Exelon Generation Company, LLC; Dresden Nuclear Power Station, Units 2 and 3, 68573-68578 [2015-28290]
Download as PDF
Federal Register / Vol. 80, No. 214 / Thursday, November 5, 2015 / Notices
Application Details
Permit Application: 2016–022
1. Applicant; Joseph Wilson, Penguin
Films LTd, 1 St Augustine’s Lane,
Bristol BS1 5DE United Kingdom.
Activity for Which Permit Is Requested
ASPA entry; Applicant requests entry
to Cape Crozier, ASPA 124 in order to
film an Adelie penguin documentary
film for Disney. The applicant and team
would use long lens filming techniques,
which require the camera person to be
at a distance from the animals in order
to capture natural behaviors. The work
would be observational and would not
involve interactions with penguins. The
team would be working with penguin
scientists who conduct work in Cape
Crozier.
Location
Cape Crozier, ASPA 124
Dates
December 25, 2015–February 10, 2015
Nadene G. Kennedy,
Polar Coordination Specialist, Division of
Polar Programs.
[FR Doc. 2015–28195 Filed 11–4–15; 8:45 am]
BILLING CODE 7555–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–237 and 50–249; NRC–
2015–0250]
Exelon Generation Company, LLC;
Dresden Nuclear Power Station, Units
2 and 3
Nuclear Regulatory
Commission.
ACTION: License amendment application;
opportunity to comment, request a
hearing, and petition for leave to
intervene; order.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is considering
issuance of an amendment to Facility
Operating License Nos. DPR–19 and
DPR–25, issued to Exelon Generation
Company, LLC (the licensee), for
operation of the Dresden Nuclear Power
Station (DNPS), Units 2 and 3. The
proposed amendment uses a new
Criticality Safety Analysis (CSA)
methodology for performing the
criticality safety evaluation for legacy
fuel types in addition to the new
ATRIUM 10XM fuel design in the DNPS
spent fuel pools (SFPs). In addition, the
licensee’s amendment request proposes
a change to the DNPS Technical
Specification (TS) 4.3.1, ‘‘Criticality,’’ in
support of the new CSA.
jstallworth on DSK7TPTVN1PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
15:06 Nov 04, 2015
Submit comments by December
7, 2015. Requests for a hearing or
petition for leave to intervene must be
filed by January 4, 2016.
ADDRESSES: You may submit comments
by any of the following methods (unless
this document describes a different
method for submitting comments on a
specific subject):
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2015–0250. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• Mail comments to: Cindy Bladey,
Office of Administration, Mail Stop:
OWFN–12–H08, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
For additional direction on obtaining
information and submitting comments,
see ‘‘Obtaining Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
FOR FURTHER INFORMATION CONTACT:
Russell S. Haskell, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
1129, email: Russell.Haskell@nrc.gov.
SUPPLEMENTARY INFORMATION:
DATES:
Jkt 238001
I. Obtaining Information and
Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC–2015–
0250 when contacting the NRC about
the availability of information for this
action. You may obtain publiclyavailable information related to this
action by any of the following methods:
• Federal rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2015–0250.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
license amendment request dated
December 30, 2014, and supplemental
letters dated May 8, and July 30, 2015,
are publicly available in ADAMS under
PO 00000
Frm 00082
Fmt 4703
Sfmt 4703
68573
Accession Nos. ML14364A100,
ML15128A305, and ML15215A336.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC–2015–
0250 in your comment submission.
The NRC cautions you not to include
identifying or contact information that
you do not want to be publicly
disclosed in your comment submission.
The NRC will post all comment
submissions at https://
www.regulations.gov as well as enter the
comment submissions into ADAMS.
The NRC does not routinely edit
comment submissions to remove
identifying or contact information.
If you are requesting or aggregating
comments from other persons for
submission to the NRC, then you should
inform those persons not to include
identifying or contact information that
they do not want to be publicly
disclosed in their comment submission.
Your request should state that the NRC
does not routinely edit comment
submissions to remove such information
before making the comment
submissions available to the public or
entering the comment into ADAMS.
II. Introduction
The NRC is considering issuance of an
amendment to Facility Operating
License Nos. DPR–19 and DPR–25,
issued to Exelon Generation Company,
LLC, for operation of the Dresden
Nuclear Power Station (DNPS), Units 2
and 3, located in Grundy County,
Illinois. The proposed amendment uses
a new Criticality Safety Analysis (CSA)
methodology for performing the
criticality safety evaluation for legacy
fuel types in addition to the new
ATRIUM 10XM fuel design in the DNPS
spent fuel pools (SFPs). In addition, the
licensee’s amendment request proposes
a change to the DNPS Technical
Specification (TS) 4.3.1, ‘‘Criticality,’’ in
support of the new CSA.
Before any issuance of the proposed
license amendment, the NRC will need
to make the findings required by the
Atomic Energy Act of 1954, as amended
(the Act), and NRC’s regulations.
The NRC has made a proposed
determination that the license
amendment request involves no
significant hazards consideration. Under
the NRC’s regulations in § 50.92 of title
10 of the Code of Federal Regulations
(10 CFR), this means that operation of
the facility in accordance with the
proposed amendment would not: (1)
E:\FR\FM\05NON1.SGM
05NON1
jstallworth on DSK7TPTVN1PROD with NOTICES
68574
Federal Register / Vol. 80, No. 214 / Thursday, November 5, 2015 / Notices
involve a significant increase in the
probability or consequences of an
accident previously evaluated; (2) create
the possibility of a new or different kind
of accident from any accident
previously evaluated; or (3) involve a
significant reduction in a margin of
safety. As required by 10 CFR 50.91(a),
the licensee has provided its analysis of
the issue of no significant hazards
consideration, which is presented
below:
1. Does the proposed amendment
involve a significant increase in the
probability or consequences of an
accident previously evaluated?
Response: No.
The proposed amendment involves a
revised CSA for the DNPS Units 2 and
3, SFPs using a new methodology and
proposes a new TS requirement limiting
the maximum in-rack k-infinity. The
proposed amendment does not change
or modify the fuel, fuel handling
processes, spent fuel storage racks,
number of fuel assemblies that may be
stored in the SFP, decay heat generation
rate, or the SFP cooling and cleanup
system.
The proposed amendment was
evaluated for impact on the following
previously evaluated events and
accidents:
• A fuel handling accident (FHA),
• A fuel mis-positioning event,
• A seismic event, and
• A loss of SFP cooling event
The probability of a FHA is not
increased because implementation of
the proposed amendment will employ
the same equipment and processes to
handle fuel assemblies that are currently
used. The FHA radiological
consequences are not increased because
the methodology used in support of the
CSA does not impact the radiological
source term of a single fuel assembly.
Therefore, the proposed amendment
does not significantly increase the
probability or consequences of an FHA.
Operation in accordance with the
proposed amendment will not
significantly increase the probability of
a fuel mis-positioning event because
fuel movement will continue to be
controlled by approved fuel handling
procedures. These procedures continue
to require identification of the initial
and target locations for each fuel
assembly that is moved. The
consequences of a fuel mis-positioning
event are not changed because the
reactivity analysis demonstrates that the
new sub-criticality criteria and
requirements will be met for the worstcase fuel mis-positioning event.
Operation in accordance with the
proposed amendment will not change
the probability of a seismic event. The
VerDate Sep<11>2014
15:06 Nov 04, 2015
Jkt 238001
consequences of a seismic event are not
increased because the forcing functions
for seismic excitation are not increased
and because the mass of storage racks
has not changed. Operation in
accordance with the proposed
amendment will not change the
probability of a loss of SFP cooling
event because the systems and events
that could affect SFP cooling are
unchanged. The consequences are not
significantly increased because there are
no changes in the SFP heat load or SFP
cooling systems, structures or
components due to the proposed change
in CSA methodology. Furthermore,
conservative analyses indicate that the
current design requirements and criteria
continue to be met with the presence of
Boral blisters.
Therefore, the proposed change does
not involve a significant increase in the
probability or consequences of an
accident previously evaluated.
2. Does the proposed amendment
create the possibility of a new or
different kind of accident from any
accident previously evaluated?
Response: No.
Onsite storage of spent fuel
assemblies in the DNPS, Units 2 and 3,
SFPs is a normal activity for which
DNPS has been designed and licensed.
As part of assuring that this normal
activity can be performed without
endangering the public health and
safety, the ability to safely accommodate
different possible accidents in the spent
fuel pool have been previously
analyzed. These analyses address
accidents such as radiological releases
due to dropping a fuel assembly; and
potential inadvertent criticality due to
mis-loading a fuel assembly. The
proposed amendment does not change
the method of fuel movement or spent
fuel storage and does not create the
potential for a new accident.
The proposed use of a new
methodology for performing the DNPS
SFP CSA and addition of a new TS
requirement limiting the maximum inrack k-infinity does not change or
modify the fuel, fuel handling
processes, spent fuel racks, number of
fuel assemblies that may be stored in the
pool, decay heat generation rate, or the
SFP cooling and cleanup system. The
potential for blistering on the Boral has
been evaluated and the neutron poison
will continue to fulfill its function.
The limiting fuel assembly mispositioning event does not represent a
new or different type of accident. The
mis-positioning of a fuel assembly
within the fuel storage racks has always
been possible. The proposed
amendment involves a revised CSA for
the DNPS Units 2 and 3, SFPs using a
PO 00000
Frm 00083
Fmt 4703
Sfmt 4703
new methodology. The associated
analysis results show that the storage
racks remain sub-critical, with
substantial margin, following a worstcase fuel mis-loading event.
Therefore, the proposed change does
not create the possibility of a new or
different kind of accident from any
previously evaluated.
3. Does the proposed amendment
involve a significant reduction in a
margin of safety?
Response: No.
The proposed amendment involves a
revised CSA for the DNPS Units 2 and
3, SFPs using a new methodology and
proposes a new TS requirement limiting
the maximum in-rack k-infinity. This
change was evaluated for its effect on
margins of safety related to criticality
and spent fuel heat removal capability.
DNPS TS 4.3, ‘‘Fuel Storage,’’
Specification 4.3.1.1.a requires the spent
fuel storage racks to maintain the
effective neutron multiplication factor,
k-eff, less than or equal to 0.95 when
fully flooded with unborated water,
which includes an allowance for
uncertainties. Therefore, for spent fuel
pool criticality considerations, the
required safety margin is 5 percent.
The proposed change ensures, as
verified by the associated criticality
analysis, that k-eff continues to be less
than or equal to 0.95, thus preserving
the required safety margin of 5 percent.
In addition, using the in-rack k-infinity
limit ensures that the SFP criticality
analysis remains bounding and provides
adequate protection to ensure public
health and safety in that it determines
the reactivity limit for the fuel
assemblies that are allowed to be stored
in the SFP storage racks.
The proposed use of a new
methodology for performing the DNPS
SFP CSA does not affect spent fuel heat
generation or the spent fuel cooling
systems. A conservative analysis
indicates that the design basis
requirements and criteria for spent fuel
cooling continue to be met with Boral
blistering considered.
In addition, the radiological
consequences of a dropped fuel
assembly remain unchanged as the
anticipated fuel damage due to a fuel
handling accident is unaffected by the
use of a new methodology to perform
the CSA. The proposed change also does
not increase the capacity of the Unit 2
and Unit 3 spent fuel pools beyond the
current capacity of not more than 3537
fuel assemblies.
The NRC staff has reviewed the
licensee’s analysis and, based on this
review, it appears that the three
standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff
E:\FR\FM\05NON1.SGM
05NON1
Federal Register / Vol. 80, No. 214 / Thursday, November 5, 2015 / Notices
jstallworth on DSK7TPTVN1PROD with NOTICES
proposes to determine that the license
amendment request involves a No
Significant Hazards Consideration.
The NRC is seeking public comments
on this proposed determination that the
license amendment request involves no
significant hazards consideration. Any
comments received within 30 days after
the date of publication of this notice
will be considered in making any final
determination.
Normally, the Commission will not
issue the amendment until the
expiration of 60 days after the date of
publication of this notice. The
Commission may issue the license
amendment before expiration of the 60day notice period if the Commission
concludes the amendment involves no
significant hazards consideration. In
addition, the Commission may issue the
amendment prior to the expiration of
the 30-day comment period should
circumstances change during the 30-day
comment period such that failure to act
in a timely way would result, for
example, in derating or shutdown of the
facility. Should the Commission take
action prior to the expiration of either
the comment period or the notice
period, it will publish in the Federal
Register a notice of issuance. Should the
Commission make a final No Significant
Hazards Consideration Determination,
any hearing will take place after
issuance. The Commission expects that
the need to take this action will occur
very infrequently.
III. Opportunity To Request a Hearing
and Petition for Leave To Intervene
Within 60 days after the date of
publication of this notice, any person(s)
whose interest may be affected by this
action may file a request for a hearing
and a petition to intervene with respect
to issuance of the amendment to the
subject facility operating license or
combined license. Requests for a
hearing and a petition for leave to
intervene shall be filed in accordance
with the Commission’s ‘‘Agency Rules
of Practice and Procedure’’ in 10 CFR
part 2. Interested person(s) should
consult a current copy of 10 CFR 2.309,
which is available at the NRC’s PDR,
located at One White Flint North, Room
O1–F21, 11555 Rockville Pike (first
floor), Rockville, Maryland 20852. The
NRC’s regulations are accessible
electronically from the NRC Library on
the NRC’s Web site at https://www.nrc.
gov/reading-rm/doc-collections/cfr/. If a
request for a hearing or petition for
leave to intervene is filed within 60
days, the Commission or a presiding
officer designated by the Commission or
by the Chief Administrative Judge of the
Atomic Safety and Licensing Board
VerDate Sep<11>2014
15:06 Nov 04, 2015
Jkt 238001
Panel, will rule on the request and/or
petition; and the Secretary or the Chief
Administrative Judge of the Atomic
Safety and Licensing Board will issue a
notice of a hearing or an appropriate
order.
As required by 10 CFR 2.309, a
request for hearing or petition for leave
to intervene must set forth with
particularity the interest of the
petitioner in the proceeding, and how
that interest may be affected by the
results of the proceeding. The hearing
request or petition must specifically
explain the reasons why intervention
should be permitted with particular
reference to the following general
requirements: (1) The name, address,
and telephone number of the requestor
or petitioner; (2) the nature of the
requestor’s/petitioner’s right under the
Act to be made a party to the
proceeding; (3) the nature and extent of
the requestor’s/petitioner’s property,
financial, or other interest in the
proceeding; and (4) the possible effect of
any decision or order which may be
entered in the proceeding on the
requestor’s/petitioner’s interest. The
petition must also set forth the specific
contentions which the requestor/
petitioner seeks to have litigated at the
proceeding.
Each contention must consist of a
specific statement of the issue of law or
fact to be raised or controverted. In
addition, the requestor/petitioner shall
provide a brief explanation of the bases
for the contention and a concise
statement of the alleged facts or expert
opinion which support the contention
and on which the requestor/petitioner
intends to rely in proving the contention
at the hearing. The requestor/petitioner
must also provide references to those
specific sources and documents of
which the petitioner is aware and on
which the requestor/petitioner intends
to rely to establish those facts or expert
opinion. The petition must include
sufficient information to show that a
genuine dispute exists with the
applicant on a material issue of law or
fact. Contentions shall be limited to
matters within the scope of the
amendment under consideration. The
contention must be one which, if
proven, would entitle the requestor/
petitioner to relief. A requestor/
petitioner who fails to satisfy these
requirements with respect to at least one
contention will not be permitted to
participate as a party.
Those permitted to intervene become
parties to the proceeding, subject to any
limitations in the order granting leave to
intervene, and have the opportunity to
participate fully in the conduct of the
hearing with respect to resolution of
PO 00000
Frm 00084
Fmt 4703
Sfmt 4703
68575
that person’s admitted contentions,
including the opportunity to present
evidence and to submit a crossexamination plan for cross-examination
of witnesses, consistent with NRC
regulations, policies and procedures.
Petitions for leave to intervene must
be filed no later than 60 days from the
date of publication of this notice.
Requests for hearing, petitions for leave
to intervene, and motions for leave to
file new or amended contentions that
are filed after the 60-day deadline will
not be entertained absent a
determination by the presiding officer
that the filing demonstrates good cause
by satisfying the three factors in 10 CFR
2.309(c)(1)(i)–(iii).
If a hearing is requested, and the
Commission has not made a final
determination on the issue of no
significant hazards consideration, the
Commission will make a final
determination on the issue of no
significant hazards consideration. The
final determination will serve to decide
when the hearing is held. If the final
determination is that the amendment
request involves no significant hazards
consideration, the Commission may
issue the amendment and make it
immediately effective, notwithstanding
the request for a hearing. Any hearing
held would take place after issuance of
the amendment. If the final
determination is that the amendment
request involves a significant hazards
consideration, then any hearing held
would take place before the issuance of
any amendment unless the Commission
finds an imminent danger to the health
or safety of the public, in which case it
will issue an appropriate order or rule
under 10 CFR part 2.
A State, local governmental body,
Federally-recognized Indian tribe, or
agency thereof, may submit a petition to
the Commission to participate as a party
under 10 CFR 2.309(h)(1). The petition
should state the nature and extent of the
petitioner’s interest in the proceeding.
The petition should be submitted to the
Commission by January 4, 2016. The
petition must be filed in accordance
with the filing instructions in the
‘‘Electronic Submissions (E-Filing)’’
section of this document, and should
meet the requirements for petitions for
leave to intervene set forth in this
section, except that under § 2.309(h)(2)
a State, local governmental body, or
Federally-recognized Indian tribe, or
agency thereof does not need to address
the standing requirements in 10 CFR
2.309(d) if the facility is located within
its boundaries. A State, local
governmental body, Federallyrecognized Indian tribe, or agency
E:\FR\FM\05NON1.SGM
05NON1
68576
Federal Register / Vol. 80, No. 214 / Thursday, November 5, 2015 / Notices
thereof may also have the opportunity to
participate under 10 CFR 2.315(c).
If a hearing is granted, any person
who does not wish, or is not qualified,
to become a party to the proceeding
may, in the discretion of the presiding
officer, be permitted to make a limited
appearance pursuant to the provisions
of 10 CFR 2.315(a). A person making a
limited appearance may make an oral or
written statement of position on the
issues, but may not otherwise
participate in the proceeding. A limited
appearance may be made at any session
of the hearing or at any prehearing
conference, subject to the limits and
conditions as may be imposed by the
presiding officer. Persons desiring to
make a limited appearance are
requested to inform the Secretary of the
Commission by January 4, 2016.
jstallworth on DSK7TPTVN1PROD with NOTICES
IV. Electronic Submissions (E-Filing)
All documents filed in NRC
adjudicatory proceedings, including a
request for hearing, a petition for leave
to intervene, any motion or other
document filed in the proceeding prior
to the submission of a request for
hearing or petition to intervene, and
documents filed by interested
governmental entities participating
under 10 CFR 2.315(c), must be filed in
accordance with the NRC’s E-Filing rule
(72 FR 49139; August 28, 2007). The EFiling process requires participants to
submit and serve all adjudicatory
documents over the internet, or in some
cases to mail copies on electronic
storage media. Participants may not
submit paper copies of their filings
unless they seek an exemption in
accordance with the procedures
described below.
To comply with the procedural
requirements of E-Filing, at least 10
days prior to the filing deadline, the
participant should contact the Office of
the Secretary by email at
hearing.docket@nrc.gov, or by telephone
at 301–415–1677, to request (1) a digital
identification (ID) certificate, which
allows the participant (or its counsel or
representative) to digitally sign
documents and access the E-Submittal
server for any proceeding in which it is
participating; and (2) advise the
Secretary that the participant will be
submitting a request or petition for
hearing (even in instances in which the
participant, or its counsel or
representative, already holds an NRCissued digital ID certificate). Based upon
this information, the Secretary will
establish an electronic docket for the
hearing in this proceeding if the
Secretary has not already established an
electronic docket.
VerDate Sep<11>2014
15:06 Nov 04, 2015
Jkt 238001
Information about applying for a
digital ID certificate is available on the
NRC’s public Web site at https://www.
nrc.gov/site-help/e-submittals/gettingstarted.html. System requirements for
accessing the E-Submittal server are
detailed in the NRC’s ‘‘Guidance for
Electronic Submission,’’ which is
available on the agency’s public Web
site at https://www.nrc.gov/site-help/esubmittals.html. Participants may
attempt to use other software not listed
on the Web site, but should note that the
NRC’s E-Filing system does not support
unlisted software, and the NRC Meta
System Help Desk will not be able to
offer assistance in using unlisted
software.
If a participant is electronically
submitting a document to the NRC in
accordance with the E-Filing rule, the
participant must file the document
using the NRC’s online, Web-based
submission form. In order to serve
documents through the Electronic
Information Exchange System, users
will be required to install a Web
browser plug-in from the NRC’s Web
site. Further information on the Webbased submission form, including the
installation of the Web browser plug-in,
is available on the NRC’s public Web
site at https://www.nrc.gov/site-help/esubmittals.html.
Once a participant has obtained a
digital ID certificate and a docket has
been created, the participant can then
submit a request for hearing or petition
for leave to intervene. Submissions
should be in Portable Document Format
(PDF) in accordance with NRC guidance
available on the NRC’s public Web site
at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered
complete at the time the documents are
submitted through the NRC’s E-Filing
system. To be timely, an electronic
filing must be submitted to the E-Filing
system no later than 11:59 p.m. Eastern
Time on the due date. Upon receipt of
a transmission, the E-Filing system
time-stamps the document and sends
the submitter an email notice
confirming receipt of the document. The
E-Filing system also distributes an email
notice that provides access to the
document to the NRC’s Office of the
General Counsel and any others who
have advised the Office of the Secretary
that they wish to participate in the
proceeding, so that the filer need not
serve the documents on those
participants separately. Therefore,
applicants and other participants (or
their counsel or representative) must
apply for and receive a digital ID
certificate before a hearing request/
petition to intervene is filed so that they
PO 00000
Frm 00085
Fmt 4703
Sfmt 4703
can obtain access to the document via
the E-Filing system.
A person filing electronically using
the NRC’s adjudicatory E-Filing system
may seek assistance by contacting the
NRC Meta System Help Desk through
the ‘‘Contact Us’’ link located on the
NRC’s public Web site at https://
www.nrc.gov/site-help/esubmittals.html, by email to
MSHD.Resource@nrc.gov, or by a tollfree call at 1–866–672–7640. The NRC
Meta System Help Desk is available
between 8 a.m. and 8 p.m., Eastern
Time, Monday through Friday,
excluding government holidays.
Participants who believe that they
have a good cause for not submitting
documents electronically must file an
exemption request, in accordance with
10 CFR 2.302(g), with their initial paper
filing requesting authorization to
continue to submit documents in paper
format. Such filings must be submitted
by: (1) First class mail addressed to the
Office of the Secretary of the
Commission, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, Attention: Rulemaking and
Adjudications Staff; or (2) courier,
express mail, or expedited delivery
service to the Office of the Secretary,
Sixteenth Floor, One White Flint North,
11555 Rockville Pike, Rockville,
Maryland 20852, Attention: Rulemaking
and Adjudications Staff. Participants
filing a document in this manner are
responsible for serving the document on
all other participants. Filing is
considered complete by first-class mail
as of the time of deposit in the mail, or
by courier, express mail, or expedited
delivery service upon depositing the
document with the provider of the
service. A presiding officer, having
granted an exemption request from
using E-Filing, may require a participant
or party to use E-Filing if the presiding
officer subsequently determines that the
reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory
proceedings will appear in the NRC’s
electronic hearing docket which is
available to the public at https://
ehd1.nrc.gov/ehd/, unless excluded
pursuant to an order of the Commission,
or the presiding officer. Participants are
requested not to include personal
privacy information, such as social
security numbers, home addresses, or
home phone numbers in their filings,
unless an NRC regulation or other law
requires submission of such
information. However, in some
instances, a request to intervene will
require including information on local
residence in order to demonstrate a
proximity assertion of interest in the
E:\FR\FM\05NON1.SGM
05NON1
Federal Register / Vol. 80, No. 214 / Thursday, November 5, 2015 / Notices
jstallworth on DSK7TPTVN1PROD with NOTICES
proceeding. With respect to copyrighted
works, except for limited excerpts that
serve the purpose of the adjudicatory
filings and would constitute a Fair Use
application, participants are requested
not to include copyrighted materials in
their submission.
For further details with respect to this
amendment action, see the application
for amendment which is available for
public inspection at the NRC’s PDR,
located at One White Flint North, Room
O1–F21, 11555 Rockville Pike (first
floor), Rockville, Maryland 20852.
Publicly available documents created or
received at the NRC are accessible
electronically through ADAMS in the
NRC Library at https://www.nrc.gov/
reading-rm/adams.html. If you do not
have access to ADAMS or if there are
problems in accessing the documents
located in ADAMS, contact the PDR’s
Reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov.
The NRC staff has reviewed the
licensee’s analysis and, based on this
review, it appears that the three
standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff
proposes to determine that the
amendment request involves no
significant hazards consideration.
Attorney for licensee: Tamra (Tami)
Domeyer, Exelon Generation Company,
LLC, 4300 Winfield Road, Warrenville,
Illinois 60555.
NRC Branch Chief: Travis L. Tate.
Order Imposing Procedures for Access
to Sensitive Unclassified NonSafeguards Information for Contention
Preparation
A. This Order contains instructions
regarding how potential parties to this
proceeding may request access to
documents containing SUNSI.
B. Within 10 days after publication of
this notice of hearing and opportunity to
petition for leave to intervene, any
potential party who believes access to
SUNSI is necessary to respond to this
notice may request such access. A
‘‘potential party’’ is any person who
intends to participate as a party by
demonstrating standing and filing an
admissible contention under 10 CFR
2.309. Requests for access to SUNSI
submitted later than 10 days after
publication of this notice will not be
considered absent a showing of good
cause for the late filing, addressing why
the request could not have been filed
earlier.
C. The requester shall submit a letter
requesting permission to access SUNSI
to the Office of the Secretary, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001, Attention:
VerDate Sep<11>2014
15:06 Nov 04, 2015
Jkt 238001
Rulemakings and Adjudications Staff,
and provide a copy to the Associate
General Counsel for Hearings,
Enforcement and Administration, Office
of the General Counsel, Washington, DC
20555–0001. The expedited delivery or
courier mail address for both offices is:
U.S. Nuclear Regulatory Commission,
11555 Rockville Pike, Rockville,
Maryland 20852. The email address for
the Office of the Secretary and the
Office of the General Counsel are
Hearing.Docket@nrc.gov and
OGCmailcenter@nrc.gov, respectively.1
The request must include the following
information:
(1) A description of the licensing
action with a citation to this Federal
Register notice;
(2) The name and address of the
potential party and a description of the
potential party’s particularized interest
that could be harmed by the action
identified in C.(1); and
(3) The identity of the individual or
entity requesting access to SUNSI and
the requester’s basis for the need for the
information in order to meaningfully
participate in this adjudicatory
proceeding. In particular, the request
must explain why publicly-available
versions of the information requested
would not be sufficient to provide the
basis and specificity for a proffered
contention.
D. Based on an evaluation of the
information submitted under paragraph
C.(3) the NRC staff will determine
within 10 days of receipt of the request
whether:
(1) There is a reasonable basis to
believe the petitioner is likely to
establish standing to participate in this
NRC proceeding; and
(2) The requestor has established a
legitimate need for access to SUNSI.
E. If the NRC staff determines that the
requestor satisfies both D.(1) and D.(2)
above, the NRC staff will notify the
requestor in writing that access to
SUNSI has been granted. The written
notification will contain instructions on
how the requestor may obtain copies of
the requested documents, and any other
conditions that may apply to access to
those documents. These conditions may
include, but are not limited to, the
signing of a Non-Disclosure Agreement
or Affidavit, or Protective Order 2 setting
1 While a request for hearing or petition to
intervene in this proceeding must comply with the
filing requirements of the NRC’s ‘‘E-Filing Rule,’’
the initial request to access SUNSI under these
procedures should be submitted as described in this
paragraph.
2 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SUNSI must
be filed with the presiding officer or the Chief
Administrative Judge if the presiding officer has not
PO 00000
Frm 00086
Fmt 4703
Sfmt 4703
68577
forth terms and conditions to prevent
the unauthorized or inadvertent
disclosure of SUNSI by each individual
who will be granted access to SUNSI.
F. Filing of Contentions. Any
contentions in these proceedings that
are based upon the information received
as a result of the request made for
SUNSI must be filed by the requestor no
later than 25 days after the requestor is
granted access to that information.
However, if more than 25 days remain
between the date the petitioner is
granted access to the information and
the deadline for filing all other
contentions (as established in the notice
of hearing or opportunity for hearing),
the petitioner may file its SUNSI
contentions by that later deadline. This
provision does not extend the time for
filing a request for a hearing and
petition to intervene, which must
comply with the requirements of 10 CFR
2.309.
G. Review of Denials of Access.
(1) If the request for access to SUNSI
is denied by the NRC staff after a
determination on standing and need for
access, the NRC staff shall immediately
notify the requestor in writing, briefly
stating the reason or reasons for the
denial.
(2) The requester may challenge the
NRC staff’s adverse determination by
filing a challenge within 5 days of
receipt of that determination with: (a)
The presiding officer designated in this
proceeding; (b) if no presiding officer
has been appointed, the Chief
Administrative Judge, or if he or she is
unavailable, another administrative
judge, or an administrative law judge
with jurisdiction pursuant to 10 CFR
2.318(a); or (c) officer if that officer has
been designated to rule on information
access issues.
H. Review of Grants of Access. A
party other than the requester may
challenge an NRC staff determination
granting access to SUNSI whose release
would harm that party’s interest
independent of the proceeding. Such a
challenge must be filed with the Chief
Administrative Judge within 5 days of
the notification by the NRC staff of its
grant of access.
If challenges to the NRC staff
determinations are filed, these
procedures give way to the normal
process for litigating disputes
concerning access to information. The
availability of interlocutory review by
the Commission of orders ruling on
such NRC staff determinations (whether
yet been designated, within 30 days of the deadline
for the receipt of the written access request.
E:\FR\FM\05NON1.SGM
05NON1
68578
Federal Register / Vol. 80, No. 214 / Thursday, November 5, 2015 / Notices
granting or denying access) is governed
by 10 CFR 2.311.3
I. The Commission expects that the
NRC staff and presiding officers (and
any other reviewing officers) will
consider and resolve requests for access
to SUNSI, and motions for protective
orders, in a timely fashion in order to
minimize any unnecessary delays in
identifying those petitioners who have
standing and who have propounded
contentions meeting the specificity and
basis requirements in 10 CFR part 2.
Attachment 1 to this Order summarizes
the general target schedule for
processing and resolving requests under
these procedures.
It is ordered.
Dated at Rockville, Maryland, this 30th day
of October, 2015.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE
UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING
Day
Event/Activity
0 ........................
Publication of FEDERAL REGISTER notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests.
Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information:
Supporting the standing of a potential party identified by name and address; describing the need for the information in order
for the potential party to participate meaningfully in an adjudicatory proceeding.
Deadline for submitting petition for intervention containing: (i) Demonstration of standing; and (ii) all contentions whose formulation does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply).
U.S. Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for
access provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation of redactions or review of redacted documents).
If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling
to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief
Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any
party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to
file a motion seeking a ruling to reverse the NRC staff’s grant of access.
Deadline for NRC staff reply to motions to reverse NRC staff determination(s).
(Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and
file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure
Agreement for SUNSI.
If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for access
to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a
final adverse determination by the NRC staff.
Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective order.
Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days
remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as
established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later
deadline.
(Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.
(Answer receipt +7) Petitioner/Intervenor reply to answers.
Decision on contention admission.
10 ......................
60 ......................
20 ......................
25 ......................
30 ......................
40 ......................
A .......................
A + 3 .................
A + 28 ...............
A + 53 ...............
A + 60 ...............
>A + 60 .............
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 52–037; NRC–2008–0556]
AmerenUE Combined License
Application for Callaway Plant, Unit 2
Nuclear Power Plant
Nuclear Regulatory
Commission.
ACTION: Application for combined
license; withdrawal.
jstallworth on DSK7TPTVN1PROD with NOTICES
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is withdrawing an
SUMMARY:
3 Requesters should note that the filing
requirements of the NRC’s E-Filing Rule (72 FR
49139; August 28, 2007) apply to appeals of NRC
VerDate Sep<11>2014
15:06 Nov 04, 2015
Jkt 238001
application for a combined license
(COL) for the Callaway Plant, Unit 2
Nuclear Power Plant in Callaway
County, Missouri. The COL application
is being withdrawn at the request of the
applicant, AmerenUE (Ameren).
DATES: The effective date of the
withdrawal of Ameren’s combined
license application for Callaway Plant,
Unit 2 Nuclear Power Plant is November
5, 2015.
ADDRESSES: Please refer to Docket ID
NRC–2008–0556 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0556. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
staff determinations (because they must be served
on a presiding officer or the Commission, as
[FR Doc. 2015–28290 Filed 11–4–15; 8:45 am]
applicable), but not to the initial SUNSI request
submitted to the NRC staff under these procedures.
PO 00000
Frm 00087
Fmt 4703
Sfmt 4703
E:\FR\FM\05NON1.SGM
05NON1
Agencies
[Federal Register Volume 80, Number 214 (Thursday, November 5, 2015)]
[Notices]
[Pages 68573-68578]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-28290]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-237 and 50-249; NRC-2015-0250]
Exelon Generation Company, LLC; Dresden Nuclear Power Station,
Units 2 and 3
AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment application; opportunity to comment, request
a hearing, and petition for leave to intervene; order.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of an amendment to Facility Operating License Nos. DPR-19 and
DPR-25, issued to Exelon Generation Company, LLC (the licensee), for
operation of the Dresden Nuclear Power Station (DNPS), Units 2 and 3.
The proposed amendment uses a new Criticality Safety Analysis (CSA)
methodology for performing the criticality safety evaluation for legacy
fuel types in addition to the new ATRIUM 10XM fuel design in the DNPS
spent fuel pools (SFPs). In addition, the licensee's amendment request
proposes a change to the DNPS Technical Specification (TS) 4.3.1,
``Criticality,'' in support of the new CSA.
DATES: Submit comments by December 7, 2015. Requests for a hearing or
petition for leave to intervene must be filed by January 4, 2016.
ADDRESSES: You may submit comments by any of the following methods
(unless this document describes a different method for submitting
comments on a specific subject):
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2015-0250. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
Mail comments to: Cindy Bladey, Office of Administration,
Mail Stop: OWFN-12-H08, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
For additional direction on obtaining information and submitting
comments, see ``Obtaining Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Russell S. Haskell, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-1129, email: Russell.Haskell@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2015-0250 when contacting the NRC
about the availability of information for this action. You may obtain
publicly-available information related to this action by any of the
following methods:
Federal rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2015-0250.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
license amendment request dated December 30, 2014, and supplemental
letters dated May 8, and July 30, 2015, are publicly available in ADAMS
under Accession Nos. ML14364A100, ML15128A305, and ML15215A336.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2015-0250 in your comment submission.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC will post all comment submissions at https://www.regulations.gov as well as enter the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment into ADAMS.
II. Introduction
The NRC is considering issuance of an amendment to Facility
Operating License Nos. DPR-19 and DPR-25, issued to Exelon Generation
Company, LLC, for operation of the Dresden Nuclear Power Station
(DNPS), Units 2 and 3, located in Grundy County, Illinois. The proposed
amendment uses a new Criticality Safety Analysis (CSA) methodology for
performing the criticality safety evaluation for legacy fuel types in
addition to the new ATRIUM 10XM fuel design in the DNPS spent fuel
pools (SFPs). In addition, the licensee's amendment request proposes a
change to the DNPS Technical Specification (TS) 4.3.1, ``Criticality,''
in support of the new CSA.
Before any issuance of the proposed license amendment, the NRC will
need to make the findings required by the Atomic Energy Act of 1954, as
amended (the Act), and NRC's regulations.
The NRC has made a proposed determination that the license
amendment request involves no significant hazards consideration. Under
the NRC's regulations in Sec. 50.92 of title 10 of the Code of Federal
Regulations (10 CFR), this means that operation of the facility in
accordance with the proposed amendment would not: (1)
[[Page 68574]]
involve a significant increase in the probability or consequences of an
accident previously evaluated; (2) create the possibility of a new or
different kind of accident from any accident previously evaluated; or
(3) involve a significant reduction in a margin of safety. As required
by 10 CFR 50.91(a), the licensee has provided its analysis of the issue
of no significant hazards consideration, which is presented below:
1. Does the proposed amendment involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
The proposed amendment involves a revised CSA for the DNPS Units 2
and 3, SFPs using a new methodology and proposes a new TS requirement
limiting the maximum in-rack k-infinity. The proposed amendment does
not change or modify the fuel, fuel handling processes, spent fuel
storage racks, number of fuel assemblies that may be stored in the SFP,
decay heat generation rate, or the SFP cooling and cleanup system.
The proposed amendment was evaluated for impact on the following
previously evaluated events and accidents:
A fuel handling accident (FHA),
A fuel mis-positioning event,
A seismic event, and
A loss of SFP cooling event
The probability of a FHA is not increased because implementation of
the proposed amendment will employ the same equipment and processes to
handle fuel assemblies that are currently used. The FHA radiological
consequences are not increased because the methodology used in support
of the CSA does not impact the radiological source term of a single
fuel assembly.
Therefore, the proposed amendment does not significantly increase
the probability or consequences of an FHA.
Operation in accordance with the proposed amendment will not
significantly increase the probability of a fuel mis-positioning event
because fuel movement will continue to be controlled by approved fuel
handling procedures. These procedures continue to require
identification of the initial and target locations for each fuel
assembly that is moved. The consequences of a fuel mis-positioning
event are not changed because the reactivity analysis demonstrates that
the new sub-criticality criteria and requirements will be met for the
worst-case fuel mis-positioning event.
Operation in accordance with the proposed amendment will not change
the probability of a seismic event. The consequences of a seismic event
are not increased because the forcing functions for seismic excitation
are not increased and because the mass of storage racks has not
changed. Operation in accordance with the proposed amendment will not
change the probability of a loss of SFP cooling event because the
systems and events that could affect SFP cooling are unchanged. The
consequences are not significantly increased because there are no
changes in the SFP heat load or SFP cooling systems, structures or
components due to the proposed change in CSA methodology. Furthermore,
conservative analyses indicate that the current design requirements and
criteria continue to be met with the presence of Boral blisters.
Therefore, the proposed change does not involve a significant
increase in the probability or consequences of an accident previously
evaluated.
2. Does the proposed amendment create the possibility of a new or
different kind of accident from any accident previously evaluated?
Response: No.
Onsite storage of spent fuel assemblies in the DNPS, Units 2 and 3,
SFPs is a normal activity for which DNPS has been designed and
licensed. As part of assuring that this normal activity can be
performed without endangering the public health and safety, the ability
to safely accommodate different possible accidents in the spent fuel
pool have been previously analyzed. These analyses address accidents
such as radiological releases due to dropping a fuel assembly; and
potential inadvertent criticality due to mis-loading a fuel assembly.
The proposed amendment does not change the method of fuel movement or
spent fuel storage and does not create the potential for a new
accident.
The proposed use of a new methodology for performing the DNPS SFP
CSA and addition of a new TS requirement limiting the maximum in-rack
k-infinity does not change or modify the fuel, fuel handling processes,
spent fuel racks, number of fuel assemblies that may be stored in the
pool, decay heat generation rate, or the SFP cooling and cleanup
system. The potential for blistering on the Boral has been evaluated
and the neutron poison will continue to fulfill its function.
The limiting fuel assembly mis-positioning event does not represent
a new or different type of accident. The mis-positioning of a fuel
assembly within the fuel storage racks has always been possible. The
proposed amendment involves a revised CSA for the DNPS Units 2 and 3,
SFPs using a new methodology. The associated analysis results show that
the storage racks remain sub-critical, with substantial margin,
following a worst-case fuel mis-loading event.
Therefore, the proposed change does not create the possibility of a
new or different kind of accident from any previously evaluated.
3. Does the proposed amendment involve a significant reduction in a
margin of safety?
Response: No.
The proposed amendment involves a revised CSA for the DNPS Units 2
and 3, SFPs using a new methodology and proposes a new TS requirement
limiting the maximum in-rack k-infinity. This change was evaluated for
its effect on margins of safety related to criticality and spent fuel
heat removal capability.
DNPS TS 4.3, ``Fuel Storage,'' Specification 4.3.1.1.a requires the
spent fuel storage racks to maintain the effective neutron
multiplication factor, k-eff, less than or equal to 0.95 when fully
flooded with unborated water, which includes an allowance for
uncertainties. Therefore, for spent fuel pool criticality
considerations, the required safety margin is 5 percent.
The proposed change ensures, as verified by the associated
criticality analysis, that k-eff continues to be less than or equal to
0.95, thus preserving the required safety margin of 5 percent. In
addition, using the in-rack k-infinity limit ensures that the SFP
criticality analysis remains bounding and provides adequate protection
to ensure public health and safety in that it determines the reactivity
limit for the fuel assemblies that are allowed to be stored in the SFP
storage racks.
The proposed use of a new methodology for performing the DNPS SFP
CSA does not affect spent fuel heat generation or the spent fuel
cooling systems. A conservative analysis indicates that the design
basis requirements and criteria for spent fuel cooling continue to be
met with Boral blistering considered.
In addition, the radiological consequences of a dropped fuel
assembly remain unchanged as the anticipated fuel damage due to a fuel
handling accident is unaffected by the use of a new methodology to
perform the CSA. The proposed change also does not increase the
capacity of the Unit 2 and Unit 3 spent fuel pools beyond the current
capacity of not more than 3537 fuel assemblies.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff
[[Page 68575]]
proposes to determine that the license amendment request involves a No
Significant Hazards Consideration.
The NRC is seeking public comments on this proposed determination
that the license amendment request involves no significant hazards
consideration. Any comments received within 30 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of 60 days after the date of publication of this notice. The
Commission may issue the license amendment before expiration of the 60-
day notice period if the Commission concludes the amendment involves no
significant hazards consideration. In addition, the Commission may
issue the amendment prior to the expiration of the 30-day comment
period should circumstances change during the 30-day comment period
such that failure to act in a timely way would result, for example, in
derating or shutdown of the facility. Should the Commission take action
prior to the expiration of either the comment period or the notice
period, it will publish in the Federal Register a notice of issuance.
Should the Commission make a final No Significant Hazards Consideration
Determination, any hearing will take place after issuance. The
Commission expects that the need to take this action will occur very
infrequently.
III. Opportunity To Request a Hearing and Petition for Leave To
Intervene
Within 60 days after the date of publication of this notice, any
person(s) whose interest may be affected by this action may file a
request for a hearing and a petition to intervene with respect to
issuance of the amendment to the subject facility operating license or
combined license. Requests for a hearing and a petition for leave to
intervene shall be filed in accordance with the Commission's ``Agency
Rules of Practice and Procedure'' in 10 CFR part 2. Interested
person(s) should consult a current copy of 10 CFR 2.309, which is
available at the NRC's PDR, located at One White Flint North, Room O1-
F21, 11555 Rockville Pike (first floor), Rockville, Maryland 20852. The
NRC's regulations are accessible electronically from the NRC Library on
the NRC's Web site at https://www.nrc.gov/reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to intervene is
filed within 60 days, the Commission or a presiding officer designated
by the Commission or by the Chief Administrative Judge of the Atomic
Safety and Licensing Board Panel, will rule on the request and/or
petition; and the Secretary or the Chief Administrative Judge of the
Atomic Safety and Licensing Board will issue a notice of a hearing or
an appropriate order.
As required by 10 CFR 2.309, a request for hearing or petition for
leave to intervene must set forth with particularity the interest of
the petitioner in the proceeding, and how that interest may be affected
by the results of the proceeding. The hearing request or petition must
specifically explain the reasons why intervention should be permitted
with particular reference to the following general requirements: (1)
The name, address, and telephone number of the requestor or petitioner;
(2) the nature of the requestor's/petitioner's right under the Act to
be made a party to the proceeding; (3) the nature and extent of the
requestor's/petitioner's property, financial, or other interest in the
proceeding; and (4) the possible effect of any decision or order which
may be entered in the proceeding on the requestor's/petitioner's
interest. The petition must also set forth the specific contentions
which the requestor/petitioner seeks to have litigated at the
proceeding.
Each contention must consist of a specific statement of the issue
of law or fact to be raised or controverted. In addition, the
requestor/petitioner shall provide a brief explanation of the bases for
the contention and a concise statement of the alleged facts or expert
opinion which support the contention and on which the requestor/
petitioner intends to rely in proving the contention at the hearing.
The requestor/petitioner must also provide references to those specific
sources and documents of which the petitioner is aware and on which the
requestor/petitioner intends to rely to establish those facts or expert
opinion. The petition must include sufficient information to show that
a genuine dispute exists with the applicant on a material issue of law
or fact. Contentions shall be limited to matters within the scope of
the amendment under consideration. The contention must be one which, if
proven, would entitle the requestor/petitioner to relief. A requestor/
petitioner who fails to satisfy these requirements with respect to at
least one contention will not be permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing with respect to resolution of that person's admitted
contentions, including the opportunity to present evidence and to
submit a cross-examination plan for cross-examination of witnesses,
consistent with NRC regulations, policies and procedures.
Petitions for leave to intervene must be filed no later than 60
days from the date of publication of this notice. Requests for hearing,
petitions for leave to intervene, and motions for leave to file new or
amended contentions that are filed after the 60-day deadline will not
be entertained absent a determination by the presiding officer that the
filing demonstrates good cause by satisfying the three factors in 10
CFR 2.309(c)(1)(i)-(iii).
If a hearing is requested, and the Commission has not made a final
determination on the issue of no significant hazards consideration, the
Commission will make a final determination on the issue of no
significant hazards consideration. The final determination will serve
to decide when the hearing is held. If the final determination is that
the amendment request involves no significant hazards consideration,
the Commission may issue the amendment and make it immediately
effective, notwithstanding the request for a hearing. Any hearing held
would take place after issuance of the amendment. If the final
determination is that the amendment request involves a significant
hazards consideration, then any hearing held would take place before
the issuance of any amendment unless the Commission finds an imminent
danger to the health or safety of the public, in which case it will
issue an appropriate order or rule under 10 CFR part 2.
A State, local governmental body, Federally-recognized Indian
tribe, or agency thereof, may submit a petition to the Commission to
participate as a party under 10 CFR 2.309(h)(1). The petition should
state the nature and extent of the petitioner's interest in the
proceeding. The petition should be submitted to the Commission by
January 4, 2016. The petition must be filed in accordance with the
filing instructions in the ``Electronic Submissions (E-Filing)''
section of this document, and should meet the requirements for
petitions for leave to intervene set forth in this section, except that
under Sec. 2.309(h)(2) a State, local governmental body, or Federally-
recognized Indian tribe, or agency thereof does not need to address the
standing requirements in 10 CFR 2.309(d) if the facility is located
within its boundaries. A State, local governmental body, Federally-
recognized Indian tribe, or agency
[[Page 68576]]
thereof may also have the opportunity to participate under 10 CFR
2.315(c).
If a hearing is granted, any person who does not wish, or is not
qualified, to become a party to the proceeding may, in the discretion
of the presiding officer, be permitted to make a limited appearance
pursuant to the provisions of 10 CFR 2.315(a). A person making a
limited appearance may make an oral or written statement of position on
the issues, but may not otherwise participate in the proceeding. A
limited appearance may be made at any session of the hearing or at any
prehearing conference, subject to the limits and conditions as may be
imposed by the presiding officer. Persons desiring to make a limited
appearance are requested to inform the Secretary of the Commission by
January 4, 2016.
IV. Electronic Submissions (E-Filing)
All documents filed in NRC adjudicatory proceedings, including a
request for hearing, a petition for leave to intervene, any motion or
other document filed in the proceeding prior to the submission of a
request for hearing or petition to intervene, and documents filed by
interested governmental entities participating under 10 CFR 2.315(c),
must be filed in accordance with the NRC's E-Filing rule (72 FR 49139;
August 28, 2007). The E-Filing process requires participants to submit
and serve all adjudicatory documents over the internet, or in some
cases to mail copies on electronic storage media. Participants may not
submit paper copies of their filings unless they seek an exemption in
accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least 10
days prior to the filing deadline, the participant should contact the
Office of the Secretary by email at hearing.docket@nrc.gov, or by
telephone at 301-415-1677, to request (1) a digital identification (ID)
certificate, which allows the participant (or its counsel or
representative) to digitally sign documents and access the E-Submittal
server for any proceeding in which it is participating; and (2) advise
the Secretary that the participant will be submitting a request or
petition for hearing (even in instances in which the participant, or
its counsel or representative, already holds an NRC-issued digital ID
certificate). Based upon this information, the Secretary will establish
an electronic docket for the hearing in this proceeding if the
Secretary has not already established an electronic docket.
Information about applying for a digital ID certificate is
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/getting-started.html. System requirements for accessing
the E-Submittal server are detailed in the NRC's ``Guidance for
Electronic Submission,'' which is available on the agency's public Web
site at https://www.nrc.gov/site-help/e-submittals.html. Participants
may attempt to use other software not listed on the Web site, but
should note that the NRC's E-Filing system does not support unlisted
software, and the NRC Meta System Help Desk will not be able to offer
assistance in using unlisted software.
If a participant is electronically submitting a document to the NRC
in accordance with the E-Filing rule, the participant must file the
document using the NRC's online, Web-based submission form. In order to
serve documents through the Electronic Information Exchange System,
users will be required to install a Web browser plug-in from the NRC's
Web site. Further information on the Web-based submission form,
including the installation of the Web browser plug-in, is available on
the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a request for
hearing or petition for leave to intervene. Submissions should be in
Portable Document Format (PDF) in accordance with NRC guidance
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the
documents are submitted through the NRC's E-Filing system. To be
timely, an electronic filing must be submitted to the E-Filing system
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of
a transmission, the E-Filing system time-stamps the document and sends
the submitter an email notice confirming receipt of the document. The
E-Filing system also distributes an email notice that provides access
to the document to the NRC's Office of the General Counsel and any
others who have advised the Office of the Secretary that they wish to
participate in the proceeding, so that the filer need not serve the
documents on those participants separately. Therefore, applicants and
other participants (or their counsel or representative) must apply for
and receive a digital ID certificate before a hearing request/petition
to intervene is filed so that they can obtain access to the document
via the E-Filing system.
A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System
Help Desk through the ``Contact Us'' link located on the NRC's public
Web site at https://www.nrc.gov/site-help/e-submittals.html, by email to
MSHD.Resource@nrc.gov, or by a toll-free call at 1-866-672-7640. The
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m.,
Eastern Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, Sixteenth
Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland
20852, Attention: Rulemaking and Adjudications Staff. Participants
filing a document in this manner are responsible for serving the
document on all other participants. Filing is considered complete by
first-class mail as of the time of deposit in the mail, or by courier,
express mail, or expedited delivery service upon depositing the
document with the provider of the service. A presiding officer, having
granted an exemption request from using E-Filing, may require a
participant or party to use E-Filing if the presiding officer
subsequently determines that the reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in the
NRC's electronic hearing docket which is available to the public at
https://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the
Commission, or the presiding officer. Participants are requested not to
include personal privacy information, such as social security numbers,
home addresses, or home phone numbers in their filings, unless an NRC
regulation or other law requires submission of such information.
However, in some instances, a request to intervene will require
including information on local residence in order to demonstrate a
proximity assertion of interest in the
[[Page 68577]]
proceeding. With respect to copyrighted works, except for limited
excerpts that serve the purpose of the adjudicatory filings and would
constitute a Fair Use application, participants are requested not to
include copyrighted materials in their submission.
For further details with respect to this amendment action, see the
application for amendment which is available for public inspection at
the NRC's PDR, located at One White Flint North, Room O1-F21, 11555
Rockville Pike (first floor), Rockville, Maryland 20852. Publicly
available documents created or received at the NRC are accessible
electronically through ADAMS in the NRC Library at https://www.nrc.gov/reading-rm/adams.html. If you do not have access to ADAMS or if there
are problems in accessing the documents located in ADAMS, contact the
PDR's Reference staff at 1-800-397-4209, 301-415-4737, or by email to
pdr.resource@nrc.gov.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
Attorney for licensee: Tamra (Tami) Domeyer, Exelon Generation
Company, LLC, 4300 Winfield Road, Warrenville, Illinois 60555.
NRC Branch Chief: Travis L. Tate.
Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation
A. This Order contains instructions regarding how potential parties
to this proceeding may request access to documents containing SUNSI.
B. Within 10 days after publication of this notice of hearing and
opportunity to petition for leave to intervene, any potential party who
believes access to SUNSI is necessary to respond to this notice may
request such access. A ``potential party'' is any person who intends to
participate as a party by demonstrating standing and filing an
admissible contention under 10 CFR 2.309. Requests for access to SUNSI
submitted later than 10 days after publication of this notice will not
be considered absent a showing of good cause for the late filing,
addressing why the request could not have been filed earlier.
C. The requester shall submit a letter requesting permission to
access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, Attention: Rulemakings and
Adjudications Staff, and provide a copy to the Associate General
Counsel for Hearings, Enforcement and Administration, Office of the
General Counsel, Washington, DC 20555-0001. The expedited delivery or
courier mail address for both offices is: U.S. Nuclear Regulatory
Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The email
address for the Office of the Secretary and the Office of the General
Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov,
respectively.\1\ The request must include the following information:
---------------------------------------------------------------------------
\1\ While a request for hearing or petition to intervene in this
proceeding must comply with the filing requirements of the NRC's
``E-Filing Rule,'' the initial request to access SUNSI under these
procedures should be submitted as described in this paragraph.
---------------------------------------------------------------------------
(1) A description of the licensing action with a citation to this
Federal Register notice;
(2) The name and address of the potential party and a description
of the potential party's particularized interest that could be harmed
by the action identified in C.(1); and
(3) The identity of the individual or entity requesting access to
SUNSI and the requester's basis for the need for the information in
order to meaningfully participate in this adjudicatory proceeding. In
particular, the request must explain why publicly-available versions of
the information requested would not be sufficient to provide the basis
and specificity for a proffered contention.
D. Based on an evaluation of the information submitted under
paragraph C.(3) the NRC staff will determine within 10 days of receipt
of the request whether:
(1) There is a reasonable basis to believe the petitioner is likely
to establish standing to participate in this NRC proceeding; and
(2) The requestor has established a legitimate need for access to
SUNSI.
E. If the NRC staff determines that the requestor satisfies both
D.(1) and D.(2) above, the NRC staff will notify the requestor in
writing that access to SUNSI has been granted. The written notification
will contain instructions on how the requestor may obtain copies of the
requested documents, and any other conditions that may apply to access
to those documents. These conditions may include, but are not limited
to, the signing of a Non-Disclosure Agreement or Affidavit, or
Protective Order \2\ setting forth terms and conditions to prevent the
unauthorized or inadvertent disclosure of SUNSI by each individual who
will be granted access to SUNSI.
---------------------------------------------------------------------------
\2\ Any motion for Protective Order or draft Non-Disclosure
Affidavit or Agreement for SUNSI must be filed with the presiding
officer or the Chief Administrative Judge if the presiding officer
has not yet been designated, within 30 days of the deadline for the
receipt of the written access request.
---------------------------------------------------------------------------
F. Filing of Contentions. Any contentions in these proceedings that
are based upon the information received as a result of the request made
for SUNSI must be filed by the requestor no later than 25 days after
the requestor is granted access to that information. However, if more
than 25 days remain between the date the petitioner is granted access
to the information and the deadline for filing all other contentions
(as established in the notice of hearing or opportunity for hearing),
the petitioner may file its SUNSI contentions by that later deadline.
This provision does not extend the time for filing a request for a
hearing and petition to intervene, which must comply with the
requirements of 10 CFR 2.309.
G. Review of Denials of Access.
(1) If the request for access to SUNSI is denied by the NRC staff
after a determination on standing and need for access, the NRC staff
shall immediately notify the requestor in writing, briefly stating the
reason or reasons for the denial.
(2) The requester may challenge the NRC staff's adverse
determination by filing a challenge within 5 days of receipt of that
determination with: (a) The presiding officer designated in this
proceeding; (b) if no presiding officer has been appointed, the Chief
Administrative Judge, or if he or she is unavailable, another
administrative judge, or an administrative law judge with jurisdiction
pursuant to 10 CFR 2.318(a); or (c) officer if that officer has been
designated to rule on information access issues.
H. Review of Grants of Access. A party other than the requester may
challenge an NRC staff determination granting access to SUNSI whose
release would harm that party's interest independent of the proceeding.
Such a challenge must be filed with the Chief Administrative Judge
within 5 days of the notification by the NRC staff of its grant of
access.
If challenges to the NRC staff determinations are filed, these
procedures give way to the normal process for litigating disputes
concerning access to information. The availability of interlocutory
review by the Commission of orders ruling on such NRC staff
determinations (whether
[[Page 68578]]
granting or denying access) is governed by 10 CFR 2.311.\3\
---------------------------------------------------------------------------
\3\ Requesters should note that the filing requirements of the
NRC's E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals
of NRC staff determinations (because they must be served on a
presiding officer or the Commission, as applicable), but not to the
initial SUNSI request submitted to the NRC staff under these
procedures.
---------------------------------------------------------------------------
I. The Commission expects that the NRC staff and presiding officers
(and any other reviewing officers) will consider and resolve requests
for access to SUNSI, and motions for protective orders, in a timely
fashion in order to minimize any unnecessary delays in identifying
those petitioners who have standing and who have propounded contentions
meeting the specificity and basis requirements in 10 CFR part 2.
Attachment 1 to this Order summarizes the general target schedule for
processing and resolving requests under these procedures.
It is ordered.
Dated at Rockville, Maryland, this 30th day of October, 2015.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
Attachment 1--General Target Schedule for Processing and Resolving
Requests for Access to Sensitive Unclassified Non-Safeguards Information
in this Proceeding
------------------------------------------------------------------------
Day Event/Activity
------------------------------------------------------------------------
0........................ Publication of Federal Register notice of
hearing and opportunity to petition for
leave to intervene, including order with
instructions for access requests.
10....................... Deadline for submitting requests for access
to Sensitive Unclassified Non-Safeguards
Information (SUNSI) with information:
Supporting the standing of a potential party
identified by name and address; describing
the need for the information in order for
the potential party to participate
meaningfully in an adjudicatory proceeding.
60....................... Deadline for submitting petition for
intervention containing: (i) Demonstration
of standing; and (ii) all contentions whose
formulation does not require access to SUNSI
(+25 Answers to petition for intervention;
+7 petitioner/requestor reply).
20....................... U.S. Nuclear Regulatory Commission (NRC)
staff informs the requester of the staff's
determination whether the request for access
provides a reasonable basis to believe
standing can be established and shows need
for SUNSI. (NRC staff also informs any party
to the proceeding whose interest independent
of the proceeding would be harmed by the
release of the information.) If NRC staff
makes the finding of need for SUNSI and
likelihood of standing, NRC staff begins
document processing (preparation of
redactions or review of redacted documents).
25....................... If NRC staff finds no ``need'' or no
likelihood of standing, the deadline for
petitioner/requester to file a motion
seeking a ruling to reverse the NRC staff's
denial of access; NRC staff files copy of
access determination with the presiding
officer (or Chief Administrative Judge or
other designated officer, as appropriate).
If NRC staff finds ``need'' for SUNSI, the
deadline for any party to the proceeding
whose interest independent of the proceeding
would be harmed by the release of the
information to file a motion seeking a
ruling to reverse the NRC staff's grant of
access.
30....................... Deadline for NRC staff reply to motions to
reverse NRC staff determination(s).
40....................... (Receipt +30) If NRC staff finds standing and
need for SUNSI, deadline for NRC staff to
complete information processing and file
motion for Protective Order and draft Non-
Disclosure Affidavit. Deadline for applicant/
licensee to file Non-Disclosure Agreement
for SUNSI.
A........................ If access granted: Issuance of presiding
officer or other designated officer decision
on motion for protective order for access to
sensitive information (including schedule
for providing access and submission of
contentions) or decision reversing a final
adverse determination by the NRC staff.
A + 3.................... Deadline for filing executed Non-Disclosure
Affidavits. Access provided to SUNSI
consistent with decision issuing the
protective order.
A + 28................... Deadline for submission of contentions whose
development depends upon access to SUNSI.
However, if more than 25 days remain between
the petitioner's receipt of (or access to)
the information and the deadline for filing
all other contentions (as established in the
notice of hearing or opportunity for
hearing), the petitioner may file its SUNSI
contentions by that later deadline.
A + 53................... (Contention receipt +25) Answers to
contentions whose development depends upon
access to SUNSI.
A + 60................... (Answer receipt +7) Petitioner/Intervenor
reply to answers.
>A + 60.................. Decision on contention admission.
------------------------------------------------------------------------
[FR Doc. 2015-28290 Filed 11-4-15; 8:45 am]
BILLING CODE 7590-01-P