Dominion Transmission, Inc.; Notice of Application, 64408-64409 [2015-26899]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
64408
Federal Register / Vol. 80, No. 205 / Friday, October 23, 2015 / Notices
Filed Date: 10/16/15.
Accession Number: 20151016–5405.
Comments Due: 5 p.m. ET 11/6/15.
Docket Numbers: ER16–110–000.
Applicants: Windom Transmission,
LLC.
Description: § 205(d) Rate Filing:
Windom Transmission and White Caps
Interconnection and Transmission
Agreement to be effective 12/15/2015.
Filed Date: 10/16/15.
Accession Number: 20151016–5407.
Comments Due: 5 p.m. ET 11/6/15.
Docket Numbers: ER16–111–000.
Applicants: Puget Sound Energy, Inc.
Description: § 205(d) Rate Filing:
Vantage Long Term P–T–P Service
Agreement to be effective 10/1/2015.
Filed Date: 10/16/15.
Accession Number: 20151016–5452.
Comments Due: 5 p.m. ET 11/6/15.
Docket Numbers: ER16–112–000.
Applicants: Puget Sound Energy, Inc.
Description: Initial rate filing: Kittitas
NITSA SA No. 796 and NOA SA No.
797 to be effective 9/1/2015.
Filed Date: 10/16/15.
Accession Number: 20151016–5460.
Comments Due: 5 p.m. ET 11/6/15.
Docket Numbers: ER16–113–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: First
Revised Service Agreement No. 3990;
Queue W1–130 (WMPA) to be effective
9/30/2015.
Filed Date: 10/19/15.
Accession Number: 20151019–5203.
Comments Due: 5 p.m. ET 11/9/15.
Docket Numbers: ER16–114–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Ameren Illinois Company.
Description: § 205(d) Rate Filing:
2015–10–19_SA 1975 Ameren-Norris
4th Rev WDS Agreement to be effective
10/1/2015.
Filed Date: 10/19/15.
Accession Number: 20151019–5215.
Comments Due: 5 p.m. ET 11/9/15.
Docket Numbers: ER16–115–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: 3rd
Quarter 2015 Update to OA/RAA
Member Lists to be effective 9/30/2015.
Filed Date: 10/19/15.
Accession Number: 20151019–5243.
Comments Due: 5 p.m. ET 11/9/15.
Docket Numbers: ER16–116–000.
Applicants: ISO New England Inc.,
Eversource Energy Service Company.
Description: § 205(d) Rate Filing:
Eversource Energy Service Company—
Attachment F to be effective 4/16/2015.
Filed Date: 10/19/15.
Accession Number: 20151019–5244.
VerDate Sep<11>2014
18:05 Oct 22, 2015
Jkt 238001
Comments Due: 5 p.m. ET 11/9/15.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: October 19, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–26959 Filed 10–22–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD06–6–000]
Joint Meeting of the Nuclear
Regulatory Commission and the
Federal Energy Regulatory
Commission; Notice of Joint Meeting
of the Federal Energy Regulatory
Commission and the Nuclear
Regulatory Commission
The Federal Energy Regulatory
Commission (FERC) and the Nuclear
Regulatory Commission (NRC) will hold
a joint meeting on Wednesday, October
21, 2015 at the headquarters of the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426. The meeting is expected to begin
at 9:00 a.m. and conclude at
approximately 11:30 a.m. Eastern Time.
Members of the public may attend the
open session. Commissioners from both
agencies are expected to participate.
The format for the joint meeting will
consist of discussions between the two
sets of Commissioners following
presentations by their respective staffs.
In addition, representatives of the North
American Electric Reliability
Corporation (NERC) will attend and
participate in this meeting.
The technical conference will be
transcribed. Transcripts of the technical
conference will be available for a fee
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
from Ace-Federal Reporters, Inc. (202)
347–3700. There will be a free webcast
of the conference. The webcast will
allow persons to listen to the technical
conference, but not participate. Anyone
with Internet access can listen to the
conference by navigating to the
Calendar of Events at www.ferc.gov and
locating the technical conference in the
Calendar. The technical conference will
contain a link to its webcast. The
Capital Connection provides technical
support for the webcast and offers the
option of listing to the meeting via
phone-bridge for a fee. If you have any
questions, please visit
www.CapitolConnection.org or call 703–
993–3100.1
Pre-registration is not required but is
highly encouraged for those attending in
person. Attendees may register in
advance at the following Web page:
https://www.ferc.gov/whats-new/
registration/10-21-15-NRC-form.asp.
Attendees should bring a photo ID and
allow time to pass through building
security procedures. There is no fee to
attend the open meeting.
Commission conferences are
accessible under section 508 of the
Rehabilitation Act of 1973. For
accessibility accommodations please
send an email to accessibility@ferc.gov
or call toll free 1–866–208–3372 (voice)
or 202–502 -8659 (TTY); or send a fax
to 202–208–2106 with the required
accommodations.
Questions about the meeting should
be directed to Sarah McKinley at
sarah.mckinley@ferc.gov or by phone at
202–502–8368.
Dated: October 16, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–26898 Filed 10–22–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–1–000]
Dominion Transmission, Inc.; Notice of
Application
Take notice that on October 1, 2015,
Dominion Transmission, Inc. (DTI) 120
Tredegar Street, Richmond, VA, filed an
application pursuant to section 7(b) of
the Natural Gas Act (NGA) and the
Federal Energy Regulatory
Commission’s (Commission) regulations
seeking authorization to: (1) Abandon
1 The webcast will continue to be available on the
Calendar of Events on the Commission’s Web site
www.ferc.gov for three months after the conference.
E:\FR\FM\23OCN1.SGM
23OCN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 205 / Friday, October 23, 2015 / Notices
by sale its gathering and products
extraction facilities to Dominion
Gathering & Processing, Inc. (DGP)
located within the states of West
Virginia and Pennsylvania; and (2)
refunctionalize certain compression
facilities at a processing plant located in
Lewis County, West Virginia to
gathering and include the compression
facilities in the abandonment by sale to
DGP, all as more fully described in the
application which is on file with the
Commission and open to public
inspection. The filing may also be
viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
Any questions regarding this
application should be directed Machelle
F. Grim, Dominion Resources Services,
Inc., 701 East Cary Street, Richmond,
VA 23219, or call (804) 771–3805, or fax
(804) 771–4804, or by email:
Machelle.F.Grim@dom.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
VerDate Sep<11>2014
18:05 Oct 22, 2015
Jkt 238001
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time on November 6, 2015.
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
64409
Dated: October 16, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–26899 Filed 10–22–15; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–9023–6]
Environmental Impact Statements;
Notice of Availability
Responsible Agency: Office of Federal
Activities, General Information (202)
564–7146 or https://www2.epa.gov/nepa.
Weekly receipt of Environmental Impact
Statements (EISs).
Filed 10/12/2015 Through 10/16/2015.
Pursuant to 40 CFR 1506.9.
Notice
Section 309(a) of the Clean Air Act
requires that EPA make public its
comments on EISs issued by other
Federal agencies. EPA’s comment letters
on EISs are available at: https://
cdxnodengn.epa.gov/cdx-nepa-public/
action/eis/search.
EIS No. 20150291, Draft, NMFS, FL,
Regulatory Amendment 16 to the
Fishery Management Plan for the
Snapper-Grouper Fishery of the South
Atlantic Region, Comment Period
Ends: 12/07/2015, Contact: Rick
DeVictor 727–551–5720.
EIS No. 20150292, Final, HUD, CA,
Potrero HOPE SF Master Plan, Review
Period Ends: 11/23/2015, Contact:
Eugene Flannery 415–701–5598.
EIS No. 20150293, Final, USFS, AK,
Saddle Lakes Timber Sale, Review
Period Ends: 12/07/2015, Contact:
Daryl Bingham 907–228–4114.
EIS No. 20150294, Draft, FHWA, NC, I–
26 Asheville Connector, Comment
Period Ends: 12/07/2015, Contact:
John F. Sullivan, III 919–856–4346
ext. 122.
Dated: October 20, 2015.
Karin Leff
Acting Director, NEPA Compliance Division,
Office of Federal Activities.
[FR Doc. 2015–27054 Filed 10–22–15; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPPT–2015–0503; FRL–9934–96]
Certain New Chemicals; Receipt and
Status Information for August 2015
Environmental Protection
Agency (EPA).
AGENCY:
E:\FR\FM\23OCN1.SGM
23OCN1
Agencies
[Federal Register Volume 80, Number 205 (Friday, October 23, 2015)]
[Notices]
[Pages 64408-64409]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-26899]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP16-1-000]
Dominion Transmission, Inc.; Notice of Application
Take notice that on October 1, 2015, Dominion Transmission, Inc.
(DTI) 120 Tredegar Street, Richmond, VA, filed an application pursuant
to section 7(b) of the Natural Gas Act (NGA) and the Federal Energy
Regulatory Commission's (Commission) regulations seeking authorization
to: (1) Abandon
[[Page 64409]]
by sale its gathering and products extraction facilities to Dominion
Gathering & Processing, Inc. (DGP) located within the states of West
Virginia and Pennsylvania; and (2) refunctionalize certain compression
facilities at a processing plant located in Lewis County, West Virginia
to gathering and include the compression facilities in the abandonment
by sale to DGP, all as more fully described in the application which is
on file with the Commission and open to public inspection. The filing
may also be viewed on the web at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-
free, (866) 208-3676 or TTY, (202) 502-8659.
Any questions regarding this application should be directed
Machelle F. Grim, Dominion Resources Services, Inc., 701 East Cary
Street, Richmond, VA 23219, or call (804) 771-3805, or fax (804) 771-
4804, or by email: Machelle.F.Grim@dom.com.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 7 copies of filings made in the proceeding with the Commission
and must mail a copy to the applicant and to every other party. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commentors will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commentors will not be required to serve copies of filed
documents on all other parties. However, the non-party commentors will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 5 copies of the protest or intervention to the
Federal Energy regulatory Commission, 888 First Street NE., Washington,
DC 20426.
Comment Date: 5:00 p.m. Eastern Time on November 6, 2015.
Dated: October 16, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-26899 Filed 10-22-15; 8:45 am]
BILLING CODE 6717-01-P