Roger Rolfe; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene, 71789-71790 [2015-29264]

Download as PDF Federal Register / Vol. 80, No. 221 / Tuesday, November 17, 2015 / Notices Amendment (Add CVEC TalladegaMitchell Rd DP) to be effective 10/31/ Federal Energy Regulatory 2015. Commission Filed Date: 11/9/15. Accession Number: 20151109–5206. Combined Notice of Filings #1 Comments Due: 5 p.m. ET 11/30/15. Docket Numbers: ER16–297–000. Take notice that the Commission Applicants: Southwest Power Pool, received the following electric corporate Inc. filings: Description: § 205(d) Rate Filing: Docket Numbers: EC16–31–000. Applicants: Slate Creek Wind Project, 2652R3 Waverly Wind Farm LLC GIA to be effective 10/19/2015. LLC. Filed Date: 11/10/15. Description: Application for Accession Number: 20151110–5033. Authorization under Section 203 of the Comments Due: 5 p.m. ET 12/1/15. FPA of Slate Creek Wind Project, LLC Docket Numbers: ER16–298–000. and Requests for Expedited Applicants: American Electric Power Consideration and Confidential Service Corporation. Treatment. Description: Application for Limited Filed Date: 11/9/15. Waiver of American Electric Power Accession Number: 20151109–5244. Service Corporation, on behalf of its Comments Due: 5 p.m. ET 11/30/15. state-regulated utility affiliates within Docket Numbers: EC16–32–000. PJM Interconnection, L.L.C. Applicants: CPV Shore, LLC. Filed Date: 11/9/15. Description: Application for Accession Number: 20151109–5252. Authorization Under Section 203 of the Comments Due: 5 p.m. ET 11/30/15. Federal Power Act and Request for Docket Numbers: ER16–299–000. Waivers, Confidential Treatment, Applicants: AEP Texas North Expedited Action and Shortened Company. Comment Period of CPV Shore, LLC. Description: § 205(d) Rate Filing: Filed Date: 11/10/15. TNC-SolaireHolman 1 Interconnection Accession Number: 20151110–5137. Agreement to be effective 10/22/2015. Comments Due: 5 p.m. ET 12/1/15. Filed Date: 11/10/15. Take notice that the Commission Accession Number: 20151110–5051. received the following electric rate Comments Due: 5 p.m. ET 12/1/15. filings: Docket Numbers: ER16–300–000. Docket Numbers: ER15–746–002. Applicants: AEP Texas Central Applicants: RC Cape May Holdings, Company. LLC. Description: § 205(d) Rate Filing: TCCDescription: Report Filing: The City of Brownsville TX IA First Supplement to Refund Report to be Amend & Restated to be effective 10/16/ effective N/A. 2015. Filed Date: 11/9/15. Filed Date: 11/10/15. Accession Number: 20151109–5113. Accession Number: 20151110–5056. Comments Due: 5 p.m. ET 11/30/15. Comments Due: 5 p.m. ET 12/1/15. Docket Numbers: ER15–2418–002. Docket Numbers: ER16–301–000. Applicants: Pacific Gas and Electric Applicants: Southern California Company. Description: Compliance filing: eTariff Edison Company. Description: § 205(d) Rate Filing: Migration Compliance Filing for BART NITSA Schedule 7 to be effective 12/31/ Distribution Service Agmt with Calleguas Municipal Water District to be 9998. effective 1/10/2016. Filed Date: 11/9/15. Filed Date: 11/10/15. Accession Number: 20151109–5195. Accession Number: 20151110–5077. Comments Due: 5 p.m. ET 11/30/15. Comments Due: 5 p.m. ET 12/1/15. Docket Numbers: ER16–132–001. Docket Numbers: ER16–302–000. Applicants: Michigan Electric Applicants: Southern California Transmission Company, LLC. Description: Tariff Amendment: Filing Edison Company. Description: § 205(d) Rate Filing: of Agreement for Sharing of Security Related Costs to be effective 12/21/2015. True-Up SGIA and Distribution Service Agmt US Borax to be effective 1/10/ Filed Date: 11/10/15. 2016. Accession Number: 20151110–5093. Filed Date: 11/10/15. Comments Due: 5 p.m. ET 12/1/15. Accession Number: 20151110–5079. Docket Numbers: ER16–296–000. Comments Due: 5 p.m. ET 12/1/15. Applicants: Alabama Power Docket Numbers: ER16–303–000. Company. Applicants: Southern California Description: § 205(d) Rate Filing: SWE Edison Company. (PowerSouth Territorial) NITSA mstockstill on DSK4VPTVN1PROD with NOTICES DEPARTMENT OF ENERGY VerDate Sep<11>2014 18:14 Nov 16, 2015 Jkt 238001 PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 71789 Description: § 205(d) Rate Filing: GIA & Distribution Service Agreement Ganna Halvorsen Covina Solar Project to be effective 1/10/2016. Filed Date: 11/10/15. Accession Number: 20151110–5094. Comments Due: 5 p.m. ET 12/1/15. Docket Numbers: ER16–304–000. Applicants: PacifiCorp. Description: § 205(d) Rate Filing: BPA Construction Agmt—Conversion RossLex-Swift to be effective 1/10/2016. Filed Date: 11/10/15. Accession Number: 20151110–5105. Comments Due: 5 p.m. ET 12/1/15. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and § 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: November 10, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–29265 Filed 11–16–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CD16–2–000] Roger Rolfe; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene On November 3, 2015, Roger Rolfe filed a notice of intent to construct a qualifying conduit hydropower facility, pursuant to section 30 of the Federal Power Act (FPA), as amended by section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The proposed Rolfe Hydro Project would have an installed capacity of 2 kilowatts (kW) and would be located at the vault on the 6-inch diameter irrigation pipe on the Rolfe property. The project would be located near the town of E:\FR\FM\17NON1.SGM 17NON1 71790 Federal Register / Vol. 80, No. 221 / Tuesday, November 17, 2015 / Notices Cimarron in Gunnison County, Colorado. Applicant Contact: Gabe Stephens, Black Canyon Resources, LLC, P.O. Box 1781, Gunnison, CO 81230, Phone No. (970) 946–5096. FERC Contact: Robert Bell, Phone No. (202) 502–6062, email: robert.bell@ ferc.gov. Qualifying Conduit Hydropower Facility Description: The proposed project would consist of: (1) Replacing the existing gate valves with an impulse turbine with an installed capacity of 2 kW; (3) a 15-foot-long, 8-inch-diameter discharge pipe reducing to 6-inch diameter connecting to the existing 6inch-diameter irrigation pipeline; and (4) appurtenant facilities. The proposed project would have an estimated annual generating capacity of 11.4 megawatthours. A qualifying conduit hydropower facility is one that is determined or deemed to meet all of the criteria shown in the table below. TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY Description Satisfies (Y/N) The conduit the facility uses a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity. The facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a non-federally owned conduit. The facility has an installed capacity that does not exceed 5 megawatts .................................. Y Statutory provision FPA 30(a)(3)(A), as amended by HREA. mstockstill on DSK4VPTVN1PROD with NOTICES FPA 30(a)(3)(C)(i), as amended by HREA. FPA 30(a)(3)(C)(ii), as amended by HREA. FPA 30(a)(3)(C)(iii), as amended by HREA. On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA. Preliminary Determination: Based upon the above criteria, Commission staff preliminarily determines that the proposal satisfies the requirements for a qualifying conduit hydropower facility, which is not required to be licensed or exempted from licensing. Comments and Motions to Intervene: Deadline for filing comments contesting whether the facility meets the qualifying criteria is 45 days from the issuance date of this notice. Deadline for filing motions to intervene is 30 days from the issuance date of this notice. Anyone may submit comments or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 385.214. Any motions to intervene must be received on or before the specified deadline date for the particular proceeding. Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the ‘‘COMMENTS CONTESTING QUALIFICATION FOR A CONDUIT HYDROPOWER FACILITY’’ or ‘‘MOTION TO INTERVENE,’’ as applicable; (2) state in the heading the name of the applicant and the project number of the application to which the filing responds; (3) state the name, address, and telephone number of the person filing; and (4) otherwise comply with the requirements of sections 385.2001 through 385.2005 of the Commission’s regulations.1 All comments contesting Commission staff’s preliminary determination that the 1 18 CFR 385.2001–2005 (2015). VerDate Sep<11>2014 18:14 Nov 16, 2015 Jkt 238001 facility meets the qualifying criteria must set forth their evidentiary basis. The Commission strongly encourages electronic filing. Please file motions to intervene and comments using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Locations of Notice of Intent: Copies of the notice of intent can be obtained directly from the applicant or such copies can be viewed and reproduced at the Commission in its Public Reference Room, Room 2A, 888 First Street NE., Washington, DC 20426. The filing may also be viewed on the web at https:// www.ferc.gov/docs-filing/elibrary.asp using the ‘‘eLibrary’’ link. Enter the docket number (e.g., CD16–2–000) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3676 or email FERCOnline Support@ferc.gov. For TTY, call (202) 502–8659. PO 00000 Frm 00021 Fmt 4703 Sfmt 9990 Y Y Y Dated: November 10, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–29264 Filed 11–16–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 10309–001] Darren K. Vaughn, Scott M. Fodor, Trust; Notice of Transfer of Exemption 1. By letter filed November 3, 2015, Darren K. Vaughn informed the Commission that the exemption from licensing for the Flying W Project No. 10309, originally issued July 21, 1987 1 has been transferred to Scott M. Fodor, Trust. The name of the project has been changed from Flying W to Scott M. Fodor, Trust. The project is located on an irrigation pipe near Emmett in Valley County, Idaho. The transfer of an exemption does not require Commission approval. 2. Scott M. Fodor, Trust is now the exemptee of the Scott M. Fodor, Trust Project, No. 10309. All correspondence should be forwarded to: Scott M. Fodor, Trust, 10644 W. Coleman Road, Barryton, MI 49305. Dated: November 10, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–29267 Filed 11–16–15; 8:45 am] BILLING CODE 6717–01–P 1 40 FERC ¶ 62,056 (1987), Order Granting Exemption from Licensing (Conduit). E:\FR\FM\17NON1.SGM 17NON1

Agencies

[Federal Register Volume 80, Number 221 (Tuesday, November 17, 2015)]
[Notices]
[Pages 71789-71790]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-29264]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD16-2-000]


Roger Rolfe; Notice of Preliminary Determination of a Qualifying 
Conduit Hydropower Facility and Soliciting Comments and Motions To 
Intervene

    On November 3, 2015, Roger Rolfe filed a notice of intent to 
construct a qualifying conduit hydropower facility, pursuant to section 
30 of the Federal Power Act (FPA), as amended by section 4 of the 
Hydropower Regulatory Efficiency Act of 2013 (HREA). The proposed Rolfe 
Hydro Project would have an installed capacity of 2 kilowatts (kW) and 
would be located at the vault on the 6-inch diameter irrigation pipe on 
the Rolfe property. The project would be located near the town of

[[Page 71790]]

Cimarron in Gunnison County, Colorado.
    Applicant Contact: Gabe Stephens, Black Canyon Resources, LLC, P.O. 
Box 1781, Gunnison, CO 81230, Phone No. (970) 946-5096.
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
robert.bell@ferc.gov.
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) Replacing the existing gate valves with 
an impulse turbine with an installed capacity of 2 kW; (3) a 15-foot-
long, 8-inch-diameter discharge pipe reducing to 6-inch diameter 
connecting to the existing 6-inch-diameter irrigation pipeline; and (4) 
appurtenant facilities. The proposed project would have an estimated 
annual generating capacity of 11.4 megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
              Statutory provision                                 Description                    Satisfies (Y/N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA...........  The conduit the facility uses a tunnel, canal,                Y
                                                 pipeline, aqueduct, flume, ditch, or similar
                                                 manmade water conveyance that is operated for
                                                 the distribution of water for agricultural,
                                                 municipal, or industrial consumption and not
                                                 primarily for the generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA........  The facility is constructed, operated, or                     Y
                                                 maintained for the generation of electric
                                                 power and uses for such generation only the
                                                 hydroelectric potential of a non-federally
                                                 owned conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA.......  The facility has an installed capacity that                   Y
                                                 does not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA......  On or before August 9, 2013, the facility is                  Y
                                                 not licensed, or exempted from the licensing
                                                 requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------

    Preliminary Determination: Based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2015).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at https://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (e.g., CD16-2-000) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, 
call (202) 502-8659.

    Dated: November 10, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-29264 Filed 11-16-15; 8:45 am]