Download as PDF 65992 Federal Register / Vol. 80, No. 208 / Wednesday, October 28, 2015 / Notices the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with he Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a) (1) (iii) and the instructions on the Commission’s Web site (www.ferc.gov) under the ‘‘e-Filing’’ link. Persons unable to file electronically should submit original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Dated: October 22, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–27400 Filed 10–27–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. OR16–1–000] mstockstill on DSK4VPTVN1PROD with NOTICES Bayou Bridge Pipeline, LLC; Notice of Petition for Declaratory Order Take notice that on October 19, 2015, pursuant to Rule 207(a)(2) of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.207(a)(2) (2015), Bayou Bridge Pipeline, LLC (Petitioner), filed a petition for a declaratory order seeking approval of the specified rate structure, terms of service, and prorationing methodology for the proposed Bayou Bridge pipeline project (the ‘‘Bayou Bridge Project’’). Petitioner states that the Bayou Bridge Project is VerDate Sep<11>2014 19:16 Oct 27, 2015 Jkt 238001 intended to provide cost-effective crude oil pipeline transportation from the crude oil terminals, storage, and transportation hub in the vicinity of Nederland, Texas, to refineries and markets in Louisiana, all as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern time on November 19, 2015. Dated: October 22, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–27403 Filed 10–27–15; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00010 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 6643–015] Lee R. and A. Leon Thayn; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Amendment of Exemption. b. Project No: 6643–015. c. Date Filed: October 19, 2015. d. Applicant: Lee R. and A. Leon Thayn. e. Name of Projects: Thayn Project. f. Location: The project is located on the Green River, along the boundary of Grand and Emory Counties, Utah. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Lee R. Thayn, P.O. Box 447, Green River, UT 84525, (435) 564–3325; or Rick Kaster, 4860 N. 115 East, Buhl, ID 83316, (208) 731– 9975. i. FERC Contact: B. Peter Yarrington, (202) 502–6129 or peter.yarrington@ ferc.gov. j. Deadline for filing comments, motions to intervene, and protests is 15 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, or comments using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Please include the project number (P– 6643–015) on any comments, motions to intervene, or protests filed. k. Description of Request: The applicant proposes replacement of the existing rock and timber diversion dam with a new structure primarily consisting of sheet pile walls, structural fill material, and a concrete cap. The existing diversion dam, which is over E:\FR\FM\28OCN1.SGM 28OCN1 mstockstill on DSK4VPTVN1PROD with NOTICES Federal Register / Vol. 80, No. 208 / Wednesday, October 28, 2015 / Notices 100 years old, has undergone significant deterioration, most recently during a high-flow event in 2011. The proposed new diversion dam was designed by the Green River Conservation District and the exemptee in consultation with federal and state resource agencies to ensure a continued supply of agricultural water for local irrigators, and to improve public safety and fish passage. The work would not result in any significant changes to water levels or project operation. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1 (866) 208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply VerDate Sep<11>2014 19:16 Oct 27, 2015 Jkt 238001 with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the amendment application. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: October 21, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–27405 Filed 10–27–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14703–000] Empire State Hydro 302, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On August 25, 2015, Empire State Hydro 302, LLC, filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Braendly Dam Hydroelectric Project to be located on Fishkill River in Dutchess County, New York. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would redevelop an abandoned project and consist of: (1) An existing 130-foot-long, PO 00000 Frm 00011 Fmt 4703 Sfmt 9990 65993 18-foot-high cut stone with a concrete cap dam creating a reservoir with a surface area of approximately 3 acres and a storage capacity of 15 acre-feet at a normal water surface elevation of 119.5 feet mean sea level; (2) a new 6foot-diameter, 300-foot-long steel penstock; (3) a new 50-foot-long by 35foot-wide powerhouse containing two Kaplan turbine units with a rated capacity of 450 kilowatts each; and (4) a new 12.7-kilovolt, 500-foot-long transmission line. The project would have an annual generation of 3,200 megawatt-hours. Applicant Contact: Mark Boumansour, Empire State Hydro 302, LLC, 1401 Walnut Street, Suite 220, Boulder, CO 80302; phone: 303–440– 3378. FERC Contact: Monir Chowdhury; phone: (202) 502–6736. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. The first page of any filing should include docket number P–14703–000. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14703) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: October 22, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–27407 Filed 10–27–15; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\28OCN1.SGM 28OCN1

Agencies

[Federal Register Volume 80, Number 208 (Wednesday, October 28, 2015)]
[Notices]
[Pages 65992-65993]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-27405]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 6643-015]


Lee R. and A. Leon Thayn; Notice of Application Accepted for 
Filing, Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Amendment of Exemption.
    b. Project No: 6643-015.
    c. Date Filed: October 19, 2015.
    d. Applicant: Lee R. and A. Leon Thayn.
    e. Name of Projects: Thayn Project.
    f. Location: The project is located on the Green River, along the 
boundary of Grand and Emory Counties, Utah.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Lee R. Thayn, P.O. Box 447, Green River, UT 
84525, (435) 564-3325; or Rick Kaster, 4860 N. 115 East, Buhl, ID 
83316, (208) 731-9975.
    i. FERC Contact: B. Peter Yarrington, (202) 502-6129 or 
peter.yarrington@ferc.gov.
    j. Deadline for filing comments, motions to intervene, and protests 
is 15 days from the issuance date of this notice by the Commission. The 
Commission strongly encourages electronic filing. Please file motions 
to intervene, protests, or comments using the Commission's eFiling 
system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. Please include the project number (P-
6643-015) on any comments, motions to intervene, or protests filed.
    k. Description of Request: The applicant proposes replacement of 
the existing rock and timber diversion dam with a new structure 
primarily consisting of sheet pile walls, structural fill material, and 
a concrete cap. The existing diversion dam, which is over

[[Page 65993]]

100 years old, has undergone significant deterioration, most recently 
during a high-flow event in 2011. The proposed new diversion dam was 
designed by the Green River Conservation District and the exemptee in 
consultation with federal and state resource agencies to ensure a 
continued supply of agricultural water for local irrigators, and to 
improve public safety and fish passage. The work would not result in 
any significant changes to water levels or project operation.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits 
in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1 (866) 208-3676 or email 
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or 
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis and otherwise comply with the requirements of 18 CFR 
4.34(b). All comments, motions to intervene, or protests should relate 
to project works which are the subject of the amendment application. 
Agencies may obtain copies of the application directly from the 
applicant. A copy of any protest or motion to intervene must be served 
upon each representative of the applicant specified in the particular 
application. If an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 
385.2010.

    Dated: October 21, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-27405 Filed 10-27-15; 8:45 am]
 BILLING CODE 6717-01-P