Drawbridge Operation Regulation; Atlantic Intracoastal Waterway, John F. Kennedy Space Center/NASA Parkway Bridge, Addison Point, FL, 65138 [2015-27115]
Download as PDF
65138
Federal Register / Vol. 80, No. 206 / Monday, October 26, 2015 / Rules and Regulations
Coastal
Bridge Company, LLC, on behalf of
Louisiana Department of Transportation
and Development (LDOTD), requested a
deviation from the operating regulation
for the SR 22 Bridge across the
Tchefuncta River, mile 2.5, at
Madisonville, St. Tammany Parish,
Louisiana. The SR 22 Bridge is a swing
bridge with a vertical clearance of 6.2
feet above Mean High Water (MHW) in
the closed-to-navigation position and
unlimited clearance in the open-tonavigation position. The operation of
this bridge is currently governed by 33
CFR 117.500.
The closure is necessary for
mechanical and electrical rehabilitation
of the bridge. The deviation from the
operating regulations will be in effect
from Monday, November 2, 2015 until
Tuesday, December 15, 2015, except for
weekends. Within this time frame there
will be multiple closure periods,
deviating from the regular operating
schedule, as follows:
(1) The first closure period will be
from 7 a.m. on November 9th, until 7
p.m. on November 13th, 2015, except
that the bridge will open at 9 a.m. and
7 p.m., daily, to pass all vessel traffic;
(2) The second closure period will be
from 7 a.m. on November 16th until 9
p.m. on November 17th except that the
bridge will open at 9 a.m. and 7 p.m.,
daily, to pass all vessel traffic;
(3) The third closure period will be
from 7 a.m. on November 23rd until 9
p.m. on November 24th except that the
bridge will open at 9 a.m. and 7 p.m.,
daily, to pass all vessel traffic;
(4) The fourth closure period will be
a total closure from 7 a.m. on November
30th until 7 p.m. on December 4th; there
will be no openings during this period;
(5) The fifth and final closure period
will be a total closure from 9 a.m. on
December 14th until 7 p.m. on
December 15th; there will be no
openings during this period. All work is
expected to be completed by 7 p.m. on
Tuesday, December 15, 2015.
Any changes to the scheduled closure
times will be announced through the
Local Notice to Mariners or through a
broadcast. The traffic on the Tchefuncta
River is primarily recreational with
minimal commercial traffic. The
contractor approached each marina and
business that could possibly be
impacted and forwarded them a copy of
the work schedule. No negative
comments were noted.
Vessels able to pass through the
bridge in the closed-to-navigation
position may do so at anytime. The
bridge will not be able to open for
emergencies and there is no immediate
alternate route for vessels to pass. The
asabaliauskas on DSK5VPTVN1PROD with RULES
SUPPLEMENTARY INFORMATION:
VerDate Sep<11>2014
17:27 Oct 23, 2015
Jkt 238001
Coast Guard will also inform the users
of the waterways through our Local and
Broadcast Notices to Mariners of the
change in operating schedule for the
bridge so that vessels can arrange their
transits to minimize any impact caused
by the temporary deviation.
In accordance with 33 CFR 117.35(e),
the drawbridge must return to its regular
operating schedule immediately at the
end of the designated time periods. This
deviation from the operating regulations
is authorized under 33 CFR 117.35.
Dated: October 20, 2015.
David M. Frank,
Bridge Administrator, Eighth Coast Guard
District.
[FR Doc. 2015–27131 Filed 10–23–15; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2015–0904]
RIN 1625–AA09
Drawbridge Operation Regulation;
Atlantic Intracoastal Waterway, John F.
Kennedy Space Center/NASA Parkway
Bridge, Addison Point, FL
Notice of deviation from
drawbridge regulation.
ACTION:
The Coast Guard has issued a
temporary deviation from the operating
schedule that governs the John F.
Kennedy Space Center/NASA Parkway
Bridge across the Atlantic Intracoastal
Waterway, mile 885.0, Addison Point,
FL. For the safety of the participants,
this temporary operating schedule will
allow the bridge to not open to
navigation including tugs with tows,
during the Rocketman Triathlon in
November.
SUMMARY:
This deviation is effective from
7:30 a.m. on November 15, 2015 through
3 p.m. November 15, 2015.
ADDRESSES: The docket for this
deviation, [USCG–2015–0904] is
available at https://www.regulations.gov.
FOR FURTHER INFORMATION CONTACT: If
you have questions about this temporary
deviation, call or email LT Storm, Coast
Guard Sector Jacksonville, Chief,
Prevention Office; telephone 904–564–
7563, email Allan.h.storm@uscg.mil.
SUPPLEMENTARY INFORMATION: In order to
accommodate the annual Triathlon, a
temporary schedule deviation has been
authorized for the John F. Kennedy
Space Center (NASA) Parkway Bridge,
DATES:
PO 00000
Frm 00018
Fmt 4700
Sfmt 4700
across the Atlantic Intracoastal
Waterway, mile 885.0 at Addison Point,
FL. This deviation is in effect from 7:30
a.m. to 3 p.m. on November 15, 2015.
During this time, the bridge shall remain
closed to navigation, including tugs
with tows. Currently, the bridge opens
as required per 33 CFR 117.261(l). The
regulation changes may have a minor
impact on vessels transiting the Atlantic
Intracoastal Waterway in the vicinity of
Addison Point, FL, but will still meet
the reasonable needs of navigation.
The John F. Kennedy Space Center
(NASA) Parkway Bridge provides a
vertical clearance of 27 feet at mean
high water in the closed position and a
horizontal clearance of 90 feet. Vessels
able to pass through the bridge in the
closed position may do so at anytime.
The bridge will be able to open for
emergencies. The Coast Guard will
inform users of the waterways through
Local and Broadcast Notices to Mariners
of the change in operating schedule for
the bridge so that vessels can arrange
transits to minimize any impact caused
by the temporary deviation.
In accordance with 33 CFR 117.35(e),
the drawbridge must return to its regular
operating schedule immediately
following the end of the effective period
of this temporary deviation. This
deviation from the normal operating
regulations is authorized under 33 CFR
117.35.
Dated: 21 October 2015.
Barry Dragon,
Director, Bridge Administration, Seventh
Coast Guard District.
[FR Doc. 2015–27115 Filed 10–23–15; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2015–0970]
Drawbridge Operation Regulation;
Houma Navigation Canal, Mile 36.0, at
Houma, Terrebonne Parish, LA
Coast Guard, DHS.
Notice of deviation from
regulation.
AGENCY:
ACTION:
The Coast Guard has issued a
temporary deviation from the operating
schedule that governs the SR 661 Swing
Bridge across the Houma Navigation
Canal, mile 36.0, in Houma, Terrebonne
Parish, Louisiana. The deviation is
necessary to conduct scheduled metal
repairs and maintenance. This deviation
allows the bridge to remain closed-to-
SUMMARY:
E:\FR\FM\26OCR1.SGM
26OCR1
Agencies
[Federal Register Volume 80, Number 206 (Monday, October 26, 2015)]
[Rules and Regulations]
[Page 65138]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-27115]
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG-2015-0904]
RIN 1625-AA09
Drawbridge Operation Regulation; Atlantic Intracoastal Waterway,
John F. Kennedy Space Center/NASA Parkway Bridge, Addison Point, FL
ACTION: Notice of deviation from drawbridge regulation.
-----------------------------------------------------------------------
SUMMARY: The Coast Guard has issued a temporary deviation from the
operating schedule that governs the John F. Kennedy Space Center/NASA
Parkway Bridge across the Atlantic Intracoastal Waterway, mile 885.0,
Addison Point, FL. For the safety of the participants, this temporary
operating schedule will allow the bridge to not open to navigation
including tugs with tows, during the Rocketman Triathlon in November.
DATES: This deviation is effective from 7:30 a.m. on November 15, 2015
through 3 p.m. November 15, 2015.
ADDRESSES: The docket for this deviation, [USCG-2015-0904] is available
at https://www.regulations.gov.
FOR FURTHER INFORMATION CONTACT: If you have questions about this
temporary deviation, call or email LT Storm, Coast Guard Sector
Jacksonville, Chief, Prevention Office; telephone 904-564-7563, email
Allan.h.storm@uscg.mil.
SUPPLEMENTARY INFORMATION: In order to accommodate the annual
Triathlon, a temporary schedule deviation has been authorized for the
John F. Kennedy Space Center (NASA) Parkway Bridge, across the Atlantic
Intracoastal Waterway, mile 885.0 at Addison Point, FL. This deviation
is in effect from 7:30 a.m. to 3 p.m. on November 15, 2015. During this
time, the bridge shall remain closed to navigation, including tugs with
tows. Currently, the bridge opens as required per 33 CFR 117.261(l).
The regulation changes may have a minor impact on vessels transiting
the Atlantic Intracoastal Waterway in the vicinity of Addison Point,
FL, but will still meet the reasonable needs of navigation.
The John F. Kennedy Space Center (NASA) Parkway Bridge provides a
vertical clearance of 27 feet at mean high water in the closed position
and a horizontal clearance of 90 feet. Vessels able to pass through the
bridge in the closed position may do so at anytime. The bridge will be
able to open for emergencies. The Coast Guard will inform users of the
waterways through Local and Broadcast Notices to Mariners of the change
in operating schedule for the bridge so that vessels can arrange
transits to minimize any impact caused by the temporary deviation.
In accordance with 33 CFR 117.35(e), the drawbridge must return to
its regular operating schedule immediately following the end of the
effective period of this temporary deviation. This deviation from the
normal operating regulations is authorized under 33 CFR 117.35.
Dated: 21 October 2015.
Barry Dragon,
Director, Bridge Administration, Seventh Coast Guard District.
[FR Doc. 2015-27115 Filed 10-23-15; 8:45 am]
BILLING CODE 9110-04-P