Download as PDF tkelley on DSK3SPTVN1PROD with NOTICES Federal Register / Vol. 80, No. 220 / Monday, November 16, 2015 / Notices 309 of the Federal Power Act (FPA), 16 U.S.C. 824e, 825e, and 825h, Rule 206 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.206, Industrial Energy Users—Ohio filed a formal complaint against Ohio Power Company (AEP-Ohio) and PJM Interconnection, LLC (PJM) alleging that AEP-Ohio has taken, and PJM has allowed to be taken actions in contravention of the PJM Open Access Transmission Tariff and that such actions are unjust, unreasonable, and unduly discriminatory, in violation of the Federal Power Act, as more fully explained in the complaint. The Complainant states that a copy of the complaint has been served on the Respondents. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for electronic review in the Commission’s Public Reference Room in Washington, DC There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on November 25, 2015 VerDate Sep<11>2014 19:47 Nov 13, 2015 Jkt 238001 Dated: November 6, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–29145 Filed 11–13–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Total Peaking Services, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Vaporization Capacity Increase and Bog Compressor Project, and Request for Comments on Environmental Issues November 9, 2015. The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Vaporization Capacity Increase and BOG Compressor Project (Project) involving construction and operation of facilities by Total Peaking Services, LLC (Total Peaking) in Milford, Connecticut. The Commission will use this EA in its decision-making process to determine whether the Project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the Project. You can make a difference by providing us with your specific comments or concerns about the Project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before December 9, 2015. If you sent comments on this Project to the Commission before the opening of this docket on September 22, 2015, you will need to file those comments in Docket No. CP15–557–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this Project. State and local government representatives should notify their constituents of this proposed Project and encourage them to comment on their areas of concern. Frm 00029 Fmt 4703 Sfmt 4703 Total Peaking provided affected landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically asked questions, including how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). Public Participation [Docket No. CP15–557–000] PO 00000 70775 For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’ as the filing type; or (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the Project docket number (CP15–557– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Summary of the Proposed Project Total Peaking proposes to modify its existing liquefied natural gas peak shaving facility 1 in Milford, Connecticut to increase the vaporization send out capabilities from 90 million standard cubic feet per day (MMscf/d) to 105 MMscf/d. According to Total Peaking, the Project would meet its future system needs and projected peak day requirements. The Project would consist of the following modifications: 1 Peak shaving facilities liquefy and store natural gas during warmer months for vaporization and injection into natural gas pipelines during peak conditions such as cold weather. E:\FR\FM\16NON1.SGM 16NON1 70776 Federal Register / Vol. 80, No. 220 / Monday, November 16, 2015 / Notices • Installation of two new vaporizers and removal of three existing vaporizers; • installation of an additional boiloff gas (BOG) compressor; • installation of a 1,500 kilovoltampere transformer and three new 400 kilowatt emergency generators to replace the existing transformer and emergency generator; and • installation of a new 4,160 volt electric interconnection service line to provide the LNG facility with additional electricity to operate the new vaporization equipment. The general location of the Project facilities is shown in appendix 1.2 Land Requirements for Construction Construction of the proposed facilities would occur entirely within the fence line of the existing facility on paved and graveled areas. The construction would disturb about 0.44 acres of land within the approximately 24-acre facility site. Permanent operation of the Project’s facilities would require about 0.18 acres. The EA Process tkelley on DSK3SPTVN1PROD with NOTICES The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 3 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed Project under these general headings: • Geology and soils; • land use; • water resources, fisheries, and wetlands; • cultural resources; • vegetation and wildlife; 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. VerDate Sep<11>2014 19:47 Nov 13, 2015 Jkt 238001 • air quality and noise; • endangered and threatened species; • public safety; and • cumulative impacts We will also evaluate reasonable alternatives to the proposed Project or portions of the Project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this Project to formally cooperate with us in the preparation of the EA.4 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the Project’s potential effects on historic properties.5 We will define the Project-specific Area of Potential Effects (APE) in consultation with the SHPO as the Project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, 4 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 5 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 and access roads). Our EA for this Project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Environmental Mailing List The environmental mailing list includes: Federal, state, and local government representatives and agencies; elected officials; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for Project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the Project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed Project. If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the ‘‘Document-less Intervention Guide’’ under the ‘‘e-filing’’ link on the Commission’s Web site. Motions to intervene are more fully described at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. Additional Information Additional information about the Project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number E:\FR\FM\16NON1.SGM 16NON1 Federal Register / Vol. 80, No. 220 / Monday, November 16, 2015 / Notices field (i.e., CP15–557). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: November 9, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–29147 Filed 11–13–15; 8:45 am] BILLING CODE 6717–01–P intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible online at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern time on December 3, 2015. DEPARTMENT OF ENERGY Dated: November 9, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. Federal Energy Regulatory Commission [FR Doc. 2015–29153 Filed 11–13–15; 8:45 am] BILLING CODE 6717–01–P [Docket No. OR16–3–000] tkelley on DSK3SPTVN1PROD with NOTICES Oryx Southern Delaware Oil Gathering and Transport LLC; Notice of Petition for Declaratory Order Take notice that on November 3, 2015, pursuant to Rule 207(a)(2) of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.207(a)(2) (2015), Oryx Southern Delaware Gathering and Transport LLC, filed a petition for a declaratory order seeking order approving general rate structure and terms of service for new crude oil pipeline from Permian Basin receipt points to delivery points in Crane and Midland, Texas, all as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of VerDate Sep<11>2014 19:47 Nov 13, 2015 Jkt 238001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #2 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC15–210–000. Applicants: Dominion Solar Projects A, Inc., Dominion Solar Projects I, Inc. Description: Clarification to September 24, 2015 Application for Authorization Under Section 203 of the Federal Power Act of Dominion Solar Projects A, Inc., et al. Filed Date: 10/30/15. Accession Number: 20151030–5509. Comments Due: 5 p.m. ET 11/13/15. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER14–1210–005. Applicants: Midcontinent Independent System Operator, Inc. Description: Compliance filing: 2015– 11–09_SA 6502 Edwards SSR 2014 PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 70777 Agreement Compliance to be effective 7/ 22/2014. Filed Date: 11/9/15. Accession Number: 20151109–5117. Comments Due: 5 p.m. ET 11/30/15. Docket Numbers: ER14–2605–002. Applicants: Midcontinent Independent System Operator, Inc. Description: Compliance filing: 2015– 11–09_SSR ER14–2605 Compliance Filing to be effective 7/22/2014. Filed Date: 11/9/15. Accession Number: 20151109–5103. Comments Due: 5 p.m. ET 11/30/15. Docket Numbers: ER15–943–003. Applicants: Midcontinent Independent System Operator, Inc. Description: Compliance filing: 2015– 11–09_SA 6502 Edwards SSR 2015 Agreement Compliance to be effective 1/ 1/2015. Filed Date: 11/9/15. Accession Number: 20151109–5122. Comments Due: 5 p.m. ET 11/30/15. Docket Numbers: ER16–293–000. Applicants: Mesquite Solar 2, LLC. Description: Baseline eTariff Filing: Mesquite Solar 2, LLC Certificate of Concurrence to be effective 11/20/2015. Filed Date: 11/9/15. Accession Number: 20151109–5073. Comments Due: 5 p.m. ET 11/30/15. Docket Numbers: ER16–294–000. Applicants: Mesquite Solar 3, LLC. Description: Baseline eTariff Filing: Mesquite Solar 3, LLC Certificate of Concurrence to be effective 11/20/2015. Filed Date: 11/9/15. Accession Number: 20151109–5074. Comments Due: 5 p.m. ET 11/30/15. Docket Numbers: ER16–295–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2015–11–09_SA 1503 NSP-Mankato 2nd Rev. GIA (G261) to be effective 11/10/ 2015. Filed Date: 11/9/15. Accession Number: 20151109–5085. Comments Due: 5 p.m. ET 11/30/15. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and § 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, E:\FR\FM\16NON1.SGM 16NON1

Agencies

[Federal Register Volume 80, Number 220 (Monday, November 16, 2015)]
[Notices]
[Pages 70775-70777]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-29147]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-557-000]


Total Peaking Services, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Vaporization Capacity 
Increase and Bog Compressor Project, and Request for Comments on 
Environmental Issues

November 9, 2015.
    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Vaporization Capacity Increase 
and BOG Compressor Project (Project) involving construction and 
operation of facilities by Total Peaking Services, LLC (Total Peaking) 
in Milford, Connecticut. The Commission will use this EA in its 
decision-making process to determine whether the Project is in the 
public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the Project. You can make a difference by providing us with 
your specific comments or concerns about the Project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before December 9, 2015.
    If you sent comments on this Project to the Commission before the 
opening of this docket on September 22, 2015, you will need to file 
those comments in Docket No. CP15-557-000 to ensure they are considered 
as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this Project. State and local government 
representatives should notify their constituents of this proposed 
Project and encourage them to comment on their areas of concern.
    Total Peaking provided affected landowners with a fact sheet 
prepared by the FERC entitled ``An Interstate Natural Gas Facility On 
My Land? What Do I Need To Know?'' This fact sheet addresses a number 
of typically asked questions, including how to participate in the 
Commission's proceedings. It is also available for viewing on the FERC 
Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the Project docket number 
(CP15-557-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    Total Peaking proposes to modify its existing liquefied natural gas 
peak shaving facility \1\ in Milford, Connecticut to increase the 
vaporization send out capabilities from 90 million standard cubic feet 
per day (MMscf/d) to 105 MMscf/d. According to Total Peaking, the 
Project would meet its future system needs and projected peak day 
requirements.
---------------------------------------------------------------------------

    \1\ Peak shaving facilities liquefy and store natural gas during 
warmer months for vaporization and injection into natural gas 
pipelines during peak conditions such as cold weather.
---------------------------------------------------------------------------

    The Project would consist of the following modifications:


[[Page 70776]]

 Installation of two new vaporizers and removal of three 
existing vaporizers;
     installation of an additional boiloff gas (BOG) 
compressor;
     installation of a 1,500 kilovolt-ampere transformer and 
three new 400 kilowatt emergency generators to replace the existing 
transformer and emergency generator; and
     installation of a new 4,160 volt electric interconnection 
service line to provide the LNG facility with additional electricity to 
operate the new vaporization equipment.
    The general location of the Project facilities is shown in appendix 
1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would occur entirely within 
the fence line of the existing facility on paved and graveled areas. 
The construction would disturb about 0.44 acres of land within the 
approximately 24-acre facility site. Permanent operation of the 
Project's facilities would require about 0.18 acres.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed Project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts
    We will also evaluate reasonable alternatives to the proposed 
Project or portions of the Project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this Project to formally cooperate with us in the preparation of the 
EA.\4\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the Project's potential effects on 
historic properties.\5\ We will define the Project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the Project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this Project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes: Federal, state, and local 
government representatives and agencies; elected officials; Native 
American Tribes; other interested parties; and local libraries and 
newspapers. This list also includes all affected landowners (as defined 
in the Commission's regulations) who are potential right-of-way 
grantors, whose property may be used temporarily for Project purposes, 
or who own homes within certain distances of aboveground facilities, 
and anyone who submits comments on the Project. We will update the 
environmental mailing list as the analysis proceeds to ensure that we 
send the information related to this environmental review to all 
individuals, organizations, and government entities interested in and/
or potentially affected by the proposed Project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's Web site. Motions to intervene are more fully 
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the Project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number

[[Page 70777]]

field (i.e., CP15-557). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: November 9, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-29147 Filed 11-13-15; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.