. The USACE is
cooperating agency with the NRC in the
preparation of information in the final
EIS for use in both agencies’ decisionmaking processes. The site is located in
Salem County, New Jersey.
DATES: The final EIS is available as of
November 13, 2015.
ADDRESSES: Please refer to Docket ID
NRC–2014–0149, when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this action by the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2014–0149. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’S Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
tkelley on DSK3SPTVN1PROD with NOTICES
VerDate Sep<11>2014
17:39 Nov 19, 2015
Jkt 238001
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The final
EIS and an accompanying reader’s guide
are available in ADAMS under
Accession No. ML15176A444.
• NRC’s Public Document Room: You
may examine and purchase copies of
public documents at the NRC’s PDR,
Room O1–F21, One White Flint North,
11555 Rockville Pike, Rockville,
Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Allen Fetter, Office of New Reactors,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001, telephone:
301–415–8556, email: Allen.Fetter@
nrc.gov.
staff’s consideration of comments
received during the environmental
review; and (5) the assessments
summarized in the final EIS, including
the potential mitigation measures
identified in the ER and in the final EIS.
In addition, in making its preliminary
recommendation, the NRC staff has
concluded that there are no
environmentally preferable or obviously
superior sites in the region of interest.
SUPPLEMENTARY INFORMATION:
found at https://www.nsf.gov/nsb/
meetings/notices.jsp.
SUMMARY:
72751
[FR Doc. 2015–29698 Filed 11–19–15; 8:45 am]
I. Background
BILLING CODE 7590–01–P
In accordance with § 51.118 of title 10
of the Code of Federal Regulations, the
NRC is issuing the NUREG–2168,
‘‘Environmental Impact Statement for an
Early Site Permit at the PSEG Site: Final
Report.’’ A notice of availability of the
draft EIS was published by the NRC in
the Federal Register on August 22, 2014
(79 FR 49820) and also noticed by the
U.S. Environmental Protection Agency
on August 29, 2014 (79 FR 49774). The
public comment period was extended
on the draft EIS until December 6, 2014,
and the comments received are
addressed in the final EIS. The final EIS
is available for public inspection as
indicated in the ADDRESSES section of
this document, and at the Salem Free
Public Library, 112 West Broadway,
Salem, New Jersey, 08079. The final EIS
also can be accessed online at the PSEG
ESP specific Web page at https://
www.nrc.gov/reactors/new-reactors/esp/
pseg.html.
The final EIS also supports the
USACE’s review of the Department of
the Army permit application for certain
construction activities on the PSEG site.
The USACE’s Department of the Army
permit application number for the PSEG
site project is CENAP–OP–R–2009–
0157–45. The USACE’s Public Interest
Review will be part of its Record of
Decision and is not addressed in the
final EIS.
II. Discussion
As discussed in the final EIS, the NRC
staff’s recommendation related to the
environmental aspects of the proposed
action is that the ESP should be issued.
This recommendation is based on: (1)
The environmental report (ER)
submitted by PSEG Power, LLC, and
PSEG Nuclear, LLC (PSEG), as revised;
(2) consultation with Federal, State,
Tribal and local agencies; (3) the NRC
staff’s independent review; (4) the NRC
PO 00000
Frm 00072
Fmt 4703
Sfmt 4703
Dated at Rockville, Maryland, this 13th day
of November, 2015.
For the Nuclear Regulatory Commission.
Frank Akstulewicz,
Director, Division of New Reactor Licensing,
Office of New Reactors.
OVERSEAS PRIVATE INVESTMENT
CORPORATION
Sunshine Act Meeting Notice
Thursday, December 10,
2015, 2 p.m. (OPEN Portion) 2:15 p.m.
(CLOSED Portion)
PLACE: Offices of the Corporation,
Twelfth Floor Board Room, 1100 New
York Avenue NW., Washington, DC.
STATUS: Meeting OPEN to the Public
from 2 p.m. to 2:15 p.m. Closed portion
will commence at 2:15 p.m. (approx.).
TIME AND DATE:
Matters To Be Considered
1. President’s Report
2. Tribute—Naomi Walker
3. Minutes of the Open Session of the
September 17, 2015 Board of
Directors Meeting
Further Matters To Be Considered
(Closed to the Public 2:15 p.m.)
1. Finance Project—Africa, South Asia
2. Finance Project—Colombia, Mexico,
Peru
3. Finance Project—Asia, Africa
4. Finance Project—Asia, Africa
5. Finance Project—South and
Southeast Asia
6. Finance Project—Sub-Saharan Africa
7. Finance Project—Global
8. Finance Project—Sub-Saharan Africa
9. Finance Project—Turkey
10. Minutes of the Closed Session of the
September 17, 2015 Board of
Directors Meeting
11. Reports
12. Pending Projects
FOR MORE INFORMATION CONTACT:
Information on the meeting may be
obtained from Catherine F. I. Andrade at
(202) 336–8768, or via email at
Catherine.Andrade@opic.gov.
E:\FR\FM\20NON1.SGM
20NON1
Agencies
[Federal Register Volume 80, Number 224 (Friday, November 20, 2015)]
[Notices]
[Page 72751]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-29698]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 52-043; NRC-2014-0149]
Early Site Permit for the PSEG Site
AGENCY: Nuclear Regulatory Commission.
ACTION: Final environmental impact statement; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) and the U.S. Army
Corps of Engineers (USACE), Philadelphia District, have completed the
final environmental impact statement (EIS), NUREG-2168, ``Environmental
Impact Statement for an Early Site Permit (ESP) at the PSEG Site: Final
Report'' for the PSEG Site ESP application in accordance with the
National Environmental Policy Act of 1969, as amended. The USACE is
cooperating agency with the NRC in the preparation of information in
the final EIS for use in both agencies' decision-making processes. The
site is located in Salem County, New Jersey.
DATES: The final EIS is available as of November 13, 2015.
ADDRESSES: Please refer to Docket ID NRC-2014-0149, when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this action by the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2014-0149. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC'S Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
final EIS and an accompanying reader's guide are available in ADAMS
under Accession No. ML15176A444.
NRC's Public Document Room: You may examine and purchase
copies of public documents at the NRC's PDR, Room O1-F21, One White
Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Allen Fetter, Office of New Reactors,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001,
telephone: 301-415-8556, email: Allen.Fetter@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background
In accordance with Sec. 51.118 of title 10 of the Code of Federal
Regulations, the NRC is issuing the NUREG-2168, ``Environmental Impact
Statement for an Early Site Permit at the PSEG Site: Final Report.'' A
notice of availability of the draft EIS was published by the NRC in the
Federal Register on August 22, 2014 (79 FR 49820) and also noticed by
the U.S. Environmental Protection Agency on August 29, 2014 (79 FR
49774). The public comment period was extended on the draft EIS until
December 6, 2014, and the comments received are addressed in the final
EIS. The final EIS is available for public inspection as indicated in
the ADDRESSES section of this document, and at the Salem Free Public
Library, 112 West Broadway, Salem, New Jersey, 08079. The final EIS
also can be accessed online at the PSEG ESP specific Web page at https://www.nrc.gov/reactors/new-reactors/esp/pseg.html.
The final EIS also supports the USACE's review of the Department of
the Army permit application for certain construction activities on the
PSEG site. The USACE's Department of the Army permit application number
for the PSEG site project is CENAP-OP-R-2009-0157-45. The USACE's
Public Interest Review will be part of its Record of Decision and is
not addressed in the final EIS.
II. Discussion
As discussed in the final EIS, the NRC staff's recommendation
related to the environmental aspects of the proposed action is that the
ESP should be issued. This recommendation is based on: (1) The
environmental report (ER) submitted by PSEG Power, LLC, and PSEG
Nuclear, LLC (PSEG), as revised; (2) consultation with Federal, State,
Tribal and local agencies; (3) the NRC staff's independent review; (4)
the NRC staff's consideration of comments received during the
environmental review; and (5) the assessments summarized in the final
EIS, including the potential mitigation measures identified in the ER
and in the final EIS. In addition, in making its preliminary
recommendation, the NRC staff has concluded that there are no
environmentally preferable or obviously superior sites in the region of
interest.
Dated at Rockville, Maryland, this 13th day of November, 2015.
For the Nuclear Regulatory Commission.
Frank Akstulewicz,
Director, Division of New Reactor Licensing, Office of New Reactors.
[FR Doc. 2015-29698 Filed 11-19-15; 8:45 am]
BILLING CODE 7590-01-P