Pipeline Safety: Safety of Hazardous Liquid Pipelines, 61609-61643 [2015-25359]
Download as PDF
Vol. 80
Tuesday,
No. 197
October 13, 2015
Part III
Department of Transportation
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Pipeline and Hazardous Materials Safety Administration
49 CFR Part 195
Pipeline Safety: Safety of Hazardous Liquid Pipelines; Proposed Rule
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
PO 00000
Frm 00001
Fmt 4717
Sfmt 4717
E:\FR\FM\13OCP3.SGM
13OCP3
61610
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials
Safety Administration
49 CFR Part 195
[Docket No. PHMSA–2010–0229]
RIN 2137–AE66
Pipeline Safety: Safety of Hazardous
Liquid Pipelines
Pipeline and Hazardous
Materials Safety Administration
(PHMSA), Department of Transportation
(DOT).
ACTION: Notice of proposed rulemaking.
AGENCY:
In recent years, there have
been significant hazardous liquid
pipeline accidents, most notably the
2010 crude oil spill near Marshall,
Michigan, during which almost one
million gallons of crude oil were spilled
into the Kalamazoo River. In response to
accident investigation findings, incident
report data and trends, and stakeholder
input, PHMSA published an Advance
Notice of Proposed Rulemaking
(ANPRM) in the Federal Register on
October 18, 2010. The ANPRM solicited
stakeholder and public input and
comments on several aspects of
hazardous liquid pipeline regulations
being considered for revision or
updating in order to address the lessons
learned from the Marshall, Michigan
accident and other pipeline safety
issues. Subsequently, Congress enacted
the Pipeline Safety, Regulatory
Certainty, and Job Creation Act that
included several provisions that are
relevant to the regulation of hazardous
liquid pipelines. Shortly after the
Pipeline Safety, Regulatory Certainty,
and Job Creation Act was passed, the
National Transportation Safety Board
(NTSB) issued its accident investigation
report on the Marshall, Michigan
accident. In it, NTSB made additional
recommendations regarding the need to
revise and update hazardous liquid
pipeline regulations.
In response to these mandates,
recommendations, lessons learned, and
public input, PHMSA is proposing to
make changes to the hazardous liquid
pipeline safety regulations. PHMSA is
proposing these changes to improve
protection of the public, property, and
the environment by closing regulatory
gaps where appropriate, and ensuring
that operators are increasing the
detection and remediation of unsafe
conditions, and mitigating the adverse
effects of pipeline failures.
DATES: Persons interested in submitting
written comments on this NPRM must
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
SUMMARY:
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
do so by January 8, 2016. PHMSA will
consider late filed comments so far as
practicable.
ADDRESSES: You may submit comments
identified by the docket number
PHMSA–2010–0229 by any of the
following methods:
Federal eRulemaking Portal: https://
www.regulations.gov. Follow the online
instructions for submitting comments.
Fax: 1–202–493–2251.
Mail: Hand Delivery: U.S. DOT Docket
Management System, West Building
Ground Floor, Room W12–140, 1200
New Jersey Avenue SE., Washington,
DC 20590–0001, between 9 a.m. and 5
p.m., Monday through Friday, except
federal holidays.
Instructions: If you submit your
comments by mail, submit two copies.
To receive confirmation that PHMSA
received your comments, include a selfaddressed stamped postcard.
Note: Comments are posted without
changes or edits to https://
www.regulations.gov, including any personal
information provided. There is a privacy
statement published on https://
www.regulations.gov.
FOR FURTHER INFORMATION CONTACT:
Mike Israni, by telephone at 202–366–
4571, by fax at 202–366–4566, or by
mail at U.S. DOT, PHMSA, 1200 New
Jersey Avenue SE., PHP–30,
Washington, DC 20590–0001.
SUPPLEMENTARY INFORMATION:
Outline of this document:
I. Executive Summary
II. Background and NPRM Proposals
III. Analysis of Advance Notice of Proposed
Rulemaking
A. Scope of Part 195 and Existing
Regulatory Exceptions
B. Definition of High Consequence Area
C. Leak Detection Equipment and
Emergency Flow Restricting Devices
D. Valve Spacing
E. Repair Criteria Outside of High
Consequence Areas
F. Stress Corrosion Cracking
IV. Section by Section Analysis
V. Regulatory Notices and Proposed Changes
to Regulatory Text
I. Executive Summary
In recent years, there have been
significant hazardous liquid pipeline
accidents, most notably the 2010 crude
oil spill near Marshall, Michigan, during
which almost one million gallons of
crude oil were spilled into the
Kalamazoo River. In response to
accident investigation findings, incident
report data and trends, and stakeholder
input, PHMSA published an ANPRM in
the Federal Register on October 18,
2010, (75 FR 63774). The ANPRM
solicited stakeholder and public input
and comments on several aspects of
PO 00000
Frm 00002
Fmt 4701
Sfmt 4702
hazardous liquid pipeline regulations
being considered for revision or
updating in order to address the lessons
learned from the Marshall, Michigan
accident and other pipeline safety
issues.
Subsequently, Congress enacted the
Pipeline Safety, Regulatory Certainty,
and Job Creation Act of 2011 (Pub. L.
112–90) (The Act). That legislation
included several provisions that are
relevant to the regulation of hazardous
liquid pipelines. Shortly after the Act
was passed, NTSB issued its accident
investigation report on the Marshall,
Michigan accident. In it, NTSB made
additional recommendations regarding
the need to revise and update hazardous
liquid pipeline regulations. Specifically,
the NTSB issued recommendations P–
12–03 and P–12–04 respectively, which
addressed detection of pipeline cracks
and ‘‘discovery of condition’’. The
‘‘discovery of condition’’
recommendation would require, in
cases where a determination about
pipeline threats has not been obtained
within 180 days following the date of
inspection, that pipeline operators
notify the Pipeline and Hazardous
Materials Safety Administration and
provide an expected date when
adequate information will become
available.
The Government Accounting Office
(GAO) also issued a recommendation in
2012 concerning hazardous liquid and
gas gathering pipelines.
Recommendation GAO–12–388, dated
March 22, 2012, states ‘‘To enhance the
safety of unregulated onshore hazardous
liquid and gas gathering pipelines, the
Secretary of Transportation should
direct the PHMSA Administrator to
collect data from operators of federally
unregulated onshore hazardous liquid
and gas gathering pipelines, subsequent
to an analysis of the benefits and
industry burdens associated with such
data collection’’.
In response to these mandates,
recommendations, lessons learned, and
public input, PHMSA is proposing to
make certain changes to the Hazardous
Liquid Pipeline Safety Regulations. The
first and second proposals are to extend
reporting requirements to all hazardous
liquid gravity and gathering lines. The
collection of information about these
lines is authorized under the Pipeline
Safety Laws, and the resulting data will
assist in determining whether the
existing federal and state regulations for
these lines are adequate.
The third proposal is to require
inspections of pipelines in areas
affected by extreme weather, natural
disasters, and other similar events. Such
inspections will ensure that pipelines
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
are still capable of being safely operated
after these events. The fourth proposal
is to require periodic inline integrity
assessments of hazardous liquid
pipelines that are located outside of
HCAs. HCA’s are already covered under
the IM program requirements. These
assessments will provide critical
information about the condition of these
pipelines, including the existence of
internal and external corrosion and
deformation anomalies.
The fifth proposal is to require the use
of leak detection systems on hazardous
liquid pipelines in all locations. The use
of such systems will help to mitigate the
effects of hazardous liquid pipeline
failures that occur outside of HCAs. The
sixth proposal is to modify the
provisions for making pipeline repairs.
Additional conservatism will be
incorporated into the existing repair
criteria and an adjusted schedule will be
established to provide greater
uniformity. These criteria will also be
made applicable to all hazardous liquid
pipelines, with an extended timeframe
for making repairs outside of HCAs.
The seventh proposal is to require
that all pipelines subject to the IM
requirements be capable of
accommodating inline inspection tools
within 20 years, unless the basic
construction of a pipeline cannot be
modified to permit that accommodation.
Inline inspection tools are an effective
means of assessing the integrity of a
pipeline and broadening their use will
improve the detection of anomalies and
prevent or mitigate future accidents in
high-risk areas. Finally, other
regulations will be clarified to improve
certainty and compliance. PHMSA
estimates that 421 hazardous liquid
operators may incur costs to comply
with the proposed rule. The estimated
annual costs for the different
requirements range from approximately
$1,000 to $16.7 million, with aggregate
costs of approximately $22.4 million.
These wide ranges exist because the
requirements vary widely. For example,
some requirements apply only to
pipelines within HCAs, some only to
those outside HCAs, and some to both;
other requirements apply only to
onshore pipelines, and others to both
on- and offshore; the length of pipeline,
and the number of operators affected
both vary for the different requirements.
These proposals are designed to mitigate
or prevent some number of hazardous
liquid pipeline incidents resulting in
annualized benefits estimated between
approximately $3.5 and $17.7 million,
depending on the requirement. Factors
such as increased safety, public
confidence that all pipelines are
regulated, quicker discovery of leaks
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
and mitigation of environmental
damages, and better risk management
are considered in this analysis. The
dollar value of fatalities, injuries, and
property damages due to pipeline
incidents are societal costs and their
prevention represents potential benefits.
The changes proposed in this Notice of
Proposed Rulemaking (NPRM) are
expected to enhance overall pipeline
safety and protection of the
environment.
II. Background and NPRM Proposals
Congress established the current
framework for regulating the safety of
hazardous liquid pipelines in the
Hazardous Liquid Pipeline Safety Act
(HLPSA) of 1979 (Pub. L. 96–129). Like
its predecessor, the Natural Gas Pipeline
Safety Act (NGPSA) of 1968 (Pub. L. 90–
481), the HLPSA provides the Secretary
of Transportation (Secretary) with the
authority to prescribe minimum federal
safety standards for hazardous liquid
pipeline facilities. That authority, as
amended in subsequent
reauthorizations, is currently codified in
the Pipeline Safety Laws (49 U.S.C.
60101 et seq.).
PHMSA is the agency within DOT
that administers the Pipeline Safety
Laws. PHMSA has issued a set of
comprehensive safety standards for the
design, construction, testing, operation,
and maintenance of hazardous liquid
pipelines. Those standards are codified
in the Hazardous Liquid Pipeline Safety
Regulations (49 CFR part 195).
Part 195 applies broadly to the
transportation of hazardous liquids or
carbon dioxide by pipeline, including
on the Outer Continental Shelf, with
certain exceptions set forth by statute or
regulation. Performance-based safety
standards are generally favored (i.e., a
particular objective is specified, but the
method of achieving that objective is
not). Risk management principles play a
critical role in the IM requirements for
HCA’s.
PHMSA exercises primary regulatory
authority over interstate hazardous
liquid pipelines, and the owners and
operators of those facilities must comply
with safety standards in part 195. The
states may submit a certification to
regulate the safety standards and
practices for intrastate pipelines. States
certified to regulate their intrastate lines
can also enter into agreements with
PHMSA to serve as an agent for
inspecting interstate facilities.
Most state pipeline safety programs
are administered by public utility
commissions. These state authorities
must adopt the Pipeline Safety
Regulations as part of a certification or
agreement, but can establish more
PO 00000
Frm 00003
Fmt 4701
Sfmt 4702
61611
stringent safety standards for those
intrastate pipeline facilities that they
have responsibility to regulate. PHMSA
cannot regulate the safety standards or
practices for an intrastate pipeline
facility if a state has a current
certification to regulate such facilities.
Congress recently enacted the
Pipeline Safety, Regulatory Certainty,
and Job Creation Act of 2011 (Pub. L.
112–90) (The Act). That legislation
included several provisions that are
relevant to the regulation of hazardous
liquid pipelines. As part of the
rulemaking process, PHMSA presented
proposed changes in response to this
Act in an ANPRM published in the
Federal Register on October 18, 2010,
(75 FR 63774). This NPRM will, in the
paragraphs that follow, describe each of
the proposals PHMSA will make along
with a statement of need for each and
an explanation of how each of these
proposals improve the pipeline safety
regulations.
Extend Certain Reporting Requirements
to All Gravity and Rural Hazardous
Liquid Gathering Lines
Gravity lines; pipelines that carry
product by means of gravity, are
currently exempt from PHMSA
regulations. Many gravity lines are short
and within tank farms or other pipeline
facilities; however, some gravity lines
are longer and are capable of building
up large amounts of pressure. PHMSA is
aware of gravity lines that traverse long
distances with significant elevation
changes which could have significant
consequences in the event of a release.
In order for PHMSA to effectively
analyze safety performance and pipeline
risk of gravity lines, PHMSA needs basic
data about those pipelines. The agency
has the statutory authority to gather data
for all gravity lines (49 U.S.C. 60117(b)),
and that authority was not affected by
any of the provisions in the Pipeline
Safety Act of 2011. Accordingly,
PHMSA is proposing to add 49 CFR
195.1(a)(5) to require that the operators
of all gravity lines comply with
requirements for submitting annual,
safety-related condition, and incident
reports. PHMSA estimates that, at most,
five hazardous liquid pipeline operators
will be affected. Based on comments
from API–AOPL to the ANPRM, 3
operators have approximately 17 miles
of gravity fed pipelines. PHMSA
estimated that proportionally 5
operators would have 28 miles of
gravity-fed pipelines.
PHMSA is also proposing to extend
the reporting requirements of part 195 to
all hazardous liquid gathering lines.
According to the legislative history,
Congress originally opposed any
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
61612
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
regulation of rural gathering lines in the
Hazardous Liquid Pipeline Safety Act of
1979 (Pub. L. 96–129) for policy reasons
(i.e., those lines did not present a
significant risk to public safety to justify
federal regulation based on the data
available at that time). See S. REP. NO.
96–182 (May 15, 1979), reprinted in
1979 U.S.C.C.A.N. 1971, 1972. However,
Congress eventually relaxed that
prohibition in the Pipeline Safety Act of
1992 (Pub. L. 102–508) and authorized
the issuance of safety standards for
regulated rural gathering lines based on
a consideration of certain factors and
subject to certain exclusions. When
PHMSA adopted the current
requirements for regulated rural
gathering lines, the agency made certain
policy judgments in implementing those
statutory provisions based on the
information available at that time.
Recent data indicates, however, that
PHMSA regulates less than 4,000 miles
of the approximately 30,000 to 40,000
miles of onshore hazardous liquid
gathering lines in the United States.
That means that as much as 90 percent
of the onshore gathering line mileage is
not currently subject to any minimum
federal pipeline safety standards. The
NTSB has also raised concerns about the
safety of hazardous liquid gathering
lines in the Gulf of Mexico and its
inlets, which are only subject to certain
inspection and reburial requirements.1
Congress also ordered the review of
existing state and federal regulations for
hazardous liquid gathering lines in the
Pipeline Safety Act of 2011, to prepare
a report on whether any of the existing
exceptions for these lines should be
modified or repealed, and to determine
whether hazardous liquid gathering
lines located offshore or in the inlets of
the Gulf of Mexico should be subjected
to the same safety standards as all other
hazardous liquid gathering lines. Based
on the study titled ‘‘Review of Existing
Federal and State Regulations for Gas
and Hazardous Liquid Gathering
Lines,’’ 2 that was performed by the Oak
Ridge National Laboratory and
published on May 8, 2015, PHMSA is
proposing additional regulations to
ensure the safety of hazardous liquid
gathering lines.
In order for PHMSA to effectively
analyze safety performance and pipeline
risk of gathering lines, we need basic
data about those pipelines. PHMSA has
statutory authority to gather data for all
gathering lines (49 U.S.C. 60117(b)), and
1 https://app.ntsb.gov/news/2010/100624b.html.
2 https://www.phmsa.dot.gov/pv_obj_cache/pv_
obj_id_7B2B80704EBC3EBABDB5B9F701F184
E0854F3600/filename/report_to_congress_on_
gathering_lines.pdf.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
that authority was not affected by any of
the provisions in the Pipeline Safety Act
of 2011. Accordingly, PHMSA is
proposing to add § 195.1(a)(5) to require
that the operators of all gathering lines
(whether onshore, offshore, regulated, or
unregulated) comply with requirements
for submitting annual, safety-related
condition, and incident reports.
In the ANPRM, PHMSA asked
whether the agency should repeal or
modify any of the exceptions for
hazardous liquid gathering lines.
Section 195.1(a)(4)(ii) states that part
195 applies to a ‘‘regulated rural
gathering line as provided in § 195.11.’’
PHMSA adopted a regulation in a June
2008 final rule (73 FR 31634) that
prescribed certain safety requirements
for regulated rural gathering lines (i.e.,
the filing of accident, safety-related
condition and annual reports;
establishing the maximum operating
pressure according to § 195.406;
installing line markers; and establishing
programs for public awareness, damage
prevention, corrosion control, and
operator qualification of personnel).
The June 2008 final rule did not
establish safety standards for all rural
hazardous liquid gathering lines. Some
of those lines cannot be regulated by
statute (i.e., 49 U.S.C. 60101(b)(2)(B)
states that ‘‘the definition of ‘regulated
gathering line’ for hazardous liquid may
not include a crude oil gathering line
that has a nominal diameter of not more
than 6 inches, is operated at low
pressure, and is located in a rural area
that is not unusually sensitive to
environmental damage.’’) and Congress
did not remove this exemption in the
2011 Act. However, the 2011 Act did
require that PHMSA review whether
currently unregulated gathering lines
should be made subject to the same
regulations as other pipelines.
Require Inspections of Pipelines in
Areas Affected by Extreme Weather,
Natural Disasters, and Other Similar
Events
In July 2011 a pipeline failure
occurred near Laurel, Montana, causing
the release of an estimated 1,000 barrels
of crude oil into the Yellowstone River.
That area had experienced extensive
flooding in the weeks leading up to the
failure, and the operator has estimated
the cleanup costs at approximately $135
million. An instance of flooding also
occurred in 1994 in the State of Texas,
leading to the failure of eight pipelines
and the release of more than 35,000
barrels of hazardous liquids into the San
Jacinto River. Some of that released
product also ignited, causing minor
burns and other injuries to nearly 550
people according to the NTSB. As the
PO 00000
Frm 00004
Fmt 4701
Sfmt 4702
agency has noted in a series of advisory
bulletins, hurricanes are capable of
causing extensive damage to both
offshore and inland pipelines (e.g.,
Hurricane Ivan, September 23, 2004 (69
FR 57135); Hurricane Katrina,
September 7, 2004 (70 FR 53272);
Hurricane Rita, September 1, 2011 (76
FR 54531)).
These events demonstrate the
importance of ensuring that our nation’s
waterways are adequately protected in
the event of a natural disaster or
extreme weather. PHMSA is aware that
responsible operators might do such
inspections; however, because it is not
a requirement, some operators do not.
Therefore, PHMSA is proposing to
require that operators perform an
additional inspection within 72 hours
after the cessation of an extreme
weather event such as a hurricane or
flood, an earthquake, a natural disaster,
or other similar event.
Specifically, under this proposal an
operator must inspect all potentially
affected pipeline facilities post extreme
weather event to ensure that no
conditions exist that could adversely
affect the safe operation of that pipeline.
The operator would be required to
consider the nature of the event and the
physical characteristics, operating
conditions, location, and prior history of
the affected pipeline in determining the
appropriate method for performing the
inspection required. The inspection
must occur within 72 hours after the
cessation of the event, or as soon as the
affected area can be safely accessed by
the personnel and equipment required
to perform the inspection. PHMSA has
found that 72 hours is reasonable and
achievable in most cases. If an adverse
condition is found, the operator must
take appropriate remedial action to
ensure the safe operation of a pipeline
based on the information obtained as a
result of performing the inspection.
Such actions might include, but are not
limited to:
• Reducing the operating pressure or
shutting down the pipeline;
• Modifying, repairing, or replacing
any damaged pipeline facilities;
• Preventing, mitigating, or
eliminating any unsafe conditions in the
pipeline right-of-ways (ROWS);
• Performing additional patrols,
surveys, tests, or inspections;
• Implementing emergency response
activities with federal, state, or local
personnel; and
• Notifying affected communities of
the steps that can be taken to ensure
public safety.
This proposal is based on the
experience of PHMSA and is expected
to increase the likelihood that safety
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
conditions will be found earlier and
responded to more quickly. PHMSA
invites comment on this and other
proposals in this NPRM. In regard to
this proposal, PHMSA has particular
interest in additional comments
concerning how operators currently
respond to these events, what type of
events are encountered and if a 72 hour
response time is reasonable.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Require Periodic Assessments of
Pipelines That Are Not Already Covered
Under the IM Program Requirements
PHMSA is proposing to require
assessments for pipeline segments in
non-HCAs. PHMSA believes that
expanded assessment of non-HCA
pipeline segments areas will provide
operators with valuable information
they may not have collected if
regulations were not in place such a
requirement would ensure prompt
detection and remediation of corrosion
and other deformation anomalies in all
locations, not just HCAs. Specifically,
the proposed § 195.416 would require
operators to assess non-HCA (non-IM)
pipeline segments with an inline
inspection (ILI) tool at least once every
10 years. PHMSA needs operators to
complete assessments in HCAs followed
by assessments in non-HCAs. Other
assessment methods could be used if an
operator provides the Office of Pipeline
Safety (OPS) with prior written notice
that a pipeline is not capable of
accommodating an ILI tool. The written
notice provided to PHMSA must
include a technical demonstration of
why the pipeline is not capable of
accommodating an ILI tool and what
alternative technology the operator
proposes to use. The operator must also
detail how the alternative technology
would provide a substantially
equivalent understanding of the
pipeline’s condition in light of the
threats that could affect its safe
operation. Such alternative technologies
would include hydrostatic pressure
testing or appropriate forms of direct
assessment.
The individuals who review the
results of these periodic assessments
would need to be qualified by
knowledge, training, and experience
and would be required to consider any
uncertainty in the results obtained,
including ILI tool tolerance, when
determining whether any conditions
could adversely affect the safe operation
of a pipeline. Such determinations
would have to be made promptly, but
no later than 180 days after an
inspection, unless the operator
demonstrates that the 180-day deadline
is impracticable.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
Operators would be required to
comply with the other provisions in part
195 in implementing the requirements
in § 195.416. That includes having
appropriate provisions for performing
these periodic assessments and any
resulting repairs in an operator’s
procedural manual (see § 195.402),
adhering to the recordkeeping
provisions for inspections, test, and
repairs (see § 195.404), and taking
appropriate remedial action under
§ 195.422, as discussed below. Section
195.11 would also be amended to
subject regulated onshore gathering
lines to the periodic assessment
requirement.
PHMSA believes by proposing the
above amendment to the existing
pipeline safety regulations, safety will
be increased for all pipelines both in
and out of HCAs. Such a requirement
would ensure operators obtain
information necessary for prompt
detection and remediation of corrosion
and other deformation anomalies in all
locations, not just HCAs. Currently,
operators have indicated that they are
performing ILI assessments on a large
majority of their pipelines even though
no regulation requires them to do so
outside of HCAs. PHMSA wants to
ensure that current assessment rates
continue and expand to those areas not
voluntarily assessed. Of the many
methods to assess, PHMSA has found
that ILI in many cases is the most
efficient and effective. PHMSA
considered alternatives to its proposal
that would likely have lower overall
costs and benefits, but potentially
higher net benefits. For instance,
PHMSA considered limiting the
proposed expansion of certain IM
requirements to those pipelines where a
spill could affect a building or occupied
site such as a playground, or highway.
Under this alternative, pipelines in a
location where a spill could not affect
a building, occupied site, or highway
would not be subject to these new
requirements. However, this alternative
would offer less protection to the
natural environment, including
sensitive and protected habitats and
species. PHMSA also considered
alternative assessment intervals to the
proposed 10 year interval, such as a 15or 20-year interval. However, substantial
changes to pipeline integrity can occur
in a short timeframe. PHMSA declined
to propose these alternatives because
they would provide fewer benefits than
the proposed approach. More
specifically, liquid spills, even in
remote areas, can result in
environmental damage necessitating
clean up and incurring restoration costs
PO 00000
Frm 00005
Fmt 4701
Sfmt 4702
61613
and lost use and nonuse values. If pipe
is not assessed and repaired in
accordance with this proposal, liquid
spills are likely to occur.
Also, a longer interval between
assessments would increase risks of
integrity-related failure compared to
PHMSA’s proposal. PHMSA was unable
to quantify the benefits and costs of
these alternatives due to limitations in
available information, such as the
amount of unassessed pipe where a spill
could not affect a building, occupied
site, or highway; the environmental
impact of spills from such pipe; and the
incremental reduction in benefit
between 10-year and alternative interval
periods. PHMSA seeks public comments
on these alternatives, and the regulatory
impact analysis contains specific
questions for public comment on
quantifying these alternatives.
Modify the IM Repair Criteria and Apply
Those Same Criteria to Any Pipeline
Where the Operator Has Identified
Repair Conditions
Inspection experience indicates a
weakness in current repair criteria.
Specifically, the current repair criteria
in non-HCAs (immediate and reasonable
time) does not specify anomaly or repair
time frames. It is left entirely at the
operator’s discretion. Therefore,
PHMSA is proposing to modify the IM
pipeline repair criteria and to apply the
criteria to non-IM pipeline repairs.
Specifically, the criteria in § 195.452(h)
for IM repairs would be modified to:
• Categorize bottom-side dents with
stress risers as immediate repair
conditions;
• Require immediate repairs
whenever the calculated burst pressure
is less than 1.1 times maximum
operating pressure;
• Eliminate the 60-day and 180-day
repair categories; and
• Establish a new, consolidated 270day repair category.
PHMSA is also proposing to amend
the requirements in § 195.422 for
performing non-IM repairs by:
• Applying the criteria in the
immediate repair category in
§ 195.452(h); and
• Establishing an 18-month repair
category for hazardous liquid pipelines
that are not subject to IM requirements.
PHMSA believes that these changes
will ensure that immediate action is
taken to remediate anomalies that
present an imminent threat to the
integrity of hazardous liquid pipelines
in all locations. Moreover, many
anomalies that would not qualify as
immediate repairs under the current
criteria will meet that requirement as a
result of the additional conservatism
E:\FR\FM\13OCP3.SGM
13OCP3
61614
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
that will be incorporated into the burst
pressure calculations. The new time
frames for performing non-immediate
repairs will also allow operators to
remediate those conditions in a timely
manner while allocating resources to
those areas that present a higher risk of
harm to the public, property, and the
environment. The existing requirements
in § 195.422 would also be modified to
include a general requirement for
performing all other repairs within a
reasonable time. A proposed
amendment to § 195.11 would extend
these new pipeline remediation
requirements to regulated onshore
gathering lines.
As a result of these changes, PHMSA
would modify the existing general
requirements for pipeline repairs in
§ 195.401(b). Paragraph (b)(1) would be
modified to reference the new
timeframes in § 195.422(d) and (e) for
remediating conditions that could
adversely affect the safe operation of a
pipeline segment not subject to the IM
requirements in § 195.452. The
requirements in paragraph (b)(2) for IM
repairs under § 195.452(h) will be
retained without change. A new
paragraph (b)(3) will be added, however,
to require operators to consider the risk
to people, property, and the
environment in prioritizing the
remediation of any condition that could
adversely affect the safe operation of a
pipeline system, including those
covered by the timeframes specified in
§§ 195.422(d) and (e) and 195.452(h).
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Expand the Use of Leak Detection
Systems for All Hazardous Liquid
Pipelines
PHMSA is proposing to amend
§ 195.134 to require that all new
hazardous liquid pipelines be designed
to include leak detection systems.
Recent pipeline accidents, including a
pair of related failures that occurred in
2010 on a crude oil pipeline in Salt Lake
City, Utah, corroborate the significance
of having an adequate means for
identifying leaks in all locations.
PHMSA, aware of the significance of
leak detection, held two recent
workshops in Rockville, Maryland on
March 27–28 of 2012. These workshops
sought comment from the public
concerning many of the issues raised in
the 2010 ANPRM, including leak
detection expansion. Both workshops
were well attended and PHMSA
received valuable input from
stakeholders.
Currently, part 195 contains
mandatory leak detection requirements
for hazardous liquid pipelines that
could affect an HCA.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
Congress included additional
requirements for leak detection systems
in section 8 of the Pipeline Safety Act
of 2011. That legislation requires the
Secretary to submit a report to Congress,
within 1-year of the enactment date, on
the use of leak detection systems,
including an analysis of the technical
limitations and the practicability, safety
benefits, and adverse consequence of
establishing additional standards for the
use of those systems. To provide
Congress with an opportunity to review
that report, the Secretary is prohibited
from issuing any final leak detection
regulations for a specified time period
(i.e., 2 years from the date of the
enactment of the Pipeline Safety Act of
2011, or 1-year after the submission of
the leak detection report to Congress,
whichever is earlier), unless a condition
exists that poses a risk to public safety,
property, or the environment, or is an
imminent hazard, and the issuance of
such regulations would address that risk
or hazard. Other provisions in part 195
help to detect and mitigate the effects of
pipeline leaks, including the Right of
Way (ROW).
In addition to modifying § 195.444 to
require a means for detecting leaks on
all portions of a hazardous liquid
pipeline system, PHMSA is proposing
that operators be required to have an
evaluation performed to determine what
kinds of systems must be installed to
adequately protect the public, property,
and the environment. The factors that
must be considered in performing that
evaluation would include the
characteristics and history of the
affected pipeline, the capabilities of the
available leak detection systems, and
the location of emergency response
personnel. A proposed amendment to
§ 195.11 would extend these new leak
detection requirements to regulated
onshore gathering lines. PHMSA is
retaining and is not proposing any
modification to the requirement in
§§ 195.134 and 195.444 that each new
computational leak detection system
comply with the applicable
requirements in the API RP 1130
standard.
PHMSA does not propose to make any
additional changes to the regulations
concerning specific leak detection
requirements at this time. PHMSA will
be studying this issue further and may
make proposals concerning this topic in
a later rulemaking. PHMSA recently
publicly provided the results of the
2012 Keifner and Associates study of
leak detection systems in the pipeline
industry, including the current state of
technology.
PO 00000
Frm 00006
Fmt 4701
Sfmt 4702
Increase the Use of Inline Inspection
Tools
PHMSA is proposing to require that
all hazardous liquid pipelines in HCA’s
and areas that could affect an HCA be
made capable of accommodating ILI
tools within 20 years, unless the basic
construction of a pipeline will not
accommodate the passage of such a
device.
The current requirements for the
passage of ILI devices in hazardous
liquid pipelines are prescribed in
§ 195.120, which require that new and
replaced pipelines are designed to
accommodate inline inspection tools.
The basis for these requirements was a
1988 law that addressed the Secretary’s
authority with regard to requiring the
accommodation of ILI tools. This law
required the Secretary to establish
minimum federal safety standards for
the use of ILI tools, but only in newly
constructed and replaced hazardous
liquid pipelines (Pub. L. 100–561).
In 1996, Congress passed another law
further expanding the Secretary’s
authority to require pipeline operators
to have systems that can accommodate
ILI tools. In particular, Congress
provided additional authority for the
Secretary to require the modification of
existing pipelines whose basic
construction would accommodate an ILI
tool to accommodate such a tool and
permit internal inspection (Pub. L. 104–
304).
As the Research and Special Programs
Administration (RSPA), (a predecessor
agency of PHMSA) explained in the
final rule April 12, 1994 (59 FR 17275)
that promulgated § 195.120, ‘‘[t]he clear
intent of th[at] congressional mandate
[wa]s to improve an existing pipeline’s
piggability,’’ and to ‘‘require[] the
gradual elimination of restrictions in
existing hazardous liquid and carbon
dioxide lines in a manner that will
eventually make the lines piggable.’’
April 2, 1994, (59 FR 17279). RSPA also
noted that Congress amended the 1988
law in the Pipeline Safety Act of 1992
(Pub. L. 102–508) to require the periodic
internal inspection of hazardous liquid
pipelines, including with ILI tools in
appropriate circumstances April 2,
1994, (59 FR 17275). RSPA established
requirements for the use of ILI tools in
pipelines that could affect HCAs in the
December 2000 IM final rule December
1, 2000, (65 FR 75378).
Section 60102(f)(1)(B) of the Pipeline
Safety Laws allows the requirements for
the passage of ILI tools to be extended
to existing hazardous liquid pipeline
facilities, provided the basic
construction of those facilities can be
modified to permit the use of smart pigs.
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
The current requirements apply only to
new hazardous liquid pipelines and to
line sections where the line pipe,
valves, fittings, or other components are
replaced. Exceptions are also provided
for certain kinds of pipeline facilities,
including manifolds, piping at stations
and storage facilities, piping of a size
that cannot be inspected with a
commercially available ILI tool, and
smaller diameter offshore pipelines.
PHMSA is proposing to use the
authority provided in section
60102(f)(1)(B) to further facilitate the
‘‘gradual elimination’’ of pipelines that
are not capable of accommodating smart
pigs. PHMSA would limit the
circumstances where a pipeline can be
constructed without being able to
accommodate a smart pig. Under the
current regulation, an operator can
petition the PHMSA Administrator for
such an allowance for reasons of
impracticability, emergencies,
construction time constraints, and other
unforeseen construction problems.
PHMSA believes that an exception
should still be available for emergencies
and where the basic construction of a
pipeline makes that accommodation
impracticable, but that the other, less
urgent circumstances listed in the
regulation are no longer appropriate.
Accordingly, the allowances for
construction-related time constraints
and problems would be repealed.
Modern ILI tools are capable of
providing a relatively complete
examination of the entire length of a
pipeline, including information about
threats that cannot always be identified
using other assessment methods. ILI
tools also provide superior information
about incipient flaws (i.e., flaws that are
not yet a threat to pipeline integrity, but
that could become so in the future),
thereby allowing these conditions to be
monitored over consecutive inspections
and remediated before a pipeline failure
occurs. Hydrostatic pressure testing,
another well-recognized method, reveals
flaws (such as wall loss and cracking
flaws) that cause pipe failures at
pressures that exceed actual operating
conditions. Similarly, external corrosion
direct assessment (ECDA) can identify
instances where coating damage may be
affecting pipeline integrity, but
additional activities, including followup excavations and direct examinations,
must be performed to verify the extent
of that threat. ECDA also provides less
information about the internal condition
of a pipe than ILI tools.
As with new pipelines, operators will
be allowed to petition the PHMSA
Administrator for a finding that the
basic construction, (i.e., terrain or
location, of a pipeline or an emergency)
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
will not permit the accommodation of a
smart pig.
Clarify Other Requirements
PHMSA is also proposing several
other clarifying changes to the
regulations that are intended to improve
compliance and enforcement. First,
PHMSA is proposing to revise
paragraph (b)(1) of § 195.452 to correct
an inconsistency in the current
regulations. Currently, § 195.452(b)(2)
requires that segments of new pipelines
that could affect HCAs be identified
before the pipeline begins operations
and § 195.452(d)(1) requires that
baseline assessments for covered
segments of new pipelines be completed
by the date the pipeline begins
operation. However, § 195.452(b)(1)
does not require an operator to draft its
IM program for a new pipeline until
one-year after the pipeline begins
operation. These provisions are
inconsistent as the identification could
affect segments, and performance of
baseline assessments are elements of the
written IM program. PHMSA would
amend the table in (b)(1) to resolve this
inconsistency by eliminating the oneyear compliance deadline for Category 3
pipelines. An operator of a new pipeline
would be required to develop its written
IM program before the pipeline begins
operation.
A decade’s worth of IM inspection
experience has shown that many
operators are performing inadequate
information analyses (e.g., they are
collecting information, but not affording
it sufficient consideration). Integration
is one of the most important aspects of
the IM program because it is used in
identifying interactions between threats
or conditions affecting the pipeline and
in setting priorities for dealing with
identified issues. For example, evidence
of potential corrosion in an area with
foreign line crossings and recent aerial
patrol indications of excavation activity
could indicate a priority need for further
investigation. Consideration of each of
these factors individually would not
reveal any need for priority attention.
PHMSA is concerned that a major
benefit to pipeline safety intended in
the initial rule is not being realized
because of inadequate information
analyses.
For this reason, PHMSA is proposing
to add additional specificity to
paragraph (g) by establishing a number
of pipeline attributes that must be
included in these analyses and to
require explicitly that operators
integrate analyzed information. PHMSA
is also proposing that operators consider
explicitly any spatial relationships
among anomalous information. PHMSA
PO 00000
Frm 00007
Fmt 4701
Sfmt 4702
61615
supports the use of computer-based
geographic information systems (GIS) to
record this information. GIS systems can
be beneficial in identifying spatial
relationships, but analysis is required to
identify where these relationships could
result in situations adverse to pipeline
integrity.
Second, PHMSA is proposing that
operators verify their segment
identification annually by determining
whether factors considered in their
analysis have changed. Section
195.452(b) currently requires that
operators identify each segment of their
pipeline that could affect an HCA in the
event of a release but there is no explicit
requirement that operators assure that
their identification of covered segments
remains current. As time goes by, the
likelihood increases that factors
considered in the original identification
of covered segments may have changed.
PHMSA believes that operators should
periodically re-visit their initial
analyses to determine whether they
need to be updated. New HCAs may be
identified. Construction activities or
erosion near the pipeline could change
local topography in a way that could
cause product released in an accident to
travel further than initially analyzed.
Changes in agricultural land use could
also affect an operator’s analysis of the
distance released product could be
expected to travel. Changes in the
deployment of emergency response
personnel could increase the time
required to respond to a release and
result in a larger area being affected by
a potential release if the original
segment identification relied on
emergency response to limit the
transport of released product.
The change that PHMSA is proposing
would not require that operators reperform their segment analyses. Rather,
it would require operators to identify
the factors considered in their original
analyses, determine whether those
factors have changed, and consider
whether any such change would be
likely to affect the results of the original
segment identification. If so, the
operator would be required to perform
a new analysis to validate or change the
endpoints of the segments affected by
the change.
Third, PHMSA is proposing to clarify,
through the use of an explicit reference
that the IM requirements apply to
portions of ‘‘pipelines’’ other than line
pipe. Unlike integrity assessments for
line pipe, § 195.452 does not include
explicit deadlines for completing the
analyses of other facilities within the
definition of ‘‘pipeline’’ or for
implementing actions in response to
those analyses. Through IM inspections,
E:\FR\FM\13OCP3.SGM
13OCP3
61616
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
PHMSA has learned that some operators
have not completed analyses of their
non-pipe facilities such as pump
stations and breakout tanks and have
not implemented appropriate protective
and mitigative measures.
Section 29 of the Pipeline Safety,
Regulatory Certainty, and Job Creation
Act of 2011 states that ‘‘[i]n identifying
and evaluating all potential threats to
each pipeline segment pursuant to parts
192 and 195 of title 49, Code of Federal
Regulations, an operator of a pipeline
facility shall consider the seismicity of
the area.’’ While seismicity is already
mentioned at several points in the IM
program guidance provided in
Appendix C of part 195, PHMSA is
proposing to further comply with
Congress’s directive by including an
explicit reference to seismicity in the
list of risk factors that must be
considered in establishing assessment
schedules (§ 195.452(e)), performing
information analyses (§ 195.452(g)), and
implementing preventive and mitigative
measures (§ 195.452(i)) under the IM
requirements.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
III. Analysis of Advance Notice of
Proposed Rulemaking
On October 18, 2010, (75 FR 63774),
PHMSA published an ANPRM asking
the public to comment on several
proposed changes to part 195. The
ANPRM sought comments on:
• Scope of part 195 and existing
regulatory exceptions;
• Criteria for designation of HCAs;
• Leak detection and emergency flow
restricting devices;
• Valve spacing;
• Repair criteria outside of HCAs; and
• Stress corrosion cracking.
The ANPRM may be viewed at https://
www.regulations.gov by searching for
Docket ID PHMSA–2010–0229.
Twenty-one organizations and
individuals submitted comments in
response to the ANPRM. The individual
docket item numbers are listed for each
comment.
• Associations representing pipeline
operators (trade associations)
Æ American Petroleum Institute—
Association of Oil Pipelines (API–
AOPL) (PHMSA–2010–0229–0030)
Æ Independent Petroleum Association
of America (IPAA) (PHMSA–2010–
0229–0024)
Æ Canadian Energy Pipeline
Association (CEPA) (PHMSA–2010–
0229–0008)
Æ Oklahoma Independent Petroleum
Association (OIPA) (PHMSA–2010–
0229–0018)
Æ Texas Pipeline Association (TPA)
(PHMSA–2010–0229–0011)
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
Æ Louisiana Midcontinent Oil & Gas
Association (LMOGA) (PHMSA–
2010–0229–0018)
Æ Texas Oil & Gas Association
(TxOGA) (PHMSA–2010–0229–
0022)
• Transmission and Distribution
Pipeline Companies
Æ TransCanada Keystone (PHMSA–
2010–0229–0027)
• Government/Municipalities
Æ Defense Logistics Agency (DLA)
(PHMSA–2010–0229–0016)
Æ Metro Area Water Utility
Commission (MAWUC) (PHMSA–
2010–0229–0031)
Æ North Slope Borough (NSB)
(PHMSA–2010–0229–0012)
• Pipeline Safety Regulators
Æ National Association of Pipeline
Safety Representatives (NAPSR)
(PHMSA–2010–0229–0032)
• Citizens’ Groups
Æ Pipeline Safety Trust (PST)
(PHMSA–2010–0229–0014)
Æ Cook Inlet Regional Citizens
Advisory Council (CRAC))
(PHMSA–2010–0229–0019)
Æ The Wilderness Society (TWS)
(PHMSA–2010–0229–0025)
Æ National Resources Defense
Council et al. (NRDC) (PHMSA–
2010–0229–0021)
Æ Alaska Wilderness League et al.
(AKW) (PHMSA–2010–0229–0026)
• Citizens
Æ Patrick Coyle (PHMSA–2010–0229–
0002)
Æ Marian J. Stec (PHMSA–2010–
0229–0007)
Æ Pamela A. Miller (PHMSA–2010–
0229–0013)
Æ Anonymous (PHMSA–2010–0229–
0005) (The anonymous comment
dealt with quality of drinking water
and release permits under the Clean
Water Act.
These topics are beyond the scope of
PHMSA’s jurisdiction and are not
discussed further).
Comments are reviewed in the order
the ANPRM presented questions for
comment. PHMSA responses to the
comments follow.
A. Scope of Part 195 and Existing
Regulatory Exceptions
Comments
API–AOPL, LMOGA, TxOGA, and
TransCanada Keystone expressed
support for the gravity line exception.
These commenters stated that gravity
lines are short, pose little risk, and are
usually located within other regulated
facilities, such as tank farms. NAPSR
did not support a complete repeal of
this exception, suggesting there was no
data to support such an action. NAPSR
PO 00000
Frm 00008
Fmt 4701
Sfmt 4702
did suggest that the exception should
not apply to ethanol pipelines, which
are very susceptible to internal
corrosion.
MAWUC indicated that gravity lines
in HCAs should be regulated because of
the sensitivity of these areas. MAWUC
further stated that these lines (and other
rural onshore gathering lines) contain
contaminants that are not present in
products carried by other pipelines, that
these contaminants are dangerous to
pipeline workers, and that the impact of
releases from these pipelines on the
environment is the same as releases
from regulated pipelines.
Response
PHMSA does not, at this time, intend
to repeal the exemption for gravity lines,
but does propose to extend reporting
requirements to all hazardous liquid
gravity lines. The collection of
information about these lines is
authorized under the Pipeline Safety
Laws, and the resulting data will assist
in determining whether the existing
federal and state regulations for these
lines are adequate.
Rural Gathering Lines
Comments
PHMSA received a number of
comments on whether to modify or
repeal the requirements in § 195.1(a)(4).
API–AOPL, LMOG, IPAA, OIPA, and
TxOGA stated that the regulatory
exception for rural gathering lines is
appropriate and should not be repealed
or modified. They indicated that these
lines are the source of a small
percentage of spills, and that gathering
lines in populated areas and near
navigable waterways are already subject
to PHMSA regulation.
Among citizens’ groups, TWS
suggested that PHMSA should examine
federal and state release data from all
excepted pipelines and regulate those
with release rates similar to currently
regulated pipelines. PST supported
expansion of the definition of gathering
line to the extent statutorily possible to
capture all lines. Similarly, CRAC, TWS,
and AKW indicated the exception
should be removed and regulation
expanded to include produced water
lines and production lines. TWS and
AKW also stated that flow lines, which
are currently defined by regulation as
production facilities, should be
reclassified and regulated as gathering
lines.
The government/municipalities NSB
and MAWUC also commented
concerning the rural gathering line
exception. NSB requested PHMSA place
a high priority on removing the
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
exception for gathering lines. MAWUC
supported no gathering line exceptions
in HCAs.
Citizen Miller commented that
PHMSA should regulate production and
produced water lines on Alaska’s North
Slope, because this area is very sensitive
and includes pristine wetlands and fish
and wildlife habitats of national and
international importance. She further
commented that river and coastline
pipeline routes and crossings in the
Arctic and subarctic Alaska are
particularly of concern due to the rapid
change in permafrost, as well as high
rates of coastal erosion which greatly
increases the environmental and human
impacts of spills.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Response
PHMSA believes that the
requirements of the Pipeline Safety Act
of 2011 and concerns for adequate
regulatory oversight can only be
addressed if PHMSA obtains additional
information about gathering lines.
PHMSA has the statutory authority to
gather data for all gathering lines (49
U.S.C. 60117(b)), and that authority was
not affected by any of the provisions in
the Pipeline Safety Act of 2011.
Accordingly, PHMSA is proposing to
amend 49 CFR 195.1(a)(5) to require that
the operators of all gathering lines
(whether onshore, offshore, regulated, or
unregulated) comply with requirements
for submitting annual, safety-related
condition, and incident reports.
Carbon Dioxide Lines
In the ANPRM, PHMSA asked
whether the agency should repeal or
modify the regulatory exception for
carbon dioxide pipelines used in the
well injection and recovery production
process. Section 195.1(b)(10) states that
part 195 does not apply to the
transportation of carbon dioxide
downstream from the applicable
following point:
(i) The inlet of a compressor used in
the injection of carbon dioxide for oil
recovery operations, or the point where
recycled carbon dioxide enters the
injection system, whichever is farther
upstream; or
(ii) The connection of the first branch
pipeline in the production field where
the pipeline transports carbon dioxide
to an injection well or to a header or
manifold from which a pipeline
branches to an injection well.
Comments
The trade associations, LMOGA, API–
AOPL, OIPA, TxOGA, and IPAA,
commented that PHMSA should not
repeal the exception for carbon dioxide
lines used in the well injection and
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
recovery production process. They
indicated the potential risk from a
production facility carbon dioxide
pipeline failure is low due to factors of
low potential release volumes, rapid
dispersion, and low potential for human
exposure. NAPSR suggested the current
exception is appropriate and noted that
there is no data indicating the need for
a repeal.
Response
The regulatory history shows that the
exception in § 195.1(b)(10) is limited in
scope and only applies to carbon
dioxide pipelines that are directly used
in the production of hazardous liquids.
See June 12, 1994, (56 FR 26923)
(stating in preamble to 1991 final rule
that ‘‘the exception is limited to lines
downstream of where carbon dioxide is
delivered to a production facility in the
vicinity of a well site, rather than
excepting all the CO2 lines in the broad
expanses of a production field.’’);
January 21, 1994, (59 FR 3390) (stating
in preamble to June 1994 that agency
adopted amendment ‘‘to clarify that the
exception covers pipelines used in the
injection of carbon dioxide for oil
recovery operations.’’). Congress has
indicated that such facilities should not
be subject to federal regulation, and
none of the commenters supported a
repeal or modification of this exception.
Accordingly, PHMSA is not proposing
to repeal or modify § 195.1(b)(10).
Offshore Lines in State Waters
In the ANPRM, PHMSA asked
whether the agency should repeal or
modify any of the exceptions for
offshore pipelines in state waters.
Comments
TransCanada Keystone, an industry
commenter, and the trade associations,
API–AOPL, LMOGA and TxOGA, stated
the current exception should not be
changed. API–AOPL pointed out that
PHMSA’s jurisdiction lies only with the
transportation of hazardous liquids, not
hydrocarbon production areas of
offshore operations. API–AOPL further
stated that changing the state waters
exception would unnecessarily add a
duplicative layer of federal regulation.
The citizens’ groups, TWS and AKW,
supported removal of this exemption
and increased enforcement in state
waters. Likewise, among the
government/municipality comments,
NSB indicated that the regulations need
to be expanded to include lines in
offshore state waters. NSB expressed
concerns with lack of state enforcement,
high corrosion potential, and the
sensitivity of the location of the offshore
PO 00000
Frm 00009
Fmt 4701
Sfmt 4702
61617
lines, such as those in the Beaufort and
Chukchi Seas.
The prohibitions of the Pipeline
Safety Act of 2011 do not affect
PHMSA’s authority to ensure the safety
of offshore gathering lines under other
statutory provisions, including if such a
line is hazardous to life, property, or the
environment (49 U.S.C. 60112)).
PHMSA also notes that the generallyapplicable limitation in section
60101(a)(22) of the Pipeline Safety Laws
only applies to ‘‘onshore production
. . . facilities,’’ and that the states may
regulate such intrastate facilities (see
e.g., Tex. Admin. Code Title. 16, sec.
8.1(a)(1)(D)).
Response
Congress has indicated that additional
federal safety standards may be
warranted for offshore gathering lines.
First, we would note that this does not
include offshore production pipelines.
Section 195.1(b)(5) states that part 195
does not apply to the: Transportation of
hazardous liquid or carbon dioxide in
an offshore pipeline in state waters
where the pipeline is located upstream
from the outlet flange of the following
farthest downstream facility; the facility
where hydrocarbons or carbon dioxide
are produced; or the facility where
produced hydrocarbons or carbon
dioxide are first separated, dehydrated,
or otherwise processed.
RSPA, a predecessor agency of
PHMSA, adopted § 195.1(b)(5) in a June
1994 final rule June 28, 1994, (59 FR
33388). Before that time, part 195 only
included an explicit exception for
offshore production pipelines located
on the Outer Continental Shelf.
However, as explained in the preamble
to the June 1994 final rule, RSPA
believed that the same exception should
be applied to all offshore production
pipelines, including those located in
state waters. Under the federal pipeline
safety laws, the agency does not regulate
production facilities at all. Section 21 of
the Pipeline Safety Act of 2011 requires
the Secretary to review the existing
federal and state regulations for
gathering lines and to submit a report to
Congress with the results of that review.
A study on these regulations, titled
‘‘Review of Existing Federal and State
Regulations for Gas and Hazardous
Liquid Lines,’’ was performed by the
Oak Ridge National Laboratory and was
published on May 8, 2015. The
Secretary is also required, if
appropriate, to issue regulations
subjecting hazardous liquid gathering
lines located offshore and in the inlets
of the Gulf of Mexico to the same safety
standards that apply to all other
hazardous gathering lines. Section 21
E:\FR\FM\13OCP3.SGM
13OCP3
61618
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
states that any such regulations cannot
be applied to production pipelines or
flow lines.
Congress also included a provision
authorizing the collection of geospatial
or technical data on transportationrelated flow lines in section 12 of the
Pipeline Safety Act of 2011. A
transportation-related flow line is
defined for purposes of that provision as
‘‘a pipeline transporting oil off of the
grounds of the well where it originated
and across areas not owned by the
producer, regardless of the extent to
which the oil has been processed, if at
all.’’ Section 12 also states that nothing
in that provision ‘‘authorizes the
Secretary to prescribe standards for the
movement of oil through production,
refining, or manufacturing facilities or
through oil production flow lines
located on the grounds of wells.’’
Producer-Operated Pipelines on Outer
Continental Shelf
In the ANPRM, PHMSA asked
whether the agency should repeal or
modify any of the exceptions for
pipelines on the OCS.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Comments
TransCanada Keystone, an industry
commenter, and the trade associations,
API–AOPL, LMOGA, and TxOGA,
stated that the current exceptions for
pipelines on the OCS should remain
unchanged. API–AOPL requested that
PHMSA indicate what impact the
Bureau of Ocean Energy Management,
Regulation and Enforcement’s
(BOEMRE) recent publication regarding
Safety and Environmental Management
Systems (SEMS) has on transportation
operators. API–AOPL expressed concern
that joint jurisdiction, if created by the
recent BOEMRE publication, would
result in regulatory uncertainty.
NAPSR responded that the exceptions
for pipelines on the OCS should not be
changed as these lines are already
regulated by the Department of Interior.
Response
Section 195.1(b)(6) states that part 195
does not apply to the transportation of
hazardous liquid or carbon dioxide in a
pipeline on the OCS where the pipeline
is located upstream of the point at
which operating responsibility transfers
from a producting operator to a
transporting operator. Section
195.1(b)(7) further provides that part
195 does not apply to a pipeline
segment upstream (generally seaward)
of the last valve on the last production
facility on the OCS where a pipeline on
the OCS is producer-operated and
crosses into state waters without first
connecting to a transporting operator’s
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
facility on the OCS. Safety equipment
protecting PHMSA-regulated pipeline
segments is not excluded. A producing
operator of a segment falling within this
exception may petition the
Administrator, under § 190.9 of this
chapter, for approval to operate under
PHMSA regulations governing pipeline
design, construction, operation, and
maintenance. These exceptions are
designed to ensure that a single federal
agency is responsible for regulating the
safety of any given pipeline segment on
the OCS (i.e., the Department of Interior
for producer-operated pipelines and
PHMSA for transporter-operated
pipelines). See final rule codifying 1976
Memorandum of Understanding (MOU)
between the Departments of
Transportation and Interior on the
regulation of offshore pipelines in
§ 195.1 August 12, 1976 (41 FR 34040);
direct final rule codifying 1996 MOU
between the Departments of
Transportation and Interior on the
regulation of offshore pipelines in
§ 195.1 November 19, 1997 (62 FR
61692); and final rule clarifying
regulation of producer-operated
pipelines that cross the federal-state
boundary in offshore waters without
first connecting to a transportingoperator’s facility on the OCS) August 5,
2003 (68 FR 46109).
None of the commenters supported
the repeal or modification of
§ 195.1(b)(6) or (7). Accordingly,
PHMSA is not proposing to take any
further action with respect to these two
provisions. It should also be noted that
PHMSA is not responsible for
administering another federal agency’s
statutes or regulations.
Breakout Tanks Not Used for
Reinjection or Continued Transportation
In the ANPRM, PHMSA asked for
comment on whether the agency should
expand the extent to which part 195
applies to breakout tanks.
Comments
PHMSA received several comments
on whether the agency should expand
the extent to which part 195 applies to
breakout tanks. API–AOPL, supported
by the industry commenter,
TransCanada Keystone, and the trade
associations, LMOGA and TxOGA,
stated that the current definition is
appropriate, and that PHMSA should
review its current MOU with the
Environmental Protection Agency (EPA)
before making any changes to avoid
duplicative regulation of these facilities.
DLA, a governmental/municipal entity,
echoed the comments of API–AOPL.
Conversely, NAPSR stated that if
PHMSA is referring to the large number
PO 00000
Frm 00010
Fmt 4701
Sfmt 4702
of small tanks that are technically under
PHMSA’s authority, but currently not
regulated, then this exception should be
removed.
Response
The Pipeline Safety Laws provide
PHMSA with broad authority to regulate
‘‘the storage of hazardous liquid
incidental to the movement of
hazardous liquid by pipeline’’ (49
U.S.C. 60101(a)(22)(A)). The term
‘‘breakout tank’’ is defined in § 195.2 to
designate which aboveground tanks are
regulated as breakout under part 195.
See Exxon Corporation v. U.S.
Department of Transportation, 978
F.Supp. 946, 949–54 (E.D. Wash. 1997).
As some of the commenters noted,
PHMSA has an MOU with EPA on the
treatment of breakout tanks and bulk
storage tanks under the requirements of
the Oil Pollution Act of 1990. Such
agreements can ensure the effective
regulation of facilities that are subject to
regulation by more than one federal
agency. As in the case of offshore
pipeline facilities, those agreements can
also serve as a guideline on whether a
tank is transportation related or nontransportation related.
Accordingly, PHMSA will review its
agreements with EPA to determine
whether any modifications are
necessary, but is not proposing to
change the definition of a ‘‘breakout
tank’’ in part 195 at this time.
Other Exceptions or Limitations in Part
195
In the ANPRM, PHMSA asked for
comment on whether the agency should
repeal or modify any of the other
exceptions in part 195. API–AOPL,
supported by several other trade
associations, including LMOGA,
TxOGA, OIPA, and IPAA, commented
that the exception in § 195.1(b)(8) for
transportation of hazardous liquid or
carbon dioxide through onshore
production (including flow lines),
refining, or manufacturing facilities or
storage or in-plant pipeline systems
associated with such facilities should
not be changed. API–AOPL commented
that these facilities are not within the
scope of the Pipeline Safety Laws,
because they are not typically operated
by midstream oil and gas pipeline
companies operating in the pipeline
transportation system. These facilities
are already covered under a 1972 MOU
with EPA and do not require further
duplicative regulation.
Comments
API–AOPL commented that the
exception in § 195.1(b)(9) for piping
located on the grounds of a materials
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
transportation terminal used exclusively
to transfer products between nonpipeline modes of transportation should
not be changed. This piping is typically
isolated from pipeline pressure by
devices that control pressure in the
pipeline under § 195.406(b).
TransCanada Keystone, an industry
commenter, supported API–AOPL’s
comments.
The citizens’ groups NRDC and PST
indicated that PHMSA should establish
additional standards for diluted
bitumen. Both groups suggested PHMSA
establish additional regulations for that
commodity due to the high
temperatures and pressures at which the
lines that carry it operate.
Both regulatory associations, NAPSR
and MAWUC, commented on other
exemptions or limitations of the
pipeline safety regulations. NAPSR
indicated that the exemptions for
pipelines under 1-mile long that serve
refining, manufacturing, or terminal
facilities should be eliminated for
ethanol pipelines. NAPSR also
requested that PHMSA verify that
intrastate lines carrying other hazardous
liquids, such as sulfuric acid, are
regulated by the states. MAWUC
indicated that there should be no
regulatory exceptions in HCA segments,
because these areas must be treated with
the highest degree of both prevention
and emergency remediation measures.
Among government and municipality
commenters, NSB stated that § 195.1
should be amended to include
regulation of all onshore pipelines and
offshore pipelines in areas of the North
Slope. NSB suggests regulation should
occur where the consequences of a
hazardous liquid pipeline failure could
adversely impact: (1) An endangered,
threatened or depleted species; (2)
subsistence resources and subsistence
use areas; (3) a drinking water supply;
(4) cultural, archeological, and historical
resources; (5) navigable waterways
(including waterways navigated by rural
residents for the purposes of recreation,
commerce, and subsistence use); (6)
recreational use areas; or (7) the
functioning of other regulated facilities.
Regulation of all high pressure, large
diameter (6-inch and greater) onshore
pipelines and all offshore pipelines
should start at the wellhead.
One citizen commented that the river
and coastline routes in the Arctic and
sub-Arctic are particularly of concern
because of the rapid change in
permafrost, as well as high rate of
coastal erosion, which greatly increase
the environmental and human impacts
of hazardous liquid spills.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
Response
Section 195.1(b)(8) states that part 195
does not apply to the transportation of
hazardous liquid or carbon dioxide
through onshore production (including
flow lines), refining, or manufacturing
facilities or storage or in-plant piping
systems associated with such facilities.
That exception is based on section
60101(a)(22) of the Pipeline Safety
Laws, which exempts the movement of
hazardous liquid through onshore
production, refining, or manufacturing
facilities; or storage or in-plant piping
systems associated with onshore
production, refining, or manufacturing
facilities. Accordingly, PHMSA agrees
with the commenters that the exception
in § 195.1(b)(8) should not be changed.
With respect to the terminal
exemption in § 195.1(b)(9)(ii), it should
first be noted that the term ‘‘Pipeline or
pipeline system’’ is defined in § 195.2 as
‘‘all parts of a pipeline facility through
which a hazardous liquid or carbon
dioxide moves in transportation,
including, but not limited to, line pipe,
valves, and other appurtenances
connected to line pipe, pumping units,
fabricated assemblies associated with
pumping units, metering and delivery
stations and fabricated assemblies
therein, and breakout tanks.’’ The term
‘‘Pipeline facility’’ is defined in § 195.2
as ‘‘new and existing pipe, rights-of-way
and any equipment, facility, or building
used in the transportation of hazardous
liquids or carbon dioxide.’’ Under 49
U.S.C. 60101(a)(22), ‘‘transporting
hazardous liquid’’ includes ‘‘the storage
of hazardous liquid incidental to the
movement of hazardous liquid by
pipeline.’’
Section 195.1(b)(9) states that part 195
does not apply to the transportation of
hazardous liquid or carbon dioxide by
vessel, aircraft, tank truck, tank car, or
other non-pipeline mode of
transportation or through facilities
located on the grounds of a materials
transportation terminal if the facilities
are used exclusively to transfer
hazardous liquid or carbon dioxide
between non-pipeline modes of
transportation or between a nonpipeline mode and a pipeline. These
facilities do not include any device and
associated piping that are necessary to
control pressure in the pipeline under
§ 195.406(b).
One of PHMSA’s predecessors, the
Materials Transportation Bureau (MTB),
adopted the original version of that
exception in a July 1981 final rule July
27, 1981, (46 FR 38357). In excepting
the ‘‘[t]ransportation of a hazardous
liquid by vessel, aircraft, tank truck,
tank car, or other vehicle or terminal
PO 00000
Frm 00011
Fmt 4701
Sfmt 4702
61619
facilities used exclusively to transfer
hazardous liquids between such modes
of transportation,’’ MTB stated that: [Its]
authority to establish minimum Federal
hazardous liquid pipeline safety
standards under the [Hazardous Liquid
Pipeline Safety Act (HLPSA) of 1979]
extends to ‘‘the movement of hazardous
liquids by pipeline, or their storage
incidental to such movement.’’ The
Senate report that accompanied the
HLPSA states that, ‘‘It is not intended
that authority over storage facilities
extend to storage in marine vessels or
storage other than those which are
incidental to pipeline transportation.’’
(Sen. Rpt. 96–182, 1st Sess., 96th Cong.
(1979), p. 18.) Earlier laws had vested
DOT with extensive authority to
prescribe safety standards governing the
movement of hazardous liquids in
seagoing vessels, barges, rail cars, trucks
or aircraft and storage incidental to
those forms of transportation. From the
words of the new HLPSA and the
related Senate report language, it is clear
that Congress did not want to duplicate
or overlap any of those earlier laws.
Thus, HLPSA regulatory authority over
storage does not extend to any form of
transportation other than pipeline or to
any storage or terminal facilities that are
used exclusively for transfer of
hazardous liquids in or between any of
the other forms of transportation unless
that storage or terminal facility is also
‘‘incidental’’ to a pipeline which is
subject to the HLPSA. These storage and
terminal facilities are expressly
excluded from the coverage of part 195
July 27, 1981, (46 FR 38358). RSPA
modified that exception in the final rule
June 28, 1994, (59 FR 33388).
RSPA, however, continued to
maintain the exclusion for the
transportation of hazardous liquids or
carbon dioxide by non-pipeline modes,
and added a more detailed exclusion for
transfer piping located on the grounds
of a materials transportation terminal.
The regulatory history demonstrates
that the exception in § 195.1(b)(9) is
designed to exclude piping used in
transfers to non-pipeline modes of
transportation and the facilities and
piping at terminals that are used
exclusively for such transfers. The
provision is drafted to ensure that any
piping that is not used exclusively to
transfer product between non-pipeline
modes or transportation between a nonpipeline mode and a pipeline and
facilities are subject to regulation by
PHMSA. None of the commenters
argued in favor of changing the
exception, and there is no information
to suggest that such action is necessary
at this time. Accordingly, PHMSA is not
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
61620
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
proposing to modify or repeal
§ 195.1(b)(9).
With regard to the remaining
comments, section 16 of the Pipeline
Safety Act of 2011 requires the Secretary
to perform a comprehensive review of
whether the requirements in part 195
are sufficient to ensure the safety of
pipelines that transport diluted bitumen
(dilbit) and to provide Congress with a
report on the results of that review. That
review, titled ‘‘Effects of Diluted
Bitumen on Crude Oil Transmission
Pipelines,’’ was performed by the
National Academy of Sciences and was
published in 2013. The review found
there were no causes of pipeline failure
unique to the transportation of diluted
bitumen, or evidence of chemical or
physical properties of diluted bitumen
shipments that are outside the range of
other crude oil shipments, or any other
aspect of diluted bitumen’s
transportation by pipeline that would
make it more likely than other crude
oils to cause releases.3 However, the
safety proposals in this rulemaking
address all hazardous liquid pipelines,
which include pipelines that transport
diluted bitumen.
Multiproduct petroleum pipelines
transporting ethanol blends of up to
95% are currently regulated by PHMSA
under part 195 and no major ethanol
spills have occurred on these pipelines.
PHMSA is performing additional
research into the technical issues
associated with the transportation of
ethanol by pipeline and will use that
information to determine whether such
transportation should be subject to any
additional safety requirements in the
future. This NPRM proposes to conform
part 195 with 49 U.S.C. 60101(a)(4)
making the transportation by pipeline of
any biofuel that is flammable, toxic,
corrosive, or would be harmful to the
environment if released in significant
quantities, subject to part 195.
The requirements for HCA’s are
addressed in another portion of this
document. As noted above, PHMSA is
proposing to extend the federal
reporting requirements to all hazardous
liquid gathering lines (whether onshore,
offshore, regulated, or unregulated).
In conclusion, PHMSA will not be
proposing to change or eliminate any
other regulatory exceptions at this time.
The exception for carbon dioxide
pipelines is limited in scope and only
applies to production facilities.
Although breakout tanks are defined in
a way that limits the application of part
195, these certain storage tanks may also
3 https://phmsa.dot.gov/staticfiles/PHMSA/
DownloadableFiles/Files/Pipeline/Dilbit_1_
Transmittal_to_Congress.pdf.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
be subject to regulation by EPA. PHMSA
continues to study the scope of the
gathering line exemptions, but is not
proposing to modify these or any other
exemption. At present, nothing
indicates that any of the other
exceptions should be modified as part of
this rulemaking proceeding, or that the
issuance of regulations for underground
storage facilities is necessary.
Additional Safety Standards for
Underground Hazardous Liquid Storage
Facilities
The definition of a pipeline facility in
part 195 includes ‘‘any equipment,
facility, or building used in the
transportation of hazardous liquids
. . .’’ and, as already noted above,
includes storage terminals. While
surface piping in storage fields located
at midstream terminal facilities falls
within this definition, part 195 does not
contain comprehensive safety standards
for the ‘‘downhole’’ underground
hazardous liquid storage caverns. In
addition, surface piping at storage fields
located either at the production facility
where a pipeline originates or a
destination/consumption facility where
a pipeline terminates would generally
not be considered part of the
transportation and, therefore, not be
regulated by PHMSA in the manner that
such piping located on the grounds of
the midstream terminal would. RSPA
provided an explanation in a July 1997
advisory bulletin June 2, 1997, (62 FR
37118) which the agency issued in
response to a NTSB recommendation on
the regulation of underground storage
caverns (P–93–9). RSPA noted in that
advisory bulletin that a recent report
indicated that state regulations applied
in some form to significant percentages
of these facilities, and that API had
developed a set of comprehensive
guidelines for the underground storage
of liquid hydrocarbons. As result of
these state regulations, the API
guidelines, and ‘‘the varying and diverse
geology and hydrology of the many
sites’’ RSPA stated that agency had
‘‘decided that generally applicable
federal standards may not be
appropriate for underground storage
facilities.’’ June 2, 1997, (62 FR 37118)
RSPA further stated it would be
‘‘encouraging state action and voluntary
industry action as a way to assure
underground storage safety instead of
proposing additional federal
regulations.’’ Id. PHMSA understands
that Court decisions preempting state
from regulating interstate facilities
appears to be a concern for state
regulators.
PO 00000
Frm 00012
Fmt 4701
Sfmt 4702
Comments
PHMSA requested comment on the
promulgation of new or additional
safety standards for underground
hazardous liquid storage. The industry
commenter, TransCanada Keystone,
supported the comments of API–AOPL,
as did the trade associations LMOGA
and TxOGA. API–AOPL stated that the
current exclusion of the underground
cavern is appropriate as they are already
regulated by the states. API–AOPL
indicated that the states are better suited
to regulate these facilities because of
their knowledge of these facilities and
locations.
One government/municipality, DLA,
commented that there was no need for
new regulations for underground
hazardous liquid storage facilities. DLA
maintains that these facilities are
currently regulated for purposes of the
Clean Air Act under both 40 CFR parts
112 and 280 by the EPA.
Response
None of the commenters supported
the issuance of additional regulations
for underground hazardous liquid
storage caverns, and there is no
information suggesting that such action
is necessary at this time. Therefore,
PHMSA is not proposing to issue any
new regulations for underground storage
of hazardous liquids in this proceeding.
Order in Which Regulatory Changes
Should Be Made in to Best Protect the
Public, Property, or the Environment
Comments
PHMSA received comments from
industry, trade associations, one
government/municipality, and one
regulatory association responding to the
question on the order of the actions
PHMSA should take to best protect the
public, property, or the environment.
API–AOPL, supported by TransCanada
Keystone and the trade associations,
OIPA, TxOGA, and LMOGA, indicated
that PHMSA’s actions should be riskbased. Similarly, NAPSR had no
recommendation on the order, but
suggested that it be based on risk.
The government/municipality NSB
requested that PHMSA place a high
priority on the repeal of regulatory
exceptions for gathering of hazardous
liquids in rural areas, offshore pipelines
in state waters, and producer-operated
lines on the OCS. NSB stated that
unregulated rural pipelines are located
in Unusually Sensitive Areas (USAs) of
the NSB. These pipelines cross sensitive
arctic tundra vegetation and impact
areas used by endangered species. As
North Slope development continues to
expand to the west, east, and south,
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
impacts to NSB communities and USAs
will increase.
Response
PHMSA is proposing to repeal the
exception for gravity lines and to apply
the reporting requirements in part 195
to all gathering lines.
B. Definition of High Consequence Area
In the ANPRM, PHMSA asked for
public comment on whether to modify
the requirements in part 195 for HCAs.
Specifically, PHMSA asked whether:
• The criteria for identifying HCAs
should be changed to incorporate
additional pipeline mileage or better
reflect risk;
• All navigable waterways should be
included within the definition of an
HCA;
• The process for making HCA
determinations on pipeline ROWs can
be improved;
• The public and state and local
governments should be more involved
in making HCA determinations;
• Additional safety requirements
should be developed for areas outside of
HCAs; and
• Major road and railway crossings
should be included within the
definition of an HCA.
As discussed in detail later in the
Background and NPRM Proposals
section, PHMSA is proposing to adopt
additional safety standards for pipelines
that are located outside of areas that
could affect an HCA. These measures
will increase the safety of all of the
nation’s pipelines without necessitating
any change to the HCA definition;
therefore, PHMSA is not taking any
further action on that proposal at this
time.
Expanding the Definition of HCA To
Include Additional Pipeline Mileage
In the ANPRM, PHMSA asked
whether the current criteria for
identifying HCAs should be modified to
incorporate additional pipeline mileage.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Comments
TransCanada Keystone recommended
that PHMSA further define the meaning
of an HCA, and that the agency provide
greater clarity with respect to the HCA
classification, including the magnitude
of impacts that differentiate HCAs from
other areas.
API–AOPL, supported by the trade
associations, TxOGA and LMOGA, and
an industry commenter, TransCanada
Keystone, stated that the current criteria
should not be changed. API–AOPL
stated that PHMSA should serve a
clearinghouse function by displaying
HCA information on the NPMS, with
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
updates every 10 years based on census
information. API–AOPL further noted
that ‘‘other populated areas’’ includes
Census-delineated areas, like
Metropolitan Statistical Areas (MSA)
and Consolidated Metropolitan
Statistical Areas, which are not densely
populated, and that the current HCA
criteria are thus conservative. API–
AOPL also stated that the current ability
of operators to demonstrate why
segments of pipeline could not affect an
HCA should be retained.
The trade associations, OIPA and
TPA, suggested that more data is needed
to make a decision on HCA definition
expansion, and that any changes would
likely impact small operators.
Among citizens’ groups, PST favored
expanding the IM requirements to all
hazardous liquid lines, with initial
inspections required within 5 years of
identification. PST stated that using
census data to designate high
population and other population areas
is arbitrary and not necessarily a
predictor of risk. Noting that the public
could not fully comment because HCA
boundaries are not publicly available
(for security reasons); PST stated that
the definition of HCA should be
expanded to include national parks,
monuments, recreation areas, and
national forests. PST also pointed to the
recent trend in extreme accidents in
HCAs.
Two other citizens’ groups, AKW and
NRDC, commented. AKW requested that
the criteria be changed. NRDC indicated
that PHMSA should have a broader
definition of HCAs, particularly with
respect to ecological resources and
drinking water criterion.
NAPSR commented that the current
criteria are generally adequate, but that
other threats and risks could be
considered, including petroleum
product supply loss, leaks that could
affect private wells, and impacts to
major infrastructure.
NSB favored an expansion of HCAs to
include pipelines located in subsistence
areas, cultural resources, archeological,
historical, and recreational areas of
significance and offshore.
Response
Congress recently directed the
Secretary to prepare a report on whether
the IM requirements should be extended
to pipelines outside of areas that could
affect HCAs. The Secretary is prohibited
from issuing any final regulations that
would expand those requirements
during a subsequent Congressional
review period, unless those regulations
are necessary to address a condition
posing a risk to public safety, property,
or the environment, or an imminent
PO 00000
Frm 00013
Fmt 4701
Sfmt 4702
61621
hazard. PHMSA is preparing the
Secretary’s report to Congress on the
need to expand the IM requirements and
is not proposing to change the definition
of an HCA to incorporate additional
pipeline mileage at this time.
PHMSA is, however, proposing to
adopt additional safety standards for
pipelines that are not covered under the
IM program requirements. The
proposals are detailed later in this
NPRM under the Background and
NPRM proposals section.
PHMSA is aware of its obligation to
consider other locations near pipeline
ROWs in defining USAs, including
‘‘critical wetlands, riverine or estuarine
systems, national parks, wilderness
areas, wildlife preservation areas or
refuges, wild and scenic rivers, or
critical habitat areas for threatened and
endangered species.’’ However, PHMSA
is not proposing to make any of these
areas USAs in light of the new
requirements that are being proposed for
non-IM pipelines. PHMSA will be
considering whether to include these
locations in the HCA definition in
performing the evaluation required
under section 5 of the Pipeline Safety
Act of 2011 and will comply with the
applicable provisions of that legislation
before taking any final regulatory action
to adopt the proposed requirements for
non-IM pipelines.
Modifying the Definition of HCA to
Better Reflect Risk
PHMSA asked whether the criteria for
identifying HCAs should be changed to
better reflect risk.
Comments
TransCanada Keystone’s comment
focused specifically on the classification
of groundwater USAs in § 195.6, stating
that groundwater HCA buffers should
not be expanded, and that the existing
criteria, which identify community
water intakes where contamination has
the potential to cause greater impacts
compared to other areas, are sufficient.
API–AOPL stated that there are
various risk factors applicable to HCA
classifications and that the current
definition should not be changed. API–
AOPL recommended that buffer zones
be used as an acceptable alternative to
the more detailed ‘‘could affect’’
analysis for new, expanded, or modified
HCAs. API–AOPL also suggested that
operators should retain the ability, with
technical justification, to determine
whether a pipeline can actually impact
an HCA. TransCanada Keystone,
LMOGA, and TxOGA endorsed API–
AOPL’s comments. TPA, the other trade
association commenter, mentioned that
E:\FR\FM\13OCP3.SGM
13OCP3
61622
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
more data was needed to make a final
decision on this matter.
A number of citizens’ groups
commented on this issue. NRDC, AKW,
and TWS indicated the HCA definition
needs to be broadened to reflect risk and
to include entire pipelines in some
cases. NRDC stated that the threshold
for a populated area should be lowered,
and that the definition of populated
areas and USA should be improved.
NRDC commented that the current HCA
definition provides limited protection to
threatened or endangered species.
NRDC also recommended strengthening
the USA definition to protect more
migratory bird areas and national
landmarks, including national parks,
wild and scenic rivers, estuaries,
wilderness areas, wildlife refuges, and
drinking water sources, including
private wells and open source aquifers.
TWS and AKW proposed to revise the
HCA criteria to include all
transportation infrastructure, public
lands, waterways, wetlands, and
cultural, historic, archeological, and
recreation sites, including subsistence
areas.
NAPSR stated that the current HCA
definition should not be changed, but
that PHMSA should consider
incorporating others threats and risks,
including supply interruptions and
small leaks that could affect private
wells.
NSB favored changing the existing
HCA definition. NSB stated that USAs
should include subsistence, cultural,
archeological, historical, and
recreational areas of significance within
the NSB and offshore waters of the
Beaufort and Chukchi Seas. NSB
suggested a formal process for
nominating areas that should be
afforded HCA status, and that the NPMS
data should be updated.
Both MAWUC and DLA indicated the
definition could be modified to better
reflect risk. MAWUC suggested a tiered,
prioritized system with enforceable
criteria that are appropriate for the risk
to water supplies. DLA stated that
higher risk locations should be
protected instead of simply creating
more HCAs.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Response
PHMSA is not proposing to make any
changes to the criteria for identifying
HCAs at this time. The existing Censusbased approach for determining high
population and other populated areas
ensures uniformity and provides an
adequate margin of safety by including
some less densely populated areas.
None of the commenters offered a more
effective alternative.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
PHMSA recognizes that other areas of
ecological, cultural, or national
significance could be designated as
USAs. However, PHMSA is not
proposing to add any of these areas in
light of the new safety standards that are
being proposed for hazardous liquid
pipelines that are not subject to the IM
program requirements.
PHMSA does not support any of the
suggested alternative approaches for
identifying HCAs. The widespread use
of the buffer method is not justified
based on the available information, and
the use of a more lenient standard in
making HCA determinations would not
provide adequate protection for these
sensitive areas. PHMSA will revisit
these conclusions in preparing the
Secretary’s report to Congress on
expanding the IM program for
hazardous liquid pipelines.
Commercial Limitation on Navigable
Waterways
The ANPRM posed the question of
expansion of the definition of HCAs
beyond commercially navigable
waterways.
Comments
Several trade associations, API–
AOPL, OIPA, and IPAA, and one
industry representative, TransCanada
Keystone, opposed expanding the HCA
definition beyond commercially
navigable waterways. These
commenters stated that the vast majority
of surface waters are already covered
under the present criteria. TPA stated
that adopting a navigable waters
standard would make every creek an
HCA, resulting in a significant increase
in the burden associated with
implementing IM requirements.
Two citizens’ groups commented on
the phrase ‘‘commercially navigable.’’
PST also recommended defining HCA to
include all ‘‘waters of the United
States,’’ provided PHMSA did not adopt
its suggestion to apply IM requirements
to all regulated pipelines. NRDC
proposed to amend the term
‘‘commercially navigable waterways’’ to
include other bodies of water that are
not necessarily navigable, such as lakes,
streams, and wetlands.
Two government/municipalities
commented on the commercial
limitation on navigable waterways.
DLA, a government/municipality,
echoed the comments of the trade
associations and TransCanada Keystone
previously mentioned. NSB requested
PHMSA change commercially navigable
to ‘‘navigable waters’’ or ‘‘waters of the
U.S.’’ to encompass more
environmentally-sensitive areas.
PO 00000
Frm 00014
Fmt 4701
Sfmt 4702
Response
Section 195.450 states that an HCA
includes any ‘‘waterway where a
substantial likelihood of commercial
navigation exists.’’ RSPA first proposed
to include commercially navigable
waterways as HCAs in the April 2000
NPRM that contained the original IM
requirements for hazardous liquid
pipelines April 24, 2000, (65 FR 21695).
RSPA stated that it ‘‘[wa]s including
commercially navigable waterways in
the proposed [HCA] definition[,]
[b]ecause these waterways are critical to
interstate and foreign commerce and
supply vital resources to many
American communities, are a major
means of commercial transportation,
and are a part of a national defense
system, a pipeline release in these areas
could have significant impacts.’’ April
24, 2000, (65 FR 21700).
RSPA adopted the HCA definition as
proposed in the NPRM in the final rule
December 1, 2000, (65 FR 75378). In the
preamble to that final rule, RSPA stated
that it had received the following
comments on its proposal to include
commercially navigable waterways in
the HCA definition:
API and liquid operators questioned
the inclusion of commercially navigable
waterways into the HCA’s definition.
API pointed out that Congress required
OPS to identify hazardous liquid
pipelines that cross waters where a
substantial likelihood of commercial
navigation exists and once identified,
issue standards, if necessary, requiring
periodic inspection of the pipelines in
these areas. API said that OPS had not
determined the necessity for including
these waterways in areas that trigger
additional integrity protections. BP
Amoco said the rule should be limited
to protection of public safety, rather
than commercial interests. Enbridge and
Lakehead also questioned why
waterways that are not otherwise
environmentally sensitive should be
included for protection.
EPA Region III said that we should
also consider recreational and
waterways other than those for
commercial use. Environmental
Defense, Batten, City of Austin and
other[s] commented that we should
consider all navigable waterways as
HCA’s, because of the environmental
consequences a hazardous liquid release
could have on such waters. December 1,
2000, (65 FR 75390).
RSPA provided the following
response to those comments:
‘‘Our inclusion of commercially
navigable waterways for public safety
and secondary reasons is not based on
the ecological sensitivity of these
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
waterways. Parts of waterways sensitive
for ecological purposes are covered in
the proposed USA definition, to the
extent that they contain occurrences of
a threatened and endangered species,
critically imperiled or imperiled
species, depleted marine mammal,
depleted multi-species area, Western
Hemispheric Shorebird Reserve
Network or Ramsar site. We are
including commercially navigable
waterways as HCAs because these
waterways are a major means of
commercial transportation, are critical
to interstate and foreign commerce,
supply vital resources to many
American communities, and are part of
a national defense system. A pipeline
release could have significant
consequences on such vital areas by
interrupting supply operations due to
potentially long response and recovery
operations that occur with hazardous
liquid spills. December 1, 2000, (65 FR
75391–2).
For these reasons, RSPA defined
HCAs in § 195.450 to include
commercially navigable waterways.
Thus, the Pipeline Safety Laws do not
necessarily limit the definition of an
HCA to commercially navigable
waterways. RSPA relied on several
statutes in promulgating the IM
requirements for hazardous liquid
pipelines, including the mandates that
required the Secretary to establish
criteria for identifying pipelines in high
density population and environmentally
sensitive areas (49 U.S.C. 60109(a)(1))
and to promulgate standards for
ensuring the periodic inspection of
these lines (49 U.S.C. 60102(f)(2)).
Nothing in these provisions or the
Pipeline Safety Act of 2011 prohibits
PHSMA from using its general
rulemaking authority to apply the
hazardous liquid pipeline IM
regulations to waterways that are not
used for commercial navigation. Other
kinds of waterways are also referenced
in the statutory criteria that must be
considered in defining USAs.
PHMSA will be considering the
expansion of current HCA or the
extension of critical IM requirements to
non-HCAs-when completing the
Secretary’s report to Congress on the
need to expand the IM requirement
under section 5 of the Pipeline Safety
Act of 2011. In the meantime, PHMSA
is not proposing to include any
additional waterways in the HCA
definition.
PHMSA is, however, proposing to
adopt other regulations that will
increase the safety of our nation’s
waterways. One such proposal is to
require leak detection systems for
pipelines in all locations, that operators
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
perform periodic assessments of
pipelines not already covered under the
IM program requirements, and that new
pipeline repair criteria be applied to
anomalous conditions discovered in all
areas. Another proposal is to require
operators to inspect their pipelines in
areas affected by extreme weather,
natural disasters, and other similar
events (e.g., flooding, hurricanes,
tornados, earthquakes, landslides, etc.).
Following a disaster event, operators
will be required to determine whether
any conditions exist that could
adversely affect the safe operation of a
pipeline and to take appropriate
remedial actions, such as reductions in
operating pressures and repairs of any
damaged facilities or equipment.
In regard to seismic events and
earthquakes, in determining whether a
pipeline has potentially been affected
and needs inspection, operators should
consider relevant factors such as
magnitude of the earthquake, distance
from the epicenter, and pipeline
characteristics and history. PHMSA
recognizes that after considering these
factors, operators may determine that
smaller seismic events do not have the
potential to affect their pipelines. Based
on available studies, however,
earthquakes over 6.0 in magnitude can
potentially damage pipelines and
operators would be required to inspect
these pipelines.
Operator Process and Public
Participation in Making HCA
Determinations
PHMSA requested comment on
whether the operator’s process for
making HCA determinations should be
modified, including by having greater
involvement by the public and state and
local governments.
Comments
PHMSA received comments from
industry, trade associations, and one
regulatory association. API–AOPL
supported the existing process for
identifying HCAs and suggested that
any input from local communities
should be through the regulating
agency, rather than pipeline operators.
OPIA and IPAA noted that a consistent
and reliable approach is needed to
prevent variations that would result in
unnecessary confusion.
The trade associations, TxOGA,
LMOGA, API–AOPL, supported by
TransCanada Keystone, indicated that
operators perform geographic overlay of
their pipeline systems with PHMSAdetermined HCAs. Operators also utilize
the ‘‘could affect’’ analysis, which
typically considers technical
assessments using dispersion models.
PO 00000
Frm 00015
Fmt 4701
Sfmt 4702
61623
Through the process of HCA evaluation,
operators are sometimes able to
determine, with technical justification,
that their assets are not capable of
impacting an HCA.
NAPSR indicated that PHMSA could
consider adding minimum time
intervals for operators to review HCA
identifications, including a shorter time
interval if a pipeline is routed through
high population areas. NAPSR also
stated that there are areas where private
wells have been extremely affected by
small leaks that go undetected for years,
that this is especially true in areas of
sandy soil where leaks do not
necessarily bubble up to the surface,
and that there should be some
consideration to address these ‘‘seepers’’
that have very large total leak volume
over time.
On the matter of greater public
participation, TransCanada Keystone
suggested that PHMSA collect data from
the states and provide updated HCA
information for operator use. The trade
associations, LMOGA, TxOGA and API–
AOPL, supported by TransCanada
Keystone, recommended that additional
local involvement be routed through the
regulating agency, such as PHMSA.
TPA, in contrast, stated that there
should be no requirement for public
involvement. OIPA and IPAA held that
a consistent and reliable approach is
needed for the issue of public
involvement.
Among the citizens’ groups, NRDC
supported additional public
involvement. Several commenters,
including NRDC, PST, and TWS,
recommended that the NPMS be revised
to display all HCAs so that the public
can be better informed.
One regulatory association, NAPSR,
suggested that the public be allowed to
comment. NAPSR recognized that
PHMSA has a process in place for HCA
selection that can be enhanced if the
public is allowed to provide input.
NAPSR stated that the general public
and local communities often recognize
changes in areas near pipelines before
operators.
Government and municipal
commenters supported local
involvement in the HCA determination
process. MAWUC commented that it is
important that local communities and
water suppliers play a role in preventing
and minimizing pipeline failures,
including HCA identification. DLA also
supported additional public
involvement. NSB recommended that
state and local governments, as well as
local tribes, villages, and the Alaskan
Eskimo Whaling Commission, have a
role in making HCA determinations.
E:\FR\FM\13OCP3.SGM
13OCP3
61624
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
Response
Congress included new requirements
for promoting public education and
awareness in section 6 of the Pipeline
Safety Act of 2011. Specifically, that
provision requires PHMSA (1) to
maintain, and update on a biennial
basis, a map of designated HCAs in the
NPMS; (2) to establish a program that
promotes greater awareness of the
existence of the NPMS to state and local
emergency responders and other
interested parties, to include the
issuance of guidance on using the
NPMS to locate pipelines in
communities and local jurisdictions;
and (3) to issue additional guidance to
owners and operators of pipeline
facilities on the importance of providing
system-specific information to
emergency response agencies. PHMSA
believes that such actions will address
many of the concerns raised by the
commenters.
Additional Safety Requirements for
Non-HCA Areas
PHMSA inquired as to whether
additional safety measures should be
developed for areas outside of HCAs.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Comments
PHMSA received comments from
three trade associations and one
regulatory association. TransCanada
Keystone, TxOGA, API–AOPL, and
LMOGA indicated that no new
requirements are necessary for areas
outside of HCAs. The regulatory
association, NAPSR, remarked that
operators should be precluded from
turning off in-line inspection sensors
outside of an HCA when performing an
integrity assessment under the IM
regulations.
Response
PHMSA agrees with the NAPSR
comment and has likewise found that
some operators do turn off inspection
tools outside of HCAs. Therefore,
PHMSA is proposing to require that
operators perform periodic assessments
of pipelines that are not already covered
under the IM program requirements in
§ 195.452. Promulgation of such a
requirement will ensure that pipeline
operators obtain the information
necessary for the prompt detection and
remediation of corrosion and other
deformation anomalies (e.g., dents,
gouges, and grooves) in all locations, not
just in areas that could affect HCAs.
Inclusion of Major Road and Railway
Crossings as HCAs
PHMSA requested comment on the
need to include major road and railway
crossings as HCAs.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
Comments
Industry, three trade associations,
three citizens’ groups, one regulatory
association, one government/
municipality, and one citizen
commented on this question.
TransCanada Keystone, supported by
the trade associations, API–AOPL, TPA,
TxOGA, and LMOGA, opposed
including major roads and railway
crossings as HCAs. The commenters
offered several reasons to support that
position (e.g., such a change would
draw resources from other more high
risk areas, non-HCA areas are already
assessed and remediated, and there is
no data to support such an action).
Among the citizens’ groups, PST
stated that rail and major road crossings
should be included. TWS and AKW
stated that all transportation
infrastructure, public lands, wetlands
under the Clean Water Act (CWA),
cultural, historical, archeological and
recreation areas used for subsistence be
included in HCAs.
NAPSR also suggested that rail and
major road crossings should be
included. NAPSR urged PHMSA to
consider the effect of a release on
electric transmission facilities, gas
pipelines, and railroads if major road
and rail crossings were not to be
included in HCAs. NAPSR would
consider the effect of a release on
electric transmission facilities, gas
pipelines, railroads, etc., and would
treat major road and rail crossings as
HCAs for highly volatile liquids (HVLs)
pipelines.
The only government/municipality to
comment on this question was DLA.
DLA indicated that these structures
should be included in HCAs.
Citizen Coyle commented that major
roadways should be HCAs because these
areas could be affected by pipelines
carrying HVLs that would produce
poisonous clouds if released.
Response
PHMSA is not proposing to designate
major road and railway crossings as
HCAs, but will consider whether the
pipeline IM requirements should be
applied to these areas when completing
the study that Congress mandated under
section 5 of the Pipeline Safety Act of
2011. PHMSA notes that the pipelines at
such crossings would be afforded
additional protections under the other
proposals made in this proceeding,
including the requirements for the
performance of periodic internal
inspections and the use of leak
detection systems.
PO 00000
Frm 00016
Fmt 4701
Sfmt 4702
C. Leak Detection Equipment and
Emergency Flow Restricting Devices
In the ANPRM, PHMSA asked for
comment on whether to modify the
current requirements part 195 for leak
detection equipment and emergency
flow restricting devices (EFRDs).
Specifically, PHMSA asked whether
• The use of leak detection
equipment should be required for
hazardous liquid pipelines;
• The pipeline industry has
developed any practices, standards, or
leak detection technologies that should
be incorporated by reference;
• Any industry practices or standards
adequately address the relevant safety
considerations;
• State regulations for leak detection
should be adopted by regulation;
• Any new leak detection
requirements should vary based on the
sensitivity of the affected areas;
• The pipeline industry has
developed standards or practices for the
performance and location of EFRDs;
• The location of EFRDs should be
specified by regulation; and
• Additional research and
development is needed to demonstrate
the suitability of any new leak detection
technologies.
As discussed below, PHMSA is
considering requiring that all hazardous
liquid pipelines have a system for
detecting leaks and expand the use of
EFRDs.
Expansion of Leak Detection
Requirements
In the ANPRM, PHMSA asked for
comment on whether the agency should
expand the leak detection requirements.
Comments
Industry and trade associations
generally supported expansion of the
existing requirement in § 195.452(i)(3)
to most pipelines, but opposed
including more-specific requirements in
the regulations. API–AOPL, TxOGA,
TransCanada Keystone, and LMOGA
supported extending leak detection
requirements to all PHMSA-regulated
pipelines, except for rural gathering
lines.
Citizens’ groups supported enhanced
leak detection requirements. TWS and
PST opposed additional reliance on the
current requirements in § 195.452(i)(3),
stating that this regulation includes no
acceptance criteria and is virtually
unenforceable. TWS further supported
expanding leak detection requirements
to all pipelines under PHMSA
jurisdiction. NRDC indicated that leak
detection requirements should be
expanded to include a requirement that
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
worst-case-discharge-pumping times be
based on historical shutdown times,
rather than expected times. NRDC also
said that operators should immediately
contact first responders at the first sign
of an issue. One citizen, Stec, suggested
requiring use of ‘‘smart coating’’ with
embedded conductors that would break
to indicate coating damage and which
could then trigger automatic response
actions.
The regulatory associations, DLA and
MAWUC, supported expanded leak
detection requirements. MAWUC
suggested PHMSA require the use of
leak detection equipment in all HCAs.
DLA indicated that any new
requirements should be delayed until
better technology is available.
The government/municipality, NSB,
recommended leak detection
requirements be expanded to all
pipelines under PHMSA regulation.
NSB encouraged adoption of more
stringent leak detection requirements for
sensitive offshore areas of the Beaufort
and Chukchi seas.
Response
As discussed earlier in this NPRM
under the Background and Proposals
section, PHMSA will propose to expand
the leak detection requirements for HCA
and non-HCA areas.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Consideration of New Industry
Standards or Practices in Leak Detection
PHMSA asked for public comment on
whether any new industry standards or
practices should be considered for
adoption in part 195.
Comments
API–AOPL, TxOGA, LMOGA, and
TransCanada Keystone all indicated that
the API–AOPL standard RP1165
(SCADA), RP 1167 (Pipeline Alarm
Management), and RP1168 (Control
Room Management) are good standards
to utilize for leak detection systems.
API–AOPL also pointed out that many
new technologies are being developed
and existing methodologies are
continuously being improved for better
leak detection capability; however,
many of these new technologies have
not been proven in service on crosscountry pipelines.
One citizens’ group, NRDC,
commented that new leak detection
standards should address the additional
demands posed by hazardous liquids. In
particular, NRDC mentioned some
hazardous liquids, such as diluted
bitumen, have multiphase properties
that can cause false alarms.
The regulatory associations, NAPSR
and DLA, both commented on new
industry standards and practices in leak
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
detection. NAPSR mentioned the new
technology forward-looking infrared
radar (FLIR) and encouraged PHMSA to
consider using such new technologies.
NAPSR reported that FLIR can detect
changes in temperature near a pipeline
from a winter leak, even under snow,
and that it can be used from aerial
patrols.
DLA indicated that any leak detection
standards should be third-party
validated and listed by the National
Work Group on Leak Detection
Evaluations (NWGLDE) and that leak
detection in general for large volume
pipelines is not very effective at this
time.
Response
The commenters only offered three
specific industry standards or practices
for consideration, and two of those
standards, API RP1165 (SCADA) and
RP1168 (Control Room Management),
are already incorporated into part 195
(see 49 CFR 195.3). PHMSA has
concerns about the adequacy and
enforceability of the third standard, API
RP 1167 (Pipeline Alarm Management),
and does not believe that it should be
incorporated by reference at this time.
As previously discussed, PHMSA is
proposing to require that operators have
a means for detecting leaks on all
portions of a hazardous liquid pipeline
system. Consideration of FLIR and any
other emerging technologies would be
required in evaluating what kinds of
leak detection systems are appropriate
for a particular pipeline. PHMSA will
also be considering whether the use of
specific leak detection technologies
should be required in preparing the
Secretary’s report to Congress on that
issue.
PHMSA does not agree that thirdparty validation is a prerequisite to
issuing new leak detection requirements
for hazardous liquid pipelines. That
limitation is not included in the
Pipeline Safety Laws, and PHMSA does
not believe that such action is necessary
as a matter of administrative discretion.
Adequacy of Existing Industry
Standards or Practices for Leak
Detection
PHMSA asked for public comment on
whether any existing industry standards
or practices for leak detection are
adequate for adoption into part 195.
Comments
TransCanada Keystone, TxOGA,
LMOGA and API–AOPL submitted
comments indicating that the current
leak detection evaluations performed as
a requirement of the IM program
encompass many important factors for
PO 00000
Frm 00017
Fmt 4701
Sfmt 4702
61625
proper leak detection. PHMSA should
allow for the implementation of recent
regulatory changes, including the new
Control Room Management (CRM) rule,
before making any changes. NAPSR
commented that all pipeline operators
should, at a minimum, perform a tank
balance periodically to detect leakage.
NSB recommended that PHMSA
adopt improved leak detection system
standards and implement more stringent
leak detection requirements for the
sensitive offshore areas of the Beaufort
and Chukchi seas. NSB stated that
PHMSA should require: (1) Redundant
leak detection systems for offshore
pipelines; (2) All offshore pipeline leak
detection systems to have the
continuous capability to detect a daily
discharge equal to not more than 0.5%
of daily throughput within 15 minutes,
and detect a pinhole leak within less
than 24 hours; (3) All onshore pipeline
leak detection systems to have the
continuous capability to detect a daily
discharge equal to not more than 1% of
daily throughput within 15 minutes,
and detect a pinhole leak within less
than 24 hours; and (4) An initial
performance test to verify leak detection
accuracy upon installation and at
regular intervals thereafter.
Response
PHMSA agrees that the factors listed
in § 195.452(i)(3) are an appropriate
basis for determining whether
hazardous liquid pipelines have an
adequate leak detection system and is
proposing to use those factors as the
basis for the requirements that would
apply in all other locations. However, a
December 31, 2007, report that PHMSA
prepared in response to a mandate in
the Pipeline Inspection, Protection,
Enforcement, and Safety Act (PIPES
Act) of 2006 (Pub. L. 109–468),
confirmed that some operators had IM
procedures that did not require the
performance of a leak detection
evaluation, and others had adopted an
inadequate process for performing those
evaluations. Operators are reminded
that any failure to comply with part 195,
including the leak detection
requirements in § 195.452(i)(3) and the
proposed modifications to §§ 195.134
and 195.444, increases both the
likelihood and severity of pipeline
accidents.
PHMSA agrees that the new CRM
requirements will improve the detection
and mitigation of leaks on hazardous
liquid pipeline systems, but does not
agree that the implementation of
improved leak detection requirements
should be delayed solely on account of
the recent issuance of those regulations.
PHMSA will be monitoring the use of
E:\FR\FM\13OCP3.SGM
13OCP3
61626
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
leak detection systems by operators in
complying with those requirements in
determining if additional safety
standards are needed.
procedure for responding to alarms. The
pipeline company must maintain leak
detection maintenance and alarm
records.
Consideration of State Requirements/
Regulations for Leak Detection
Some states have established leak
detection requirements for hazardous
liquid pipeline systems. For example,
the Alaska Department of
Environmental Conservation (ADEC)
has promulgated a regulation (18 AAC
75.055) that states:
(a) A crude oil transmission pipeline
must be equipped with a leak detection
system capable of promptly detecting a
leak, including
(1) if technically feasible, the
continuous capability to detect a daily
discharge equal to not more than one
percent of daily throughput;
(2) flow verification through an
accounting method, at least once every
24 hours; and
(3) for a remote pipeline not otherwise
directly accessible, weekly aerial
surveillance, unless precluded by safety
or weather conditions.
(b) The owner or operator of a crude
oil transmission pipeline shall ensure
that the incoming flow of oil can be
completely stopped within one hour
after detection of a discharge.
(c) If above ground oil storage tanks
are present at the crude oil transmission
pipeline facility, the owner or operator
shall meet the applicable requirements
of 18 AAC 75.065, 18 AAC 75.066, and
18 AAC 75.075.
(d) For facility oil piping connected to
or associated with the main crude oil
transmission pipeline the owner or
operator shall meet the requirements of
18 AAC 75.080.
Operators who install online leak
detection systems can also receive a
reduction in the volume of crude oil
that must be used in complying with
Alaska’s oil spill response planning
requirements (18 AAC 75.436(c)(3)).
The State of Washington has also
prescribed leak detection requirements
for hazardous liquid pipelines (WAC
480–75–300). Those requirements,
which are administered by the
Washington Utilities and Transportation
Commission (WUTC), state:
(1) Pipeline companies must rapidly
locate leaks from their pipeline.
Pipeline companies must provide leak
detection under flow and no flow
conditions.
(2) Leak detection systems must be
capable of detecting an eight percent of
maximum flow leak within fifteen
minutes or less.
(3) Pipeline companies must have a
leak detection procedure and a
Comments
PHMSA received comments from
several trade associations and one
citizens’ group on state requirements for
leak detection systems. API–AOPL
indicated that pipeline configuration
and operational factors vary by
geographic location, and that other
variability exists, including fluid or
product differences, batching, and other
operational conditions. Due to these
factors, any type of prescriptive
approach to standards for leak detection
is difficult to achieve and would be
better served using a performance
standard. CRAC noted that multi-phase
lines are more susceptible to internal
corrosion, and that state regulations do
not require IM or leak detection.
NAPSR and DLA also commented.
NAPSR encouraged PHMSA to allow
the states to set minimum leak detection
criteria for intrastate pipelines. DLA
opposed development of criteria based
on state requirements and suggested that
new requirements be third-party
validated and listed by NWGLDE.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
Response
PHMSA favors the use of
performance-based safety standards and
believes that the regulations adopted by
ADEC and WUTC show that certain
minimum threshold requirements can
be established for leak detection
systems. PHMSA will be considering
these and other similar regulations in an
evaluation of leak detection systems.
With regard to NAPSR’s comment,
section 60104(c) of the Pipeline Safety
Laws allows states that have submitted
a current certification to adopt
additional or more stringent safety
standards for intrastate hazardous liquid
pipeline facilities, so long as those
requirements are compatible with the
minimum federal safety standards.
PHMSA has prescribed mandatory leak
detection requirements for hazardous
liquid pipelines that could affect HCAs
and is proposing to make those
requirements applicable to all pipelines
subject to part 195. States that have
submitted a current certification can
establish additional or more stringent
leak detection standards for intrastate
hazardous liquid pipeline facilities,
subject to the statutory compatibility
requirement.
PHMSA does not agree that thirdparty validation is a prerequisite to
issuing new leak detection requirements
for hazardous liquid pipelines. That
limitation is not included in the
PO 00000
Frm 00018
Fmt 4701
Sfmt 4702
Pipeline Safety Laws, and PHMSA does
not believe that such action is necessary
as a matter of administrative discretion.
Different Leak Detection Requirements
for Sensitive Areas
Section 195.452(i)(3) contains a
mandatory leak detection requirement
for hazardous liquid pipelines that
could affect an HCA. That regulation
requires operators to consider several
factors (i.e., the length and size of the
pipeline, type of product carried,
proximity to the HCA, the swiftness of
leak detection, location of nearest
response personnel, leak history, and
risk assessment results) in selecting an
appropriate leak detection system.
Comments
PHMSA received many comments in
response to whether there should be
different leak detection requirements for
sensitive areas. The trade associations,
TxOGA and LMOGA, supported API–
AOPL’s comments that most leak
detection methods cannot target specific
areas. API–AOPL further stated that leak
detection for sensitive areas can be
achieved through comprehensive riskbased evaluation, but that external
monitoring is too invasive and is not yet
proven or cost effective.
The regulatory associations,
government/municipalities, and citizens
all supported increased leak detection
requirements for sensitive areas. The
regulatory association, NAPSR,
mentioned the use of FLIR for sensitive
areas and stated that special actions
beyond patrols should be required for
sensitive areas. DLA indicated leak
detection standards should be thirdparty validated. MAWUC and a citizen,
Coyle, recommended requiring external
leak detectors in HCAs. Coyle would
also require external leak detectors for
above-ground pipelines transporting
highly volatile liquids. NSB encouraged
PHMSA to adopt improved leak
detection standards and implement
more stringent requirements for
sensitive areas.
Response
PHMSA believes that the leak
detection requirements in § 195.452(i)(3)
can provide adequate protection for
sensitive areas and is proposing to use
those requirements as the basis for
establishing requirements that would
apply to hazardous liquid pipelines in
all other locations. Under the current
and proposed regulations, operators are
required to consider several factors in
selecting an appropriate leak detection
system, including the characteristics
and history of the affected pipeline, the
capabilities of the available leak
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
detection systems, and the location of
emergency response personnel. PHMSA
commissioned Kiefner and Associates,
Inc., to perform a study on leak
detection systems used by hazardous
liquid operators. That study, titled
‘‘Leak Detection Study,’’ 4 was
completed on December 10, 2012, and
was submitted to Congress on December
27, 2012. PHMSA is considering, in a
different rulemaking activity, whether to
adopt additional or more stringent
requirements for sensitive areas in
response to this study.
Key Issues for New Leak Detection
Standards
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Comments
The trade associations, TxOGA,
LMOGA, and API–AOPL, supported by
an industry commenter, TransCanada
Keystone, stated that PHMSA should
identify issues that might adversely
affect response times, including limiting
the consequences for first responder
deployment and allowing for the
withdrawal of erroneous leak
notifications. NAPSR, the only
regulatory association to comment,
found that any new standards should
consider detection of small leaks in
HCAs, maintenance, accuracy, transient
conditions, system capabilities, and
alarm management.
Three government/municipalities
commented on this issue. DLA stated
that any standards should address
sensitivity, probability of false alarms,
minimum leak detection capabilities,
frequency, and be based on leak
detection technology. MAWUC
supported more stringent reporting and
repair requirements. NSB indicated that
PHMSA should require redundant leak
detection systems for offshore lines.
NSB also indicated the technology
available for leak detection systems is
vastly improved and industry should
bear the burden to utilize these systems.
Response
The Pipeline Safety Laws contain a
number of general factors that must be
considered in prescribing new safety
standards, including the reasonableness
of the standard, the estimated benefits
and costs, and the views and
recommendations of the Technical
Hazardous Liquid Pipeline Safety
Standards Committee (49 U.S.C.
60102(b)). The Pipeline Safety Laws also
contain specific factors that must be
considered in prescribing certain safety
standards, such as for smart pigs (49
4 https://www.phmsa.dot.gov/pv_obj_cache/pv_
obj_id_4A77C7A89CAA18E285898295888E3DB9
C5924400/filename/Leak%20Detection%20Study.
pdf
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
U.S.C. 60102(f)) or low-stress hazardous
liquid pipelines (49 U.S.C. 60102(k)).
In the case of leak detection, Congress
has enacted prior statutory mandates
that required the Secretary to survey
and assess the need for additional safety
standards. PHMSA and its predecessor
agency, RSPA, complied with those
mandates by producing two reports and
promulgating additional safety
standards for leak detection systems.
Congress enacted a similar provision in
section 8 of the Pipeline Safety Act of
2011, including a requirement that the
Secretary submit a report to Congress
that provides an analysis of the
technical limitations of current leak
detection systems and the practicability,
safety benefits, and adverse
consequence of establishing additional
standards for the use of such systems.
The commenters identified several
issues that should be considered in
establishing new leak detection
standards, including the need to
minimize false alarms, to set
appropriate volumetric thresholds, and
to encourage the use of best available
technologies.
Statistical Analyses of Leak Detection
Requirements
PHMSA asked the public to comment
on the availability of statistics on
whether existing practices or standards
on leak detection have contributed to
reduced spill volumes and
consequences.
Comments
One response submitted by API–
AOPL, supported by TransCanada
Keystone, LMOGA, and TxOGA, stated
that the association was unaware of any
recent statistics in regard to this topic.
API–AOPL further indicated that
PHMSA should allow time for recent
regulatory changes to take effect on the
regulated population.
Response
PHMSA’s December 2007 report on
leak detection systems noted that from
1997 to 2007 ‘‘the median volume lost
from hazardous liquid pipeline
accidents dropped by more than half,
from 200 to less than 100 barrels,’’ and
that ‘‘the number of accidents declined
by over a third.’’ The report attributed
that positive trend to the
implementation of the pipeline IM
requirements in § 195.452. However, the
report also indicated that all of the
available leak detection technologies
have strengths and weakness, that some
are only suitable for use on particular
pipeline systems, and that establishing
safety standards would require
consideration of a number of factors.
PO 00000
Frm 00019
Fmt 4701
Sfmt 4702
61627
Consideration of Industry Practices or
Standards for Location of EFRDs
Part 195 requires that EFRDs be
considered as potential mitigation
measure on pipeline segments that
could affect HCAs. In terms of
§§ 195.450 and 195.452 the definition
for check valve means a valve that
permits fluid to flow freely in one
direction and contains a mechanism to
automatically prevent flow in the other
direction. Likewise, remote control
valve or RCV means any valve that is
operated from a location remote from
where the valve is installed. The RCV is
usually operated by the supervisory
control and data acquisition (SCADA)
system. The linkage between the
pipeline control center and the RCV
may be by fiber optics, microwave,
telephone lines, or satellite.
Section 195.452(i)(4) further states
that if an operator determines that an
EFRD is needed on a pipeline segment
to protect a high consequence area in
the event of a hazardous liquid pipeline
release, an operator must install the
EFRD. In making this determination, an
operator must, at least, consider the
following factors—the swiftness of leak
detection and pipeline shutdown
capabilities, the type of commodity
carried, the rate of potential leakage, the
volume that can be released, topography
or pipeline profile, the potential for
ignition, proximity to power sources,
location of nearest response personnel,
specific terrain between the pipeline
segment and the high consequence area,
and benefits expected by reducing the
spill size.
RSPA adopted the EFRD requirements
in §§ 195.450 and 195.452 in a
December 2000 final rule December 1,
2000, (65 FR 75378). Part 195 does not
require that EFRDs be used on pipelines
outside of HCAs, but § 195.260 does
require that valves be installed at certain
locations.
Congress included additional
requirements for the use of automatic
and remote-controlled shut-off valves in
section 4 of the Pipeline Safety Act of
2011. That provision requires the
Secretary, if appropriate and where
economically, technically, and
operationally feasible, to issue
regulations for the use of automatic and
remote-controlled shut-off valves on
transmission lines that are newly
constructed or entirely replaced. The
Comptroller General is also required to
perform a study on the effectiveness of
these valves and to provide a report to
Congress within one year of the date of
the enactment of that legislation.
PHMSA commissioned a study titled
‘‘Studies for the Requirements of
E:\FR\FM\13OCP3.SGM
13OCP3
61628
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
Automatic and Remotely Controlled
Shutoff Valves on Hazardous Liquids
and Natural Gas Pipelines With Respect
to Public and Environmental Safety,’’ 5
to help provide input on regulatory
considerations regarding the feasibility
and effectiveness of automatic and
remote-control shutoff valves on
hazardous liquid and natural gas
transmission lines. The study was
completed by the Oak Ridge National
Laboratory on October 31, 2012, and it
was submitted to Congress on December
27, 2012. PHMSA is using
considerations from this study as it
drafts a rulemaking titled ‘‘Amendments
to Parts 192 and 195 to require Valve
installation and Minimum Rupture
Detection Standards.’’
Comments
PHMSA received comment on this
issue from industry and trade
associations. API–AOPL, TxOGA,
LMOGA, and TransCanada Keystone
reported that no industry standards
currently address EFRD use, although
ASME B31.4, ‘‘Pipeline Transportation
Systems for Liquid Hydrocarbons and
Other Liquids’’ (2009), addresses
mainline valves and requires remote
operation and/or check valves in some
instances. ASME B31.4 (2009) also has
guidelines for mainline valves and
requires remote and check valves, but is
not currently incorporated by reference
into part 195. Section 195.452 does
require that operators identify the need
for additional preventive and mitigation
measures.
Response
PHMSA is studying issues concerning
the development of additional safety
standards for the use of EFRDs. PHMSA
will consider the industry standards
mentioned by the commenters, as well
as the results of the September 1996
Volpe Report, the December 2007 Leak
Detection Study, and the 2012 Oak
Ridge National Laboratory study, for the
purposes of any future rulemaking on
the topic.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Adequacy of Existing Industry Practices
or Standards for EFRDs
PHMSA asked for comment on the
adequacy of existing industry practices
or standards for EFRDs.
Comments
API–AOPL, TxOGA, LMOGA, and
TransCanada Keystone stated that there
is no current industry standard that sets
a maximum spill volume or activation
5 https://www.phmsa.dot.gov/pv_obj_cache/pv_
obj_id_
2C1A725B08C5F72F305689E943053A96232AB200/
filename/Final%20Valve_Study.pdf
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
timing due to the widespread variation
in pipeline dynamics; therefore, it
would be difficult to establish a onesize-fits-all maximum spill volume
requirement. API–AOPL suggests
PHMSA should focus on prevention and
response rather than spill size reduction
through EFRDs.
Response
Section 195.452(i)(4) contains a
requirement for the use of EFRDs on
hazardous liquid pipelines that could
affect an HCA. PHMSA agrees with the
commenters that oil spill prevention
and response are important to ensuring
the safety of hazardous liquid pipelines,
and believes that the appropriate use of
EFRDs could be complementary to these
efforts.
Consideration of Additional Standards
Specifying the Location of EFRDs
Part 195 requires that EFRDs be
considered as potential mitigation
measure on pipeline segments that
could affect HCAs, but it does not
specify any particular location for the
use of those devices. Operators must
perform a risk analysis in determining
whether and where to install EFRDs for
such lines. Part 195 does not require
that EFRDs be used on pipelines outside
of HCAs. In the ANPRM, PHMSA asked
for comment on whether additional
standards should be developed to
specify the location for EFRDs.
Comments
PHMSA received comments from four
trade associations, one industry
operator, and one regulatory association
regarding prescriptive location of
EFRDs. API–AOPL, TransCanada
Keystone, LMOGA, and TxOGA
indicated PHMSA should not specify
location of EFRD placement for the
reasons provided in response to
previous questions. TPA agreed that no
general criteria beyond those in existing
regulations are appropriate because
decisions on EFRD placement are driven
by local factors. NAPSR supported the
comments of the trade associations.
Response
PHMSA recognizes the commenters’
concerns about mandating the
installation of EFRDs in particular
locations, but notes that other
provisions in part 195 require that
valves and other safety devices be
installed in certain areas.
Mandated Use of EFRDs in All
Locations
PHMSA requested comment on
mandated use of EFRDs in all locations
under PHMSA jurisdiction.
PO 00000
Frm 00020
Fmt 4701
Sfmt 4702
Comments
API–AOPL, TransCanada Keystone,
LMOGA, and TxOGA indicated that a
requirement to place EFRDs at
predetermined locations or fixed
intervals would be arbitrary, costly, and
potentially counterproductive to
pipeline safety. They noted that not all
valves are mainline valves, and that a
requirement for all valves to be remote
would cause confusion. Many valves are
at manned facilities. Some EFRDs are
check valves, which are not amenable to
remote control. API–AOPL noted that
costs related to providing remote
operation would vary based on
proximity to power and
communications, but that a December
2010 study by the Congressional
Research Service estimated retrofit costs
of $40K to $1.5M per valve. NAPSR
agreed with the comments supplied by
the trade associations and TransCanada
Keystone. Finally, NSB stated EFRDs
should be required on all pipelines
PHMSA regulates with specific
instruction on when and where EFRDs
need to be utilized.
Response
PHMSA recognizes the commenters’
concerns about mandating the
installation of EFRDs in all locations
and plans on continuing to study this
issue.
Additional Research for Leak Detection
PHMSA requested comment regarding
what leak detection technologies or
methods require further research and
development to demonstrate their
efficacy.
Comments
PHMSA received no comments in
response to this question.
D. Valve Spacing
Valve Spacing
The ANPRM asked whether PHMSA
should repeal or modify the valve
spacing requirements in part 195.
Specifically, the ANPRM asked:
• For information on the average
distance between valves;
• Whether valves are manually
operated or remotely controlled;
• Whether additional standards
should be adopted for evaluating valve
spacing and location;
• Whether the maximum permissible
distance between valves should be
specified by regulation;
• Whether to adopt additional valve
spacing requirements for hazardous
liquid pipelines near HCAs;
• Whether additional valve spacing
requirements should be adopted to
protect narrower bodies of water;
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
• Whether all valves should be
remotely controlled; and
• What the cost impact would be
from requiring the installation of certain
types of valves.
As discussed below, PHMSA is not
proposing to adopt any additional
standards for valve spacing, but will be
considering that issue in complying
with the various mandates in the
Pipeline Safety Act of 2011.
Part 195 contains general construction
requirements for valves. Specifically,
§ 195.258 provides that each valve must
be installed in a location that is
accessible to authorized employees and
protected from damage or tampering.
This section further states that
submerged valves located offshore or in
inland navigable waters must be
marked, or located by conventional
survey techniques, to facilitate quick
location when operation of the valve is
required.
PHMSA pipeline safety regulations
found in section 195.260 indicate that a
valve must be installed at certain
locations. The locations named include
on the suction end and the discharge
end of a pump station or a breakout
storage tank area in a manner that
permits isolation of the tank area from
other facilities and on each mainline at
locations along the pipeline system that
will minimize damage or pollution from
accidental hazardous liquid discharge,
as appropriate for the terrain in open
country, for offshore areas, or for
populated areas. Three additional
requirements for valve location in
section 195.260 include each lateral
takeoff from a trunk line, on each side
of a water crossing that is more than 100
feet (30 meters) wide from high-water
mark to high-water mark and on each
side of a reservoir holding water for
human consumption. The Department
adopted these regulations in an October
1969 final rule October 4, 1969, (34 FR
15475).
As discussed in section 3, part 195
requires the use of EFRDs as a potential
mitigation measure on pipeline
segments that could affect HCAs. As
also discussed in section 3, Congress
included new provisions for the use of
automatic and remote-controlled shutoff valves and leak detection systems in
the Pipeline Safety Act of 2011.
Comments
The commenters did not provide any
data on the average distance between
valves, but did provide general
information on valve spacing, location,
and type. The commenters further noted
that ASME B31.4, a consensus industry
standard, includes a minimum valve
spacing requirement of 7.5 miles for
liquefied petroleum gas (LPG) and
anhydrous ammonia pipelines in
populated areas.
Specifically, API–AOPL, LMOGA,
TxOGA, and TransCanada Keystone
stated that valve spacing varies, that
most mainline valves are manually
operated, that check valves are used in
certain cases, and that some remotely
controlled valves had been added as a
result of the IM requirements. API–
AOPL also commented that ASME
B31.4 provides additional requirements
for LPG and anhydrous ammonia in
populated areas, including a 7.5-mile
spacing requirement for valves, but
noted that PHMSA had not incorporated
this version of B31.4 into part 195.
NAPSR stated that proper valve location
is more important than distance
placement.
Information on Average Distance
Between Valves and Manual or Remote
Operation
Response
Part 195 requires the installation of
valves at certain locations, including
pump stations, breakout tanks,
mainlines, lateral lines, water crossings,
and reservoirs. These requirements are
generally directed toward achieving a
particular result (e.g., isolation of a
facility, minimization of damage or
pollution, etc.) and do not mandate that
valves be installed at specific distances.
Part 195 does not prescribe whether
manual or remotely controlled valves
must be installed at particular locations,
but does require consideration of check
valves and remotely controlled valves
under the EFRD requirements for
pipelines that could affect an HCA.
Section 4 of the Pipeline Safety Act of
2011 includes new requirements for
evaluating and issuing additional
regulations for the use of the automatic
and remote-controlled shut-off valves.
PHMSA is not proposing to make any
changes to the current valve spacing
requirements at this time. A coordinated
analysis will ensure that these issues are
addressed in a way that maximizes the
potential benefits and minimizes the
potential burdens imposed by any new
leak detection and valve spacing
standards.
PHMSA asked the public to provide
information on the average distance
between valves and whether such valves
are manually operated or remotely
controlled.
Adoption of Additional Standards for
Valve Spacing and Location
PHMSA asked for comment on the
adoption of additional standards for
valve spacing and location.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
PO 00000
Frm 00021
Fmt 4701
Sfmt 4702
61629
Comments
TransCanada Keystone, API–AOPL,
TxOGA, and LMOGA stated that the
standards in §§ 195.260 and 195.452 are
satisfactory. NAPSR supported the
comments of API–AOPL. NSB
recommended that DOT adopt standards
for pipeline operators to use in
evaluating valve spacing and location
and identifying the maximum distance
between valves.
Response
PHMSA is not proposing to adopt any
additional standards for valve spacing
and locations, but will be considering
that issue in complying with the various
mandates in the Pipeline Safety Act of
2011. PHMSA held a public meeting/
workshop on valve spacing and
locations on March 28, 2012.
Information from this workshop was
used in Oak Ridge National Laboratory’s
study, completed October 31, 2012,
titled: ‘‘Studies for the Requirements of
Automatic and Remotely Controlled
Shutoff Valves on Hazardous Liquids
and Natural Gas Pipelines with Respect
to Public and Environmental Safety’’ 6 to
help determine the need for additional
valve and location standards.
Additional Standards for Specifying the
Maximum Distance Between Valves
PHMSA asked for public comment on
whether part 195 should specify the
maximum permissible distance between
valves.
Comment
API–AOPL, TxOGA, LMOGA,
TransCanada Keystone, and TPA
opposed such a requirement and stated
that valve spacing should be based on
conditions and terrain. NAPSR also
supported this position. NSB and
MAWUC recommended the DOT adopt
specific valve spacing standards.
MAWUC stated that the criteria for
valve spacing should be developed, but
that the precise location of valves
should not be made publicly available.
Response
Similarly, PHMSA is not proposing to
adopt any additional standards for valve
spacing at this time. PHMSA will be
studying this issue and may make
proposals concerning this topic in a
later rulemaking.
6 https://www.phmsa.dot.gov/pv_obj_cache/pv_
obj_id_
2C1A725B08C5F72F305689E943053A96232AB200/
filename/Final%20Valve_Study.pdf
E:\FR\FM\13OCP3.SGM
13OCP3
61630
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
Response
Additional Requirements for Valve
Spacing Near HCAs Beyond Those
Required for EFRDs
PHMSA asked for public comment on
whether part 195 should contain
additional requirements for valve
spacing in areas near HCAs beyond
what is already required in
§ 195.452(i)(4) for EFRDs.
Comments
NSB encouraged PHMSA to adopt
additional requirements for these areas.
Taking a contrary position, API–AOPL,
LMOGA, TxOGA, NAPSR, and
TransCanada Keystone indicated that
the current requirements adequately
address the need for EFRDs and allow
operators to assess the specific risks on
each individual pipeline that could
affect an HCA.
Response
PHMSA does not propose to make any
changes to the regulations concerning
the valve spacing at this time. PHMSA
will be studying this issue and may
make proposals concerning this topic in
a later rulemaking.
Modifying the Scope of 49 CFR
195.260(e) To Include Narrower Bodies
of Water
Section 195.260(e) requires the
installation of a valve ‘‘[o]n each side of
a water crossing that is more than 100
feet (30 meters) wide from high-water
mark to high-water mark unless the
Administrator finds in a particular case
that valves are not justified.’’ The
Department adopted that requirement in
an October 1969 final rule October 4,
1969, (34 FR 15475) after adding the
provision that allows the Administrator
to find that the installation of a valve is
not justified in specific cases. Such a
finding requires the filing of a petition
with the Administrator under 49 CFR
190.9.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Comments
API–AOPL, TxOGA, LMOGA, and
TransCanada Keystone indicated that
the current water crossing requirements
are adequate, but that PHMSA could
improve the regulation by allowing a
risk-based approach for valve placement
at water crossings and adding an
exclusion for carbon dioxide pipelines.
TWS stated that PHMSA should
require valves for waterways that are at
least 25-feet in width and all feeder
streams and creeks leading to such
waterways. NSB supported the view of
TWS and indicated the current 100-foot
threshold for waterways should be
reduced to 25 feet.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
As mentioned previously, PHMSA is
proposing that all pipelines be
inspected after extreme weather events
or natural disasters. This is a natural
extension of IM and ensures continued
safe operations of the pipeline after
abnormal operating conditions. Past
events have strongly demonstrated that
inspections after these events do
prevent pipeline incidents from
occurring. PHMSA is also proposing to
require that all hazardous liquid
pipelines have leak detection systems;
that pipelines in areas that could affect
HCAs be capable of accommodating ILIs
within 20 years, unless the basic
construction of the pipeline will not
permit such an accommodation; that
periodic assessments be performed of
pipelines that are not already receiving
such assessments under the IM program
requirements; and that modified repair
criteria be applied to pipelines in all
locations. PHMSA will comply with the
applicable provisions in the Pipeline
Safety Act of 2011 before adopting any
of these proposals in a final rule.
Adopting Safety Standards That Require
All Valves To Be Remotely Controlled
PHMSA asked the public to comment
on whether part 195 should include a
requirement mandating the use of
remotely-controlled valves in all cases.
Comments
API–AOPL, LMOGA, and TxOGA
stated that PHMSA should not require
remotely controlled valves in all cases.
API–AOPL indicated that such a
requirement would cause confusion as
to which valves need to be operated
manually, burden the industry with
additional costs, and provide minimal
safety benefits. API–AOPL submitted
that the costs of retrofitting a valve to be
remotely controlled varies widely from
$40,000 to $1.5 million per valve as
indicated in a recent report issued by
the Congressional Research Service on
pipeline safety and security. TPA
further stated that the benefits of such
requirements are dependent on local
factors, and that additional
requirements would add to pipeline
system complexity and increase the
probability of failure. Similarly, NAPSR
stated that remote control valves should
not be required, but that PHMSA should
consider performance language for
maximum response time to operate
manual valves.
MAWUC indicated that PHMSA
should consider requiring all valves to
be remotely controlled, but that its
decision should be based on an analysis
of benefits and risks. NSB supported the
PO 00000
Frm 00022
Fmt 4701
Sfmt 4702
use of remotely controlled valves in all
instances. Coyle, a citizen, commented
that PHMSA should promulgate
regulatory language requiring remotely
controlled valves for poison inhalation
hazard pipelines.
Response
PHMSA notes that a risk-assessment
must be performed in developing any
new safety standards for the use of
remotely controlled valves, and that any
such standards will only be proposed
upon a reasoned determination that the
benefits justify the costs.
Requiring Installation of EFRDs To
Protect HCAs
Section 195.452(i)(4) does not require
the installation of an EFRD on all
pipeline segments that could affect
HCAs. Rather, it states that ‘‘[i]f an
operator determines that an EFRD is
needed on a pipeline segment to protect
a high consequence area in the event of
a hazardous liquid pipeline release, an
operator must install the EFRD.’’ It also
states that an operator must at least
consider a list of factors in making that
determination.
Comments
API–AOPL, LMOGA, TxOGA and
TransCanada Keystone stated that
§ 192.452 already requires EFRDs to be
installed to protect a HCA if the
operator finds, through a risk
assessment, that an HCA is threatened.
MAWUC commented that EFRDs should
be required if they can limit a spill.
Likewise, NSB supported the use of
EFRDs for HCAs.
Response
PHMSA does not propose to make any
changes to the regulations concerning
the use of EFRDs at this time. PHMSA
will be studying this issue and may
make proposals concerning this topic in
a later rulemaking.
Determining the Applicability of New
Valve Location Requirements
In the ANPRM, PHMSA asked for
public comment on how the agency
should apply any new valve location
requirements that are developed for
hazardous liquid pipelines.
Comments
The trade association, API–AOPL,
supported by TransCanada Keystone,
LMOGA, and TxOGA, indicated that
valve spacing requirements should not
be changed, and that delineating new
construction for any type of
grandfathering purpose would be
difficult and confusing. Requiring
retrofitting of existing lines to meet any
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
type of new requirement would be
expensive for industry, create
environmental impacts, potential
construction accidents, and may cause
interruption of service.
The regulatory association, NAPSR,
suggested that exemptions to new valve
location requirements should be based
on the consequence of failure. Particular
attention should be paid to spills into
water as even a small spill can create a
large problem.
Two government/municipalities
commented. MAWUC indicated that
there should be no waivers for valve
spacing in HCAs due to the importance
and interconnectivity of water supplies.
NSB recommended that any new valve
locations or remote actuation regulation
be applied to new pipelines or existing
pipelines that are repaired.
Response
PHMSA will continue to study valve
spacing and automatic valve placement
and may address these issues in a future
rulemaking.
E. Repair Criteria Outside of HCAs
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Repair Criteria
The ANPRM asked for public
comment on whether to extend the IM
repair criteria in § 195.452(h) to pipeline
segments that are not located in HCAs.
Specifically, the ANPRM asked
‘‘Whether the IM repair criteria should
apply to anomalous conditions
discovered in areas outside of HCAs;
whether the application of the IM repair
criteria to non-HCA areas should be
tiered on the basis of risk; what
schedule should be applied to the repair
of anomalous conditions discovered in
non-HCA areas; whether standards
should be specified for the accuracy and
tolerance of inline inspection (ILI) tools;
and whether additional standards
should be established for performing ILI
inspections with ‘‘smart pigs’’.
As discussed below, PHMSA is
proposing to modify the provisions for
making pipeline repairs. Additional
conservatism will be incorporated into
the existing IM repair criteria and an
adjusted schedule for making immediate
and non-immediate repairs will be
established to provide greater
uniformity. These criteria will also be
made applicable to all pipelines, with
an extended timeframe for making
repairs outside of HCAs.
Application of IM Repair Criteria to
Anomalous Conditions Discovered
Outside of HCAs
In the ANPRM, PHMSA asked for
comment on whether the IM repair
criteria should apply to anomalous
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
conditions discovered in areas outside
of HCAs.
Comments
API–AOPL, supported by
TransCanada Keystone, LMOGA, and
TxOGA, stated that the repair criteria in
or outside of HCAs should be the same.
Likewise, the citizens’ groups TWS and
AKW echoed the comments of API–
AOPL and further recommended that a
phased-in time period should be
utilized. NSB commented that
anomalous conditions found during
inspection in non-HCA areas should
trigger expedited repair times.
Response
Section 195.452(h) specifies the
actions that an operator must take to
address integrity issues on hazardous
liquid pipelines that could affect an
HCA in the event of a leak or failure.
Those actions include initiating
temporary and long-term pressure
reductions and evaluating and
remediating certain anomalous
conditions (e.g., metal loss, dents,
corrosion, cracks, gouges, grooves, and
other any condition that could impair
the integrity of the pipelines).
Depending on the severity of the
condition, such actions must be taken
immediately, within 60 days, or within
180 days of the date of discovery.
Section 5 of the Pipeline Safety Act of
2011 requires the Secretary to perform
an evaluation to determine if the IM
requirements should be extended
outside of and to submit a report to
Congress with the result of that review.
The Secretary is authorized to collect
data for purposes of completing the
evaluation and report to Congress.
Section 5 also prohibits the issuance of
any final regulations that would expand
the IM requirements during a
subsequent Congressional review
period, subject to a savings clause that
permits such action if a condition poses
a risk to public safety, property, or the
environment or is an imminent hazard
and the regulations in question will
address that risk or imminent hazard.
PHMSA is proposing to make certain
modifications to the IM repair criteria
and to establish similar repair criteria
for pipeline segments that are not
located in HCAs. Specifically, the repair
criteria in § 195.452(h) would be
amended to:
• Categorize bottom-side dents with
stress risers as immediate repair
conditions;
• Require immediate repairs
whenever the calculated burst pressure
is less than 1.1 times MOP;
• Eliminate the 60-day and 180-day
repair categories; and
PO 00000
Frm 00023
Fmt 4701
Sfmt 4702
61631
• Establish a new, consolidated 270day repair category.
PHMSA is also proposing to adopt new
requirements in § 195.422 that would:
Apply the criteria in the immediate
repair category in § 195.452(h) and
Establish an 18-month repair category
for hazardous liquid pipelines that are
not subject to the IM requirements.
These changes will ensure that
immediate action is taken to remediate
anomalies that present an imminent
threat to the integrity of hazardous
liquid pipelines in all locations. Many
anomalies that would not qualify as
immediate repairs under the current
criteria will meet that requirement as a
result of the additional conservatism
that will be incorporated into the burst
pressure calculations. The new
timeframes for performing other repairs
will allow operators to remediate those
conditions in a timely manner while
allocating resources to those areas that
present a higher risk of harm to the
public, property, and the environment.
Use of a Tiered, Risk-Based Approach
for Repairing Anomalous Conditions
Discovered Outside of HCAs
In the ANPRM, PHMSA asked for
comment on whether the application of
the IM repair criteria to non-HCA areas
should be tiered on the basis of risk.
Comments
API–AOPL, LMOGA, TPA, TxOGA,
and TransCanada Keystone commented
that PHMSA should not impose any sort
of tiering to repair criteria because that
is already inherent to the IM program.
Scheduling flexibility would minimize
disruption to the affected public, as well
as the overall environmental impact, by
preventing multiple excavation work on
a given property. Requiring additional
risk tiering of anomalies would not
reduce safety risks to the public.
NAPSR, in contrast, commented that
tiering should be utilized for repair
criteria inside or outside of HCAs. NSB
also indicated that risk tiering should be
used. MAWUC supported risk tiering
based on preselected criteria for HCAs.
Response
As previously discussed, PHMSA is
proposing to apply new repair criteria
for anomalous conditions discovered on
hazardous liquid pipelines that are not
located in HCAs. PHMSA is also
proposing to establish two timeframes
for performing those repairs: immediate
repair conditions and 18-month repair
conditions. If adopted as proposed,
these changes will ensure the prompt
remediation of anomalous conditions on
all hazardous liquid pipeline segments,
while allowing operators to allocate
E:\FR\FM\13OCP3.SGM
13OCP3
61632
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
their resources to those areas that
present a higher risk of harm to the
public, property, and the environment.
Updating of Dent With Metal Loss
Repair Criteria
Section 195.452(h) contains the
criteria for repairing dents with metal
loss on hazardous liquid pipeline
segments that could affect an HCA in
the event of a leak or failure. PHMSA
asked for comment on whether
advances in ILI tool capability justified
an update in the dent-with-metal-loss
repair criteria.
Comments
API–AOPL, LMOGA, TxOGA, and
TransCanada Keystone indicated that
the anticipated update to API 1160 will
contain proposals to update the dentwith-metal-loss repair criterion. API–
AOPL intends to support these
proposals with data resulting from
analyses of member company’s
experience measuring and
characterizing metal loss in dents.
NAPSR encouraged PHMSA not to
make the current standards less
stringent even for dents without metal
loss, citing a recent bottom side dent
less than 6 inches that failed. NAPSR
recommended strengthening the repair
criteria for bottom-side dents in areas of
heavy traffic or near swamps/bogs or in
clay soils.
Response
As previously discussed, PHMSA is
proposing to categorize bottom-side
dents with stress risers as an immediate
repair condition and to require
immediate repairs when calculated
burst pressure is less than 1.1 times
MOP. These changes should ensure the
prompt and effective remediation of
anomalous conditions on all pipeline
segments. With respect to API 1160,
PHMSA will consider incorporating the
2013 edition in a future rulemaking.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Adoption of Explicit Standards To
Account for Accuracy of ILI Tools
PHMSA requested comment on
whether to adopt an explicit standard to
account for the accuracy of ILI tools
when comparing ILI data with repair
criteria.
Comments
API–AOPL supports PHMSA’s
adoption of API 1163, the ‘‘In-Line
Inspection Systems Qualification
Standard’’. That standard includes a
System Results Verification section,
which describes methods to verify that
the reported inspection results meet, or
are within, the performance
specification for the pipeline being
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
inspected. That standard also requires
that inconsistencies uncovered during
the process validation be evaluated and
resolved.
NAPSR supports the adoption of a
standard because the IM process already
is considering tool accuracy during the
selection process and suggests revising
the regulations to provide minimum
standards of expected accuracy.
Response
In reviewing IM inspection data,
PHMSA discovered that some operators
were not considering the accuracy (i.e.,
tolerance) of ILI tools when evaluating
the results of the tool assessments. As a
result, random variation within the
recorded data led to both overcalls (i.e.,
an anomaly was identified to be more
extreme than it actually was) and under
calls. Over calls are conservative,
resulting in repair of some anomalies
that might not actually meet repair
criteria. Under calls are not and can
result in anomalies that exceed
specified repair criteria going unremediated. Based on our review of
inspection data, PHMSA has concluded
that operators should be explicitly
required to consider the accuracy of
their ILI tools.
Specifically, under the proposed
amendment to § 195.452(c)(1)(i) and the
new provisions in § 195.416, operators
will be required to consider tool
tolerance and other uncertainties in
evaluating ILI results for all hazardous
liquid pipeline segments. Tool accuracy
should include excavation findings and
usage of unity plots of inline tool and
excavation findings. When combined
with the proposed changes to the repair
criteria, the proposed tool tolerance
requirement will ensure the prompt
detection and remediation of anomalous
conditions on all hazardous liquid
pipelines. With respect to API 1163, as
of January 2013, PHMSA is required by
section 24 of the Pipeline Safety,
Regulatory Certainty, and Job Creation
Act of 2011 not to incorporate any
consensus standards that are not
available to the public, for free, on an
internet Web site. PHMSA has sought a
solution to this issue and as a result, all
incorporated by reference standards in
the pipeline safety regulations would be
available for viewing to the public for
free.
Additional Quality Control Standards
for ILI Tools, Assessments, and Data
Review
In the ANPRM, PHMSA asked if
additional quality control standards are
needed for conducting ILIs using smart
pigs, the qualification of persons
interpreting ILI data, the review of ILI
PO 00000
Frm 00024
Fmt 4701
Sfmt 4702
results, and the quality and accuracy of
ILI tool performance.
Comments
API–AOPL, LMOGA, TxOGA, and
TransCanada Keystone commented that
PHMSA should adopt API 1163 and
American Society of Nondestructive
Testing ILI PQ. These commenters
stated that a certification program for
analyzing ILI data would not add value
to pipeline operators’ IM programs, as
operator experience has shown that
these types of programs do not
adequately reflect the highly technical
nature of, and the intimate knowledge
and experience of personnel practicing,
IM programs. According to the
commenters, there is no evidence that
the current requirements and industry
standards are leaving the public or
environment at risk.
NAPSR indicated that if there is data
to show this is an issue, PHMSA should
adopt a standard. Additionally, a state
could impose a more stringent standard
based on prior experience. Both the NSB
and MAWUC supported adoption of
standards for ILI use.
Response
As noted in the response to the
previous question, PHMSA is proposing
to require operators to consider tool
tolerance and other uncertainties in
evaluating ILI results in complying with
the IM requirements of § 195.452 and
the proposed assessment requirement in
§ 195.416. PHMSA believes that this
requirement and the proposed changes
to the repair criteria will ensure the
prompt detection and remediation of
anomalous conditions (e.g., metal loss,
dents, corrosion, cracks, gouges,
grooves) that could adversely affect the
safe operation of a pipeline. PHMSA is
proposing by a separate rulemaking via
incorporation by reference available
industry consensus standards for
performing assessments of pipelines
using ILI tools, internal corrosion direct
assessment, and stress corrosion
cracking direct assessment.
F. Stress Corrosion Cracking
In the October 2010 ANPRM, PHMSA
asked for public comment on whether to
adopt additional safety standards for
stress corrosion cracking (SCC). SCC is
cracking induced from the combined
influence of tensile stress and a
corrosive medium. Sections 195.553 and
195.588 and Appendix C of the
Hazardous Liquid Pipeline Safety
Standards contain provisions for the
direct assessment of SCC, but do not
include comprehensive requirements for
preventing, detecting, and remediating
that condition.
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
Specifically, PHMSA asked in the
ANPRM whether:
• Any existing industry standards for
preventing, detecting, and remediating
SCC should be incorporated by
reference;
• Any data or statistics are available
on the effectiveness of these industry
standards;
• Any data or statistics are available
on the effectiveness of SCC detection
tools and methodologies;
• Any tools or methods are available
for detecting SCC associated with
longitudinal pipe seams;
• An SCC threat analysis should be
conducted for all pipeline segments;
• Any particular integrity assessment
methods should be used when SCC is a
credible threat; and
• Operators should be required to
perform a periodic analysis of the
effectiveness of their corrosion
management programs.
Adoption of NACE Standard for Stress
Corrosion Cracking Direct Assessment
Methodology or Other Industry
Standards
In the ANPRM, PHMSA asked for
comment on whether the agency should
incorporate any consensus industry
standards for assessing SCC, including
the NACE International (NACE)
SP0204–2008 (formerly RP0204), Stress
Corrosion Cracking (SCC) Direct
Assessment Methodology. https://
www.nace.org/uploadedFiles/
Committees/SP020408.pdf (last
accessed December 12, 2013) (stating
that SP0204–2008 ‘‘provides guidance
for managing SCC by selecting potential
pipeline segments, selecting dig sites
within those segments, inspecting the
pipe and collecting and analyzing data
during the dig, establishing a mitigation
program, defining the reevaluation
interval, and evaluating the
effectiveness of the SCC [direct
assessment] process.’’).
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Comments
API–AOPL, TransCanada Keystone,
TxOGA, and LMOGA stated that NACE
SP0204–2008 provides an effective
framework for the application of direct
assessment, but does not sufficiently
address other assessment methods,
including ILI and hydrostatic testing.
These commenters were also not aware
of any industry statistics that directly
correlate the application of that
standard to the SCC detection or failure
rate. These commenters stated the most
appropriate standard for SCC
assessment of hazardous liquid
pipelines is the soon-to-be-released
version of API Standard 1160, Managing
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
System Integrity for Hazardous Liquid
Pipelines.
Another trade association, TPA, stated
that ‘‘because [the NACE Standard] was
just finished in 2008, PHMSA should
wait at least 2–3 years more before
attempting to assess the desirability of
incorporating that standard into the
regulations.’’
One regulatory association, MAWUC,
commented that PHMSA should adopt
standards that address direct
assessment, prevention, and
remediation of SCC. The municipality/
government entity, NSB, offered a
similar comment.
Response
The commenters did not indicate that
NACE SP0204–2008 would address the
full lifecycle of SCC safety issues.
Moreover, none of the commenters
identified any other industry standards
that would be appropriate for adoption
at this time.
PHMSA recognizes that SCC is an
important safety concern, but does not
believe that further action can be taken
based on the information available in
this proceeding. PHMSA is establishing
a team of experts to study this issue and
will be holding a public forum on the
development of SCC standards. Once
that process is complete, PHMSA will
consider whether to establish new safety
standards for SCC. With respect to
NACE SP0204–2008 PHMSA is
proposing this standard by a separate
rulemaking via incorporation by
reference.
Identification of Standards and Practices
for Prevention, Detection, Assessment
and Remediation of SCC
PHMSA asked the public to identify
any other standards and practices for
the prevention, detection, assessment,
and remediation of SCC.
Comments
API–AOPL, LMOGA, and TxOGA
indicated that there are several good
standards that address SCC, including
API 1160, ASME STP–PT–011, Integrity
Management of Stress Corrosion
Cracking in Gas Pipeline High
Consequence Areas, and the Canadian
Energy Pipeline Association (CEPA)
Stress Corrosion Cracking
Recommended Practices (CEPA SCC
RP), but acknowledged that all of these
standards have weaknesses.
The trade association, CEPA, also
stated that the 2008 ASME STP–PT–011
should be considered. While written for
gas pipelines, CEPA stated that this
standard could be adapted to hazardous
liquids.
PO 00000
Frm 00025
Fmt 4701
Sfmt 4702
61633
Response
PHMSA appreciates the information
provided by the commenters. PHMSA
will be studying the SCC issue and will
consider incorporating by reference
suggested standards in future
rulemakings.
Implementation of Canadian Energy
Pipeline Association RP on SCC
CEPA is an organization that
represents Canada’s transmission
pipeline companies. In 1997, CEPA
developed its SCC Recommended
Practice (RP) in response to a public
inquiry by National Energy Board of
Canada. In 2007, CEPA released an
updated version of its SCC RP, https://
www.cepa.com/wp-content/uploads/
2011/06/Stress-Corrosion-CrackingRecommended-Practices-2007.pdf. In
the ANPRM, PHSMA asked for
comment on the experience of operators
in implementing CEPA’s SCC RP.
Comments
API–AOPL, LMOGA, TxOGA, and
TransCanada Keystone commented that
the CEPA SCC RP provides the most
thorough overview of the various
assessment techniques, but is limited to
near neutral SCC in terms of causal
considerations. These commenters also
stated that there are no industry
statistics on the application of the CEPA
RP SCC. CEPA and API–AOPL both
indicated that companies continue to
use the CEPA SCC RP as a guideline, but
that there are no statistics on its use.
Response
PHMSA appreciates the comments
provided on the use of the CEPA SCC
RP and will consider that standard in its
study of comprehensive safety
requirements for SCC and in future
rulemakings.
Effectiveness of SCC Detection Tools
and Methods
PHMSA requested comment as to the
effectiveness of current SCC detection
tools and methods.
Comments
API–AOPL, supported by LMOGA,
TxOGA, and TransCanada Keystone,
stated that there are no industry
statistics that directly correlate the
application of the CEPA RP to the SCC
detection or failure rate, but that the
National Energy Board of Canada has
noted the effectiveness of the CEPA RP
for managing SCC. API–AOPL also
stated the planned revisions of API 1160
and 1163 will address the current gaps
regarding SCC in the standards and
recommended practices relevant to
liquid pipelines. One citizens’ group,
E:\FR\FM\13OCP3.SGM
13OCP3
61634
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
TWS, mentioned that gathering lines do
not require corrosion prevention and
that this should be required.
Response
PHMSA appreciates the comments
provided on the effectiveness of SCC
detection tools and methods and will be
considering that information in
evaluating comprehensive safety
requirements for SCC and consider
incorporating in future rulemakings.
IV. Section-by-Section Analysis
§ 195.1 Which pipelines are covered by
this part?
Section 195.1(a) lists the pipelines
that are subject to the requirements in
part 195, including gathering lines that
cross waterways used for commercial
navigation as well as certain onshore
gathering lines (i.e., those that are
located in a non-rural area, that meet the
definition of a regulated onshore
gathering line, or that are located in an
inlet of the Gulf of Mexico). PHMSA has
determined that additional information
about unregulated gathering lines is
needed to fulfill its statutory
obligations. Accordingly, the NPRM
extend the reporting requirements in
subpart B of part 195 to all gathering
lines (whether regulated, unregulated,
onshore, or offshore) by adding a new
paragraph (a)(5) to § 195.1.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
§ 195.2
Definitions
Section 195.2 provides definitions for
various terms used throughout part 195.
On August 10, 2007, (72 FR 45002;
Docket number PHMSA–2007–28136)
PHMSA published a policy statement
and request for comment on the
transportation of ethanol, ethanol
blends, and other biofuels by pipeline.
PHMSA noted in the policy statement
that the demand for biofuels was
projected to increase in the future as a
result of several federal energy policy
initiatives, and that the predominant
modes for transporting such
commodities (i.e., truck, rail, or barge)
would expand over time to include
greater use of pipelines. PHMSA also
stated that ethanol and other biofuels
are substances that ‘‘may pose an
unreasonable risk to life or property’’
within the meaning of 49 U.S.C.
60101(a)(4)(B) and accordingly these
materials constitute ‘‘hazardous liquids’’
for purposes of the pipeline safety laws
and regulations.
PHMSA is now proposing to modify
its definition of hazardous liquid in
§ 195.2. Such a change would make
clear that the transportation of biofuel
by pipeline is subject to the
requirements of 49 CFR part 195.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
PHMSA is also proposing to add a
new definition of ‘‘Significant Stress
Corrosion Cracking.’’ This new
definition will provide criteria for
determining when a probable crack
defect in a pipeline segment must be
excavated and repaired.
pipelines are designed to include leak
detection systems based upon standards
in section 4.2 of API 1130 or other
applicable design criteria in the
standard.
§ 195.11 What is a regulated rural
gathering line and what requirements
apply?
Section 195.11 defines and establishes
the requirements that are applicable to
regulated rural gathering lines. PHMSA
has determined that these lines should
be subject to the new requirements in
the NPRM for the performance of
periodic pipeline assessments and
pipeline remediation and for
establishing leak detection systems.
Consequently, the NPRM would amend
§ 195.11 by adding paragraphs (b)(12)
and (13) to ensure that these
requirements are applicable to regulated
rural gathering lines.
Section 195.401 prescribes general
requirements for the operation and
maintenance of hazardous liquid
pipelines. PHMSA is proposing to
modify the pipeline repair requirements
in § 195.401(b). Paragraph (b)(1) will be
modified to reference the new
timeframes in § 195.422 for performing
non-IM repairs. The requirements in
paragraph (b)(2) for IM repairs will be
retained without change. A new
paragraph (b)(3) will be added, however,
to clearly require operators to consider
the risk to people, property, and the
environment in prioritizing the
remediation of any condition that could
adversely affect the safe operation of a
pipeline system, including those
covered by the timeframes specified in
§§ 195.422(d) and (e) and 195.452(h).
§ 195.13 What requirements apply to
pipelines transporting hazardous
liquids by gravity?
Section 195.13 will be added which
subjects gravity lines to the same
reporting requirements in subpart B of
part 195 as other hazardous liquid
pipelines. PHMSA has determined that
additional information about gravity
lines is needed to fulfill its statutory
obligations.
§ 195.120 Passage of Internal
Inspection Devices
Section 195.120 contains the
requirements for accommodating the
passage of internal inspection devices in
the design and construction of new or
replaced pipelines. PHMSA has decided
that, in the absence of an emergency or
where the basic construction makes that
accommodation impracticable, a
pipeline should be designed and
constructed to permit the use of ILIs.
Accordingly, the NPRM would repeal
the provisions in the regulation that
allow operators to petition the
Administrator for a finding that the ILI
compatibility requirement should not
apply as a result of construction-related
time constraints and problems. The
other provisions in § 195.120 would be
re-organized without altering the
existing substantive requirements.
§ 195.134 Leak Detection
Section 195.134 contains the design
requirements for computational pipeline
monitoring leak detection systems. The
NPRM would restructure the existing
requirements into paragraphs (a) and (b)
and add a new provision in paragraph
(c) to ensure that all newly constructed
PO 00000
Frm 00026
Fmt 4701
Sfmt 4702
§ 195.401
General Requirements
§ 195.414 Inspections of Pipelines in
Areas Affected by Extreme Weather, a
Natural Disaster, and Other Similar
Events
Extreme weather, natural disasters
and other similar events can affect the
safe operation of a pipeline.
Accordingly, the NPRM would establish
a new regulation in § 195.414 that
would require operators to perform
inspections after these events and to
take appropriate remedial actions.
§ 195.416
Pipeline Assessments
Periodic assessments, particularly
with ILI tools, provide critical
information about the condition of a
pipeline, but are only currently required
under IM requirements in §§ 195.450
through 195.452. PHMSA has
determined that operators should be
required to have the information that is
needed to promptly detect and
remediate conditions that could affect
the safe operation of pipelines in all
areas. Accordingly, the NPRM would
establish a new regulation in § 195.416
that requires operators to perform an
assessment of pipelines that are not
already subject to the IM requirements
at least once every 10 years. The
regulation would require that these
assessments be performed with an ILI
tool, unless an operator demonstrates
and provides 90-days prior notice that a
pipeline is not capable of
accommodating such a device and that
an alternative method will provide a
substantially equivalent understanding
of its condition.
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
The regulation would also require that
the results of these assessments be
reviewed by a person qualified to
determine if any conditions exist that
could affect the safe operation of a
pipeline; that such determinations be
made promptly, but no later than 180
days after the assessment; that any
unsafe conditions be remediated in
accordance with the new requirements
in § 195.422 of the NPRM; and that all
relevant information about the pipeline
be considering in complying with the
requirements of § 195.416.
§ 195.422
Pipeline Remediation
Section 195.422 contains the
requirements for performing pipeline
repairs. PHMSA has determined that
new criteria should be established for
remediating conditions that affect the
safe operation of a pipeline. The NPRM
would add a new paragraph (a)
specifying that the provisions in the
regulation are applicable to pipelines
that are not subject to the IM
requirements in § 195.452 (e.g., not in
HCAs). Paragraphs (b) and (c) would
contain the existing requirements in the
regulation, including the general duty
clause for ensuring public safety and the
provision noting the applicability of the
design and construction requirements to
piping and equipment used in
performing pipeline repairs. Paragraph
(d) would establish a new remediation
schedule based on the analogous
provisions in the IM requirements for
performing immediate and 18-month
repairs, and paragraph (e) would
contain a residual provision for
remediating all other conditions.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
§ 195.444
Leak Detection
Section 195.444 contains the
operation and maintenance
requirements for Computational
Pipeline Monitoring leak detection
systems. PHMSA is proposing that all
pipelines should have leak detection
systems. Therefore, the NPRM would
reorganize the existing requirements of
the regulation into paragraphs (a) and
(c), and add a new general provision in
paragraph (b) that would require
operators to have leak detection systems
on all pipelines and to consider certain
factors in determining what kind of
system is necessary to protect the
public, property, and the environment.
Section 195.452 Pipeline Integrity
Management in High Consequence
Areas
Section 195.452 contains the IM
requirements for hazardous liquid
pipelines that could affect a HCA in the
event of a leak or failure. The NPRM
would clarify the applicability of the
deadlines in paragraph (b) for the
development of a written program for
new pipelines, regulated rural gathering
lines, and low-stress pipelines in rural
areas. Paragraph (c)(1)(i)(A) would also
be amended to ensure that operators
consider uncertainty in tool tolerance in
reviewing the results of ILI assessments.
Paragraph (d) would be amended to
eliminate obsolete deadlines for
performing baseline assessments and to
clarify the requirements for newlyidentified HCAs. Paragraph (e)(1)(vii) is
amended to include local environmental
factors that might affect pipeline
integrity. Paragraph (g) would be
amended to expand upon the factors
and criteria that operators must consider
in performing the information analysis
that is required in periodically
evaluating the integrity of covered
pipeline segments. Paragraph (h)(1)
would also be amended by modifying
the criteria, and establishing a new,
consolidated timeframe, for performing
immediate and 270-day pipeline repairs
based on the information obtained as a
result of ILI assessments or through an
information analysis of a covered
segment.
PHMSA is also proposing to amend
the existing ‘‘discovery of condition’’
language in the pipeline safety
regulations. The revised § 195.452(h)(2)
will require, in cases where a
determination about pipeline threats has
not been obtained within 180 days
following the date of inspection, that
pipeline operators must notify PHMSA
and provide an expected date when
adequate information will become
available. Paragraphs 195.452(h)(4)(i)(E)
and (F) are also added to address issues
of significant stress corrosion cracking
and selective seam corrosion.
PHMSA proposes further changes to
§ 195.452. These changes include
paragraph (j) which would be amended
to establish a new provision for
verifying the risk factors used in
identifying covered segments on at least
an annual basis, not to exceed 15
months. A new paragraph (n) would
also be added to require that all
pipelines in areas that could affect an
HCA be made capable of
accommodating ILI tools within 20
years, unless the basic construction of a
pipeline will not permit that
accommodation or the existence of an
emergency renders such an
accommodation impracticable.
Paragraph (n) would also require that
pipelines in newly-identified HCAs
after the 20-year period be made capable
of accommodating ILIs within five years
of the date of identification or before the
performance of the baseline assessment,
whichever is sooner. Finally, an explicit
reference to seismicity will be added to
factors that must be considered in
establishing assessment schedules
under paragraph (e), for performing
information analyses under paragraph
(g), and for implementing preventive
and mitigative measures under
paragraph (i).
V. Regulatory Notices
A. Executive Order 12866, Executive
Order 13563, and DOT Regulatory
Policies and Procedures
Executive Orders 12866 and 13563
require agencies to regulate in the ‘‘most
cost-effective manner,’’ to make a
‘‘reasoned determination that the
benefits of the intended regulation
justify its costs,’’ and to develop
regulations that ‘‘impose the least
burden on society.’’ This action has
been determined to be significant under
Executive Order 12866 and the
Department of Transportation’s
Regulatory Policies and Procedures. It
has been reviewed by the Office of
Management and Budget in accordance
with Executive Order 13563 (Improving
Regulation and Regulatory Review) and
Executive Order 12866 (Regulatory
Planning and Review) and is consistent
with the requirements in both orders.
In the regulatory analysis, we discuss
the alternatives to the proposed
requirements and, where possible,
provide estimates of the benefits and
costs for specific regulatory
requirements in the eight areas. The
regulatory analysis provides PHMSA’s
best estimate of the impact of the
separate requirements. The chart below
summarizes the cost/benefit analysis:
ANNUALIZED COSTS AND BENEFITS BY REQUIREMENT AREA DISCOUNTED AT 7 PERCENT
Requirement area
Costs
Benefits
1. Extend certain reporting requirements to all hazardous liquid
(HL) gravity lines.
$900 ..............................................
Benefits not quantified, but expected to justify costs.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
PO 00000
Frm 00027
Fmt 4701
Sfmt 4702
61635
E:\FR\FM\13OCP3.SGM
Net benefits
Expected to be positive.
13OCP3
61636
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
ANNUALIZED COSTS AND BENEFITS BY REQUIREMENT AREA DISCOUNTED AT 7 PERCENT—Continued
Costs
Benefits
2. Extend certain reporting requirements to all hazardous liquid
(HL) gathering lines.
3. Require inspections of pipelines
in areas affected by extreme
weather, natural disasters, and
other similar events, as well as
appropriate remedial action if a
condition that could adversely
affect the safe operation of a
pipeline is discovered.
4. Require periodic assessments
of pipelines that are not already
covered under the IM program
requirements using an in-line inspection tool (or demonstrate to
the satisfaction of PHMSA that
the pipeline is not capable of
using this tool).
5. Require use of leak detection
systems (LDS) on new HL pipelines located in non-HCAs to
mitigate the effects of failures
that occur outside of HCAs.
6. Modify the IM repair criteria,
both by expanding the list of
conditions that require immediate remediation, consolidating
the timeframes for remediating
all other conditions, and making
explicit deadlines for repairs on
non-IM pipeline.
7. Increase the use of inline inspection (ILI) tools by requiring
that any pipeline that could affect an HCA be capable of accommodating these devices
within 20 years, unless its basic
construction will not permit that
accommodation.
8. Clarify and resolve inconsistencies regarding deadlines, and
information analyses for IM
Plans t.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
Requirement area
23,300 ...........................................
Benefits not quantified but expected to justify the costs.
Expected to be positive.
1.5 million .....................................
3.5 to 10.4 million .........................
2.0 to 8.9 million
16.7 million ...................................
17.7 million ...................................
Range 9.4–26.0 million .................
1 million
Range (–)7.3–9.3 million
Expected to be positive even at
the low end of the benefit range
if unquantified benefits are included.
Not quantified but expected to be
minimal.
Not quantified, but expected to
justify the minimal costs.
Not quanitified, but positive qualitative benefits.
Not quantified, but expected to be
minimal.
Not quantified, but expected to
justify the minimal costs.
Not quantified, but expected to be
minimal.
1.0 million .....................................
12.2 million ...................................
11.2 million
3.2 million .....................................
10.0 million ...................................
6.8 million.
Overall, factors such as increased
safety, public confidence that all
pipelines are regulated, quicker
discovery of leaks and mitigation of
environmental damages, and better risk
management are expected to yield
benefits that are in excess of the cost.
PHMSA seeks comment on the
Preliminary Regulatory Evaluation, its
approach, and the accuracy of its
estimates of costs and benefits. A copy
of the Preliminary Regulatory evaluation
has been placed in the docket.
B. Executive Order 13132: Federalism
This NPRM has been analyzed in
accordance with the principles and
criteria contained in Executive Order
13132 (‘‘Federalism’’). This NPRM does
not propose any regulation that has
substantial direct effects on the states,
the relationship between the national
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
government and the states, or the
distribution of power and
responsibilities among the various
levels of government. It does not
propose any regulation that imposes
substantial direct compliance costs on
state and local governments. Therefore,
the consultation and funding
requirements of Executive Order 13132
do not apply. Nevertheless, PHMSA has
and will continue to consult extensively
with state regulators including NAPSR
to ensure that any state concerns are
taken into account.
C. Regulatory Flexibility Act
The Regulatory Flexibility Act of 1980
(Pub. L. 96–354) (RFA) establishes ‘‘as a
principle of regulatory issuance that
agencies shall endeavor, consistent with
the objectives of the rule and of
applicable statutes, to fit regulatory and
PO 00000
Frm 00028
Fmt 4701
Sfmt 4702
Net benefits
informational requirements to the scale
of the businesses, organizations, and
governmental jurisdictions subject to
regulation. To achieve this principle,
agencies are required to solicit and
consider flexible regulatory proposals
and to explain the rationale for their
actions to assure that such proposals are
given serious consideration.’’
The RFA covers a wide range of small
entities, including small businesses,
not-for-profit organizations, and small
governmental jurisdictions. Agencies
must perform a review to determine
whether a rule will have a significant
economic impact on a substantial
number of small entities. If the agency
determines that it will, the agency must
prepare a regulatory flexibility analysis
as described in the RFA.
However, if an agency determines that
a rule is not expected to have a
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
significant economic impact on a
substantial number of small entities,
section 605(b) of the RFA provides that
the head of the agency may so certify
and a regulatory flexibility analysis is
not required. The certification must
include a statement providing the
factual basis for this determination, and
the reasoning should be clear.
PHMSA performed a screening
analysis of the potential economic
impact on small entities. The screening
analysis is available in the docket for
the rulemaking. PHMSA estimates that
the proposed rule would impact fewer
than 100 small hazardous liquid
pipeline operators, and that the majority
of these operators would experience
annual compliance costs that represent
less than 1% of annual revenues. Less
than 20 small operators would incur
annual compliance costs that represent
greater than 1% of annual revenues; less
than 10 would incur annual compliance
costs of greater than 3% of annual
revenues; and none would incur
compliance costs of more than 20% of
annual revenues. PHMSA determined
that these impacts results do not
represent a significant impact for a
substantial number of small hazardous
liquid pipeline operators. Therefore, I
certify that this action, if promulgated,
will not have a significant economic
impact on a substantial number of small
entities.
D. National Environmental Policy Act
PHMSA analyzed this NPRM in
accordance with section 102(2)(c) of the
National Environmental Policy Act (42
U.S.C. 4332), the Council on
Environmental Quality regulations (40
CFR parts 1500 through 1508), and DOT
Order 5610.1C, and has preliminarily
determined that this action will not
significantly affect the quality of the
human environment. A preliminary
environmental assessment of this
rulemaking is available in the docket
and PHMSA invites comment on
environmental impacts of this rule, if
any.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
E. Executive Order 13175: Consultation
and Coordination With Indian Tribal
Governments
This NPRM has been analyzed in
accordance with the principles and
criteria contained in Executive Order
13175 (‘‘Consultation and Coordination
with Indian Tribal Governments’’).
Because this NPRM does not have Tribal
implications and does not impose
substantial direct compliance costs on
Indian Tribal governments, the funding
and consultation requirements of
Executive Order 13175 do not apply.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
F. Paperwork Reduction Act
Paperwork Reduction Act
Pursuant to 5 CFR 1320.8(d), PHMSA
is required to provide interested
members of the public and affected
agencies with an opportunity to
comment on information collection and
recordkeeping requests. PHMSA
estimates that the proposals in this
rulemaking will add a new information
collection and impact several approved
information collections titled:
‘‘Transportation of Hazardous Liquids
by Pipeline: Recordkeeping and
Accident Reporting’’ identified under
Office of Management and Budget
(OMB) Control Number 2137–0047;
‘‘Reporting Safety-Related Conditions
on Gas, Hazardous Liquid, and Carbon
Dioxide Pipelines and Liquefied Natural
Gas Facilities’’ identified under OMB
Control Number 2137–0578;
‘‘Integrity Management in High
Consequence Areas for Operators of
Hazardous Liquid Pipelines’’ identified
under OMB Control Number 2137–0605
and;
‘‘Pipeline Safety: New Reporting
Requirements for Hazardous Liquid
Pipeline Operators: Hazardous Liquid
Annual Report’’ identified under OMB
Control Number 2137–0614.
Based on the proposals in this
rulemaking, PHMSA will submit an
information collection revision request
to OMB for approval based on the
requirements in this NPRM. The
information collection is contained in
the pipeline safety regulations, 49 CFR
parts 190 through 199. The following
information is provided for each
information collection: (1) Title of the
information collection; (2) OMB control
number; (3) Current expiration date; (4)
Type of request; (5) Abstract of the
information collection activity; (6)
Description of affected public; (7)
Estimate of total annual reporting and
recordkeeping burden; and (8)
Frequency of collection. The
information collection burden for the
following information collections are
estimated to be revised as follows:
1. Title: Transportation of Hazardous
Liquids by Pipeline: Recordkeeping and
Accident Reporting.
OMB Control Number: 2137–0047.
Current Expiration Date: April 30,
2014.
Abstract: This information collection
covers the collection of information
from owners and operators of Hazardous
Liquid Pipelines. To ensure adequate
public protection from exposure to
potential hazardous liquid pipeline
failures, PHMSA collects information on
reportable hazardous liquid pipeline
accidents. Additional information is
PO 00000
Frm 00029
Fmt 4701
Sfmt 4702
61637
also obtained concerning the
characteristics of an operator’s pipeline
system. As a result of this NPRM, 5
gravity line operators and 23 gathering
line operators would be required to
submit accident reports to PHMSA on
occasion. These 28 additional operators
will also be required to keep mandated
records. This information collection is
being revised to account for the
additional burden that will be incurred
by these newly regulated entities.
Operators currently submitting annual
reports will not be otherwise impacted
by this NPRM.
Affected Public: Owners and
operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping
Burden:
Total Annual Responses: 881.
Total Annual Burden Hours: 55,455.
Frequency of Collection: On occasion.
2. Title: Reporting Safety-Related
Conditions on Gas, Hazardous Liquid,
and Carbon Dioxide Pipelines and
Liquefied Natural Gas Facilities.
OMB Control Number: 2137–0578.
Current Expiration Date: May 31,
2014.
Abstract: 49 U.S.C. 60102 requires
each operator of a pipeline facility
(except master meter operators) to
submit to DOT a written report on any
safety-related condition that causes or
has caused a significant change or
restriction in the operation of a pipeline
facility or a condition that is a hazards
to life, property or the environment. As
a result of this NPRM, approximately 5
gravity line operators and 23 gathering
line operators will be required to adhere
to the Safety-Related Condition
reporting requirements. This
information collection is being revised
to account for the additional burden that
will be incurred by newly regulated
entities. Operators currently submitting
annual reports will not be otherwise
impacted by this rule.
Affected Public: Owners and
operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping
Burden:
Total Annual Responses: 178.
Total Annual Burden Hours: 1,020.
Frequency of Collection: On occasion.
3. Title: Integrity Management in High
Consequence Areas for Operators of
Hazardous Liquid Pipelines.
OMB Control Number: 2137–0605.
Current Expiration Date: November
30, 2016.
Abstract: Owners and operators of
Hazardous Liquid Pipelines are required
to have continual assessment and
evaluation of pipeline integrity through
inspection or testing, as well as
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
61638
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
remedial preventive and mitigative
actions. As a result of this NPRM,
operators not currently under IM plans
will be required to adhere to the repair
criteria currently required for operators
who are under IM plans. In conjunction
with this requirement, operators who
are not able to make the necessary
repairs within 180 days of the infraction
will be required to notify PHMSA in
writing. PHMSA estimates that only 1%
of repair reports will require more than
180 days. Accordingly, PHMSA
approximates that 75 reports per year
will fall within this category.
Affected Public: Owners and
operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping
Burden:
Total Annual Responses: 278.
Total Annual Burden Hours: 325,508.
Frequency of Collection: Annually.
4. Title: Pipeline Safety: New
Reporting Requirements for Hazardous
Liquid Pipeline Operators: Hazardous
Liquid Annual Report.
OMB Control Number: 2137–0614.
Current Expiration Date: April 30,
2014.
Abstract: Owners and operators of
hazardous liquid pipelines are required
to provide PHMSA with safety related
documentation relative to the annual
operation of their pipeline. The
provided information is used compile a
national pipeline inventory, identify
safety problems, and target inspections.
As a result of this NPRM, approximately
5 gravity line operators and 23 gathering
line operators will be required to submit
annual reports to PHMSA. This
information collection is being revised
to account for the additional burden that
will be incurred. Operators currently
submitting annual reports will not be
otherwise impacted by this rule.
Affected Public: Owners and
operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping
Burden:
Total Annual Responses: 475.
Total Annual Burden Hours: 8,567.
Frequency of Collection: Annually.
5. Title: Pipeline Safety: Notification
Requirements for Hazardous Liquid
Operators.
OMB Control Number: New OMB
Control No.
Current Expiration Date: TBD.
Abstract: Owners and operators of
non-High Consequence Area hazardous
liquid pipelines will be required to
provide PHMSA with notifications
when unable to assess their pipeline via
an in-line inspection.
Affected Public: Owners and
operators of Hazardous Liquid
Pipelines.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
Annual Reporting and Recordkeeping
Burden:
Total Annual Responses: 10.
Total Annual Burden Hours: 10.
Frequency of Collection: On occasion.
Requests for copies of these
information collections should be
directed to Angela Dow or Cameron
Satterthwaite, Office of Pipeline Safety
(PHP–30), Pipeline Hazardous Materials
Safety Administration (PHMSA), 2nd
Floor, 1200 New Jersey Avenue SE.,
Washington, DC 20590–0001,
Telephone (202) 366–4595.
G. Privacy Act Statement
Anyone is able to search the
electronic form of all comments
received into any of our dockets by the
name of the individual submitting the
comment (or signing the comment, if
submitted on behalf of an association,
business, labor union, etc.). You may
review DOT’s complete Privacy Act
Statement in the Federal Register
published on April 11, 2000 (65 FR
19477), or at https://
www.regulations.gov.
H. Regulation Identifier Number (RIN)
A regulation identifier number (RIN)
is assigned to each regulatory action
listed in the Unified Agenda of Federal
Regulations. The Regulatory Information
Service Center publishes the Unified
Agenda in April and October of each
year. The RIN contained in the heading
of this document may be used to crossreference this action with the Unified
Agenda.
List of Subjects in 49 CFR Part 195
Incorporation by reference, Integrity
management, Pipeline safety.
In consideration of the foregoing,
PHMSA proposes to amend 49 CFR part
195 as follows:
under paragraphs (a)(1), (2), (3) or (4) of
this section.
*
*
*
*
*
■ 3. In section 195.2, the definition for
‘‘Hazardous liquid’’ is revised and a
definition of ‘‘Significant stress
corrosion cracking’’ is added in
alphabetical order to read as follows:
§ 195.2
Definitions.
*
*
*
*
*
Hazardous liquid means petroleum,
petroleum products, anhydrous
ammonia or non-petroleum fuel,
including biofuel that is flammable,
toxic, or corrosive or would be harmful
to the environment if released in
significant quantities.
*
*
*
*
*
Significant stress corrosion cracking
means a stress corrosion cracking (SCC)
cluster in which the deepest crack, in a
series of interacting cracks, is greater
than 10% of the wall thickness and the
total interacting length of the cracks is
equal to or greater than 75% of the
critical length of a 50% through-wall
flaw that would fail at a stress level of
110% of SMYS.
*
*
*
*
*
■ 4. In section 195.11, add paragraphs
(b)(12) and (13) to read as follows:
§ 195.11 What is a regulated rural
gathering line and what requirements
apply?
*
*
*
*
*
(b) * * *
(12) Perform pipeline assessments and
remediation as required under
§§ 195.416 and 195.422.
(13) Establish a leak detection system
in compliance with §§ 195.134 and
195.444.
*
*
*
*
*
■ 5. Section 195.13 is added to subpart
A to read as follows:
PART 195—TRANSPORTATION OF
HAZARDOUS LIQUIDS BY PIPELINE
§ 195.13 What reporting requirements
apply to pipelines transporting hazardous
liquids by gravity?
1. The authority citation for part 195
is revised to read as follows:
(a) Scope. This section applies to
pipelines transporting hazardous liquids
by gravity as of [effective date of the
final rule].
(b) Annual, accident and safety
related reporting. Comply with the
reporting requirements in subpart B of
this part by [date 6 months after
effective date of the final rule].
■ 6. Section 195.120 is revised to read
as follows:
■
Authority: 49 U.S.C. 5103, 60101, 60102,
60104, 60108, 60109, 60116, 60118, 60131,
60131, 60137, and 49 CFR 1.97.
2. In § 195.1, paragraph (a)(5) is
added, paragraph (b)(2) is removed, and
paragraphs (b)(3) through (10) are redesignated as (b)(2) through (9).
The addition reads as follows:
■
§ 195.1 Which pipelines are covered by
this part?
(a) * * *
*
*
*
*
*
(5) For purposes of the reporting
requirements in subpart B of this part,
any gathering line not already covered
PO 00000
Frm 00030
Fmt 4701
Sfmt 4702
§ 195.120
devices.
Passage of internal inspection
(a) General. Except as provided in
paragraphs (b) and (c) of this section,
each new pipeline and each main line
section of a pipeline where the line
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
pipe, valve, fitting or other line
component is replaced must be
designed and constructed to
accommodate the passage of
instrumented internal inspection
devices.
(b) Exceptions. This section does not
apply to:
(1) Manifolds;
(2) Station piping such as at pump
stations, meter stations, or pressure
reducing stations;
(3) Piping associated with tank farms
and other storage facilities;
(4) Cross-overs;
(5) Pipe for which an instrumented
internal inspection device is not
commercially available; and
(6) Offshore pipelines, other than
main lines 10 inches (254 millimeters)
or greater in nominal diameter, that
transport liquids to onshore facilities.
(c) Impracticability. An operator may
file a petition under § 190.9 for a finding
that the requirements in paragraph (a)
should not be applied to a pipeline for
reasons of impracticability.
(d) Emergencies. An operator need not
comply with paragraph (a) of this
section in constructing a new or
replacement segment of a pipeline in an
emergency. Within 30 days after
discovering the emergency, the operator
must file a petition under § 190.9 for a
finding that requiring the design and
construction of the new or replacement
pipeline segment to accommodate
passage of instrumented internal
inspection devices would be
impracticable as a result of the
emergency. If the petition is denied,
within 1 year after the date of the notice
of the denial, the operator must modify
the new or replacement pipeline
segment to allow passage of
instrumented internal inspection
devices.
■ 7. Section 195.134 is revised to read
as follow:
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
§ 195.134
Leak detection.
(a) Scope. This section applies to each
hazardous liquid pipeline transporting
liquid in single phase (without gas in
the liquid).
(b) General. Each pipeline must have
a system for detecting leaks that
complies with the requirements in
§ 195.444.
(c) CPM leak detection systems. A
new computational pipeline monitoring
(CPM) leak detection system or replaced
component of an existing CPM system
must be designed in accordance with
the requirements in section 4.2 of API
RP 1130 (incorporated by reference, see
§ 195.3) and any other applicable design
criteria in that standard.
■ 8. In § 195.401, the introductory text
of paragraph (b) and paragraph (b)(1) are
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
revised and paragraph (b)(3) is added to
read as follows.
§ 195.401
General requirements.
*
*
*
*
*
(b) An operator must make repairs on
its pipeline system according to the
following requirements:
(1) Non integrity management repairs.
Whenever an operator discovers any
condition that could adversely affect the
safe operation of a pipeline not covered
under § 195.452, it must correct the
condition as prescribed in § 195.422.
However, if the condition is of such a
nature that it presents an immediate
hazard to persons or property, the
operator may not operate the affected
part of the system until it has corrected
the unsafe condition.
*
*
*
*
*
(3) Prioritizing repairs. An operator
must consider the risk to people,
property, and the environment in
prioritizing the correction of any
conditions referenced in paragraphs
(b)(1) and (2) of this section.
*
*
*
*
*
■ 9. Section 195.414 is added to read as
follows:
§ 195.414 Inspections of pipelines in areas
affected by extreme weather, a natural
disaster, and other similar events.
(a) General. Following an extreme
weather event such as a hurricane or
flood, an earthquake, a natural disaster,
or other similar event, an operator must
inspect all potentially affected pipeline
facilities to ensure that no conditions
exist that could adversely affect the safe
operation of that pipeline.
(b) Inspection method. An operator
must consider the nature of the event
and the physical characteristics,
operating conditions, location, and prior
history of the affected pipeline in
determining the appropriate method for
performing the inspection required
under paragraph (a) of this section.
(c) Time period. The inspection
required under paragraph (a) of this
section must occur within 72 hours after
the cessation of the event, or as soon as
the affected area can be safely accessed
by the personnel and equipment
required to perform the inspection as
determined under paragraph (b) of this
section.
(d) Remedial action. An operator must
take appropriate remedial action to
ensure the safe operation of a pipeline
based on the information obtained as a
result of performing the inspection
required under paragraph (a) of this
section. Such actions might include, but
are not limited to:
(1) Reducing the operating pressure or
shutting down the pipeline;
PO 00000
Frm 00031
Fmt 4701
Sfmt 4702
61639
(2) Modifying, repairing, or replacing
any damaged pipeline facilities;
(3) Preventing, mitigating, or
eliminating any unsafe conditions in the
pipeline right-of-way;
(4) Performing additional patrols,
surveys, tests, or inspections;
(5) Implementing emergency response
activities with Federal, State, or local
personnel; and
(6) Notifying affected communities of
the steps that can be taken to ensure
public safety.
■ 10. Section 195.416 is added to read
as follows:
§ 195.416
Pipeline assessments.
(a) Scope. This section applies to
pipelines that are not subject to the
integrity management requirements in
§ 195.452.
(b) General. An operator must perform
an assessment of a pipeline at least once
every 10 years, or as otherwise
necessary to ensure public safety.
(c) Method. The assessment required
under paragraph (b) of this section must
be performed with an in-line inspection
tool or tools capable of detecting
corrosion and deformation anomalies,
including dents, cracks, gouges, and
grooves, unless an operator:
(i) Demonstrates that the pipeline is
not capable of accommodating an inline
inspection tool; and that the use of an
alternative assessment method will
provide a substantially equivalent
understanding of the condition of the
pipeline; and
(ii) Notifies the Office of Pipeline
Safety (OPS) 90 days before conducting
the assessment by:
(A) Sending the notification, along
with the information required to
demonstrate compliance with paragraph
(c)(i) of this section, to the Information
Resources Manager, Office of Pipeline
Safety, Pipeline and Hazardous
Materials Safety Administration, 1200
New Jersey Avenue SE., Washington,
DC 20590; or
(B) Sending the notification, along
with the information required to
demonstrate compliance with paragraph
(c)(i) of this section, to the Information
Resources Manager by facsimile to (202)
366–7128.
(d) Data analysis. A person qualified
by knowledge, training, and experience
must analyze the data obtained from an
assessment performed under paragraph
(b) of this section to determine if a
condition could adversely affect the safe
operation of the pipeline. Uncertainties
in any reported results (including tool
tolerance) must be considered as part of
that analysis.
(e) Discovery of condition. For
purposes of § 195.422, discovery of a
E:\FR\FM\13OCP3.SGM
13OCP3
61640
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
condition occurs when an operator has
adequate information to determine that
a condition exists. An operator must
promptly, but no later than 180 days
after an assessment, obtain sufficient
information about a condition and make
the determination required under
paragraph (d) of this section, unless 180days is impracticable as determined by
PHMSA.
(f) Remediation. An operator must
comply with the requirements in
§ 195.422 if a condition that could
adversely affect the safe operation of a
pipeline is discovered in complying
with paragraphs (d) and (e) of this
section.
(g) Consideration of information. An
operator must consider all relevant
information about a pipeline in
complying with the requirements in
paragraphs (a) through (f) of this section.
■ 11. Section 195.422 is revised to read
as follows:
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
§ 195.422
Pipeline remediation.
(a) Scope. This section applies to
pipelines that are not subject to the
integrity management requirements in
§ 195.452.
(b) General. Each operator must, in
repairing its pipeline systems, ensure
that the repairs are made in a safe
manner and are made so as to prevent
damage to persons, property, or the
environment.
(c) Replacement. An operator may not
use any pipe, valve, or fitting, for
replacement in repairing pipeline
facilities, unless it is designed and
constructed as required by this part.
(d) Remediation schedule. An
operator must complete the remediation
of a condition according to the
following schedule:
(1) Immediate repair conditions. An
operator must repair the following
conditions immediately upon discovery:
(i) Metal loss greater than 80% of
nominal wall regardless of dimensions.
(ii) A calculation of the remaining
strength of the pipe shows a burst
pressure less than 1.1 times the
maximum operating pressure at the
location of the anomaly. Suitable
remaining strength calculation methods
include, but are not limited to, ASME/
ANSI B31G (‘‘Manual for Determining
the Remaining Strength of Corroded
Pipelines’’ (1991) or AGA Pipeline
Research Committee Project PR–3–805
(‘‘A Modified Criterion for Evaluating
the Remaining Strength of Corroded
Pipe’’ (December 1989)) (incorporated
by reference, see § 195.3.
(iii) A dent located anywhere on the
pipeline that has any indication of metal
loss, cracking or a stress riser.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
(iv) A dent located on the top of the
pipeline (above the 4 and 8 o’clock
positions) with a depth greater than 6%
of the nominal pipe diameter.
(v) An anomaly that in the judgment
of the person designated by the operator
to evaluate the assessment results
requires immediate action.
(vi) Any indication of significant
stress corrosion cracking (SCC).
(vii) Any indication of selective seam
weld corrosion (SSWC).
(2) Until the remediation of a
condition specified in paragraph (d)(1)
of this section is complete, an operator
must:
(i) Reduce the operating pressure of
the affected pipeline using the formula
specified in paragraph 195.422(d)(3)(iv)
or;
(ii) Shutdown the affected pipeline.
(3) 18-month repair conditions. An
operator must repair the following
conditions within 18 months of
discovery:
(i) A dent with a depth greater than
2% of the pipeline’s diameter (0.250
inches in depth for a pipeline diameter
less than NPS 12) that affects pipe
curvature at a girth weld or a
longitudinal seam weld.
(ii) A dent located on the top of the
pipeline (above 4 and 8 o’clock
position) with a depth greater than 2%
of the pipeline’s diameter (0.250 inches
in depth for a pipeline diameter less
than NPS 12).
(iii) A dent located on the bottom of
the pipeline with a depth greater than
6% of the pipeline’s diameter.
(iv) A calculation of the remaining
strength of the pipe at the anomaly
shows a safe operating pressure that is
less than the MOP at that location.
Provided the safe operating pressure
includes the internal design safety
factors in § 195.106 in calculating the
pipe anomaly safe operating pressure,
suitable remaining strength calculation
methods include, but are not limited to,
ASME/ANSI B31G (‘‘Manual for
Determining the Remaining Strength of
Corroded Pipelines’’ (1991)) or AGA
Pipeline Research Committee Project
PR–3–805 (‘‘A Modified Criterion for
Evaluating the Remaining Strength of
Corroded Pipe’’ (December 1989))
(incorporated by reference, see § 195.3).
(v) An area of general corrosion with
a predicted metal loss greater than 50%
of nominal wall.
(vi) Predicted metal loss greater than
50% of nominal wall that is located at
a crossing of another pipeline, or is in
an area with widespread circumferential
corrosion, or is in an area that could
affect a girth weld.
PO 00000
Frm 00032
Fmt 4701
Sfmt 4702
(vii) A potential crack indication that
when excavated is determined to be a
crack.
(viii) Corrosion of or along a seam
weld.
(ix) A gouge or groove greater than
12.5% of nominal wall.
(e) Other conditions. Unless another
timeframe is specified in paragraph (d)
of this section, an operator must take
appropriate remedial action to correct
any condition that could adversely
affect the safe operation of a pipeline
system within a reasonable time.
■ 12. Section 195.444 is revised to read
as follows:
§ 195.444
Leak detection.
(a) Scope. This section applies to each
hazardous liquid pipeline transporting
liquid in single phase (without gas in
the liquid).
(b) General. A pipeline must have a
system for detecting leaks. An operator
must evaluate and modify, as necessary,
the capability of its leak detection
system to protect the public, property,
and the environment. An operator’s
evaluation must, at least, consider the
following factors—length and size of the
pipeline, type of product carried, the
swiftness of leak detection, location of
nearest response personnel, and leak
history.
(c) CPM leak detection systems. Each
computational pipeline monitoring
(CPM) leak detection system installed
on a hazardous liquid pipeline must
comply with API RP 1130 (incorporated
by reference, see § 195.3) in operating,
maintaining, testing, record keeping,
and dispatcher training of the system.
■ 13. In § 195.452:
■ a. Revise paragraphs (a), (b)(1),
introductory text of paragraph (c)(1)(i),
(c)(1)(i)(A), (d), (e)(1)(vii), (g),
introductory text of (h)(1), (h)(2), and
(h)(4);
■ b. Revise paragraph (i)(2)(viii) by
removing the period at the end of the
last sentence and adding in its place a
‘‘;’’ and add paragraph (i)(2)(ix);
■ c. Revise paragraphs (j)(1) and (2);
■ d. Add paragraph (n).
The revisions and additions read as
follows:
§ 195.452 Pipeline integrity management in
high consequence areas.
(a) Which pipelines are covered by
this section? This section applies to
each hazardous liquid pipeline and
carbon dioxide pipeline that could
affect a high consequence area,
including any pipeline located in a high
consequence area, unless the operator
demonstrates that a worst case discharge
from the pipeline could not affect the
area. (Appendix C of this part provides
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
guidance on determining if a pipeline
could affect a high consequence area.)
Covered pipelines are categorized as
follows:
(1) Category 1 includes pipelines
existing on May 29, 2001, that were
owned or operated by an operator who
owned or operated a total of 500 or more
miles of pipeline subject to this part.
(2) Category 2 includes pipelines
existing on May 29, 2001, that were
owned or operated by an operator who
owned or operated less than 500 miles
of pipeline subject to this part.
(3) Category 3 includes pipelines
constructed or converted after May 29,
2001, low-stress pipelines in rural areas
under § 195.12.
(b) * * *
(1) Develop a written integrity
management program that addresses the
risks on each segment of pipeline in the
first column of the following table not
later than the date in the second
column:
Pipeline
Date
Category 1
Category 2
Category 3
March 31, 2002.
February 18, 2003.
Date the pipeline begins operation or as provided in
§ 195.12.
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
*
*
*
*
*
(c) * * *
(1) * * *
(i) The methods selected to assess the
integrity of the line pipe. An operator
must assess the integrity of the line pipe
by In Line Inspection tool unless it is
impracticable, then use methods (B), (C)
or (D) of this paragraph. The methods an
operator selects to assess low frequency
electric resistance welded pipe, or lap
welded pipe, or pipe with a seam factor
less than 1.0 as defined in § 195.106(e)
or lap welded pipe susceptible to
longitudinal seam failure must be
capable of assessing seam integrity and
of detecting corrosion and deformation
anomalies.
(A) Internal inspection tool or tools
capable of detecting corrosion, and
deformation anomalies including dents,
cracks (pipe body and weld seams),
gouges and grooves. An operator using
this method must explicitly consider
uncertainties in reported results
(including tool tolerance, anomaly
findings, and unity chart plots or
equivalent for determining
uncertainties) in identifying anomalies;
*
*
*
*
*
(d) When must operators complete
baseline assessments?
(1) All pipelines. An operator must
complete the baseline assessment before
the pipeline begins operation.
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
(2) Newly-identified areas. If an
operator obtains information (whether
from the information analysis required
under paragraph (g) of this section,
Census Bureau maps, or any other
source) demonstrating that the area
around a pipeline segment has changed
to meet the definition of a high
consequence area (see § 195.450), that
area must be incorporated into the
operator’s baseline assessment plan
within one year from the date that the
information is obtained. An operator
must complete the baseline assessment
of any pipeline segment that could
affect a newly-identified high
consequence area within five years from
the date the area is identified.
*
*
*
*
*
(e) * * *
(1) * * *
(vii) Local environmental factors that
could affect the pipeline (e.g.,
seismicity, corrosivity of soil,
subsidence, climatic);
*
*
*
*
*
(g) What is an information analysis?
In periodically evaluating the integrity
of each pipeline segment (see paragraph
(j) of this section), an operator must
analyze all available information about
the integrity of its entire pipeline and
the consequences of a possible failure
along the pipeline. This analysis must:
(1) Integrate information and
attributes about the pipeline which
include, but are not limited to:
(i) Pipe diameter, wall thickness,
grade, and seam type;
(ii) Pipe coating including girth weld
coating;
(iii) Maximum operating pressure
(MOP);
(iv) Endpoints of segments that could
affect high consequence areas (HCAs);
(v) Hydrostatic test pressure including
any test failures—if known;
(vi) Location of casings and if shorted;
(vii) Any in-service ruptures or
leaks—including identified causes;
(viii) Data gathered through integrity
assessments required under this section;
(ix) Close interval survey (CIS) survey
results;
(x) Depth of cover surveys;
(xi) Corrosion protection (CP) rectifier
readings;
(xii) CP test point survey readings and
locations;
(xiii) AC/DC and foreign structure
interference surveys;
(xiv) Pipe coating surveys and
cathodic protection surveys.
(xv) Results of examinations of
exposed portions of buried pipelines
(i.e., pipe and pipe coating condition,
see § 195.569);
(xvi) Stress corrosion cracking (SCC)
and other cracking (pipe body or weld)
PO 00000
Frm 00033
Fmt 4701
Sfmt 4702
61641
excavations and findings, including insitu non-destructive examinations and
analysis results for failure stress
pressures and cyclic fatigue crack
growth analysis to estimate the
remaining life of the pipeline;
(xvii) Aerial photography;
(xviii) Location of foreign line
crossings;
(xix) Pipe exposures resulting from
encroachments;
(xx) Seismicity of the area; and
(xxi) Other pertinent information
derived from operations and
maintenance activities and any
additional tests, inspections, surveys,
patrols, or monitoring required under
this part.
(2) Consider information critical to
determining the potential for, and
preventing, damage due to excavation,
including current and planned damage
prevention activities, and development
or planned development along the
pipeline;
(3) Consider how a potential failure
would affect high consequence areas,
such as location of a water intake.
(4) Identify spatial relationships
among anomalous information (e.g.,
corrosion coincident with foreign line
crossings; evidence of pipeline damage
where aerial photography shows
evidence of encroachment). Storing the
information in a geographic information
system (GIS), alone, is not sufficient. An
operator must analyze for
interrelationships among the data.
(h) * * *
(1) General requirements. An operator
must take prompt action to address all
anomalous conditions in the pipeline
that the operator discovers through the
integrity assessment or information
analysis. In addressing all conditions,
an operator must evaluate all anomalous
conditions and remediate those that
could reduce a pipeline’s integrity. An
operator must be able to demonstrate
that the remediation of the condition
will ensure that the condition is
unlikely to pose a threat to the longterm integrity of the pipeline. An
operator must comply with all other
applicable requirements in this part in
remediating a condition.
*
*
*
*
*
(2) Discovery of condition. Discovery
of a condition occurs when an operator
has adequate information to determine
that a condition exists. An operator
must promptly, but no later than 180
days after an assessment, obtain
sufficient information about a condition
and make the determination required,
unless the operator can demonstrate that
that 180-day is impracticable. If 180days is impracticable to make a
E:\FR\FM\13OCP3.SGM
13OCP3
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
61642
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
determination about a condition found
during an assessment, the pipeline
operator must notify PHMSA and
provide an expected date when
adequate information will become
available.
*
*
*
*
*
(4) Special requirements for
scheduling remediation—(i) Immediate
repair conditions. An operator’s
evaluation and remediation schedule
must provide for immediate repair
conditions. To maintain safety, an
operator must temporarily reduce the
operating pressure or shut down the
pipeline until the operator completes
the repair of these conditions. An
operator must calculate the temporary
reduction in operating pressure using
the formulas in paragraph (h)(4)(i)(B) of
this section, if applicable, or when the
formulas in paragraph (h)(4)(i)(B) of this
section are not applicable by using a
pressure reduction determination in
accordance with § 195.106 and the
appropriate remaining pipe wall
thickness, or if all of these are unknown
a minimum 20 percent or greater
operating pressure reduction must be
implemented until the anomaly is
repaired. If the formula is not applicable
to the type of anomaly or would
produce a higher operating pressure, an
operator must use an alternative
acceptable method to calculate a
reduced operating pressure. An operator
must treat the following conditions as
immediate repair conditions:
(A) Metal loss greater than 80% of
nominal wall regardless of dimensions.
(B) A calculation of the remaining
strength of the pipe shows a predicted
burst pressure less than 1.1 times the
maximum operating pressure at the
location of the anomaly. Suitable
remaining strength calculation methods
include, but are not limited to, ASME/
ANSI B31G (‘‘Manual for Determining
the Remaining Strength of Corroded
Pipelines’’ (1991) or AGA Pipeline
Research Committee Project PR–3–805
(‘‘A Modified Criterion for Evaluating
the Remaining Strength of Corroded
Pipe’’ (December 1989)) (incorporated
by reference, see § 195.3).
(C) A dent located anywhere on the
pipeline that has any indication of metal
loss, cracking or a stress riser.
(D) A dent located on the top of the
pipeline (above the 4 and 8 o’clock
positions) with a depth greater than 6%
of the nominal pipe diameter.
(E) Any indication of significant stress
corrosion cracking (SCC).
(F) Any indication of selective seam
weld corrosion (SSWC)
(G) An anomaly that in the judgment
of the person designated by the operator
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
to evaluate the assessment results
requires immediate action.
(ii) 270-day conditions. Except for
conditions listed in paragraph (h)(4)(i)
of this section, an operator must
schedule evaluation and remediation of
the following within 270 days of
discovery of the condition:
(A) A dent with a depth greater than
2% of the pipeline’s diameter (0.250
inches in depth for a pipeline diameter
less than NPS 12) that affects pipe
curvature at a girth weld or a
longitudinal seam weld.
(B) A dent located on the top of the
pipeline (above 4 and 8 o’clock
position) with a depth greater than 2%
of the pipeline’s diameter (0.250 inches
in depth for a pipeline diameter less
than NPS 12).
(C) A dent located on the bottom of
the pipeline with a depth greater than
6% of the pipeline’s diameter.
(D) A calculation of the remaining
strength of the pipe at the anomaly
shows a safe operating pressure that is
less than MOP at that location. Provided
the safe operating pressure includes the
internal design safety factors in
§ 195.106 in calculating the pipe
anomaly safe operating pressure,
suitable remaining strength calculation
methods include, but are not limited to,
ASME/ANSI B31G (‘‘Manual for
Determining the Remaining Strength of
Corroded Pipelines’’ (1991)) or AGA
Pipeline Research Committee Project
PR–3–805 (‘‘A Modified Criterion for
Evaluating the Remaining Strength of
Corroded Pipe’’ (December 1989))
(incorporated by reference, see § 195.3).
(E) An area of general corrosion with
a predicted metal loss greater than 50%
of nominal wall.
(F) Predicted metal loss greater than
50% of nominal wall that is located at
a crossing of another pipeline, or is in
an area with widespread circumferential
corrosion, or is in an area that could
affect a girth weld.
(G) A potential crack indication that
when excavated is determined to be a
crack.
(H) Corrosion of or along a
longitudinal seam weld.
(I) A gouge or groove greater than
12.5% of nominal wall.
(iii) Other Conditions. In addition to
the conditions listed in paragraphs
(h)(4)(i) and (ii) of this section, an
operator must evaluate any condition
identified by an integrity assessment or
information analysis that could impair
the integrity of the pipeline, and as
appropriate, schedule the condition for
remediation. Appendix C of this part
contains guidance concerning other
conditions that an operator should
evaluate.
PO 00000
Frm 00034
Fmt 4701
Sfmt 4702
(i) * * *
(2) * * *
(ix) Seismicity of the area.
*
*
*
*
*
(j) * * * (1) General. After
completing the baseline integrity
assessment, an operator must continue
to assess the line pipe at specified
intervals and periodically evaluate the
integrity of each pipeline segment that
could affect a high consequence area.
(2) Verifying covered segments. An
operator must verify the risk factors
used in identifying pipeline segments
that could affect a high consequence
area on at least an annual basis not to
exceed 15-months (Appendix C
provides additional guidance on factors
that can influence whether a pipeline
segment could affect a high
consequence area). If a change in
circumstance indicates that the prior
consideration of a risk factor is no
longer valid or that new risk factors
should be considered, an operator must
perform a new integrity analysis and
evaluation to establish the endpoints of
any previously-identified covered
segments. The integrity analysis and
evaluation must include consideration
of the results of any baseline and
periodic integrity assessments (see
paragraphs (b), (c), (d), and (e) of this
section), information analyses (see
paragraph (g) of this section), and
decisions about remediation and
preventive and mitigative actions (see
paragraphs (h) and (i) of this section).
An operator must complete the first
annual verification under this paragraph
no later than [date one year after
effective date of the final rule].
*
*
*
*
*
(n) Accommodation of internal
inspection devices—(1) Scope. This
paragraph does not apply to any
pipeline facilities listed in § 195.120(b).
(2) General. An operator must ensure
that each pipeline is modified to
accommodate the passage of an
instrumented internal inspection device
by [date 20 years from effective date of
the final rule].
(3) Newly-identified areas. If a
pipeline could affect a newly-identified
high consequence area (see paragraph
(d)(3) of this section) after [date 20 years
from effective date of the final rule], an
operator must modify the pipeline to
accommodate the passage of an
instrumented internal inspection device
within five years of the date of
identification or before performing the
baseline assessment, whichever is
sooner.
(4) Lack of accommodation. An
operator may file a petition under
§ 190.9 of this chapter for a finding that
E:\FR\FM\13OCP3.SGM
13OCP3
Federal Register / Vol. 80, No. 197 / Tuesday, October 13, 2015 / Proposed Rules
asabaliauskas on DSK5VPTVN1PROD with PROPOSALS
the basic construction (i.e. length,
diameter, operating pressure, or
location) of a pipeline cannot be
modified to accommodate the passage of
an internal inspection device.
(5) Emergencies. An operator may file
a petition under § 190.9 of this chapter
for a finding that a pipeline cannot be
modified to accommodate the passage of
VerDate Sep<11>2014
21:35 Oct 09, 2015
Jkt 238001
an instrumented internal inspection
device as a result of an emergency. Such
a petition must be filed within 30 days
after discovering the emergency. If the
petition is denied, the operator must
modify the pipeline to allow the passage
of an instrumented internal inspection
device within one year after the date of
the notice of the denial.
PO 00000
Frm 00035
Fmt 4701
Sfmt 9990
61643
Issued in Washington, DC on October 1,
2015, under authority delegated in 49 CFR
Part 1.97(a).
Linda Daugherty,
Deputy Associate Administrator for Field
Operations.
[FR Doc. 2015–25359 Filed 10–9–15; 8:45 am]
BILLING CODE 4910–60–P
E:\FR\FM\13OCP3.SGM
13OCP3
Agencies
[Federal Register Volume 80, Number 197 (Tuesday, October 13, 2015)]
[Proposed Rules]
[Pages 61609-61643]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-25359]
[[Page 61609]]
Vol. 80
Tuesday,
No. 197
October 13, 2015
Part III
Department of Transportation
-----------------------------------------------------------------------
Pipeline and Hazardous Materials Safety Administration
-----------------------------------------------------------------------
49 CFR Part 195
Pipeline Safety: Safety of Hazardous Liquid Pipelines; Proposed Rule
Federal Register / Vol. 80 , No. 197 / Tuesday, October 13, 2015 /
Proposed Rules
[[Page 61610]]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials Safety Administration
49 CFR Part 195
[Docket No. PHMSA-2010-0229]
RIN 2137-AE66
Pipeline Safety: Safety of Hazardous Liquid Pipelines
AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA),
Department of Transportation (DOT).
ACTION: Notice of proposed rulemaking.
-----------------------------------------------------------------------
SUMMARY: In recent years, there have been significant hazardous liquid
pipeline accidents, most notably the 2010 crude oil spill near
Marshall, Michigan, during which almost one million gallons of crude
oil were spilled into the Kalamazoo River. In response to accident
investigation findings, incident report data and trends, and
stakeholder input, PHMSA published an Advance Notice of Proposed
Rulemaking (ANPRM) in the Federal Register on October 18, 2010. The
ANPRM solicited stakeholder and public input and comments on several
aspects of hazardous liquid pipeline regulations being considered for
revision or updating in order to address the lessons learned from the
Marshall, Michigan accident and other pipeline safety issues.
Subsequently, Congress enacted the Pipeline Safety, Regulatory
Certainty, and Job Creation Act that included several provisions that
are relevant to the regulation of hazardous liquid pipelines. Shortly
after the Pipeline Safety, Regulatory Certainty, and Job Creation Act
was passed, the National Transportation Safety Board (NTSB) issued its
accident investigation report on the Marshall, Michigan accident. In
it, NTSB made additional recommendations regarding the need to revise
and update hazardous liquid pipeline regulations.
In response to these mandates, recommendations, lessons learned,
and public input, PHMSA is proposing to make changes to the hazardous
liquid pipeline safety regulations. PHMSA is proposing these changes to
improve protection of the public, property, and the environment by
closing regulatory gaps where appropriate, and ensuring that operators
are increasing the detection and remediation of unsafe conditions, and
mitigating the adverse effects of pipeline failures.
DATES: Persons interested in submitting written comments on this NPRM
must do so by January 8, 2016. PHMSA will consider late filed comments
so far as practicable.
ADDRESSES: You may submit comments identified by the docket number
PHMSA-2010-0229 by any of the following methods:
Federal eRulemaking Portal: https://www.regulations.gov. Follow the
online instructions for submitting comments. Fax: 1-202-493-2251.
Mail: Hand Delivery: U.S. DOT Docket Management System, West
Building Ground Floor, Room W12-140, 1200 New Jersey Avenue SE.,
Washington, DC 20590-0001, between 9 a.m. and 5 p.m., Monday through
Friday, except federal holidays.
Instructions: If you submit your comments by mail, submit two
copies. To receive confirmation that PHMSA received your comments,
include a self-addressed stamped postcard.
Note: Comments are posted without changes or edits to https://www.regulations.gov, including any personal information provided.
There is a privacy statement published on https://www.regulations.gov.
FOR FURTHER INFORMATION CONTACT: Mike Israni, by telephone at 202-366-
4571, by fax at 202-366-4566, or by mail at U.S. DOT, PHMSA, 1200 New
Jersey Avenue SE., PHP-30, Washington, DC 20590-0001.
SUPPLEMENTARY INFORMATION:
Outline of this document:
I. Executive Summary
II. Background and NPRM Proposals
III. Analysis of Advance Notice of Proposed Rulemaking
A. Scope of Part 195 and Existing Regulatory Exceptions
B. Definition of High Consequence Area
C. Leak Detection Equipment and Emergency Flow Restricting
Devices
D. Valve Spacing
E. Repair Criteria Outside of High Consequence Areas
F. Stress Corrosion Cracking
IV. Section by Section Analysis
V. Regulatory Notices and Proposed Changes to Regulatory Text
I. Executive Summary
In recent years, there have been significant hazardous liquid
pipeline accidents, most notably the 2010 crude oil spill near
Marshall, Michigan, during which almost one million gallons of crude
oil were spilled into the Kalamazoo River. In response to accident
investigation findings, incident report data and trends, and
stakeholder input, PHMSA published an ANPRM in the Federal Register on
October 18, 2010, (75 FR 63774). The ANPRM solicited stakeholder and
public input and comments on several aspects of hazardous liquid
pipeline regulations being considered for revision or updating in order
to address the lessons learned from the Marshall, Michigan accident and
other pipeline safety issues.
Subsequently, Congress enacted the Pipeline Safety, Regulatory
Certainty, and Job Creation Act of 2011 (Pub. L. 112-90) (The Act).
That legislation included several provisions that are relevant to the
regulation of hazardous liquid pipelines. Shortly after the Act was
passed, NTSB issued its accident investigation report on the Marshall,
Michigan accident. In it, NTSB made additional recommendations
regarding the need to revise and update hazardous liquid pipeline
regulations. Specifically, the NTSB issued recommendations P-12-03 and
P-12-04 respectively, which addressed detection of pipeline cracks and
``discovery of condition''. The ``discovery of condition''
recommendation would require, in cases where a determination about
pipeline threats has not been obtained within 180 days following the
date of inspection, that pipeline operators notify the Pipeline and
Hazardous Materials Safety Administration and provide an expected date
when adequate information will become available.
The Government Accounting Office (GAO) also issued a recommendation
in 2012 concerning hazardous liquid and gas gathering pipelines.
Recommendation GAO-12-388, dated March 22, 2012, states ``To enhance
the safety of unregulated onshore hazardous liquid and gas gathering
pipelines, the Secretary of Transportation should direct the PHMSA
Administrator to collect data from operators of federally unregulated
onshore hazardous liquid and gas gathering pipelines, subsequent to an
analysis of the benefits and industry burdens associated with such data
collection''.
In response to these mandates, recommendations, lessons learned,
and public input, PHMSA is proposing to make certain changes to the
Hazardous Liquid Pipeline Safety Regulations. The first and second
proposals are to extend reporting requirements to all hazardous liquid
gravity and gathering lines. The collection of information about these
lines is authorized under the Pipeline Safety Laws, and the resulting
data will assist in determining whether the existing federal and state
regulations for these lines are adequate.
The third proposal is to require inspections of pipelines in areas
affected by extreme weather, natural disasters, and other similar
events. Such inspections will ensure that pipelines
[[Page 61611]]
are still capable of being safely operated after these events. The
fourth proposal is to require periodic inline integrity assessments of
hazardous liquid pipelines that are located outside of HCAs. HCA's are
already covered under the IM program requirements. These assessments
will provide critical information about the condition of these
pipelines, including the existence of internal and external corrosion
and deformation anomalies.
The fifth proposal is to require the use of leak detection systems
on hazardous liquid pipelines in all locations. The use of such systems
will help to mitigate the effects of hazardous liquid pipeline failures
that occur outside of HCAs. The sixth proposal is to modify the
provisions for making pipeline repairs. Additional conservatism will be
incorporated into the existing repair criteria and an adjusted schedule
will be established to provide greater uniformity. These criteria will
also be made applicable to all hazardous liquid pipelines, with an
extended timeframe for making repairs outside of HCAs.
The seventh proposal is to require that all pipelines subject to
the IM requirements be capable of accommodating inline inspection tools
within 20 years, unless the basic construction of a pipeline cannot be
modified to permit that accommodation. Inline inspection tools are an
effective means of assessing the integrity of a pipeline and broadening
their use will improve the detection of anomalies and prevent or
mitigate future accidents in high-risk areas. Finally, other
regulations will be clarified to improve certainty and compliance.
PHMSA estimates that 421 hazardous liquid operators may incur costs to
comply with the proposed rule. The estimated annual costs for the
different requirements range from approximately $1,000 to $16.7
million, with aggregate costs of approximately $22.4 million. These
wide ranges exist because the requirements vary widely. For example,
some requirements apply only to pipelines within HCAs, some only to
those outside HCAs, and some to both; other requirements apply only to
onshore pipelines, and others to both on- and offshore; the length of
pipeline, and the number of operators affected both vary for the
different requirements. These proposals are designed to mitigate or
prevent some number of hazardous liquid pipeline incidents resulting in
annualized benefits estimated between approximately $3.5 and $17.7
million, depending on the requirement. Factors such as increased
safety, public confidence that all pipelines are regulated, quicker
discovery of leaks and mitigation of environmental damages, and better
risk management are considered in this analysis. The dollar value of
fatalities, injuries, and property damages due to pipeline incidents
are societal costs and their prevention represents potential benefits.
The changes proposed in this Notice of Proposed Rulemaking (NPRM) are
expected to enhance overall pipeline safety and protection of the
environment.
II. Background and NPRM Proposals
Congress established the current framework for regulating the
safety of hazardous liquid pipelines in the Hazardous Liquid Pipeline
Safety Act (HLPSA) of 1979 (Pub. L. 96-129). Like its predecessor, the
Natural Gas Pipeline Safety Act (NGPSA) of 1968 (Pub. L. 90-481), the
HLPSA provides the Secretary of Transportation (Secretary) with the
authority to prescribe minimum federal safety standards for hazardous
liquid pipeline facilities. That authority, as amended in subsequent
reauthorizations, is currently codified in the Pipeline Safety Laws (49
U.S.C. 60101 et seq.).
PHMSA is the agency within DOT that administers the Pipeline Safety
Laws. PHMSA has issued a set of comprehensive safety standards for the
design, construction, testing, operation, and maintenance of hazardous
liquid pipelines. Those standards are codified in the Hazardous Liquid
Pipeline Safety Regulations (49 CFR part 195).
Part 195 applies broadly to the transportation of hazardous liquids
or carbon dioxide by pipeline, including on the Outer Continental
Shelf, with certain exceptions set forth by statute or regulation.
Performance-based safety standards are generally favored (i.e., a
particular objective is specified, but the method of achieving that
objective is not). Risk management principles play a critical role in
the IM requirements for HCA's.
PHMSA exercises primary regulatory authority over interstate
hazardous liquid pipelines, and the owners and operators of those
facilities must comply with safety standards in part 195. The states
may submit a certification to regulate the safety standards and
practices for intrastate pipelines. States certified to regulate their
intrastate lines can also enter into agreements with PHMSA to serve as
an agent for inspecting interstate facilities.
Most state pipeline safety programs are administered by public
utility commissions. These state authorities must adopt the Pipeline
Safety Regulations as part of a certification or agreement, but can
establish more stringent safety standards for those intrastate pipeline
facilities that they have responsibility to regulate. PHMSA cannot
regulate the safety standards or practices for an intrastate pipeline
facility if a state has a current certification to regulate such
facilities.
Congress recently enacted the Pipeline Safety, Regulatory
Certainty, and Job Creation Act of 2011 (Pub. L. 112-90) (The Act).
That legislation included several provisions that are relevant to the
regulation of hazardous liquid pipelines. As part of the rulemaking
process, PHMSA presented proposed changes in response to this Act in an
ANPRM published in the Federal Register on October 18, 2010, (75 FR
63774). This NPRM will, in the paragraphs that follow, describe each of
the proposals PHMSA will make along with a statement of need for each
and an explanation of how each of these proposals improve the pipeline
safety regulations.
Extend Certain Reporting Requirements to All Gravity and Rural
Hazardous Liquid Gathering Lines
Gravity lines; pipelines that carry product by means of gravity,
are currently exempt from PHMSA regulations. Many gravity lines are
short and within tank farms or other pipeline facilities; however, some
gravity lines are longer and are capable of building up large amounts
of pressure. PHMSA is aware of gravity lines that traverse long
distances with significant elevation changes which could have
significant consequences in the event of a release.
In order for PHMSA to effectively analyze safety performance and
pipeline risk of gravity lines, PHMSA needs basic data about those
pipelines. The agency has the statutory authority to gather data for
all gravity lines (49 U.S.C. 60117(b)), and that authority was not
affected by any of the provisions in the Pipeline Safety Act of 2011.
Accordingly, PHMSA is proposing to add 49 CFR 195.1(a)(5) to require
that the operators of all gravity lines comply with requirements for
submitting annual, safety-related condition, and incident reports.
PHMSA estimates that, at most, five hazardous liquid pipeline operators
will be affected. Based on comments from API-AOPL to the ANPRM, 3
operators have approximately 17 miles of gravity fed pipelines. PHMSA
estimated that proportionally 5 operators would have 28 miles of
gravity-fed pipelines.
PHMSA is also proposing to extend the reporting requirements of
part 195 to all hazardous liquid gathering lines. According to the
legislative history, Congress originally opposed any
[[Page 61612]]
regulation of rural gathering lines in the Hazardous Liquid Pipeline
Safety Act of 1979 (Pub. L. 96-129) for policy reasons (i.e., those
lines did not present a significant risk to public safety to justify
federal regulation based on the data available at that time). See S.
REP. NO. 96-182 (May 15, 1979), reprinted in 1979 U.S.C.C.A.N. 1971,
1972. However, Congress eventually relaxed that prohibition in the
Pipeline Safety Act of 1992 (Pub. L. 102-508) and authorized the
issuance of safety standards for regulated rural gathering lines based
on a consideration of certain factors and subject to certain
exclusions. When PHMSA adopted the current requirements for regulated
rural gathering lines, the agency made certain policy judgments in
implementing those statutory provisions based on the information
available at that time.
Recent data indicates, however, that PHMSA regulates less than
4,000 miles of the approximately 30,000 to 40,000 miles of onshore
hazardous liquid gathering lines in the United States. That means that
as much as 90 percent of the onshore gathering line mileage is not
currently subject to any minimum federal pipeline safety standards. The
NTSB has also raised concerns about the safety of hazardous liquid
gathering lines in the Gulf of Mexico and its inlets, which are only
subject to certain inspection and reburial requirements.\1\
---------------------------------------------------------------------------
\1\ https://app.ntsb.gov/news/2010/100624b.html.
---------------------------------------------------------------------------
Congress also ordered the review of existing state and federal
regulations for hazardous liquid gathering lines in the Pipeline Safety
Act of 2011, to prepare a report on whether any of the existing
exceptions for these lines should be modified or repealed, and to
determine whether hazardous liquid gathering lines located offshore or
in the inlets of the Gulf of Mexico should be subjected to the same
safety standards as all other hazardous liquid gathering lines. Based
on the study titled ``Review of Existing Federal and State Regulations
for Gas and Hazardous Liquid Gathering Lines,'' \2\ that was performed
by the Oak Ridge National Laboratory and published on May 8, 2015,
PHMSA is proposing additional regulations to ensure the safety of
hazardous liquid gathering lines.
---------------------------------------------------------------------------
\2\ https://www.phmsa.dot.gov/pv_obj_cache/pv_obj_id_7B2B80704EBC3EBABDB5B9F701F184E0854F3600/filename/report_to_congress_on_gathering_lines.pdf.
---------------------------------------------------------------------------
In order for PHMSA to effectively analyze safety performance and
pipeline risk of gathering lines, we need basic data about those
pipelines. PHMSA has statutory authority to gather data for all
gathering lines (49 U.S.C. 60117(b)), and that authority was not
affected by any of the provisions in the Pipeline Safety Act of 2011.
Accordingly, PHMSA is proposing to add Sec. 195.1(a)(5) to require
that the operators of all gathering lines (whether onshore, offshore,
regulated, or unregulated) comply with requirements for submitting
annual, safety-related condition, and incident reports.
In the ANPRM, PHMSA asked whether the agency should repeal or
modify any of the exceptions for hazardous liquid gathering lines.
Section 195.1(a)(4)(ii) states that part 195 applies to a ``regulated
rural gathering line as provided in Sec. 195.11.'' PHMSA adopted a
regulation in a June 2008 final rule (73 FR 31634) that prescribed
certain safety requirements for regulated rural gathering lines (i.e.,
the filing of accident, safety-related condition and annual reports;
establishing the maximum operating pressure according to Sec. 195.406;
installing line markers; and establishing programs for public
awareness, damage prevention, corrosion control, and operator
qualification of personnel).
The June 2008 final rule did not establish safety standards for all
rural hazardous liquid gathering lines. Some of those lines cannot be
regulated by statute (i.e., 49 U.S.C. 60101(b)(2)(B) states that ``the
definition of `regulated gathering line' for hazardous liquid may not
include a crude oil gathering line that has a nominal diameter of not
more than 6 inches, is operated at low pressure, and is located in a
rural area that is not unusually sensitive to environmental damage.'')
and Congress did not remove this exemption in the 2011 Act. However,
the 2011 Act did require that PHMSA review whether currently
unregulated gathering lines should be made subject to the same
regulations as other pipelines.
Require Inspections of Pipelines in Areas Affected by Extreme Weather,
Natural Disasters, and Other Similar Events
In July 2011 a pipeline failure occurred near Laurel, Montana,
causing the release of an estimated 1,000 barrels of crude oil into the
Yellowstone River. That area had experienced extensive flooding in the
weeks leading up to the failure, and the operator has estimated the
cleanup costs at approximately $135 million. An instance of flooding
also occurred in 1994 in the State of Texas, leading to the failure of
eight pipelines and the release of more than 35,000 barrels of
hazardous liquids into the San Jacinto River. Some of that released
product also ignited, causing minor burns and other injuries to nearly
550 people according to the NTSB. As the agency has noted in a series
of advisory bulletins, hurricanes are capable of causing extensive
damage to both offshore and inland pipelines (e.g., Hurricane Ivan,
September 23, 2004 (69 FR 57135); Hurricane Katrina, September 7, 2004
(70 FR 53272); Hurricane Rita, September 1, 2011 (76 FR 54531)).
These events demonstrate the importance of ensuring that our
nation's waterways are adequately protected in the event of a natural
disaster or extreme weather. PHMSA is aware that responsible operators
might do such inspections; however, because it is not a requirement,
some operators do not. Therefore, PHMSA is proposing to require that
operators perform an additional inspection within 72 hours after the
cessation of an extreme weather event such as a hurricane or flood, an
earthquake, a natural disaster, or other similar event.
Specifically, under this proposal an operator must inspect all
potentially affected pipeline facilities post extreme weather event to
ensure that no conditions exist that could adversely affect the safe
operation of that pipeline. The operator would be required to consider
the nature of the event and the physical characteristics, operating
conditions, location, and prior history of the affected pipeline in
determining the appropriate method for performing the inspection
required. The inspection must occur within 72 hours after the cessation
of the event, or as soon as the affected area can be safely accessed by
the personnel and equipment required to perform the inspection. PHMSA
has found that 72 hours is reasonable and achievable in most cases. If
an adverse condition is found, the operator must take appropriate
remedial action to ensure the safe operation of a pipeline based on the
information obtained as a result of performing the inspection. Such
actions might include, but are not limited to:
Reducing the operating pressure or shutting down the
pipeline;
Modifying, repairing, or replacing any damaged pipeline
facilities;
Preventing, mitigating, or eliminating any unsafe
conditions in the pipeline right-of-ways (ROWS);
Performing additional patrols, surveys, tests, or
inspections;
Implementing emergency response activities with federal,
state, or local personnel; and
Notifying affected communities of the steps that can be
taken to ensure public safety.
This proposal is based on the experience of PHMSA and is expected
to increase the likelihood that safety
[[Page 61613]]
conditions will be found earlier and responded to more quickly. PHMSA
invites comment on this and other proposals in this NPRM. In regard to
this proposal, PHMSA has particular interest in additional comments
concerning how operators currently respond to these events, what type
of events are encountered and if a 72 hour response time is reasonable.
Require Periodic Assessments of Pipelines That Are Not Already Covered
Under the IM Program Requirements
PHMSA is proposing to require assessments for pipeline segments in
non-HCAs. PHMSA believes that expanded assessment of non-HCA pipeline
segments areas will provide operators with valuable information they
may not have collected if regulations were not in place such a
requirement would ensure prompt detection and remediation of corrosion
and other deformation anomalies in all locations, not just HCAs.
Specifically, the proposed Sec. 195.416 would require operators to
assess non-HCA (non-IM) pipeline segments with an inline inspection
(ILI) tool at least once every 10 years. PHMSA needs operators to
complete assessments in HCAs followed by assessments in non-HCAs. Other
assessment methods could be used if an operator provides the Office of
Pipeline Safety (OPS) with prior written notice that a pipeline is not
capable of accommodating an ILI tool. The written notice provided to
PHMSA must include a technical demonstration of why the pipeline is not
capable of accommodating an ILI tool and what alternative technology
the operator proposes to use. The operator must also detail how the
alternative technology would provide a substantially equivalent
understanding of the pipeline's condition in light of the threats that
could affect its safe operation. Such alternative technologies would
include hydrostatic pressure testing or appropriate forms of direct
assessment.
The individuals who review the results of these periodic
assessments would need to be qualified by knowledge, training, and
experience and would be required to consider any uncertainty in the
results obtained, including ILI tool tolerance, when determining
whether any conditions could adversely affect the safe operation of a
pipeline. Such determinations would have to be made promptly, but no
later than 180 days after an inspection, unless the operator
demonstrates that the 180-day deadline is impracticable.
Operators would be required to comply with the other provisions in
part 195 in implementing the requirements in Sec. 195.416. That
includes having appropriate provisions for performing these periodic
assessments and any resulting repairs in an operator's procedural
manual (see Sec. 195.402), adhering to the recordkeeping provisions
for inspections, test, and repairs (see Sec. 195.404), and taking
appropriate remedial action under Sec. 195.422, as discussed below.
Section 195.11 would also be amended to subject regulated onshore
gathering lines to the periodic assessment requirement.
PHMSA believes by proposing the above amendment to the existing
pipeline safety regulations, safety will be increased for all pipelines
both in and out of HCAs. Such a requirement would ensure operators
obtain information necessary for prompt detection and remediation of
corrosion and other deformation anomalies in all locations, not just
HCAs. Currently, operators have indicated that they are performing ILI
assessments on a large majority of their pipelines even though no
regulation requires them to do so outside of HCAs. PHMSA wants to
ensure that current assessment rates continue and expand to those areas
not voluntarily assessed. Of the many methods to assess, PHMSA has
found that ILI in many cases is the most efficient and effective. PHMSA
considered alternatives to its proposal that would likely have lower
overall costs and benefits, but potentially higher net benefits. For
instance, PHMSA considered limiting the proposed expansion of certain
IM requirements to those pipelines where a spill could affect a
building or occupied site such as a playground, or highway. Under this
alternative, pipelines in a location where a spill could not affect a
building, occupied site, or highway would not be subject to these new
requirements. However, this alternative would offer less protection to
the natural environment, including sensitive and protected habitats and
species. PHMSA also considered alternative assessment intervals to the
proposed 10 year interval, such as a 15- or 20-year interval. However,
substantial changes to pipeline integrity can occur in a short
timeframe. PHMSA declined to propose these alternatives because they
would provide fewer benefits than the proposed approach. More
specifically, liquid spills, even in remote areas, can result in
environmental damage necessitating clean up and incurring restoration
costs and lost use and nonuse values. If pipe is not assessed and
repaired in accordance with this proposal, liquid spills are likely to
occur.
Also, a longer interval between assessments would increase risks of
integrity-related failure compared to PHMSA's proposal. PHMSA was
unable to quantify the benefits and costs of these alternatives due to
limitations in available information, such as the amount of unassessed
pipe where a spill could not affect a building, occupied site, or
highway; the environmental impact of spills from such pipe; and the
incremental reduction in benefit between 10-year and alternative
interval periods. PHMSA seeks public comments on these alternatives,
and the regulatory impact analysis contains specific questions for
public comment on quantifying these alternatives.
Modify the IM Repair Criteria and Apply Those Same Criteria to Any
Pipeline Where the Operator Has Identified Repair Conditions
Inspection experience indicates a weakness in current repair
criteria. Specifically, the current repair criteria in non-HCAs
(immediate and reasonable time) does not specify anomaly or repair time
frames. It is left entirely at the operator's discretion. Therefore,
PHMSA is proposing to modify the IM pipeline repair criteria and to
apply the criteria to non-IM pipeline repairs. Specifically, the
criteria in Sec. 195.452(h) for IM repairs would be modified to:
Categorize bottom-side dents with stress risers as
immediate repair conditions;
Require immediate repairs whenever the calculated burst
pressure is less than 1.1 times maximum operating pressure;
Eliminate the 60-day and 180-day repair categories; and
Establish a new, consolidated 270-day repair category.
PHMSA is also proposing to amend the requirements in Sec. 195.422
for performing non-IM repairs by:
Applying the criteria in the immediate repair category in
Sec. 195.452(h); and
Establishing an 18-month repair category for hazardous
liquid pipelines that are not subject to IM requirements.
PHMSA believes that these changes will ensure that immediate action
is taken to remediate anomalies that present an imminent threat to the
integrity of hazardous liquid pipelines in all locations. Moreover,
many anomalies that would not qualify as immediate repairs under the
current criteria will meet that requirement as a result of the
additional conservatism
[[Page 61614]]
that will be incorporated into the burst pressure calculations. The new
time frames for performing non-immediate repairs will also allow
operators to remediate those conditions in a timely manner while
allocating resources to those areas that present a higher risk of harm
to the public, property, and the environment. The existing requirements
in Sec. 195.422 would also be modified to include a general
requirement for performing all other repairs within a reasonable time.
A proposed amendment to Sec. 195.11 would extend these new pipeline
remediation requirements to regulated onshore gathering lines.
As a result of these changes, PHMSA would modify the existing
general requirements for pipeline repairs in Sec. 195.401(b).
Paragraph (b)(1) would be modified to reference the new timeframes in
Sec. 195.422(d) and (e) for remediating conditions that could
adversely affect the safe operation of a pipeline segment not subject
to the IM requirements in Sec. 195.452. The requirements in paragraph
(b)(2) for IM repairs under Sec. 195.452(h) will be retained without
change. A new paragraph (b)(3) will be added, however, to require
operators to consider the risk to people, property, and the environment
in prioritizing the remediation of any condition that could adversely
affect the safe operation of a pipeline system, including those covered
by the timeframes specified in Sec. Sec. 195.422(d) and (e) and
195.452(h).
Expand the Use of Leak Detection Systems for All Hazardous Liquid
Pipelines
PHMSA is proposing to amend Sec. 195.134 to require that all new
hazardous liquid pipelines be designed to include leak detection
systems. Recent pipeline accidents, including a pair of related
failures that occurred in 2010 on a crude oil pipeline in Salt Lake
City, Utah, corroborate the significance of having an adequate means
for identifying leaks in all locations. PHMSA, aware of the
significance of leak detection, held two recent workshops in Rockville,
Maryland on March 27-28 of 2012. These workshops sought comment from
the public concerning many of the issues raised in the 2010 ANPRM,
including leak detection expansion. Both workshops were well attended
and PHMSA received valuable input from stakeholders.
Currently, part 195 contains mandatory leak detection requirements
for hazardous liquid pipelines that could affect an HCA.
Congress included additional requirements for leak detection
systems in section 8 of the Pipeline Safety Act of 2011. That
legislation requires the Secretary to submit a report to Congress,
within 1-year of the enactment date, on the use of leak detection
systems, including an analysis of the technical limitations and the
practicability, safety benefits, and adverse consequence of
establishing additional standards for the use of those systems. To
provide Congress with an opportunity to review that report, the
Secretary is prohibited from issuing any final leak detection
regulations for a specified time period (i.e., 2 years from the date of
the enactment of the Pipeline Safety Act of 2011, or 1-year after the
submission of the leak detection report to Congress, whichever is
earlier), unless a condition exists that poses a risk to public safety,
property, or the environment, or is an imminent hazard, and the
issuance of such regulations would address that risk or hazard. Other
provisions in part 195 help to detect and mitigate the effects of
pipeline leaks, including the Right of Way (ROW).
In addition to modifying Sec. 195.444 to require a means for
detecting leaks on all portions of a hazardous liquid pipeline system,
PHMSA is proposing that operators be required to have an evaluation
performed to determine what kinds of systems must be installed to
adequately protect the public, property, and the environment. The
factors that must be considered in performing that evaluation would
include the characteristics and history of the affected pipeline, the
capabilities of the available leak detection systems, and the location
of emergency response personnel. A proposed amendment to Sec. 195.11
would extend these new leak detection requirements to regulated onshore
gathering lines. PHMSA is retaining and is not proposing any
modification to the requirement in Sec. Sec. 195.134 and 195.444 that
each new computational leak detection system comply with the applicable
requirements in the API RP 1130 standard.
PHMSA does not propose to make any additional changes to the
regulations concerning specific leak detection requirements at this
time. PHMSA will be studying this issue further and may make proposals
concerning this topic in a later rulemaking. PHMSA recently publicly
provided the results of the 2012 Keifner and Associates study of leak
detection systems in the pipeline industry, including the current state
of technology.
Increase the Use of Inline Inspection Tools
PHMSA is proposing to require that all hazardous liquid pipelines
in HCA's and areas that could affect an HCA be made capable of
accommodating ILI tools within 20 years, unless the basic construction
of a pipeline will not accommodate the passage of such a device.
The current requirements for the passage of ILI devices in
hazardous liquid pipelines are prescribed in Sec. 195.120, which
require that new and replaced pipelines are designed to accommodate
inline inspection tools. The basis for these requirements was a 1988
law that addressed the Secretary's authority with regard to requiring
the accommodation of ILI tools. This law required the Secretary to
establish minimum federal safety standards for the use of ILI tools,
but only in newly constructed and replaced hazardous liquid pipelines
(Pub. L. 100-561).
In 1996, Congress passed another law further expanding the
Secretary's authority to require pipeline operators to have systems
that can accommodate ILI tools. In particular, Congress provided
additional authority for the Secretary to require the modification of
existing pipelines whose basic construction would accommodate an ILI
tool to accommodate such a tool and permit internal inspection (Pub. L.
104-304).
As the Research and Special Programs Administration (RSPA), (a
predecessor agency of PHMSA) explained in the final rule April 12, 1994
(59 FR 17275) that promulgated Sec. 195.120, ``[t]he clear intent of
th[at] congressional mandate [wa]s to improve an existing pipeline's
piggability,'' and to ``require[] the gradual elimination of
restrictions in existing hazardous liquid and carbon dioxide lines in a
manner that will eventually make the lines piggable.'' April 2, 1994,
(59 FR 17279). RSPA also noted that Congress amended the 1988 law in
the Pipeline Safety Act of 1992 (Pub. L. 102-508) to require the
periodic internal inspection of hazardous liquid pipelines, including
with ILI tools in appropriate circumstances April 2, 1994, (59 FR
17275). RSPA established requirements for the use of ILI tools in
pipelines that could affect HCAs in the December 2000 IM final rule
December 1, 2000, (65 FR 75378).
Section 60102(f)(1)(B) of the Pipeline Safety Laws allows the
requirements for the passage of ILI tools to be extended to existing
hazardous liquid pipeline facilities, provided the basic construction
of those facilities can be modified to permit the use of smart pigs.
[[Page 61615]]
The current requirements apply only to new hazardous liquid pipelines
and to line sections where the line pipe, valves, fittings, or other
components are replaced. Exceptions are also provided for certain kinds
of pipeline facilities, including manifolds, piping at stations and
storage facilities, piping of a size that cannot be inspected with a
commercially available ILI tool, and smaller diameter offshore
pipelines.
PHMSA is proposing to use the authority provided in section
60102(f)(1)(B) to further facilitate the ``gradual elimination'' of
pipelines that are not capable of accommodating smart pigs. PHMSA would
limit the circumstances where a pipeline can be constructed without
being able to accommodate a smart pig. Under the current regulation, an
operator can petition the PHMSA Administrator for such an allowance for
reasons of impracticability, emergencies, construction time
constraints, and other unforeseen construction problems. PHMSA believes
that an exception should still be available for emergencies and where
the basic construction of a pipeline makes that accommodation
impracticable, but that the other, less urgent circumstances listed in
the regulation are no longer appropriate. Accordingly, the allowances
for construction-related time constraints and problems would be
repealed.
Modern ILI tools are capable of providing a relatively complete
examination of the entire length of a pipeline, including information
about threats that cannot always be identified using other assessment
methods. ILI tools also provide superior information about incipient
flaws (i.e., flaws that are not yet a threat to pipeline integrity, but
that could become so in the future), thereby allowing these conditions
to be monitored over consecutive inspections and remediated before a
pipeline failure occurs. Hydrostatic pressure testing, another well-
recognized method, reveals flaws (such as wall loss and cracking flaws)
that cause pipe failures at pressures that exceed actual operating
conditions. Similarly, external corrosion direct assessment (ECDA) can
identify instances where coating damage may be affecting pipeline
integrity, but additional activities, including follow-up excavations
and direct examinations, must be performed to verify the extent of that
threat. ECDA also provides less information about the internal
condition of a pipe than ILI tools.
As with new pipelines, operators will be allowed to petition the
PHMSA Administrator for a finding that the basic construction, (i.e.,
terrain or location, of a pipeline or an emergency) will not permit the
accommodation of a smart pig.
Clarify Other Requirements
PHMSA is also proposing several other clarifying changes to the
regulations that are intended to improve compliance and enforcement.
First, PHMSA is proposing to revise paragraph (b)(1) of Sec. 195.452
to correct an inconsistency in the current regulations. Currently,
Sec. 195.452(b)(2) requires that segments of new pipelines that could
affect HCAs be identified before the pipeline begins operations and
Sec. 195.452(d)(1) requires that baseline assessments for covered
segments of new pipelines be completed by the date the pipeline begins
operation. However, Sec. 195.452(b)(1) does not require an operator to
draft its IM program for a new pipeline until one-year after the
pipeline begins operation. These provisions are inconsistent as the
identification could affect segments, and performance of baseline
assessments are elements of the written IM program. PHMSA would amend
the table in (b)(1) to resolve this inconsistency by eliminating the
one-year compliance deadline for Category 3 pipelines. An operator of a
new pipeline would be required to develop its written IM program before
the pipeline begins operation.
A decade's worth of IM inspection experience has shown that many
operators are performing inadequate information analyses (e.g., they
are collecting information, but not affording it sufficient
consideration). Integration is one of the most important aspects of the
IM program because it is used in identifying interactions between
threats or conditions affecting the pipeline and in setting priorities
for dealing with identified issues. For example, evidence of potential
corrosion in an area with foreign line crossings and recent aerial
patrol indications of excavation activity could indicate a priority
need for further investigation. Consideration of each of these factors
individually would not reveal any need for priority attention. PHMSA is
concerned that a major benefit to pipeline safety intended in the
initial rule is not being realized because of inadequate information
analyses.
For this reason, PHMSA is proposing to add additional specificity
to paragraph (g) by establishing a number of pipeline attributes that
must be included in these analyses and to require explicitly that
operators integrate analyzed information. PHMSA is also proposing that
operators consider explicitly any spatial relationships among anomalous
information. PHMSA supports the use of computer-based geographic
information systems (GIS) to record this information. GIS systems can
be beneficial in identifying spatial relationships, but analysis is
required to identify where these relationships could result in
situations adverse to pipeline integrity.
Second, PHMSA is proposing that operators verify their segment
identification annually by determining whether factors considered in
their analysis have changed. Section 195.452(b) currently requires that
operators identify each segment of their pipeline that could affect an
HCA in the event of a release but there is no explicit requirement that
operators assure that their identification of covered segments remains
current. As time goes by, the likelihood increases that factors
considered in the original identification of covered segments may have
changed. PHMSA believes that operators should periodically re-visit
their initial analyses to determine whether they need to be updated.
New HCAs may be identified. Construction activities or erosion near the
pipeline could change local topography in a way that could cause
product released in an accident to travel further than initially
analyzed. Changes in agricultural land use could also affect an
operator's analysis of the distance released product could be expected
to travel. Changes in the deployment of emergency response personnel
could increase the time required to respond to a release and result in
a larger area being affected by a potential release if the original
segment identification relied on emergency response to limit the
transport of released product.
The change that PHMSA is proposing would not require that operators
re-perform their segment analyses. Rather, it would require operators
to identify the factors considered in their original analyses,
determine whether those factors have changed, and consider whether any
such change would be likely to affect the results of the original
segment identification. If so, the operator would be required to
perform a new analysis to validate or change the endpoints of the
segments affected by the change.
Third, PHMSA is proposing to clarify, through the use of an
explicit reference that the IM requirements apply to portions of
``pipelines'' other than line pipe. Unlike integrity assessments for
line pipe, Sec. 195.452 does not include explicit deadlines for
completing the analyses of other facilities within the definition of
``pipeline'' or for implementing actions in response to those analyses.
Through IM inspections,
[[Page 61616]]
PHMSA has learned that some operators have not completed analyses of
their non-pipe facilities such as pump stations and breakout tanks and
have not implemented appropriate protective and mitigative measures.
Section 29 of the Pipeline Safety, Regulatory Certainty, and Job
Creation Act of 2011 states that ``[i]n identifying and evaluating all
potential threats to each pipeline segment pursuant to parts 192 and
195 of title 49, Code of Federal Regulations, an operator of a pipeline
facility shall consider the seismicity of the area.'' While seismicity
is already mentioned at several points in the IM program guidance
provided in Appendix C of part 195, PHMSA is proposing to further
comply with Congress's directive by including an explicit reference to
seismicity in the list of risk factors that must be considered in
establishing assessment schedules (Sec. 195.452(e)), performing
information analyses (Sec. 195.452(g)), and implementing preventive
and mitigative measures (Sec. 195.452(i)) under the IM requirements.
III. Analysis of Advance Notice of Proposed Rulemaking
On October 18, 2010, (75 FR 63774), PHMSA published an ANPRM asking
the public to comment on several proposed changes to part 195. The
ANPRM sought comments on:
Scope of part 195 and existing regulatory exceptions;
Criteria for designation of HCAs;
Leak detection and emergency flow restricting devices;
Valve spacing;
Repair criteria outside of HCAs; and
Stress corrosion cracking.
The ANPRM may be viewed at https://www.regulations.gov by searching for
Docket ID PHMSA-2010-0229.
Twenty-one organizations and individuals submitted comments in
response to the ANPRM. The individual docket item numbers are listed
for each comment.
Associations representing pipeline operators (trade
associations)
[cir] American Petroleum Institute--Association of Oil Pipelines
(API-AOPL) (PHMSA-2010-0229-0030)
[cir] Independent Petroleum Association of America (IPAA) (PHMSA-
2010- 0229-0024)
[cir] Canadian Energy Pipeline Association (CEPA) (PHMSA-2010-0229-
0008)
[cir] Oklahoma Independent Petroleum Association (OIPA) (PHMSA-
2010- 0229-0018)
[cir] Texas Pipeline Association (TPA) (PHMSA-2010-0229-0011)
[cir] Louisiana Midcontinent Oil & Gas Association (LMOGA) (PHMSA-
2010-0229-0018)
[cir] Texas Oil & Gas Association (TxOGA) (PHMSA-2010-0229-0022)
Transmission and Distribution Pipeline Companies
[cir] TransCanada Keystone (PHMSA-2010-0229-0027)
Government/Municipalities
[cir] Defense Logistics Agency (DLA) (PHMSA-2010-0229-0016)
[cir] Metro Area Water Utility Commission (MAWUC) (PHMSA-2010-0229-
0031)
[cir] North Slope Borough (NSB) (PHMSA-2010-0229-0012)
Pipeline Safety Regulators
[cir] National Association of Pipeline Safety Representatives
(NAPSR) (PHMSA-2010-0229-0032)
Citizens' Groups
[cir] Pipeline Safety Trust (PST) (PHMSA-2010-0229-0014)
[cir] Cook Inlet Regional Citizens Advisory Council (CRAC)) (PHMSA-
2010-0229-0019)
[cir] The Wilderness Society (TWS) (PHMSA-2010-0229-0025)
[cir] National Resources Defense Council et al. (NRDC) (PHMSA-2010-
0229-0021)
[cir] Alaska Wilderness League et al. (AKW) (PHMSA-2010-0229-0026)
Citizens
[cir] Patrick Coyle (PHMSA-2010-0229-0002)
[cir] Marian J. Stec (PHMSA-2010-0229-0007)
[cir] Pamela A. Miller (PHMSA-2010-0229-0013)
[cir] Anonymous (PHMSA-2010-0229-0005) (The anonymous comment dealt
with quality of drinking water and release permits under the Clean
Water Act.
These topics are beyond the scope of PHMSA's jurisdiction and are not
discussed further).
Comments are reviewed in the order the ANPRM presented questions
for comment. PHMSA responses to the comments follow.
A. Scope of Part 195 and Existing Regulatory Exceptions
Comments
API-AOPL, LMOGA, TxOGA, and TransCanada Keystone expressed support
for the gravity line exception. These commenters stated that gravity
lines are short, pose little risk, and are usually located within other
regulated facilities, such as tank farms. NAPSR did not support a
complete repeal of this exception, suggesting there was no data to
support such an action. NAPSR did suggest that the exception should not
apply to ethanol pipelines, which are very susceptible to internal
corrosion.
MAWUC indicated that gravity lines in HCAs should be regulated
because of the sensitivity of these areas. MAWUC further stated that
these lines (and other rural onshore gathering lines) contain
contaminants that are not present in products carried by other
pipelines, that these contaminants are dangerous to pipeline workers,
and that the impact of releases from these pipelines on the environment
is the same as releases from regulated pipelines.
Response
PHMSA does not, at this time, intend to repeal the exemption for
gravity lines, but does propose to extend reporting requirements to all
hazardous liquid gravity lines. The collection of information about
these lines is authorized under the Pipeline Safety Laws, and the
resulting data will assist in determining whether the existing federal
and state regulations for these lines are adequate.
Rural Gathering Lines
Comments
PHMSA received a number of comments on whether to modify or repeal
the requirements in Sec. 195.1(a)(4). API-AOPL, LMOG, IPAA, OIPA, and
TxOGA stated that the regulatory exception for rural gathering lines is
appropriate and should not be repealed or modified. They indicated that
these lines are the source of a small percentage of spills, and that
gathering lines in populated areas and near navigable waterways are
already subject to PHMSA regulation.
Among citizens' groups, TWS suggested that PHMSA should examine
federal and state release data from all excepted pipelines and regulate
those with release rates similar to currently regulated pipelines. PST
supported expansion of the definition of gathering line to the extent
statutorily possible to capture all lines. Similarly, CRAC, TWS, and
AKW indicated the exception should be removed and regulation expanded
to include produced water lines and production lines. TWS and AKW also
stated that flow lines, which are currently defined by regulation as
production facilities, should be reclassified and regulated as
gathering lines.
The government/municipalities NSB and MAWUC also commented
concerning the rural gathering line exception. NSB requested PHMSA
place a high priority on removing the
[[Page 61617]]
exception for gathering lines. MAWUC supported no gathering line
exceptions in HCAs.
Citizen Miller commented that PHMSA should regulate production and
produced water lines on Alaska's North Slope, because this area is very
sensitive and includes pristine wetlands and fish and wildlife habitats
of national and international importance. She further commented that
river and coastline pipeline routes and crossings in the Arctic and
subarctic Alaska are particularly of concern due to the rapid change in
permafrost, as well as high rates of coastal erosion which greatly
increases the environmental and human impacts of spills.
Response
PHMSA believes that the requirements of the Pipeline Safety Act of
2011 and concerns for adequate regulatory oversight can only be
addressed if PHMSA obtains additional information about gathering
lines. PHMSA has the statutory authority to gather data for all
gathering lines (49 U.S.C. 60117(b)), and that authority was not
affected by any of the provisions in the Pipeline Safety Act of 2011.
Accordingly, PHMSA is proposing to amend 49 CFR 195.1(a)(5) to require
that the operators of all gathering lines (whether onshore, offshore,
regulated, or unregulated) comply with requirements for submitting
annual, safety-related condition, and incident reports.
Carbon Dioxide Lines
In the ANPRM, PHMSA asked whether the agency should repeal or
modify the regulatory exception for carbon dioxide pipelines used in
the well injection and recovery production process. Section
195.1(b)(10) states that part 195 does not apply to the transportation
of carbon dioxide downstream from the applicable following point:
(i) The inlet of a compressor used in the injection of carbon
dioxide for oil recovery operations, or the point where recycled carbon
dioxide enters the injection system, whichever is farther upstream; or
(ii) The connection of the first branch pipeline in the production
field where the pipeline transports carbon dioxide to an injection well
or to a header or manifold from which a pipeline branches to an
injection well.
Comments
The trade associations, LMOGA, API-AOPL, OIPA, TxOGA, and IPAA,
commented that PHMSA should not repeal the exception for carbon dioxide
lines used in the well injection and recovery production process. They
indicated the potential risk from a production facility carbon dioxide
pipeline failure is low due to factors of low potential release
volumes, rapid dispersion, and low potential for human exposure. NAPSR
suggested the current exception is appropriate and noted that there is
no data indicating the need for a repeal.
Response
The regulatory history shows that the exception in Sec.
195.1(b)(10) is limited in scope and only applies to carbon dioxide
pipelines that are directly used in the production of hazardous
liquids. See June 12, 1994, (56 FR 26923) (stating in preamble to 1991
final rule that ``the exception is limited to lines downstream of where
carbon dioxide is delivered to a production facility in the vicinity of
a well site, rather than excepting all the CO2 lines in the broad
expanses of a production field.''); January 21, 1994, (59 FR 3390)
(stating in preamble to June 1994 that agency adopted amendment ``to
clarify that the exception covers pipelines used in the injection of
carbon dioxide for oil recovery operations.''). Congress has indicated
that such facilities should not be subject to federal regulation, and
none of the commenters supported a repeal or modification of this
exception. Accordingly, PHMSA is not proposing to repeal or modify
Sec. 195.1(b)(10).
Offshore Lines in State Waters
In the ANPRM, PHMSA asked whether the agency should repeal or
modify any of the exceptions for offshore pipelines in state waters.
Comments
TransCanada Keystone, an industry commenter, and the trade
associations, API-AOPL, LMOGA and TxOGA, stated the current exception
should not be changed. API-AOPL pointed out that PHMSA's jurisdiction
lies only with the transportation of hazardous liquids, not hydrocarbon
production areas of offshore operations. API-AOPL further stated that
changing the state waters exception would unnecessarily add a
duplicative layer of federal regulation.
The citizens' groups, TWS and AKW, supported removal of this
exemption and increased enforcement in state waters. Likewise, among
the government/municipality comments, NSB indicated that the
regulations need to be expanded to include lines in offshore state
waters. NSB expressed concerns with lack of state enforcement, high
corrosion potential, and the sensitivity of the location of the
offshore lines, such as those in the Beaufort and Chukchi Seas.
The prohibitions of the Pipeline Safety Act of 2011 do not affect
PHMSA's authority to ensure the safety of offshore gathering lines
under other statutory provisions, including if such a line is hazardous
to life, property, or the environment (49 U.S.C. 60112)). PHMSA also
notes that the generally-applicable limitation in section 60101(a)(22)
of the Pipeline Safety Laws only applies to ``onshore production . . .
facilities,'' and that the states may regulate such intrastate
facilities (see e.g., Tex. Admin. Code Title. 16, sec. 8.1(a)(1)(D)).
Response
Congress has indicated that additional federal safety standards may
be warranted for offshore gathering lines. First, we would note that
this does not include offshore production pipelines. Section
195.1(b)(5) states that part 195 does not apply to the: Transportation
of hazardous liquid or carbon dioxide in an offshore pipeline in state
waters where the pipeline is located upstream from the outlet flange of
the following farthest downstream facility; the facility where
hydrocarbons or carbon dioxide are produced; or the facility where
produced hydrocarbons or carbon dioxide are first separated,
dehydrated, or otherwise processed.
RSPA, a predecessor agency of PHMSA, adopted Sec. 195.1(b)(5) in a
June 1994 final rule June 28, 1994, (59 FR 33388). Before that time,
part 195 only included an explicit exception for offshore production
pipelines located on the Outer Continental Shelf. However, as explained
in the preamble to the June 1994 final rule, RSPA believed that the
same exception should be applied to all offshore production pipelines,
including those located in state waters. Under the federal pipeline
safety laws, the agency does not regulate production facilities at all.
Section 21 of the Pipeline Safety Act of 2011 requires the Secretary to
review the existing federal and state regulations for gathering lines
and to submit a report to Congress with the results of that review. A
study on these regulations, titled ``Review of Existing Federal and
State Regulations for Gas and Hazardous Liquid Lines,'' was performed
by the Oak Ridge National Laboratory and was published on May 8, 2015.
The Secretary is also required, if appropriate, to issue regulations
subjecting hazardous liquid gathering lines located offshore and in the
inlets of the Gulf of Mexico to the same safety standards that apply to
all other hazardous gathering lines. Section 21
[[Page 61618]]
states that any such regulations cannot be applied to production
pipelines or flow lines.
Congress also included a provision authorizing the collection of
geospatial or technical data on transportation-related flow lines in
section 12 of the Pipeline Safety Act of 2011. A transportation-related
flow line is defined for purposes of that provision as ``a pipeline
transporting oil off of the grounds of the well where it originated and
across areas not owned by the producer, regardless of the extent to
which the oil has been processed, if at all.'' Section 12 also states
that nothing in that provision ``authorizes the Secretary to prescribe
standards for the movement of oil through production, refining, or
manufacturing facilities or through oil production flow lines located
on the grounds of wells.''
Producer-Operated Pipelines on Outer Continental Shelf
In the ANPRM, PHMSA asked whether the agency should repeal or
modify any of the exceptions for pipelines on the OCS.
Comments
TransCanada Keystone, an industry commenter, and the trade
associations, API-AOPL, LMOGA, and TxOGA, stated that the current
exceptions for pipelines on the OCS should remain unchanged. API-AOPL
requested that PHMSA indicate what impact the Bureau of Ocean Energy
Management, Regulation and Enforcement's (BOEMRE) recent publication
regarding Safety and Environmental Management Systems (SEMS) has on
transportation operators. API-AOPL expressed concern that joint
jurisdiction, if created by the recent BOEMRE publication, would result
in regulatory uncertainty.
NAPSR responded that the exceptions for pipelines on the OCS should
not be changed as these lines are already regulated by the Department
of Interior.
Response
Section 195.1(b)(6) states that part 195 does not apply to the
transportation of hazardous liquid or carbon dioxide in a pipeline on
the OCS where the pipeline is located upstream of the point at which
operating responsibility transfers from a producting operator to a
transporting operator. Section 195.1(b)(7) further provides that part
195 does not apply to a pipeline segment upstream (generally seaward)
of the last valve on the last production facility on the OCS where a
pipeline on the OCS is producer-operated and crosses into state waters
without first connecting to a transporting operator's facility on the
OCS. Safety equipment protecting PHMSA-regulated pipeline segments is
not excluded. A producing operator of a segment falling within this
exception may petition the Administrator, under Sec. 190.9 of this
chapter, for approval to operate under PHMSA regulations governing
pipeline design, construction, operation, and maintenance. These
exceptions are designed to ensure that a single federal agency is
responsible for regulating the safety of any given pipeline segment on
the OCS (i.e., the Department of Interior for producer-operated
pipelines and PHMSA for transporter-operated pipelines). See final rule
codifying 1976 Memorandum of Understanding (MOU) between the
Departments of Transportation and Interior on the regulation of
offshore pipelines in Sec. 195.1 August 12, 1976 (41 FR 34040); direct
final rule codifying 1996 MOU between the Departments of Transportation
and Interior on the regulation of offshore pipelines in Sec. 195.1
November 19, 1997 (62 FR 61692); and final rule clarifying regulation
of producer-operated pipelines that cross the federal-state boundary in
offshore waters without first connecting to a transporting-operator's
facility on the OCS) August 5, 2003 (68 FR 46109).
None of the commenters supported the repeal or modification of
Sec. 195.1(b)(6) or (7). Accordingly, PHMSA is not proposing to take
any further action with respect to these two provisions. It should also
be noted that PHMSA is not responsible for administering another
federal agency's statutes or regulations.
Breakout Tanks Not Used for Reinjection or Continued Transportation
In the ANPRM, PHMSA asked for comment on whether the agency should
expand the extent to which part 195 applies to breakout tanks.
Comments
PHMSA received several comments on whether the agency should expand
the extent to which part 195 applies to breakout tanks. API-AOPL,
supported by the industry commenter, TransCanada Keystone, and the
trade associations, LMOGA and TxOGA, stated that the current definition
is appropriate, and that PHMSA should review its current MOU with the
Environmental Protection Agency (EPA) before making any changes to
avoid duplicative regulation of these facilities. DLA, a governmental/
municipal entity, echoed the comments of API-AOPL.
Conversely, NAPSR stated that if PHMSA is referring to the large
number of small tanks that are technically under PHMSA's authority, but
currently not regulated, then this exception should be removed.
Response
The Pipeline Safety Laws provide PHMSA with broad authority to
regulate ``the storage of hazardous liquid incidental to the movement
of hazardous liquid by pipeline'' (49 U.S.C. 60101(a)(22)(A)). The term
``breakout tank'' is defined in Sec. 195.2 to designate which
aboveground tanks are regulated as breakout under part 195. See Exxon
Corporation v. U.S. Department of Transportation, 978 F.Supp. 946, 949-
54 (E.D. Wash. 1997).
As some of the commenters noted, PHMSA has an MOU with EPA on the
treatment of breakout tanks and bulk storage tanks under the
requirements of the Oil Pollution Act of 1990. Such agreements can
ensure the effective regulation of facilities that are subject to
regulation by more than one federal agency. As in the case of offshore
pipeline facilities, those agreements can also serve as a guideline on
whether a tank is transportation related or non-transportation related.
Accordingly, PHMSA will review its agreements with EPA to determine
whether any modifications are necessary, but is not proposing to change
the definition of a ``breakout tank'' in part 195 at this time.
Other Exceptions or Limitations in Part 195
In the ANPRM, PHMSA asked for comment on whether the agency should
repeal or modify any of the other exceptions in part 195. API-AOPL,
supported by several other trade associations, including LMOGA, TxOGA,
OIPA, and IPAA, commented that the exception in Sec. 195.1(b)(8) for
transportation of hazardous liquid or carbon dioxide through onshore
production (including flow lines), refining, or manufacturing
facilities or storage or in-plant pipeline systems associated with such
facilities should not be changed. API-AOPL commented that these
facilities are not within the scope of the Pipeline Safety Laws,
because they are not typically operated by midstream oil and gas
pipeline companies operating in the pipeline transportation system.
These facilities are already covered under a 1972 MOU with EPA and do
not require further duplicative regulation.
Comments
API-AOPL commented that the exception in Sec. 195.1(b)(9) for
piping located on the grounds of a materials
[[Page 61619]]
transportation terminal used exclusively to transfer products between
non-pipeline modes of transportation should not be changed. This piping
is typically isolated from pipeline pressure by devices that control
pressure in the pipeline under Sec. 195.406(b). TransCanada Keystone,
an industry commenter, supported API-AOPL's comments.
The citizens' groups NRDC and PST indicated that PHMSA should
establish additional standards for diluted bitumen. Both groups
suggested PHMSA establish additional regulations for that commodity due
to the high temperatures and pressures at which the lines that carry it
operate.
Both regulatory associations, NAPSR and MAWUC, commented on other
exemptions or limitations of the pipeline safety regulations. NAPSR
indicated that the exemptions for pipelines under 1-mile long that
serve refining, manufacturing, or terminal facilities should be
eliminated for ethanol pipelines. NAPSR also requested that PHMSA
verify that intrastate lines carrying other hazardous liquids, such as
sulfuric acid, are regulated by the states. MAWUC indicated that there
should be no regulatory exceptions in HCA segments, because these areas
must be treated with the highest degree of both prevention and
emergency remediation measures.
Among government and municipality commenters, NSB stated that Sec.
195.1 should be amended to include regulation of all onshore pipelines
and offshore pipelines in areas of the North Slope. NSB suggests
regulation should occur where the consequences of a hazardous liquid
pipeline failure could adversely impact: (1) An endangered, threatened
or depleted species; (2) subsistence resources and subsistence use
areas; (3) a drinking water supply; (4) cultural, archeological, and
historical resources; (5) navigable waterways (including waterways
navigated by rural residents for the purposes of recreation, commerce,
and subsistence use); (6) recreational use areas; or (7) the
functioning of other regulated facilities. Regulation of all high
pressure, large diameter (6-inch and greater) onshore pipelines and all
offshore pipelines should start at the wellhead.
One citizen commented that the river and coastline routes in the
Arctic and sub-Arctic are particularly of concern because of the rapid
change in permafrost, as well as high rate of coastal erosion, which
greatly increase the environmental and human impacts of hazardous
liquid spills.
Response
Section 195.1(b)(8) states that part 195 does not apply to the
transportation of hazardous liquid or carbon dioxide through onshore
production (including flow lines), refining, or manufacturing
facilities or storage or in-plant piping systems associated with such
facilities. That exception is based on section 60101(a)(22) of the
Pipeline Safety Laws, which exempts the movement of hazardous liquid
through onshore production, refining, or manufacturing facilities; or
storage or in-plant piping systems associated with onshore production,
refining, or manufacturing facilities. Accordingly, PHMSA agrees with
the commenters that the exception in Sec. 195.1(b)(8) should not be
changed.
With respect to the terminal exemption in Sec. 195.1(b)(9)(ii), it
should first be noted that the term ``Pipeline or pipeline system'' is
defined in Sec. 195.2 as ``all parts of a pipeline facility through
which a hazardous liquid or carbon dioxide moves in transportation,
including, but not limited to, line pipe, valves, and other
appurtenances connected to line pipe, pumping units, fabricated
assemblies associated with pumping units, metering and delivery
stations and fabricated assemblies therein, and breakout tanks.'' The
term ``Pipeline facility'' is defined in Sec. 195.2 as ``new and
existing pipe, rights-of-way and any equipment, facility, or building
used in the transportation of hazardous liquids or carbon dioxide.''
Under 49 U.S.C. 60101(a)(22), ``transporting hazardous liquid''
includes ``the storage of hazardous liquid incidental to the movement
of hazardous liquid by pipeline.''
Section 195.1(b)(9) states that part 195 does not apply to the
transportation of hazardous liquid or carbon dioxide by vessel,
aircraft, tank truck, tank car, or other non-pipeline mode of
transportation or through facilities located on the grounds of a
materials transportation terminal if the facilities are used
exclusively to transfer hazardous liquid or carbon dioxide between non-
pipeline modes of transportation or between a non-pipeline mode and a
pipeline. These facilities do not include any device and associated
piping that are necessary to control pressure in the pipeline under
Sec. 195.406(b).
One of PHMSA's predecessors, the Materials Transportation Bureau
(MTB), adopted the original version of that exception in a July 1981
final rule July 27, 1981, (46 FR 38357). In excepting the
``[t]ransportation of a hazardous liquid by vessel, aircraft, tank
truck, tank car, or other vehicle or terminal facilities used
exclusively to transfer hazardous liquids between such modes of
transportation,'' MTB stated that: [Its] authority to establish minimum
Federal hazardous liquid pipeline safety standards under the [Hazardous
Liquid Pipeline Safety Act (HLPSA) of 1979] extends to ``the movement
of hazardous liquids by pipeline, or their storage incidental to such
movement.'' The Senate report that accompanied the HLPSA states that,
``It is not intended that authority over storage facilities extend to
storage in marine vessels or storage other than those which are
incidental to pipeline transportation.'' (Sen. Rpt. 96-182, 1st Sess.,
96th Cong. (1979), p. 18.) Earlier laws had vested DOT with extensive
authority to prescribe safety standards governing the movement of
hazardous liquids in seagoing vessels, barges, rail cars, trucks or
aircraft and storage incidental to those forms of transportation. From
the words of the new HLPSA and the related Senate report language, it
is clear that Congress did not want to duplicate or overlap any of
those earlier laws. Thus, HLPSA regulatory authority over storage does
not extend to any form of transportation other than pipeline or to any
storage or terminal facilities that are used exclusively for transfer
of hazardous liquids in or between any of the other forms of
transportation unless that storage or terminal facility is also
``incidental'' to a pipeline which is subject to the HLPSA. These
storage and terminal facilities are expressly excluded from the
coverage of part 195 July 27, 1981, (46 FR 38358). RSPA modified that
exception in the final rule June 28, 1994, (59 FR 33388).
RSPA, however, continued to maintain the exclusion for the
transportation of hazardous liquids or carbon dioxide by non-pipeline
modes, and added a more detailed exclusion for transfer piping located
on the grounds of a materials transportation terminal.
The regulatory history demonstrates that the exception in Sec.
195.1(b)(9) is designed to exclude piping used in transfers to non-
pipeline modes of transportation and the facilities and piping at
terminals that are used exclusively for such transfers. The provision
is drafted to ensure that any piping that is not used exclusively to
transfer product between non-pipeline modes or transportation between a
non-pipeline mode and a pipeline and facilities are subject to
regulation by PHMSA. None of the commenters argued in favor of changing
the exception, and there is no information to suggest that such action
is necessary at this time. Accordingly, PHMSA is not
[[Page 61620]]
proposing to modify or repeal Sec. 195.1(b)(9).
With regard to the remaining comments, section 16 of the Pipeline
Safety Act of 2011 requires the Secretary to perform a comprehensive
review of whether the requirements in part 195 are sufficient to ensure
the safety of pipelines that transport diluted bitumen (dilbit) and to
provide Congress with a report on the results of that review. That
review, titled ``Effects of Diluted Bitumen on Crude Oil Transmission
Pipelines,'' was performed by the National Academy of Sciences and was
published in 2013. The review found there were no causes of pipeline
failure unique to the transportation of diluted bitumen, or evidence of
chemical or physical properties of diluted bitumen shipments that are
outside the range of other crude oil shipments, or any other aspect of
diluted bitumen's transportation by pipeline that would make it more
likely than other crude oils to cause releases.\3\ However, the safety
proposals in this rulemaking address all hazardous liquid pipelines,
which include pipelines that transport diluted bitumen.
---------------------------------------------------------------------------
\3\ https://phmsa.dot.gov/staticfiles/PHMSA/DownloadableFiles/Files/Pipeline/Dilbit_1_Transmittal_to_Congress.pdf.
---------------------------------------------------------------------------
Multiproduct petroleum pipelines transporting ethanol blends of up
to 95% are currently regulated by PHMSA under part 195 and no major
ethanol spills have occurred on these pipelines. PHMSA is performing
additional research into the technical issues associated with the
transportation of ethanol by pipeline and will use that information to
determine whether such transportation should be subject to any
additional safety requirements in the future. This NPRM proposes to
conform part 195 with 49 U.S.C. 60101(a)(4) making the transportation
by pipeline of any biofuel that is flammable, toxic, corrosive, or
would be harmful to the environment if released in significant
quantities, subject to part 195.
The requirements for HCA's are addressed in another portion of this
document. As noted above, PHMSA is proposing to extend the federal
reporting requirements to all hazardous liquid gathering lines (whether
onshore, offshore, regulated, or unregulated).
In conclusion, PHMSA will not be proposing to change or eliminate
any other regulatory exceptions at this time. The exception for carbon
dioxide pipelines is limited in scope and only applies to production
facilities. Although breakout tanks are defined in a way that limits
the application of part 195, these certain storage tanks may also be
subject to regulation by EPA. PHMSA continues to study the scope of the
gathering line exemptions, but is not proposing to modify these or any
other exemption. At present, nothing indicates that any of the other
exceptions should be modified as part of this rulemaking proceeding, or
that the issuance of regulations for underground storage facilities is
necessary.
Additional Safety Standards for Underground Hazardous Liquid Storage
Facilities
The definition of a pipeline facility in part 195 includes ``any
equipment, facility, or building used in the transportation of
hazardous liquids . . .'' and, as already noted above, includes storage
terminals. While surface piping in storage fields located at midstream
terminal facilities falls within this definition, part 195 does not
contain comprehensive safety standards for the ``downhole'' underground
hazardous liquid storage caverns. In addition, surface piping at
storage fields located either at the production facility where a
pipeline originates or a destination/consumption facility where a
pipeline terminates would generally not be considered part of the
transportation and, therefore, not be regulated by PHMSA in the manner
that such piping located on the grounds of the midstream terminal
would. RSPA provided an explanation in a July 1997 advisory bulletin
June 2, 1997, (62 FR 37118) which the agency issued in response to a
NTSB recommendation on the regulation of underground storage caverns
(P-93-9). RSPA noted in that advisory bulletin that a recent report
indicated that state regulations applied in some form to significant
percentages of these facilities, and that API had developed a set of
comprehensive guidelines for the underground storage of liquid
hydrocarbons. As result of these state regulations, the API guidelines,
and ``the varying and diverse geology and hydrology of the many sites''
RSPA stated that agency had ``decided that generally applicable federal
standards may not be appropriate for underground storage facilities.''
June 2, 1997, (62 FR 37118) RSPA further stated it would be
``encouraging state action and voluntary industry action as a way to
assure underground storage safety instead of proposing additional
federal regulations.'' Id. PHMSA understands that Court decisions
preempting state from regulating interstate facilities appears to be a
concern for state regulators.
Comments
PHMSA requested comment on the promulgation of new or additional
safety standards for underground hazardous liquid storage. The industry
commenter, TransCanada Keystone, supported the comments of API-AOPL, as
did the trade associations LMOGA and TxOGA. API-AOPL stated that the
current exclusion of the underground cavern is appropriate as they are
already regulated by the states. API-AOPL indicated that the states are
better suited to regulate these facilities because of their knowledge
of these facilities and locations.
One government/municipality, DLA, commented that there was no need
for new regulations for underground hazardous liquid storage
facilities. DLA maintains that these facilities are currently regulated
for purposes of the Clean Air Act under both 40 CFR parts 112 and 280
by the EPA.
Response
None of the commenters supported the issuance of additional
regulations for underground hazardous liquid storage caverns, and there
is no information suggesting that such action is necessary at this
time. Therefore, PHMSA is not proposing to issue any new regulations
for underground storage of hazardous liquids in this proceeding.
Order in Which Regulatory Changes Should Be Made in to Best Protect the
Public, Property, or the Environment
Comments
PHMSA received comments from industry, trade associations, one
government/municipality, and one regulatory association responding to
the question on the order of the actions PHMSA should take to best
protect the public, property, or the environment. API-AOPL, supported
by TransCanada Keystone and the trade associations, OIPA, TxOGA, and
LMOGA, indicated that PHMSA's actions should be risk-based. Similarly,
NAPSR had no recommendation on the order, but suggested that it be
based on risk.
The government/municipality NSB requested that PHMSA place a high
priority on the repeal of regulatory exceptions for gathering of
hazardous liquids in rural areas, offshore pipelines in state waters,
and producer-operated lines on the OCS. NSB stated that unregulated
rural pipelines are located in Unusually Sensitive Areas (USAs) of the
NSB. These pipelines cross sensitive arctic tundra vegetation and
impact areas used by endangered species. As North Slope development
continues to expand to the west, east, and south,
[[Page 61621]]
impacts to NSB communities and USAs will increase.
Response
PHMSA is proposing to repeal the exception for gravity lines and to
apply the reporting requirements in part 195 to all gathering lines.
B. Definition of High Consequence Area
In the ANPRM, PHMSA asked for public comment on whether to modify
the requirements in part 195 for HCAs. Specifically, PHMSA asked
whether:
The criteria for identifying HCAs should be changed to
incorporate additional pipeline mileage or better reflect risk;
All navigable waterways should be included within the
definition of an HCA;
The process for making HCA determinations on pipeline ROWs
can be improved;
The public and state and local governments should be more
involved in making HCA determinations;
Additional safety requirements should be developed for
areas outside of HCAs; and
Major road and railway crossings should be included within
the definition of an HCA.
As discussed in detail later in the Background and NPRM Proposals
section, PHMSA is proposing to adopt additional safety standards for
pipelines that are located outside of areas that could affect an HCA.
These measures will increase the safety of all of the nation's
pipelines without necessitating any change to the HCA definition;
therefore, PHMSA is not taking any further action on that proposal at
this time.
Expanding the Definition of HCA To Include Additional Pipeline Mileage
In the ANPRM, PHMSA asked whether the current criteria for
identifying HCAs should be modified to incorporate additional pipeline
mileage.
Comments
TransCanada Keystone recommended that PHMSA further define the
meaning of an HCA, and that the agency provide greater clarity with
respect to the HCA classification, including the magnitude of impacts
that differentiate HCAs from other areas.
API-AOPL, supported by the trade associations, TxOGA and LMOGA, and
an industry commenter, TransCanada Keystone, stated that the current
criteria should not be changed. API-AOPL stated that PHMSA should serve
a clearinghouse function by displaying HCA information on the NPMS,
with updates every 10 years based on census information. API-AOPL
further noted that ``other populated areas'' includes Census-delineated
areas, like Metropolitan Statistical Areas (MSA) and Consolidated
Metropolitan Statistical Areas, which are not densely populated, and
that the current HCA criteria are thus conservative. API-AOPL also
stated that the current ability of operators to demonstrate why
segments of pipeline could not affect an HCA should be retained.
The trade associations, OIPA and TPA, suggested that more data is
needed to make a decision on HCA definition expansion, and that any
changes would likely impact small operators.
Among citizens' groups, PST favored expanding the IM requirements
to all hazardous liquid lines, with initial inspections required within
5 years of identification. PST stated that using census data to
designate high population and other population areas is arbitrary and
not necessarily a predictor of risk. Noting that the public could not
fully comment because HCA boundaries are not publicly available (for
security reasons); PST stated that the definition of HCA should be
expanded to include national parks, monuments, recreation areas, and
national forests. PST also pointed to the recent trend in extreme
accidents in HCAs.
Two other citizens' groups, AKW and NRDC, commented. AKW requested
that the criteria be changed. NRDC indicated that PHMSA should have a
broader definition of HCAs, particularly with respect to ecological
resources and drinking water criterion.
NAPSR commented that the current criteria are generally adequate,
but that other threats and risks could be considered, including
petroleum product supply loss, leaks that could affect private wells,
and impacts to major infrastructure.
NSB favored an expansion of HCAs to include pipelines located in
subsistence areas, cultural resources, archeological, historical, and
recreational areas of significance and offshore.
Response
Congress recently directed the Secretary to prepare a report on
whether the IM requirements should be extended to pipelines outside of
areas that could affect HCAs. The Secretary is prohibited from issuing
any final regulations that would expand those requirements during a
subsequent Congressional review period, unless those regulations are
necessary to address a condition posing a risk to public safety,
property, or the environment, or an imminent hazard. PHMSA is preparing
the Secretary's report to Congress on the need to expand the IM
requirements and is not proposing to change the definition of an HCA to
incorporate additional pipeline mileage at this time.
PHMSA is, however, proposing to adopt additional safety standards
for pipelines that are not covered under the IM program requirements.
The proposals are detailed later in this NPRM under the Background and
NPRM proposals section.
PHMSA is aware of its obligation to consider other locations near
pipeline ROWs in defining USAs, including ``critical wetlands, riverine
or estuarine systems, national parks, wilderness areas, wildlife
preservation areas or refuges, wild and scenic rivers, or critical
habitat areas for threatened and endangered species.'' However, PHMSA
is not proposing to make any of these areas USAs in light of the new
requirements that are being proposed for non-IM pipelines. PHMSA will
be considering whether to include these locations in the HCA definition
in performing the evaluation required under section 5 of the Pipeline
Safety Act of 2011 and will comply with the applicable provisions of
that legislation before taking any final regulatory action to adopt the
proposed requirements for non-IM pipelines.
Modifying the Definition of HCA to Better Reflect Risk
PHMSA asked whether the criteria for identifying HCAs should be
changed to better reflect risk.
Comments
TransCanada Keystone's comment focused specifically on the
classification of groundwater USAs in Sec. 195.6, stating that
groundwater HCA buffers should not be expanded, and that the existing
criteria, which identify community water intakes where contamination
has the potential to cause greater impacts compared to other areas, are
sufficient.
API-AOPL stated that there are various risk factors applicable to
HCA classifications and that the current definition should not be
changed. API-AOPL recommended that buffer zones be used as an
acceptable alternative to the more detailed ``could affect'' analysis
for new, expanded, or modified HCAs. API-AOPL also suggested that
operators should retain the ability, with technical justification, to
determine whether a pipeline can actually impact an HCA. TransCanada
Keystone, LMOGA, and TxOGA endorsed API-AOPL's comments. TPA, the other
trade association commenter, mentioned that
[[Page 61622]]
more data was needed to make a final decision on this matter.
A number of citizens' groups commented on this issue. NRDC, AKW,
and TWS indicated the HCA definition needs to be broadened to reflect
risk and to include entire pipelines in some cases. NRDC stated that
the threshold for a populated area should be lowered, and that the
definition of populated areas and USA should be improved. NRDC
commented that the current HCA definition provides limited protection
to threatened or endangered species. NRDC also recommended
strengthening the USA definition to protect more migratory bird areas
and national landmarks, including national parks, wild and scenic
rivers, estuaries, wilderness areas, wildlife refuges, and drinking
water sources, including private wells and open source aquifers. TWS
and AKW proposed to revise the HCA criteria to include all
transportation infrastructure, public lands, waterways, wetlands, and
cultural, historic, archeological, and recreation sites, including
subsistence areas.
NAPSR stated that the current HCA definition should not be changed,
but that PHMSA should consider incorporating others threats and risks,
including supply interruptions and small leaks that could affect
private wells.
NSB favored changing the existing HCA definition. NSB stated that
USAs should include subsistence, cultural, archeological, historical,
and recreational areas of significance within the NSB and offshore
waters of the Beaufort and Chukchi Seas. NSB suggested a formal process
for nominating areas that should be afforded HCA status, and that the
NPMS data should be updated.
Both MAWUC and DLA indicated the definition could be modified to
better reflect risk. MAWUC suggested a tiered, prioritized system with
enforceable criteria that are appropriate for the risk to water
supplies. DLA stated that higher risk locations should be protected
instead of simply creating more HCAs.
Response
PHMSA is not proposing to make any changes to the criteria for
identifying HCAs at this time. The existing Census-based approach for
determining high population and other populated areas ensures
uniformity and provides an adequate margin of safety by including some
less densely populated areas. None of the commenters offered a more
effective alternative.
PHMSA recognizes that other areas of ecological, cultural, or
national significance could be designated as USAs. However, PHMSA is
not proposing to add any of these areas in light of the new safety
standards that are being proposed for hazardous liquid pipelines that
are not subject to the IM program requirements.
PHMSA does not support any of the suggested alternative approaches
for identifying HCAs. The widespread use of the buffer method is not
justified based on the available information, and the use of a more
lenient standard in making HCA determinations would not provide
adequate protection for these sensitive areas. PHMSA will revisit these
conclusions in preparing the Secretary's report to Congress on
expanding the IM program for hazardous liquid pipelines.
Commercial Limitation on Navigable Waterways
The ANPRM posed the question of expansion of the definition of HCAs
beyond commercially navigable waterways.
Comments
Several trade associations, API-AOPL, OIPA, and IPAA, and one
industry representative, TransCanada Keystone, opposed expanding the
HCA definition beyond commercially navigable waterways. These
commenters stated that the vast majority of surface waters are already
covered under the present criteria. TPA stated that adopting a
navigable waters standard would make every creek an HCA, resulting in a
significant increase in the burden associated with implementing IM
requirements.
Two citizens' groups commented on the phrase ``commercially
navigable.'' PST also recommended defining HCA to include all ``waters
of the United States,'' provided PHMSA did not adopt its suggestion to
apply IM requirements to all regulated pipelines. NRDC proposed to
amend the term ``commercially navigable waterways'' to include other
bodies of water that are not necessarily navigable, such as lakes,
streams, and wetlands.
Two government/municipalities commented on the commercial
limitation on navigable waterways. DLA, a government/municipality,
echoed the comments of the trade associations and TransCanada Keystone
previously mentioned. NSB requested PHMSA change commercially navigable
to ``navigable waters'' or ``waters of the U.S.'' to encompass more
environmentally-sensitive areas.
Response
Section 195.450 states that an HCA includes any ``waterway where a
substantial likelihood of commercial navigation exists.'' RSPA first
proposed to include commercially navigable waterways as HCAs in the
April 2000 NPRM that contained the original IM requirements for
hazardous liquid pipelines April 24, 2000, (65 FR 21695). RSPA stated
that it ``[wa]s including commercially navigable waterways in the
proposed [HCA] definition[,] [b]ecause these waterways are critical to
interstate and foreign commerce and supply vital resources to many
American communities, are a major means of commercial transportation,
and are a part of a national defense system, a pipeline release in
these areas could have significant impacts.'' April 24, 2000, (65 FR
21700).
RSPA adopted the HCA definition as proposed in the NPRM in the
final rule December 1, 2000, (65 FR 75378). In the preamble to that
final rule, RSPA stated that it had received the following comments on
its proposal to include commercially navigable waterways in the HCA
definition:
API and liquid operators questioned the inclusion of commercially
navigable waterways into the HCA's definition. API pointed out that
Congress required OPS to identify hazardous liquid pipelines that cross
waters where a substantial likelihood of commercial navigation exists
and once identified, issue standards, if necessary, requiring periodic
inspection of the pipelines in these areas. API said that OPS had not
determined the necessity for including these waterways in areas that
trigger additional integrity protections. BP Amoco said the rule should
be limited to protection of public safety, rather than commercial
interests. Enbridge and Lakehead also questioned why waterways that are
not otherwise environmentally sensitive should be included for
protection.
EPA Region III said that we should also consider recreational and
waterways other than those for commercial use. Environmental Defense,
Batten, City of Austin and other[s] commented that we should consider
all navigable waterways as HCA's, because of the environmental
consequences a hazardous liquid release could have on such waters.
December 1, 2000, (65 FR 75390).
RSPA provided the following response to those comments:
``Our inclusion of commercially navigable waterways for public
safety and secondary reasons is not based on the ecological sensitivity
of these
[[Page 61623]]
waterways. Parts of waterways sensitive for ecological purposes are
covered in the proposed USA definition, to the extent that they contain
occurrences of a threatened and endangered species, critically
imperiled or imperiled species, depleted marine mammal, depleted multi-
species area, Western Hemispheric Shorebird Reserve Network or Ramsar
site. We are including commercially navigable waterways as HCAs because
these waterways are a major means of commercial transportation, are
critical to interstate and foreign commerce, supply vital resources to
many American communities, and are part of a national defense system. A
pipeline release could have significant consequences on such vital
areas by interrupting supply operations due to potentially long
response and recovery operations that occur with hazardous liquid
spills. December 1, 2000, (65 FR 75391-2).
For these reasons, RSPA defined HCAs in Sec. 195.450 to include
commercially navigable waterways.
Thus, the Pipeline Safety Laws do not necessarily limit the
definition of an HCA to commercially navigable waterways. RSPA relied
on several statutes in promulgating the IM requirements for hazardous
liquid pipelines, including the mandates that required the Secretary to
establish criteria for identifying pipelines in high density population
and environmentally sensitive areas (49 U.S.C. 60109(a)(1)) and to
promulgate standards for ensuring the periodic inspection of these
lines (49 U.S.C. 60102(f)(2)). Nothing in these provisions or the
Pipeline Safety Act of 2011 prohibits PHSMA from using its general
rulemaking authority to apply the hazardous liquid pipeline IM
regulations to waterways that are not used for commercial navigation.
Other kinds of waterways are also referenced in the statutory criteria
that must be considered in defining USAs.
PHMSA will be considering the expansion of current HCA or the
extension of critical IM requirements to non-HCAs-when completing the
Secretary's report to Congress on the need to expand the IM requirement
under section 5 of the Pipeline Safety Act of 2011. In the meantime,
PHMSA is not proposing to include any additional waterways in the HCA
definition.
PHMSA is, however, proposing to adopt other regulations that will
increase the safety of our nation's waterways. One such proposal is to
require leak detection systems for pipelines in all locations, that
operators perform periodic assessments of pipelines not already covered
under the IM program requirements, and that new pipeline repair
criteria be applied to anomalous conditions discovered in all areas.
Another proposal is to require operators to inspect their pipelines in
areas affected by extreme weather, natural disasters, and other similar
events (e.g., flooding, hurricanes, tornados, earthquakes, landslides,
etc.). Following a disaster event, operators will be required to
determine whether any conditions exist that could adversely affect the
safe operation of a pipeline and to take appropriate remedial actions,
such as reductions in operating pressures and repairs of any damaged
facilities or equipment.
In regard to seismic events and earthquakes, in determining whether
a pipeline has potentially been affected and needs inspection,
operators should consider relevant factors such as magnitude of the
earthquake, distance from the epicenter, and pipeline characteristics
and history. PHMSA recognizes that after considering these factors,
operators may determine that smaller seismic events do not have the
potential to affect their pipelines. Based on available studies,
however, earthquakes over 6.0 in magnitude can potentially damage
pipelines and operators would be required to inspect these pipelines.
Operator Process and Public Participation in Making HCA Determinations
PHMSA requested comment on whether the operator's process for
making HCA determinations should be modified, including by having
greater involvement by the public and state and local governments.
Comments
PHMSA received comments from industry, trade associations, and one
regulatory association. API-AOPL supported the existing process for
identifying HCAs and suggested that any input from local communities
should be through the regulating agency, rather than pipeline
operators. OPIA and IPAA noted that a consistent and reliable approach
is needed to prevent variations that would result in unnecessary
confusion.
The trade associations, TxOGA, LMOGA, API-AOPL, supported by
TransCanada Keystone, indicated that operators perform geographic
overlay of their pipeline systems with PHMSA-determined HCAs. Operators
also utilize the ``could affect'' analysis, which typically considers
technical assessments using dispersion models. Through the process of
HCA evaluation, operators are sometimes able to determine, with
technical justification, that their assets are not capable of impacting
an HCA.
NAPSR indicated that PHMSA could consider adding minimum time
intervals for operators to review HCA identifications, including a
shorter time interval if a pipeline is routed through high population
areas. NAPSR also stated that there are areas where private wells have
been extremely affected by small leaks that go undetected for years,
that this is especially true in areas of sandy soil where leaks do not
necessarily bubble up to the surface, and that there should be some
consideration to address these ``seepers'' that have very large total
leak volume over time.
On the matter of greater public participation, TransCanada Keystone
suggested that PHMSA collect data from the states and provide updated
HCA information for operator use. The trade associations, LMOGA, TxOGA
and API-AOPL, supported by TransCanada Keystone, recommended that
additional local involvement be routed through the regulating agency,
such as PHMSA. TPA, in contrast, stated that there should be no
requirement for public involvement. OIPA and IPAA held that a
consistent and reliable approach is needed for the issue of public
involvement.
Among the citizens' groups, NRDC supported additional public
involvement. Several commenters, including NRDC, PST, and TWS,
recommended that the NPMS be revised to display all HCAs so that the
public can be better informed.
One regulatory association, NAPSR, suggested that the public be
allowed to comment. NAPSR recognized that PHMSA has a process in place
for HCA selection that can be enhanced if the public is allowed to
provide input. NAPSR stated that the general public and local
communities often recognize changes in areas near pipelines before
operators.
Government and municipal commenters supported local involvement in
the HCA determination process. MAWUC commented that it is important
that local communities and water suppliers play a role in preventing
and minimizing pipeline failures, including HCA identification. DLA
also supported additional public involvement. NSB recommended that
state and local governments, as well as local tribes, villages, and the
Alaskan Eskimo Whaling Commission, have a role in making HCA
determinations.
[[Page 61624]]
Response
Congress included new requirements for promoting public education
and awareness in section 6 of the Pipeline Safety Act of 2011.
Specifically, that provision requires PHMSA (1) to maintain, and update
on a biennial basis, a map of designated HCAs in the NPMS; (2) to
establish a program that promotes greater awareness of the existence of
the NPMS to state and local emergency responders and other interested
parties, to include the issuance of guidance on using the NPMS to
locate pipelines in communities and local jurisdictions; and (3) to
issue additional guidance to owners and operators of pipeline
facilities on the importance of providing system-specific information
to emergency response agencies. PHMSA believes that such actions will
address many of the concerns raised by the commenters.
Additional Safety Requirements for Non-HCA Areas
PHMSA inquired as to whether additional safety measures should be
developed for areas outside of HCAs.
Comments
PHMSA received comments from three trade associations and one
regulatory association. TransCanada Keystone, TxOGA, API-AOPL, and
LMOGA indicated that no new requirements are necessary for areas
outside of HCAs. The regulatory association, NAPSR, remarked that
operators should be precluded from turning off in-line inspection
sensors outside of an HCA when performing an integrity assessment under
the IM regulations.
Response
PHMSA agrees with the NAPSR comment and has likewise found that
some operators do turn off inspection tools outside of HCAs. Therefore,
PHMSA is proposing to require that operators perform periodic
assessments of pipelines that are not already covered under the IM
program requirements in Sec. 195.452. Promulgation of such a
requirement will ensure that pipeline operators obtain the information
necessary for the prompt detection and remediation of corrosion and
other deformation anomalies (e.g., dents, gouges, and grooves) in all
locations, not just in areas that could affect HCAs.
Inclusion of Major Road and Railway Crossings as HCAs
PHMSA requested comment on the need to include major road and
railway crossings as HCAs.
Comments
Industry, three trade associations, three citizens' groups, one
regulatory association, one government/municipality, and one citizen
commented on this question.
TransCanada Keystone, supported by the trade associations, API-
AOPL, TPA, TxOGA, and LMOGA, opposed including major roads and railway
crossings as HCAs. The commenters offered several reasons to support
that position (e.g., such a change would draw resources from other more
high risk areas, non-HCA areas are already assessed and remediated, and
there is no data to support such an action).
Among the citizens' groups, PST stated that rail and major road
crossings should be included. TWS and AKW stated that all
transportation infrastructure, public lands, wetlands under the Clean
Water Act (CWA), cultural, historical, archeological and recreation
areas used for subsistence be included in HCAs.
NAPSR also suggested that rail and major road crossings should be
included. NAPSR urged PHMSA to consider the effect of a release on
electric transmission facilities, gas pipelines, and railroads if major
road and rail crossings were not to be included in HCAs. NAPSR would
consider the effect of a release on electric transmission facilities,
gas pipelines, railroads, etc., and would treat major road and rail
crossings as HCAs for highly volatile liquids (HVLs) pipelines.
The only government/municipality to comment on this question was
DLA. DLA indicated that these structures should be included in HCAs.
Citizen Coyle commented that major roadways should be HCAs because
these areas could be affected by pipelines carrying HVLs that would
produce poisonous clouds if released.
Response
PHMSA is not proposing to designate major road and railway
crossings as HCAs, but will consider whether the pipeline IM
requirements should be applied to these areas when completing the study
that Congress mandated under section 5 of the Pipeline Safety Act of
2011. PHMSA notes that the pipelines at such crossings would be
afforded additional protections under the other proposals made in this
proceeding, including the requirements for the performance of periodic
internal inspections and the use of leak detection systems.
C. Leak Detection Equipment and Emergency Flow Restricting Devices
In the ANPRM, PHMSA asked for comment on whether to modify the
current requirements part 195 for leak detection equipment and
emergency flow restricting devices (EFRDs). Specifically, PHMSA asked
whether
The use of leak detection equipment should be required for
hazardous liquid pipelines;
The pipeline industry has developed any practices,
standards, or leak detection technologies that should be incorporated
by reference;
Any industry practices or standards adequately address the
relevant safety considerations;
State regulations for leak detection should be adopted by
regulation;
Any new leak detection requirements should vary based on
the sensitivity of the affected areas;
The pipeline industry has developed standards or practices
for the performance and location of EFRDs;
The location of EFRDs should be specified by regulation;
and
Additional research and development is needed to
demonstrate the suitability of any new leak detection technologies.
As discussed below, PHMSA is considering requiring that all
hazardous liquid pipelines have a system for detecting leaks and expand
the use of EFRDs.
Expansion of Leak Detection Requirements
In the ANPRM, PHMSA asked for comment on whether the agency should
expand the leak detection requirements.
Comments
Industry and trade associations generally supported expansion of
the existing requirement in Sec. 195.452(i)(3) to most pipelines, but
opposed including more-specific requirements in the regulations. API-
AOPL, TxOGA, TransCanada Keystone, and LMOGA supported extending leak
detection requirements to all PHMSA-regulated pipelines, except for
rural gathering lines.
Citizens' groups supported enhanced leak detection requirements.
TWS and PST opposed additional reliance on the current requirements in
Sec. 195.452(i)(3), stating that this regulation includes no
acceptance criteria and is virtually unenforceable. TWS further
supported expanding leak detection requirements to all pipelines under
PHMSA jurisdiction. NRDC indicated that leak detection requirements
should be expanded to include a requirement that
[[Page 61625]]
worst-case-discharge-pumping times be based on historical shutdown
times, rather than expected times. NRDC also said that operators should
immediately contact first responders at the first sign of an issue. One
citizen, Stec, suggested requiring use of ``smart coating'' with
embedded conductors that would break to indicate coating damage and
which could then trigger automatic response actions.
The regulatory associations, DLA and MAWUC, supported expanded leak
detection requirements. MAWUC suggested PHMSA require the use of leak
detection equipment in all HCAs. DLA indicated that any new
requirements should be delayed until better technology is available.
The government/municipality, NSB, recommended leak detection
requirements be expanded to all pipelines under PHMSA regulation. NSB
encouraged adoption of more stringent leak detection requirements for
sensitive offshore areas of the Beaufort and Chukchi seas.
Response
As discussed earlier in this NPRM under the Background and
Proposals section, PHMSA will propose to expand the leak detection
requirements for HCA and non-HCA areas.
Consideration of New Industry Standards or Practices in Leak Detection
PHMSA asked for public comment on whether any new industry
standards or practices should be considered for adoption in part 195.
Comments
API-AOPL, TxOGA, LMOGA, and TransCanada Keystone all indicated that
the API-AOPL standard RP1165 (SCADA), RP 1167 (Pipeline Alarm
Management), and RP1168 (Control Room Management) are good standards to
utilize for leak detection systems. API-AOPL also pointed out that many
new technologies are being developed and existing methodologies are
continuously being improved for better leak detection capability;
however, many of these new technologies have not been proven in service
on cross-country pipelines.
One citizens' group, NRDC, commented that new leak detection
standards should address the additional demands posed by hazardous
liquids. In particular, NRDC mentioned some hazardous liquids, such as
diluted bitumen, have multiphase properties that can cause false
alarms.
The regulatory associations, NAPSR and DLA, both commented on new
industry standards and practices in leak detection. NAPSR mentioned the
new technology forward-looking infrared radar (FLIR) and encouraged
PHMSA to consider using such new technologies. NAPSR reported that FLIR
can detect changes in temperature near a pipeline from a winter leak,
even under snow, and that it can be used from aerial patrols.
DLA indicated that any leak detection standards should be third-
party validated and listed by the National Work Group on Leak Detection
Evaluations (NWGLDE) and that leak detection in general for large
volume pipelines is not very effective at this time.
Response
The commenters only offered three specific industry standards or
practices for consideration, and two of those standards, API RP1165
(SCADA) and RP1168 (Control Room Management), are already incorporated
into part 195 (see 49 CFR 195.3). PHMSA has concerns about the adequacy
and enforceability of the third standard, API RP 1167 (Pipeline Alarm
Management), and does not believe that it should be incorporated by
reference at this time.
As previously discussed, PHMSA is proposing to require that
operators have a means for detecting leaks on all portions of a
hazardous liquid pipeline system. Consideration of FLIR and any other
emerging technologies would be required in evaluating what kinds of
leak detection systems are appropriate for a particular pipeline. PHMSA
will also be considering whether the use of specific leak detection
technologies should be required in preparing the Secretary's report to
Congress on that issue.
PHMSA does not agree that third-party validation is a prerequisite
to issuing new leak detection requirements for hazardous liquid
pipelines. That limitation is not included in the Pipeline Safety Laws,
and PHMSA does not believe that such action is necessary as a matter of
administrative discretion.
Adequacy of Existing Industry Standards or Practices for Leak Detection
PHMSA asked for public comment on whether any existing industry
standards or practices for leak detection are adequate for adoption
into part 195.
Comments
TransCanada Keystone, TxOGA, LMOGA and API-AOPL submitted comments
indicating that the current leak detection evaluations performed as a
requirement of the IM program encompass many important factors for
proper leak detection. PHMSA should allow for the implementation of
recent regulatory changes, including the new Control Room Management
(CRM) rule, before making any changes. NAPSR commented that all
pipeline operators should, at a minimum, perform a tank balance
periodically to detect leakage.
NSB recommended that PHMSA adopt improved leak detection system
standards and implement more stringent leak detection requirements for
the sensitive offshore areas of the Beaufort and Chukchi seas. NSB
stated that PHMSA should require: (1) Redundant leak detection systems
for offshore pipelines; (2) All offshore pipeline leak detection
systems to have the continuous capability to detect a daily discharge
equal to not more than 0.5% of daily throughput within 15 minutes, and
detect a pinhole leak within less than 24 hours; (3) All onshore
pipeline leak detection systems to have the continuous capability to
detect a daily discharge equal to not more than 1% of daily throughput
within 15 minutes, and detect a pinhole leak within less than 24 hours;
and (4) An initial performance test to verify leak detection accuracy
upon installation and at regular intervals thereafter.
Response
PHMSA agrees that the factors listed in Sec. 195.452(i)(3) are an
appropriate basis for determining whether hazardous liquid pipelines
have an adequate leak detection system and is proposing to use those
factors as the basis for the requirements that would apply in all other
locations. However, a December 31, 2007, report that PHMSA prepared in
response to a mandate in the Pipeline Inspection, Protection,
Enforcement, and Safety Act (PIPES Act) of 2006 (Pub. L. 109-468),
confirmed that some operators had IM procedures that did not require
the performance of a leak detection evaluation, and others had adopted
an inadequate process for performing those evaluations. Operators are
reminded that any failure to comply with part 195, including the leak
detection requirements in Sec. 195.452(i)(3) and the proposed
modifications to Sec. Sec. 195.134 and 195.444, increases both the
likelihood and severity of pipeline accidents.
PHMSA agrees that the new CRM requirements will improve the
detection and mitigation of leaks on hazardous liquid pipeline systems,
but does not agree that the implementation of improved leak detection
requirements should be delayed solely on account of the recent issuance
of those regulations. PHMSA will be monitoring the use of
[[Page 61626]]
leak detection systems by operators in complying with those
requirements in determining if additional safety standards are needed.
Consideration of State Requirements/Regulations for Leak Detection
Some states have established leak detection requirements for
hazardous liquid pipeline systems. For example, the Alaska Department
of Environmental Conservation (ADEC) has promulgated a regulation (18
AAC 75.055) that states:
(a) A crude oil transmission pipeline must be equipped with a leak
detection system capable of promptly detecting a leak, including
(1) if technically feasible, the continuous capability to detect a
daily discharge equal to not more than one percent of daily throughput;
(2) flow verification through an accounting method, at least once
every 24 hours; and
(3) for a remote pipeline not otherwise directly accessible, weekly
aerial surveillance, unless precluded by safety or weather conditions.
(b) The owner or operator of a crude oil transmission pipeline
shall ensure that the incoming flow of oil can be completely stopped
within one hour after detection of a discharge.
(c) If above ground oil storage tanks are present at the crude oil
transmission pipeline facility, the owner or operator shall meet the
applicable requirements of 18 AAC 75.065, 18 AAC 75.066, and 18 AAC
75.075.
(d) For facility oil piping connected to or associated with the
main crude oil transmission pipeline the owner or operator shall meet
the requirements of 18 AAC 75.080.
Operators who install online leak detection systems can also
receive a reduction in the volume of crude oil that must be used in
complying with Alaska's oil spill response planning requirements (18
AAC 75.436(c)(3)).
The State of Washington has also prescribed leak detection
requirements for hazardous liquid pipelines (WAC 480-75-300). Those
requirements, which are administered by the Washington Utilities and
Transportation Commission (WUTC), state:
(1) Pipeline companies must rapidly locate leaks from their
pipeline. Pipeline companies must provide leak detection under flow and
no flow conditions.
(2) Leak detection systems must be capable of detecting an eight
percent of maximum flow leak within fifteen minutes or less.
(3) Pipeline companies must have a leak detection procedure and a
procedure for responding to alarms. The pipeline company must maintain
leak detection maintenance and alarm records.
Comments
PHMSA received comments from several trade associations and one
citizens' group on state requirements for leak detection systems. API-
AOPL indicated that pipeline configuration and operational factors vary
by geographic location, and that other variability exists, including
fluid or product differences, batching, and other operational
conditions. Due to these factors, any type of prescriptive approach to
standards for leak detection is difficult to achieve and would be
better served using a performance standard. CRAC noted that multi-phase
lines are more susceptible to internal corrosion, and that state
regulations do not require IM or leak detection.
NAPSR and DLA also commented. NAPSR encouraged PHMSA to allow the
states to set minimum leak detection criteria for intrastate pipelines.
DLA opposed development of criteria based on state requirements and
suggested that new requirements be third-party validated and listed by
NWGLDE.
Response
PHMSA favors the use of performance-based safety standards and
believes that the regulations adopted by ADEC and WUTC show that
certain minimum threshold requirements can be established for leak
detection systems. PHMSA will be considering these and other similar
regulations in an evaluation of leak detection systems.
With regard to NAPSR's comment, section 60104(c) of the Pipeline
Safety Laws allows states that have submitted a current certification
to adopt additional or more stringent safety standards for intrastate
hazardous liquid pipeline facilities, so long as those requirements are
compatible with the minimum federal safety standards. PHMSA has
prescribed mandatory leak detection requirements for hazardous liquid
pipelines that could affect HCAs and is proposing to make those
requirements applicable to all pipelines subject to part 195. States
that have submitted a current certification can establish additional or
more stringent leak detection standards for intrastate hazardous liquid
pipeline facilities, subject to the statutory compatibility
requirement.
PHMSA does not agree that third-party validation is a prerequisite
to issuing new leak detection requirements for hazardous liquid
pipelines. That limitation is not included in the Pipeline Safety Laws,
and PHMSA does not believe that such action is necessary as a matter of
administrative discretion.
Different Leak Detection Requirements for Sensitive Areas
Section 195.452(i)(3) contains a mandatory leak detection
requirement for hazardous liquid pipelines that could affect an HCA.
That regulation requires operators to consider several factors (i.e.,
the length and size of the pipeline, type of product carried, proximity
to the HCA, the swiftness of leak detection, location of nearest
response personnel, leak history, and risk assessment results) in
selecting an appropriate leak detection system.
Comments
PHMSA received many comments in response to whether there should be
different leak detection requirements for sensitive areas. The trade
associations, TxOGA and LMOGA, supported API-AOPL's comments that most
leak detection methods cannot target specific areas. API-AOPL further
stated that leak detection for sensitive areas can be achieved through
comprehensive risk-based evaluation, but that external monitoring is
too invasive and is not yet proven or cost effective.
The regulatory associations, government/municipalities, and
citizens all supported increased leak detection requirements for
sensitive areas. The regulatory association, NAPSR, mentioned the use
of FLIR for sensitive areas and stated that special actions beyond
patrols should be required for sensitive areas. DLA indicated leak
detection standards should be third-party validated. MAWUC and a
citizen, Coyle, recommended requiring external leak detectors in HCAs.
Coyle would also require external leak detectors for above-ground
pipelines transporting highly volatile liquids. NSB encouraged PHMSA to
adopt improved leak detection standards and implement more stringent
requirements for sensitive areas.
Response
PHMSA believes that the leak detection requirements in Sec.
195.452(i)(3) can provide adequate protection for sensitive areas and
is proposing to use those requirements as the basis for establishing
requirements that would apply to hazardous liquid pipelines in all
other locations. Under the current and proposed regulations, operators
are required to consider several factors in selecting an appropriate
leak detection system, including the characteristics and history of the
affected pipeline, the capabilities of the available leak
[[Page 61627]]
detection systems, and the location of emergency response personnel.
PHMSA commissioned Kiefner and Associates, Inc., to perform a study on
leak detection systems used by hazardous liquid operators. That study,
titled ``Leak Detection Study,'' \4\ was completed on December 10,
2012, and was submitted to Congress on December 27, 2012. PHMSA is
considering, in a different rulemaking activity, whether to adopt
additional or more stringent requirements for sensitive areas in
response to this study.
---------------------------------------------------------------------------
\4\ https://www.phmsa.dot.gov/pv_obj_cache/pv_obj_id_4A77C7A89CAA18E285898295888E3DB9C5924400/filename/Leak%20Detection%20Study.pdf
---------------------------------------------------------------------------
Key Issues for New Leak Detection Standards
Comments
The trade associations, TxOGA, LMOGA, and API-AOPL, supported by an
industry commenter, TransCanada Keystone, stated that PHMSA should
identify issues that might adversely affect response times, including
limiting the consequences for first responder deployment and allowing
for the withdrawal of erroneous leak notifications. NAPSR, the only
regulatory association to comment, found that any new standards should
consider detection of small leaks in HCAs, maintenance, accuracy,
transient conditions, system capabilities, and alarm management.
Three government/municipalities commented on this issue. DLA stated
that any standards should address sensitivity, probability of false
alarms, minimum leak detection capabilities, frequency, and be based on
leak detection technology. MAWUC supported more stringent reporting and
repair requirements. NSB indicated that PHMSA should require redundant
leak detection systems for offshore lines. NSB also indicated the
technology available for leak detection systems is vastly improved and
industry should bear the burden to utilize these systems.
Response
The Pipeline Safety Laws contain a number of general factors that
must be considered in prescribing new safety standards, including the
reasonableness of the standard, the estimated benefits and costs, and
the views and recommendations of the Technical Hazardous Liquid
Pipeline Safety Standards Committee (49 U.S.C. 60102(b)). The Pipeline
Safety Laws also contain specific factors that must be considered in
prescribing certain safety standards, such as for smart pigs (49 U.S.C.
60102(f)) or low-stress hazardous liquid pipelines (49 U.S.C.
60102(k)).
In the case of leak detection, Congress has enacted prior statutory
mandates that required the Secretary to survey and assess the need for
additional safety standards. PHMSA and its predecessor agency, RSPA,
complied with those mandates by producing two reports and promulgating
additional safety standards for leak detection systems. Congress
enacted a similar provision in section 8 of the Pipeline Safety Act of
2011, including a requirement that the Secretary submit a report to
Congress that provides an analysis of the technical limitations of
current leak detection systems and the practicability, safety benefits,
and adverse consequence of establishing additional standards for the
use of such systems.
The commenters identified several issues that should be considered
in establishing new leak detection standards, including the need to
minimize false alarms, to set appropriate volumetric thresholds, and to
encourage the use of best available technologies.
Statistical Analyses of Leak Detection Requirements
PHMSA asked the public to comment on the availability of statistics
on whether existing practices or standards on leak detection have
contributed to reduced spill volumes and consequences.
Comments
One response submitted by API-AOPL, supported by TransCanada
Keystone, LMOGA, and TxOGA, stated that the association was unaware of
any recent statistics in regard to this topic. API-AOPL further
indicated that PHMSA should allow time for recent regulatory changes to
take effect on the regulated population.
Response
PHMSA's December 2007 report on leak detection systems noted that
from 1997 to 2007 ``the median volume lost from hazardous liquid
pipeline accidents dropped by more than half, from 200 to less than 100
barrels,'' and that ``the number of accidents declined by over a
third.'' The report attributed that positive trend to the
implementation of the pipeline IM requirements in Sec. 195.452.
However, the report also indicated that all of the available leak
detection technologies have strengths and weakness, that some are only
suitable for use on particular pipeline systems, and that establishing
safety standards would require consideration of a number of factors.
Consideration of Industry Practices or Standards for Location of EFRDs
Part 195 requires that EFRDs be considered as potential mitigation
measure on pipeline segments that could affect HCAs. In terms of
Sec. Sec. 195.450 and 195.452 the definition for check valve means a
valve that permits fluid to flow freely in one direction and contains a
mechanism to automatically prevent flow in the other direction.
Likewise, remote control valve or RCV means any valve that is operated
from a location remote from where the valve is installed. The RCV is
usually operated by the supervisory control and data acquisition
(SCADA) system. The linkage between the pipeline control center and the
RCV may be by fiber optics, microwave, telephone lines, or satellite.
Section 195.452(i)(4) further states that if an operator determines
that an EFRD is needed on a pipeline segment to protect a high
consequence area in the event of a hazardous liquid pipeline release,
an operator must install the EFRD. In making this determination, an
operator must, at least, consider the following factors--the swiftness
of leak detection and pipeline shutdown capabilities, the type of
commodity carried, the rate of potential leakage, the volume that can
be released, topography or pipeline profile, the potential for
ignition, proximity to power sources, location of nearest response
personnel, specific terrain between the pipeline segment and the high
consequence area, and benefits expected by reducing the spill size.
RSPA adopted the EFRD requirements in Sec. Sec. 195.450 and
195.452 in a December 2000 final rule December 1, 2000, (65 FR 75378).
Part 195 does not require that EFRDs be used on pipelines outside of
HCAs, but Sec. 195.260 does require that valves be installed at
certain locations.
Congress included additional requirements for the use of automatic
and remote-controlled shut-off valves in section 4 of the Pipeline
Safety Act of 2011. That provision requires the Secretary, if
appropriate and where economically, technically, and operationally
feasible, to issue regulations for the use of automatic and remote-
controlled shut-off valves on transmission lines that are newly
constructed or entirely replaced. The Comptroller General is also
required to perform a study on the effectiveness of these valves and to
provide a report to Congress within one year of the date of the
enactment of that legislation. PHMSA commissioned a study titled
``Studies for the Requirements of
[[Page 61628]]
Automatic and Remotely Controlled Shutoff Valves on Hazardous Liquids
and Natural Gas Pipelines With Respect to Public and Environmental
Safety,'' \5\ to help provide input on regulatory considerations
regarding the feasibility and effectiveness of automatic and remote-
control shutoff valves on hazardous liquid and natural gas transmission
lines. The study was completed by the Oak Ridge National Laboratory on
October 31, 2012, and it was submitted to Congress on December 27,
2012. PHMSA is using considerations from this study as it drafts a
rulemaking titled ``Amendments to Parts 192 and 195 to require Valve
installation and Minimum Rupture Detection Standards.''
---------------------------------------------------------------------------
\5\ https://www.phmsa.dot.gov/pv_obj_cache/pv_obj_id_2C1A725B08C5F72F305689E943053A96232AB200/filename/Final%20Valve_Study.pdf
---------------------------------------------------------------------------
Comments
PHMSA received comment on this issue from industry and trade
associations. API-AOPL, TxOGA, LMOGA, and TransCanada Keystone reported
that no industry standards currently address EFRD use, although ASME
B31.4, ``Pipeline Transportation Systems for Liquid Hydrocarbons and
Other Liquids'' (2009), addresses mainline valves and requires remote
operation and/or check valves in some instances. ASME B31.4 (2009) also
has guidelines for mainline valves and requires remote and check
valves, but is not currently incorporated by reference into part 195.
Section 195.452 does require that operators identify the need for
additional preventive and mitigation measures.
Response
PHMSA is studying issues concerning the development of additional
safety standards for the use of EFRDs. PHMSA will consider the industry
standards mentioned by the commenters, as well as the results of the
September 1996 Volpe Report, the December 2007 Leak Detection Study,
and the 2012 Oak Ridge National Laboratory study, for the purposes of
any future rulemaking on the topic.
Adequacy of Existing Industry Practices or Standards for EFRDs
PHMSA asked for comment on the adequacy of existing industry
practices or standards for EFRDs.
Comments
API-AOPL, TxOGA, LMOGA, and TransCanada Keystone stated that there
is no current industry standard that sets a maximum spill volume or
activation timing due to the widespread variation in pipeline dynamics;
therefore, it would be difficult to establish a one-size-fits-all
maximum spill volume requirement. API-AOPL suggests PHMSA should focus
on prevention and response rather than spill size reduction through
EFRDs.
Response
Section 195.452(i)(4) contains a requirement for the use of EFRDs
on hazardous liquid pipelines that could affect an HCA. PHMSA agrees
with the commenters that oil spill prevention and response are
important to ensuring the safety of hazardous liquid pipelines, and
believes that the appropriate use of EFRDs could be complementary to
these efforts.
Consideration of Additional Standards Specifying the Location of EFRDs
Part 195 requires that EFRDs be considered as potential mitigation
measure on pipeline segments that could affect HCAs, but it does not
specify any particular location for the use of those devices. Operators
must perform a risk analysis in determining whether and where to
install EFRDs for such lines. Part 195 does not require that EFRDs be
used on pipelines outside of HCAs. In the ANPRM, PHMSA asked for
comment on whether additional standards should be developed to specify
the location for EFRDs.
Comments
PHMSA received comments from four trade associations, one industry
operator, and one regulatory association regarding prescriptive
location of EFRDs. API-AOPL, TransCanada Keystone, LMOGA, and TxOGA
indicated PHMSA should not specify location of EFRD placement for the
reasons provided in response to previous questions. TPA agreed that no
general criteria beyond those in existing regulations are appropriate
because decisions on EFRD placement are driven by local factors. NAPSR
supported the comments of the trade associations.
Response
PHMSA recognizes the commenters' concerns about mandating the
installation of EFRDs in particular locations, but notes that other
provisions in part 195 require that valves and other safety devices be
installed in certain areas.
Mandated Use of EFRDs in All Locations
PHMSA requested comment on mandated use of EFRDs in all locations
under PHMSA jurisdiction.
Comments
API-AOPL, TransCanada Keystone, LMOGA, and TxOGA indicated that a
requirement to place EFRDs at predetermined locations or fixed
intervals would be arbitrary, costly, and potentially counterproductive
to pipeline safety. They noted that not all valves are mainline valves,
and that a requirement for all valves to be remote would cause
confusion. Many valves are at manned facilities. Some EFRDs are check
valves, which are not amenable to remote control. API-AOPL noted that
costs related to providing remote operation would vary based on
proximity to power and communications, but that a December 2010 study
by the Congressional Research Service estimated retrofit costs of $40K
to $1.5M per valve. NAPSR agreed with the comments supplied by the
trade associations and TransCanada Keystone. Finally, NSB stated EFRDs
should be required on all pipelines PHMSA regulates with specific
instruction on when and where EFRDs need to be utilized.
Response
PHMSA recognizes the commenters' concerns about mandating the
installation of EFRDs in all locations and plans on continuing to study
this issue.
Additional Research for Leak Detection
PHMSA requested comment regarding what leak detection technologies
or methods require further research and development to demonstrate
their efficacy.
Comments
PHMSA received no comments in response to this question.
D. Valve Spacing
Valve Spacing
The ANPRM asked whether PHMSA should repeal or modify the valve
spacing requirements in part 195. Specifically, the ANPRM asked:
For information on the average distance between valves;
Whether valves are manually operated or remotely
controlled;
Whether additional standards should be adopted for
evaluating valve spacing and location;
Whether the maximum permissible distance between valves
should be specified by regulation;
Whether to adopt additional valve spacing requirements for
hazardous liquid pipelines near HCAs;
Whether additional valve spacing requirements should be
adopted to protect narrower bodies of water;
[[Page 61629]]
Whether all valves should be remotely controlled; and
What the cost impact would be from requiring the
installation of certain types of valves.
As discussed below, PHMSA is not proposing to adopt any additional
standards for valve spacing, but will be considering that issue in
complying with the various mandates in the Pipeline Safety Act of 2011.
Part 195 contains general construction requirements for valves.
Specifically, Sec. 195.258 provides that each valve must be installed
in a location that is accessible to authorized employees and protected
from damage or tampering. This section further states that submerged
valves located offshore or in inland navigable waters must be marked,
or located by conventional survey techniques, to facilitate quick
location when operation of the valve is required.
PHMSA pipeline safety regulations found in section 195.260 indicate
that a valve must be installed at certain locations. The locations
named include on the suction end and the discharge end of a pump
station or a breakout storage tank area in a manner that permits
isolation of the tank area from other facilities and on each mainline
at locations along the pipeline system that will minimize damage or
pollution from accidental hazardous liquid discharge, as appropriate
for the terrain in open country, for offshore areas, or for populated
areas. Three additional requirements for valve location in section
195.260 include each lateral takeoff from a trunk line, on each side of
a water crossing that is more than 100 feet (30 meters) wide from high-
water mark to high-water mark and on each side of a reservoir holding
water for human consumption. The Department adopted these regulations
in an October 1969 final rule October 4, 1969, (34 FR 15475).
As discussed in section 3, part 195 requires the use of EFRDs as a
potential mitigation measure on pipeline segments that could affect
HCAs. As also discussed in section 3, Congress included new provisions
for the use of automatic and remote-controlled shut-off valves and leak
detection systems in the Pipeline Safety Act of 2011.
Information on Average Distance Between Valves and Manual or Remote
Operation
PHMSA asked the public to provide information on the average
distance between valves and whether such valves are manually operated
or remotely controlled.
Comments
The commenters did not provide any data on the average distance
between valves, but did provide general information on valve spacing,
location, and type. The commenters further noted that ASME B31.4, a
consensus industry standard, includes a minimum valve spacing
requirement of 7.5 miles for liquefied petroleum gas (LPG) and
anhydrous ammonia pipelines in populated areas.
Specifically, API-AOPL, LMOGA, TxOGA, and TransCanada Keystone
stated that valve spacing varies, that most mainline valves are
manually operated, that check valves are used in certain cases, and
that some remotely controlled valves had been added as a result of the
IM requirements. API-AOPL also commented that ASME B31.4 provides
additional requirements for LPG and anhydrous ammonia in populated
areas, including a 7.5-mile spacing requirement for valves, but noted
that PHMSA had not incorporated this version of B31.4 into part 195.
NAPSR stated that proper valve location is more important than distance
placement.
Response
Part 195 requires the installation of valves at certain locations,
including pump stations, breakout tanks, mainlines, lateral lines,
water crossings, and reservoirs. These requirements are generally
directed toward achieving a particular result (e.g., isolation of a
facility, minimization of damage or pollution, etc.) and do not mandate
that valves be installed at specific distances.
Part 195 does not prescribe whether manual or remotely controlled
valves must be installed at particular locations, but does require
consideration of check valves and remotely controlled valves under the
EFRD requirements for pipelines that could affect an HCA. Section 4 of
the Pipeline Safety Act of 2011 includes new requirements for
evaluating and issuing additional regulations for the use of the
automatic and remote-controlled shut-off valves.
PHMSA is not proposing to make any changes to the current valve
spacing requirements at this time. A coordinated analysis will ensure
that these issues are addressed in a way that maximizes the potential
benefits and minimizes the potential burdens imposed by any new leak
detection and valve spacing standards.
Adoption of Additional Standards for Valve Spacing and Location
PHMSA asked for comment on the adoption of additional standards for
valve spacing and location.
Comments
TransCanada Keystone, API-AOPL, TxOGA, and LMOGA stated that the
standards in Sec. Sec. 195.260 and 195.452 are satisfactory. NAPSR
supported the comments of API-AOPL. NSB recommended that DOT adopt
standards for pipeline operators to use in evaluating valve spacing and
location and identifying the maximum distance between valves.
Response
PHMSA is not proposing to adopt any additional standards for valve
spacing and locations, but will be considering that issue in complying
with the various mandates in the Pipeline Safety Act of 2011. PHMSA
held a public meeting/workshop on valve spacing and locations on March
28, 2012. Information from this workshop was used in Oak Ridge National
Laboratory's study, completed October 31, 2012, titled: ``Studies for
the Requirements of Automatic and Remotely Controlled Shutoff Valves on
Hazardous Liquids and Natural Gas Pipelines with Respect to Public and
Environmental Safety'' \6\ to help determine the need for additional
valve and location standards.
---------------------------------------------------------------------------
\6\ https://www.phmsa.dot.gov/pv_obj_cache/pv_obj_id_2C1A725B08C5F72F305689E943053A96232AB200/filename/Final%20Valve_Study.pdf
---------------------------------------------------------------------------
Additional Standards for Specifying the Maximum Distance Between Valves
PHMSA asked for public comment on whether part 195 should specify
the maximum permissible distance between valves.
Comment
API-AOPL, TxOGA, LMOGA, TransCanada Keystone, and TPA opposed such
a requirement and stated that valve spacing should be based on
conditions and terrain. NAPSR also supported this position. NSB and
MAWUC recommended the DOT adopt specific valve spacing standards. MAWUC
stated that the criteria for valve spacing should be developed, but
that the precise location of valves should not be made publicly
available.
Response
Similarly, PHMSA is not proposing to adopt any additional standards
for valve spacing at this time. PHMSA will be studying this issue and
may make proposals concerning this topic in a later rulemaking.
[[Page 61630]]
Additional Requirements for Valve Spacing Near HCAs Beyond Those
Required for EFRDs
PHMSA asked for public comment on whether part 195 should contain
additional requirements for valve spacing in areas near HCAs beyond
what is already required in Sec. 195.452(i)(4) for EFRDs.
Comments
NSB encouraged PHMSA to adopt additional requirements for these
areas. Taking a contrary position, API-AOPL, LMOGA, TxOGA, NAPSR, and
TransCanada Keystone indicated that the current requirements adequately
address the need for EFRDs and allow operators to assess the specific
risks on each individual pipeline that could affect an HCA.
Response
PHMSA does not propose to make any changes to the regulations
concerning the valve spacing at this time. PHMSA will be studying this
issue and may make proposals concerning this topic in a later
rulemaking.
Modifying the Scope of 49 CFR 195.260(e) To Include Narrower Bodies of
Water
Section 195.260(e) requires the installation of a valve ``[o]n each
side of a water crossing that is more than 100 feet (30 meters) wide
from high-water mark to high-water mark unless the Administrator finds
in a particular case that valves are not justified.'' The Department
adopted that requirement in an October 1969 final rule October 4, 1969,
(34 FR 15475) after adding the provision that allows the Administrator
to find that the installation of a valve is not justified in specific
cases. Such a finding requires the filing of a petition with the
Administrator under 49 CFR 190.9.
Comments
API-AOPL, TxOGA, LMOGA, and TransCanada Keystone indicated that the
current water crossing requirements are adequate, but that PHMSA could
improve the regulation by allowing a risk-based approach for valve
placement at water crossings and adding an exclusion for carbon dioxide
pipelines.
TWS stated that PHMSA should require valves for waterways that are
at least 25-feet in width and all feeder streams and creeks leading to
such waterways. NSB supported the view of TWS and indicated the current
100-foot threshold for waterways should be reduced to 25 feet.
Response
As mentioned previously, PHMSA is proposing that all pipelines be
inspected after extreme weather events or natural disasters. This is a
natural extension of IM and ensures continued safe operations of the
pipeline after abnormal operating conditions. Past events have strongly
demonstrated that inspections after these events do prevent pipeline
incidents from occurring. PHMSA is also proposing to require that all
hazardous liquid pipelines have leak detection systems; that pipelines
in areas that could affect HCAs be capable of accommodating ILIs within
20 years, unless the basic construction of the pipeline will not permit
such an accommodation; that periodic assessments be performed of
pipelines that are not already receiving such assessments under the IM
program requirements; and that modified repair criteria be applied to
pipelines in all locations. PHMSA will comply with the applicable
provisions in the Pipeline Safety Act of 2011 before adopting any of
these proposals in a final rule.
Adopting Safety Standards That Require All Valves To Be Remotely
Controlled
PHMSA asked the public to comment on whether part 195 should
include a requirement mandating the use of remotely-controlled valves
in all cases.
Comments
API-AOPL, LMOGA, and TxOGA stated that PHMSA should not require
remotely controlled valves in all cases. API-AOPL indicated that such a
requirement would cause confusion as to which valves need to be
operated manually, burden the industry with additional costs, and
provide minimal safety benefits. API-AOPL submitted that the costs of
retrofitting a valve to be remotely controlled varies widely from
$40,000 to $1.5 million per valve as indicated in a recent report
issued by the Congressional Research Service on pipeline safety and
security. TPA further stated that the benefits of such requirements are
dependent on local factors, and that additional requirements would add
to pipeline system complexity and increase the probability of failure.
Similarly, NAPSR stated that remote control valves should not be
required, but that PHMSA should consider performance language for
maximum response time to operate manual valves.
MAWUC indicated that PHMSA should consider requiring all valves to
be remotely controlled, but that its decision should be based on an
analysis of benefits and risks. NSB supported the use of remotely
controlled valves in all instances. Coyle, a citizen, commented that
PHMSA should promulgate regulatory language requiring remotely
controlled valves for poison inhalation hazard pipelines.
Response
PHMSA notes that a risk-assessment must be performed in developing
any new safety standards for the use of remotely controlled valves, and
that any such standards will only be proposed upon a reasoned
determination that the benefits justify the costs.
Requiring Installation of EFRDs To Protect HCAs
Section 195.452(i)(4) does not require the installation of an EFRD
on all pipeline segments that could affect HCAs. Rather, it states that
``[i]f an operator determines that an EFRD is needed on a pipeline
segment to protect a high consequence area in the event of a hazardous
liquid pipeline release, an operator must install the EFRD.'' It also
states that an operator must at least consider a list of factors in
making that determination.
Comments
API-AOPL, LMOGA, TxOGA and TransCanada Keystone stated that Sec.
192.452 already requires EFRDs to be installed to protect a HCA if the
operator finds, through a risk assessment, that an HCA is threatened.
MAWUC commented that EFRDs should be required if they can limit a
spill. Likewise, NSB supported the use of EFRDs for HCAs.
Response
PHMSA does not propose to make any changes to the regulations
concerning the use of EFRDs at this time. PHMSA will be studying this
issue and may make proposals concerning this topic in a later
rulemaking.
Determining the Applicability of New Valve Location Requirements
In the ANPRM, PHMSA asked for public comment on how the agency
should apply any new valve location requirements that are developed for
hazardous liquid pipelines.
Comments
The trade association, API-AOPL, supported by TransCanada Keystone,
LMOGA, and TxOGA, indicated that valve spacing requirements should not
be changed, and that delineating new construction for any type of
grandfathering purpose would be difficult and confusing. Requiring
retrofitting of existing lines to meet any
[[Page 61631]]
type of new requirement would be expensive for industry, create
environmental impacts, potential construction accidents, and may cause
interruption of service.
The regulatory association, NAPSR, suggested that exemptions to new
valve location requirements should be based on the consequence of
failure. Particular attention should be paid to spills into water as
even a small spill can create a large problem.
Two government/municipalities commented. MAWUC indicated that there
should be no waivers for valve spacing in HCAs due to the importance
and interconnectivity of water supplies. NSB recommended that any new
valve locations or remote actuation regulation be applied to new
pipelines or existing pipelines that are repaired.
Response
PHMSA will continue to study valve spacing and automatic valve
placement and may address these issues in a future rulemaking.
E. Repair Criteria Outside of HCAs
Repair Criteria
The ANPRM asked for public comment on whether to extend the IM
repair criteria in Sec. 195.452(h) to pipeline segments that are not
located in HCAs. Specifically, the ANPRM asked ``Whether the IM repair
criteria should apply to anomalous conditions discovered in areas
outside of HCAs; whether the application of the IM repair criteria to
non-HCA areas should be tiered on the basis of risk; what schedule
should be applied to the repair of anomalous conditions discovered in
non-HCA areas; whether standards should be specified for the accuracy
and tolerance of inline inspection (ILI) tools; and whether additional
standards should be established for performing ILI inspections with
``smart pigs''.
As discussed below, PHMSA is proposing to modify the provisions for
making pipeline repairs. Additional conservatism will be incorporated
into the existing IM repair criteria and an adjusted schedule for
making immediate and non-immediate repairs will be established to
provide greater uniformity. These criteria will also be made applicable
to all pipelines, with an extended timeframe for making repairs outside
of HCAs.
Application of IM Repair Criteria to Anomalous Conditions Discovered
Outside of HCAs
In the ANPRM, PHMSA asked for comment on whether the IM repair
criteria should apply to anomalous conditions discovered in areas
outside of HCAs.
Comments
API-AOPL, supported by TransCanada Keystone, LMOGA, and TxOGA,
stated that the repair criteria in or outside of HCAs should be the
same. Likewise, the citizens' groups TWS and AKW echoed the comments of
API-AOPL and further recommended that a phased-in time period should be
utilized. NSB commented that anomalous conditions found during
inspection in non-HCA areas should trigger expedited repair times.
Response
Section 195.452(h) specifies the actions that an operator must take
to address integrity issues on hazardous liquid pipelines that could
affect an HCA in the event of a leak or failure. Those actions include
initiating temporary and long-term pressure reductions and evaluating
and remediating certain anomalous conditions (e.g., metal loss, dents,
corrosion, cracks, gouges, grooves, and other any condition that could
impair the integrity of the pipelines). Depending on the severity of
the condition, such actions must be taken immediately, within 60 days,
or within 180 days of the date of discovery.
Section 5 of the Pipeline Safety Act of 2011 requires the Secretary
to perform an evaluation to determine if the IM requirements should be
extended outside of and to submit a report to Congress with the result
of that review. The Secretary is authorized to collect data for
purposes of completing the evaluation and report to Congress. Section 5
also prohibits the issuance of any final regulations that would expand
the IM requirements during a subsequent Congressional review period,
subject to a savings clause that permits such action if a condition
poses a risk to public safety, property, or the environment or is an
imminent hazard and the regulations in question will address that risk
or imminent hazard.
PHMSA is proposing to make certain modifications to the IM repair
criteria and to establish similar repair criteria for pipeline segments
that are not located in HCAs. Specifically, the repair criteria in
Sec. 195.452(h) would be amended to:
Categorize bottom-side dents with stress risers as
immediate repair conditions;
Require immediate repairs whenever the calculated burst
pressure is less than 1.1 times MOP;
Eliminate the 60-day and 180-day repair categories; and
Establish a new, consolidated 270-day repair category.
PHMSA is also proposing to adopt new requirements in Sec. 195.422 that
would: Apply the criteria in the immediate repair category in Sec.
195.452(h) and Establish an 18-month repair category for hazardous
liquid pipelines that are not subject to the IM requirements.
These changes will ensure that immediate action is taken to
remediate anomalies that present an imminent threat to the integrity of
hazardous liquid pipelines in all locations. Many anomalies that would
not qualify as immediate repairs under the current criteria will meet
that requirement as a result of the additional conservatism that will
be incorporated into the burst pressure calculations. The new
timeframes for performing other repairs will allow operators to
remediate those conditions in a timely manner while allocating
resources to those areas that present a higher risk of harm to the
public, property, and the environment.
Use of a Tiered, Risk-Based Approach for Repairing Anomalous Conditions
Discovered Outside of HCAs
In the ANPRM, PHMSA asked for comment on whether the application of
the IM repair criteria to non-HCA areas should be tiered on the basis
of risk.
Comments
API-AOPL, LMOGA, TPA, TxOGA, and TransCanada Keystone commented
that PHMSA should not impose any sort of tiering to repair criteria
because that is already inherent to the IM program. Scheduling
flexibility would minimize disruption to the affected public, as well
as the overall environmental impact, by preventing multiple excavation
work on a given property. Requiring additional risk tiering of
anomalies would not reduce safety risks to the public.
NAPSR, in contrast, commented that tiering should be utilized for
repair criteria inside or outside of HCAs. NSB also indicated that risk
tiering should be used. MAWUC supported risk tiering based on
preselected criteria for HCAs.
Response
As previously discussed, PHMSA is proposing to apply new repair
criteria for anomalous conditions discovered on hazardous liquid
pipelines that are not located in HCAs. PHMSA is also proposing to
establish two timeframes for performing those repairs: immediate repair
conditions and 18-month repair conditions. If adopted as proposed,
these changes will ensure the prompt remediation of anomalous
conditions on all hazardous liquid pipeline segments, while allowing
operators to allocate
[[Page 61632]]
their resources to those areas that present a higher risk of harm to
the public, property, and the environment.
Updating of Dent With Metal Loss Repair Criteria
Section 195.452(h) contains the criteria for repairing dents with
metal loss on hazardous liquid pipeline segments that could affect an
HCA in the event of a leak or failure. PHMSA asked for comment on
whether advances in ILI tool capability justified an update in the
dent-with-metal-loss repair criteria.
Comments
API-AOPL, LMOGA, TxOGA, and TransCanada Keystone indicated that the
anticipated update to API 1160 will contain proposals to update the
dent-with-metal-loss repair criterion. API-AOPL intends to support
these proposals with data resulting from analyses of member company's
experience measuring and characterizing metal loss in dents.
NAPSR encouraged PHMSA not to make the current standards less
stringent even for dents without metal loss, citing a recent bottom
side dent less than 6 inches that failed. NAPSR recommended
strengthening the repair criteria for bottom-side dents in areas of
heavy traffic or near swamps/bogs or in clay soils.
Response
As previously discussed, PHMSA is proposing to categorize bottom-
side dents with stress risers as an immediate repair condition and to
require immediate repairs when calculated burst pressure is less than
1.1 times MOP. These changes should ensure the prompt and effective
remediation of anomalous conditions on all pipeline segments. With
respect to API 1160, PHMSA will consider incorporating the 2013 edition
in a future rulemaking.
Adoption of Explicit Standards To Account for Accuracy of ILI Tools
PHMSA requested comment on whether to adopt an explicit standard to
account for the accuracy of ILI tools when comparing ILI data with
repair criteria.
Comments
API-AOPL supports PHMSA's adoption of API 1163, the ``In-Line
Inspection Systems Qualification Standard''. That standard includes a
System Results Verification section, which describes methods to verify
that the reported inspection results meet, or are within, the
performance specification for the pipeline being inspected. That
standard also requires that inconsistencies uncovered during the
process validation be evaluated and resolved.
NAPSR supports the adoption of a standard because the IM process
already is considering tool accuracy during the selection process and
suggests revising the regulations to provide minimum standards of
expected accuracy.
Response
In reviewing IM inspection data, PHMSA discovered that some
operators were not considering the accuracy (i.e., tolerance) of ILI
tools when evaluating the results of the tool assessments. As a result,
random variation within the recorded data led to both overcalls (i.e.,
an anomaly was identified to be more extreme than it actually was) and
under calls. Over calls are conservative, resulting in repair of some
anomalies that might not actually meet repair criteria. Under calls are
not and can result in anomalies that exceed specified repair criteria
going un-remediated. Based on our review of inspection data, PHMSA has
concluded that operators should be explicitly required to consider the
accuracy of their ILI tools.
Specifically, under the proposed amendment to Sec.
195.452(c)(1)(i) and the new provisions in Sec. 195.416, operators
will be required to consider tool tolerance and other uncertainties in
evaluating ILI results for all hazardous liquid pipeline segments. Tool
accuracy should include excavation findings and usage of unity plots of
inline tool and excavation findings. When combined with the proposed
changes to the repair criteria, the proposed tool tolerance requirement
will ensure the prompt detection and remediation of anomalous
conditions on all hazardous liquid pipelines. With respect to API 1163,
as of January 2013, PHMSA is required by section 24 of the Pipeline
Safety, Regulatory Certainty, and Job Creation Act of 2011 not to
incorporate any consensus standards that are not available to the
public, for free, on an internet Web site. PHMSA has sought a solution
to this issue and as a result, all incorporated by reference standards
in the pipeline safety regulations would be available for viewing to
the public for free.
Additional Quality Control Standards for ILI Tools, Assessments, and
Data Review
In the ANPRM, PHMSA asked if additional quality control standards
are needed for conducting ILIs using smart pigs, the qualification of
persons interpreting ILI data, the review of ILI results, and the
quality and accuracy of ILI tool performance.
Comments
API-AOPL, LMOGA, TxOGA, and TransCanada Keystone commented that
PHMSA should adopt API 1163 and American Society of Nondestructive
Testing ILI PQ. These commenters stated that a certification program
for analyzing ILI data would not add value to pipeline operators' IM
programs, as operator experience has shown that these types of programs
do not adequately reflect the highly technical nature of, and the
intimate knowledge and experience of personnel practicing, IM programs.
According to the commenters, there is no evidence that the current
requirements and industry standards are leaving the public or
environment at risk.
NAPSR indicated that if there is data to show this is an issue,
PHMSA should adopt a standard. Additionally, a state could impose a
more stringent standard based on prior experience. Both the NSB and
MAWUC supported adoption of standards for ILI use.
Response
As noted in the response to the previous question, PHMSA is
proposing to require operators to consider tool tolerance and other
uncertainties in evaluating ILI results in complying with the IM
requirements of Sec. 195.452 and the proposed assessment requirement
in Sec. 195.416. PHMSA believes that this requirement and the proposed
changes to the repair criteria will ensure the prompt detection and
remediation of anomalous conditions (e.g., metal loss, dents,
corrosion, cracks, gouges, grooves) that could adversely affect the
safe operation of a pipeline. PHMSA is proposing by a separate
rulemaking via incorporation by reference available industry consensus
standards for performing assessments of pipelines using ILI tools,
internal corrosion direct assessment, and stress corrosion cracking
direct assessment.
F. Stress Corrosion Cracking
In the October 2010 ANPRM, PHMSA asked for public comment on
whether to adopt additional safety standards for stress corrosion
cracking (SCC). SCC is cracking induced from the combined influence of
tensile stress and a corrosive medium. Sections 195.553 and 195.588 and
Appendix C of the Hazardous Liquid Pipeline Safety Standards contain
provisions for the direct assessment of SCC, but do not include
comprehensive requirements for preventing, detecting, and remediating
that condition.
[[Page 61633]]
Specifically, PHMSA asked in the ANPRM whether:
Any existing industry standards for preventing, detecting,
and remediating SCC should be incorporated by reference;
Any data or statistics are available on the effectiveness
of these industry standards;
Any data or statistics are available on the effectiveness
of SCC detection tools and methodologies;
Any tools or methods are available for detecting SCC
associated with longitudinal pipe seams;
An SCC threat analysis should be conducted for all
pipeline segments;
Any particular integrity assessment methods should be used
when SCC is a credible threat; and
Operators should be required to perform a periodic
analysis of the effectiveness of their corrosion management programs.
Adoption of NACE Standard for Stress Corrosion Cracking Direct
Assessment Methodology or Other Industry Standards
In the ANPRM, PHMSA asked for comment on whether the agency should
incorporate any consensus industry standards for assessing SCC,
including the NACE International (NACE) SP0204-2008 (formerly RP0204),
Stress Corrosion Cracking (SCC) Direct Assessment Methodology. https://www.nace.org/uploadedFiles/Committees/SP020408.pdf (last accessed
December 12, 2013) (stating that SP0204-2008 ``provides guidance for
managing SCC by selecting potential pipeline segments, selecting dig
sites within those segments, inspecting the pipe and collecting and
analyzing data during the dig, establishing a mitigation program,
defining the reevaluation interval, and evaluating the effectiveness of
the SCC [direct assessment] process.'').
Comments
API-AOPL, TransCanada Keystone, TxOGA, and LMOGA stated that NACE
SP0204-2008 provides an effective framework for the application of
direct assessment, but does not sufficiently address other assessment
methods, including ILI and hydrostatic testing. These commenters were
also not aware of any industry statistics that directly correlate the
application of that standard to the SCC detection or failure rate.
These commenters stated the most appropriate standard for SCC
assessment of hazardous liquid pipelines is the soon-to-be-released
version of API Standard 1160, Managing System Integrity for Hazardous
Liquid Pipelines.
Another trade association, TPA, stated that ``because [the NACE
Standard] was just finished in 2008, PHMSA should wait at least 2-3
years more before attempting to assess the desirability of
incorporating that standard into the regulations.''
One regulatory association, MAWUC, commented that PHMSA should
adopt standards that address direct assessment, prevention, and
remediation of SCC. The municipality/government entity, NSB, offered a
similar comment.
Response
The commenters did not indicate that NACE SP0204-2008 would address
the full lifecycle of SCC safety issues. Moreover, none of the
commenters identified any other industry standards that would be
appropriate for adoption at this time.
PHMSA recognizes that SCC is an important safety concern, but does
not believe that further action can be taken based on the information
available in this proceeding. PHMSA is establishing a team of experts
to study this issue and will be holding a public forum on the
development of SCC standards. Once that process is complete, PHMSA will
consider whether to establish new safety standards for SCC. With
respect to NACE SP0204-2008 PHMSA is proposing this standard by a
separate rulemaking via incorporation by reference.
Identification of Standards and Practices for Prevention, Detection,
Assessment and Remediation of SCC
PHMSA asked the public to identify any other standards and
practices for the prevention, detection, assessment, and remediation of
SCC.
Comments
API-AOPL, LMOGA, and TxOGA indicated that there are several good
standards that address SCC, including API 1160, ASME STP-PT-011,
Integrity Management of Stress Corrosion Cracking in Gas Pipeline High
Consequence Areas, and the Canadian Energy Pipeline Association (CEPA)
Stress Corrosion Cracking Recommended Practices (CEPA SCC RP), but
acknowledged that all of these standards have weaknesses.
The trade association, CEPA, also stated that the 2008 ASME STP-PT-
011 should be considered. While written for gas pipelines, CEPA stated
that this standard could be adapted to hazardous liquids.
Response
PHMSA appreciates the information provided by the commenters. PHMSA
will be studying the SCC issue and will consider incorporating by
reference suggested standards in future rulemakings.
Implementation of Canadian Energy Pipeline Association RP on SCC
CEPA is an organization that represents Canada's transmission
pipeline companies. In 1997, CEPA developed its SCC Recommended
Practice (RP) in response to a public inquiry by National Energy Board
of Canada. In 2007, CEPA released an updated version of its SCC RP,
https://www.cepa.com/wp-content/uploads/2011/06/Stress-Corrosion-Cracking-Recommended-Practices-2007.pdf. In the ANPRM, PHSMA asked for
comment on the experience of operators in implementing CEPA's SCC RP.
Comments
API-AOPL, LMOGA, TxOGA, and TransCanada Keystone commented that the
CEPA SCC RP provides the most thorough overview of the various
assessment techniques, but is limited to near neutral SCC in terms of
causal considerations. These commenters also stated that there are no
industry statistics on the application of the CEPA RP SCC. CEPA and
API-AOPL both indicated that companies continue to use the CEPA SCC RP
as a guideline, but that there are no statistics on its use.
Response
PHMSA appreciates the comments provided on the use of the CEPA SCC
RP and will consider that standard in its study of comprehensive safety
requirements for SCC and in future rulemakings.
Effectiveness of SCC Detection Tools and Methods
PHMSA requested comment as to the effectiveness of current SCC
detection tools and methods.
Comments
API-AOPL, supported by LMOGA, TxOGA, and TransCanada Keystone,
stated that there are no industry statistics that directly correlate
the application of the CEPA RP to the SCC detection or failure rate,
but that the National Energy Board of Canada has noted the
effectiveness of the CEPA RP for managing SCC. API-AOPL also stated the
planned revisions of API 1160 and 1163 will address the current gaps
regarding SCC in the standards and recommended practices relevant to
liquid pipelines. One citizens' group,
[[Page 61634]]
TWS, mentioned that gathering lines do not require corrosion prevention
and that this should be required.
Response
PHMSA appreciates the comments provided on the effectiveness of SCC
detection tools and methods and will be considering that information in
evaluating comprehensive safety requirements for SCC and consider
incorporating in future rulemakings.
IV. Section-by-Section Analysis
Sec. 195.1 Which pipelines are covered by this part?
Section 195.1(a) lists the pipelines that are subject to the
requirements in part 195, including gathering lines that cross
waterways used for commercial navigation as well as certain onshore
gathering lines (i.e., those that are located in a non-rural area, that
meet the definition of a regulated onshore gathering line, or that are
located in an inlet of the Gulf of Mexico). PHMSA has determined that
additional information about unregulated gathering lines is needed to
fulfill its statutory obligations. Accordingly, the NPRM extend the
reporting requirements in subpart B of part 195 to all gathering lines
(whether regulated, unregulated, onshore, or offshore) by adding a new
paragraph (a)(5) to Sec. 195.1.
Sec. 195.2 Definitions
Section 195.2 provides definitions for various terms used
throughout part 195. On August 10, 2007, (72 FR 45002; Docket number
PHMSA-2007-28136) PHMSA published a policy statement and request for
comment on the transportation of ethanol, ethanol blends, and other
biofuels by pipeline. PHMSA noted in the policy statement that the
demand for biofuels was projected to increase in the future as a result
of several federal energy policy initiatives, and that the predominant
modes for transporting such commodities (i.e., truck, rail, or barge)
would expand over time to include greater use of pipelines. PHMSA also
stated that ethanol and other biofuels are substances that ``may pose
an unreasonable risk to life or property'' within the meaning of 49
U.S.C. 60101(a)(4)(B) and accordingly these materials constitute
``hazardous liquids'' for purposes of the pipeline safety laws and
regulations.
PHMSA is now proposing to modify its definition of hazardous liquid
in Sec. 195.2. Such a change would make clear that the transportation
of biofuel by pipeline is subject to the requirements of 49 CFR part
195.
PHMSA is also proposing to add a new definition of ``Significant
Stress Corrosion Cracking.'' This new definition will provide criteria
for determining when a probable crack defect in a pipeline segment must
be excavated and repaired.
Sec. 195.11 What is a regulated rural gathering line and what
requirements apply?
Section 195.11 defines and establishes the requirements that are
applicable to regulated rural gathering lines. PHMSA has determined
that these lines should be subject to the new requirements in the NPRM
for the performance of periodic pipeline assessments and pipeline
remediation and for establishing leak detection systems. Consequently,
the NPRM would amend Sec. 195.11 by adding paragraphs (b)(12) and (13)
to ensure that these requirements are applicable to regulated rural
gathering lines.
Sec. 195.13 What requirements apply to pipelines transporting
hazardous liquids by gravity?
Section 195.13 will be added which subjects gravity lines to the
same reporting requirements in subpart B of part 195 as other hazardous
liquid pipelines. PHMSA has determined that additional information
about gravity lines is needed to fulfill its statutory obligations.
Sec. 195.120 Passage of Internal Inspection Devices
Section 195.120 contains the requirements for accommodating the
passage of internal inspection devices in the design and construction
of new or replaced pipelines. PHMSA has decided that, in the absence of
an emergency or where the basic construction makes that accommodation
impracticable, a pipeline should be designed and constructed to permit
the use of ILIs. Accordingly, the NPRM would repeal the provisions in
the regulation that allow operators to petition the Administrator for a
finding that the ILI compatibility requirement should not apply as a
result of construction-related time constraints and problems. The other
provisions in Sec. 195.120 would be re-organized without altering the
existing substantive requirements.
Sec. 195.134 Leak Detection
Section 195.134 contains the design requirements for computational
pipeline monitoring leak detection systems. The NPRM would restructure
the existing requirements into paragraphs (a) and (b) and add a new
provision in paragraph (c) to ensure that all newly constructed
pipelines are designed to include leak detection systems based upon
standards in section 4.2 of API 1130 or other applicable design
criteria in the standard.
Sec. 195.401 General Requirements
Section 195.401 prescribes general requirements for the operation
and maintenance of hazardous liquid pipelines. PHMSA is proposing to
modify the pipeline repair requirements in Sec. 195.401(b). Paragraph
(b)(1) will be modified to reference the new timeframes in Sec.
195.422 for performing non-IM repairs. The requirements in paragraph
(b)(2) for IM repairs will be retained without change. A new paragraph
(b)(3) will be added, however, to clearly require operators to consider
the risk to people, property, and the environment in prioritizing the
remediation of any condition that could adversely affect the safe
operation of a pipeline system, including those covered by the
timeframes specified in Sec. Sec. 195.422(d) and (e) and 195.452(h).
Sec. 195.414 Inspections of Pipelines in Areas Affected by Extreme
Weather, a Natural Disaster, and Other Similar Events
Extreme weather, natural disasters and other similar events can
affect the safe operation of a pipeline. Accordingly, the NPRM would
establish a new regulation in Sec. 195.414 that would require
operators to perform inspections after these events and to take
appropriate remedial actions.
Sec. 195.416 Pipeline Assessments
Periodic assessments, particularly with ILI tools, provide critical
information about the condition of a pipeline, but are only currently
required under IM requirements in Sec. Sec. 195.450 through 195.452.
PHMSA has determined that operators should be required to have the
information that is needed to promptly detect and remediate conditions
that could affect the safe operation of pipelines in all areas.
Accordingly, the NPRM would establish a new regulation in Sec. 195.416
that requires operators to perform an assessment of pipelines that are
not already subject to the IM requirements at least once every 10
years. The regulation would require that these assessments be performed
with an ILI tool, unless an operator demonstrates and provides 90-days
prior notice that a pipeline is not capable of accommodating such a
device and that an alternative method will provide a substantially
equivalent understanding of its condition.
[[Page 61635]]
The regulation would also require that the results of these
assessments be reviewed by a person qualified to determine if any
conditions exist that could affect the safe operation of a pipeline;
that such determinations be made promptly, but no later than 180 days
after the assessment; that any unsafe conditions be remediated in
accordance with the new requirements in Sec. 195.422 of the NPRM; and
that all relevant information about the pipeline be considering in
complying with the requirements of Sec. 195.416.
Sec. 195.422 Pipeline Remediation
Section 195.422 contains the requirements for performing pipeline
repairs. PHMSA has determined that new criteria should be established
for remediating conditions that affect the safe operation of a
pipeline. The NPRM would add a new paragraph (a) specifying that the
provisions in the regulation are applicable to pipelines that are not
subject to the IM requirements in Sec. 195.452 (e.g., not in HCAs).
Paragraphs (b) and (c) would contain the existing requirements in the
regulation, including the general duty clause for ensuring public
safety and the provision noting the applicability of the design and
construction requirements to piping and equipment used in performing
pipeline repairs. Paragraph (d) would establish a new remediation
schedule based on the analogous provisions in the IM requirements for
performing immediate and 18-month repairs, and paragraph (e) would
contain a residual provision for remediating all other conditions.
Sec. 195.444 Leak Detection
Section 195.444 contains the operation and maintenance requirements
for Computational Pipeline Monitoring leak detection systems. PHMSA is
proposing that all pipelines should have leak detection systems.
Therefore, the NPRM would reorganize the existing requirements of the
regulation into paragraphs (a) and (c), and add a new general provision
in paragraph (b) that would require operators to have leak detection
systems on all pipelines and to consider certain factors in determining
what kind of system is necessary to protect the public, property, and
the environment.
Section 195.452 Pipeline Integrity Management in High Consequence Areas
Section 195.452 contains the IM requirements for hazardous liquid
pipelines that could affect a HCA in the event of a leak or failure.
The NPRM would clarify the applicability of the deadlines in paragraph
(b) for the development of a written program for new pipelines,
regulated rural gathering lines, and low-stress pipelines in rural
areas. Paragraph (c)(1)(i)(A) would also be amended to ensure that
operators consider uncertainty in tool tolerance in reviewing the
results of ILI assessments. Paragraph (d) would be amended to eliminate
obsolete deadlines for performing baseline assessments and to clarify
the requirements for newly-identified HCAs. Paragraph (e)(1)(vii) is
amended to include local environmental factors that might affect
pipeline integrity. Paragraph (g) would be amended to expand upon the
factors and criteria that operators must consider in performing the
information analysis that is required in periodically evaluating the
integrity of covered pipeline segments. Paragraph (h)(1) would also be
amended by modifying the criteria, and establishing a new, consolidated
timeframe, for performing immediate and 270-day pipeline repairs based
on the information obtained as a result of ILI assessments or through
an information analysis of a covered segment.
PHMSA is also proposing to amend the existing ``discovery of
condition'' language in the pipeline safety regulations. The revised
Sec. 195.452(h)(2) will require, in cases where a determination about
pipeline threats has not been obtained within 180 days following the
date of inspection, that pipeline operators must notify PHMSA and
provide an expected date when adequate information will become
available. Paragraphs 195.452(h)(4)(i)(E) and (F) are also added to
address issues of significant stress corrosion cracking and selective
seam corrosion.
PHMSA proposes further changes to Sec. 195.452. These changes
include paragraph (j) which would be amended to establish a new
provision for verifying the risk factors used in identifying covered
segments on at least an annual basis, not to exceed 15 months. A new
paragraph (n) would also be added to require that all pipelines in
areas that could affect an HCA be made capable of accommodating ILI
tools within 20 years, unless the basic construction of a pipeline will
not permit that accommodation or the existence of an emergency renders
such an accommodation impracticable. Paragraph (n) would also require
that pipelines in newly-identified HCAs after the 20-year period be
made capable of accommodating ILIs within five years of the date of
identification or before the performance of the baseline assessment,
whichever is sooner. Finally, an explicit reference to seismicity will
be added to factors that must be considered in establishing assessment
schedules under paragraph (e), for performing information analyses
under paragraph (g), and for implementing preventive and mitigative
measures under paragraph (i).
V. Regulatory Notices
A. Executive Order 12866, Executive Order 13563, and DOT Regulatory
Policies and Procedures
Executive Orders 12866 and 13563 require agencies to regulate in
the ``most cost-effective manner,'' to make a ``reasoned determination
that the benefits of the intended regulation justify its costs,'' and
to develop regulations that ``impose the least burden on society.''
This action has been determined to be significant under Executive Order
12866 and the Department of Transportation's Regulatory Policies and
Procedures. It has been reviewed by the Office of Management and Budget
in accordance with Executive Order 13563 (Improving Regulation and
Regulatory Review) and Executive Order 12866 (Regulatory Planning and
Review) and is consistent with the requirements in both orders.
In the regulatory analysis, we discuss the alternatives to the
proposed requirements and, where possible, provide estimates of the
benefits and costs for specific regulatory requirements in the eight
areas. The regulatory analysis provides PHMSA's best estimate of the
impact of the separate requirements. The chart below summarizes the
cost/benefit analysis:
Annualized Costs and Benefits by Requirement Area Discounted at 7 Percent
----------------------------------------------------------------------------------------------------------------
Requirement area Costs Benefits Net benefits
----------------------------------------------------------------------------------------------------------------
1. Extend certain reporting $900................... Benefits not Expected to be
requirements to all hazardous liquid quantified, but positive.
(HL) gravity lines. expected to justify
costs.
[[Page 61636]]
2. Extend certain reporting 23,300................. Benefits not quantified Expected to be
requirements to all hazardous liquid but expected to positive.
(HL) gathering lines. justify the costs.
3. Require inspections of pipelines 1.5 million............ 3.5 to 10.4 million.... 2.0 to 8.9 million
in areas affected by extreme
weather, natural disasters, and
other similar events, as well as
appropriate remedial action if a
condition that could adversely
affect the safe operation of a
pipeline is discovered.
4. Require periodic assessments of 16.7 million........... 17.7 million........... 1 million
pipelines that are not already Range 9.4-26.0 million. Range (-)7.3-9.3
covered under the IM program million
requirements using an in-line Expected to be positive
inspection tool (or demonstrate to even at the low end of
the satisfaction of PHMSA that the the benefit range if
pipeline is not capable of using unquantified benefits
this tool). are included.
5. Require use of leak detection Not quantified but Not quantified, but Not quanitified, but
systems (LDS) on new HL pipelines expected to be minimal. expected to justify positive qualitative
located in non-HCAs to mitigate the the minimal costs. benefits.
effects of failures that occur
outside of HCAs.
6. Modify the IM repair criteria, Not quantified, but Not quantified, but Not quantified, but
both by expanding the list of expected to be minimal. expected to justify expected to be
conditions that require immediate the minimal costs. minimal.
remediation, consolidating the
timeframes for remediating all other
conditions, and making explicit
deadlines for repairs on non-IM
pipeline.
7. Increase the use of inline 1.0 million............ 12.2 million........... 11.2 million
inspection (ILI) tools by requiring
that any pipeline that could affect
an HCA be capable of accommodating
these devices within 20 years,
unless its basic construction will
not permit that accommodation.
8. Clarify and resolve 3.2 million............ 10.0 million........... 6.8 million.
inconsistencies regarding deadlines,
and information analyses for IM
Plans t.
----------------------------------------------------------------------------------------------------------------
Overall, factors such as increased safety, public confidence that
all pipelines are regulated, quicker discovery of leaks and mitigation
of environmental damages, and better risk management are expected to
yield benefits that are in excess of the cost. PHMSA seeks comment on
the Preliminary Regulatory Evaluation, its approach, and the accuracy
of its estimates of costs and benefits. A copy of the Preliminary
Regulatory evaluation has been placed in the docket.
B. Executive Order 13132: Federalism
This NPRM has been analyzed in accordance with the principles and
criteria contained in Executive Order 13132 (``Federalism''). This NPRM
does not propose any regulation that has substantial direct effects on
the states, the relationship between the national government and the
states, or the distribution of power and responsibilities among the
various levels of government. It does not propose any regulation that
imposes substantial direct compliance costs on state and local
governments. Therefore, the consultation and funding requirements of
Executive Order 13132 do not apply. Nevertheless, PHMSA has and will
continue to consult extensively with state regulators including NAPSR
to ensure that any state concerns are taken into account.
C. Regulatory Flexibility Act
The Regulatory Flexibility Act of 1980 (Pub. L. 96-354) (RFA)
establishes ``as a principle of regulatory issuance that agencies shall
endeavor, consistent with the objectives of the rule and of applicable
statutes, to fit regulatory and informational requirements to the scale
of the businesses, organizations, and governmental jurisdictions
subject to regulation. To achieve this principle, agencies are required
to solicit and consider flexible regulatory proposals and to explain
the rationale for their actions to assure that such proposals are given
serious consideration.''
The RFA covers a wide range of small entities, including small
businesses, not-for-profit organizations, and small governmental
jurisdictions. Agencies must perform a review to determine whether a
rule will have a significant economic impact on a substantial number of
small entities. If the agency determines that it will, the agency must
prepare a regulatory flexibility analysis as described in the RFA.
However, if an agency determines that a rule is not expected to
have a
[[Page 61637]]
significant economic impact on a substantial number of small entities,
section 605(b) of the RFA provides that the head of the agency may so
certify and a regulatory flexibility analysis is not required. The
certification must include a statement providing the factual basis for
this determination, and the reasoning should be clear.
PHMSA performed a screening analysis of the potential economic
impact on small entities. The screening analysis is available in the
docket for the rulemaking. PHMSA estimates that the proposed rule would
impact fewer than 100 small hazardous liquid pipeline operators, and
that the majority of these operators would experience annual compliance
costs that represent less than 1% of annual revenues. Less than 20
small operators would incur annual compliance costs that represent
greater than 1% of annual revenues; less than 10 would incur annual
compliance costs of greater than 3% of annual revenues; and none would
incur compliance costs of more than 20% of annual revenues. PHMSA
determined that these impacts results do not represent a significant
impact for a substantial number of small hazardous liquid pipeline
operators. Therefore, I certify that this action, if promulgated, will
not have a significant economic impact on a substantial number of small
entities.
D. National Environmental Policy Act
PHMSA analyzed this NPRM in accordance with section 102(2)(c) of
the National Environmental Policy Act (42 U.S.C. 4332), the Council on
Environmental Quality regulations (40 CFR parts 1500 through 1508), and
DOT Order 5610.1C, and has preliminarily determined that this action
will not significantly affect the quality of the human environment. A
preliminary environmental assessment of this rulemaking is available in
the docket and PHMSA invites comment on environmental impacts of this
rule, if any.
E. Executive Order 13175: Consultation and Coordination With Indian
Tribal Governments
This NPRM has been analyzed in accordance with the principles and
criteria contained in Executive Order 13175 (``Consultation and
Coordination with Indian Tribal Governments''). Because this NPRM does
not have Tribal implications and does not impose substantial direct
compliance costs on Indian Tribal governments, the funding and
consultation requirements of Executive Order 13175 do not apply.
F. Paperwork Reduction Act
Paperwork Reduction Act
Pursuant to 5 CFR 1320.8(d), PHMSA is required to provide
interested members of the public and affected agencies with an
opportunity to comment on information collection and recordkeeping
requests. PHMSA estimates that the proposals in this rulemaking will
add a new information collection and impact several approved
information collections titled:
``Transportation of Hazardous Liquids by Pipeline: Recordkeeping
and Accident Reporting'' identified under Office of Management and
Budget (OMB) Control Number 2137-0047;
``Reporting Safety-Related Conditions on Gas, Hazardous Liquid, and
Carbon Dioxide Pipelines and Liquefied Natural Gas Facilities''
identified under OMB Control Number 2137-0578;
``Integrity Management in High Consequence Areas for Operators of
Hazardous Liquid Pipelines'' identified under OMB Control Number 2137-
0605 and;
``Pipeline Safety: New Reporting Requirements for Hazardous Liquid
Pipeline Operators: Hazardous Liquid Annual Report'' identified under
OMB Control Number 2137-0614.
Based on the proposals in this rulemaking, PHMSA will submit an
information collection revision request to OMB for approval based on
the requirements in this NPRM. The information collection is contained
in the pipeline safety regulations, 49 CFR parts 190 through 199. The
following information is provided for each information collection: (1)
Title of the information collection; (2) OMB control number; (3)
Current expiration date; (4) Type of request; (5) Abstract of the
information collection activity; (6) Description of affected public;
(7) Estimate of total annual reporting and recordkeeping burden; and
(8) Frequency of collection. The information collection burden for the
following information collections are estimated to be revised as
follows:
1. Title: Transportation of Hazardous Liquids by Pipeline:
Recordkeeping and Accident Reporting.
OMB Control Number: 2137-0047.
Current Expiration Date: April 30, 2014.
Abstract: This information collection covers the collection of
information from owners and operators of Hazardous Liquid Pipelines. To
ensure adequate public protection from exposure to potential hazardous
liquid pipeline failures, PHMSA collects information on reportable
hazardous liquid pipeline accidents. Additional information is also
obtained concerning the characteristics of an operator's pipeline
system. As a result of this NPRM, 5 gravity line operators and 23
gathering line operators would be required to submit accident reports
to PHMSA on occasion. These 28 additional operators will also be
required to keep mandated records. This information collection is being
revised to account for the additional burden that will be incurred by
these newly regulated entities. Operators currently submitting annual
reports will not be otherwise impacted by this NPRM.
Affected Public: Owners and operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping Burden:
Total Annual Responses: 881.
Total Annual Burden Hours: 55,455.
Frequency of Collection: On occasion.
2. Title: Reporting Safety-Related Conditions on Gas, Hazardous
Liquid, and Carbon Dioxide Pipelines and Liquefied Natural Gas
Facilities.
OMB Control Number: 2137-0578.
Current Expiration Date: May 31, 2014.
Abstract: 49 U.S.C. 60102 requires each operator of a pipeline
facility (except master meter operators) to submit to DOT a written
report on any safety-related condition that causes or has caused a
significant change or restriction in the operation of a pipeline
facility or a condition that is a hazards to life, property or the
environment. As a result of this NPRM, approximately 5 gravity line
operators and 23 gathering line operators will be required to adhere to
the Safety-Related Condition reporting requirements. This information
collection is being revised to account for the additional burden that
will be incurred by newly regulated entities. Operators currently
submitting annual reports will not be otherwise impacted by this rule.
Affected Public: Owners and operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping Burden:
Total Annual Responses: 178.
Total Annual Burden Hours: 1,020.
Frequency of Collection: On occasion.
3. Title: Integrity Management in High Consequence Areas for
Operators of Hazardous Liquid Pipelines.
OMB Control Number: 2137-0605.
Current Expiration Date: November 30, 2016.
Abstract: Owners and operators of Hazardous Liquid Pipelines are
required to have continual assessment and evaluation of pipeline
integrity through inspection or testing, as well as
[[Page 61638]]
remedial preventive and mitigative actions. As a result of this NPRM,
operators not currently under IM plans will be required to adhere to
the repair criteria currently required for operators who are under IM
plans. In conjunction with this requirement, operators who are not able
to make the necessary repairs within 180 days of the infraction will be
required to notify PHMSA in writing. PHMSA estimates that only 1% of
repair reports will require more than 180 days. Accordingly, PHMSA
approximates that 75 reports per year will fall within this category.
Affected Public: Owners and operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping Burden:
Total Annual Responses: 278.
Total Annual Burden Hours: 325,508.
Frequency of Collection: Annually.
4. Title: Pipeline Safety: New Reporting Requirements for Hazardous
Liquid Pipeline Operators: Hazardous Liquid Annual Report.
OMB Control Number: 2137-0614.
Current Expiration Date: April 30, 2014.
Abstract: Owners and operators of hazardous liquid pipelines are
required to provide PHMSA with safety related documentation relative to
the annual operation of their pipeline. The provided information is
used compile a national pipeline inventory, identify safety problems,
and target inspections. As a result of this NPRM, approximately 5
gravity line operators and 23 gathering line operators will be required
to submit annual reports to PHMSA. This information collection is being
revised to account for the additional burden that will be incurred.
Operators currently submitting annual reports will not be otherwise
impacted by this rule.
Affected Public: Owners and operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping Burden:
Total Annual Responses: 475.
Total Annual Burden Hours: 8,567.
Frequency of Collection: Annually.
5. Title: Pipeline Safety: Notification Requirements for Hazardous
Liquid Operators.
OMB Control Number: New OMB Control No.
Current Expiration Date: TBD.
Abstract: Owners and operators of non-High Consequence Area
hazardous liquid pipelines will be required to provide PHMSA with
notifications when unable to assess their pipeline via an in-line
inspection.
Affected Public: Owners and operators of Hazardous Liquid
Pipelines.
Annual Reporting and Recordkeeping Burden:
Total Annual Responses: 10.
Total Annual Burden Hours: 10.
Frequency of Collection: On occasion.
Requests for copies of these information collections should be
directed to Angela Dow or Cameron Satterthwaite, Office of Pipeline
Safety (PHP-30), Pipeline Hazardous Materials Safety Administration
(PHMSA), 2nd Floor, 1200 New Jersey Avenue SE., Washington, DC 20590-
0001, Telephone (202) 366-4595.
G. Privacy Act Statement
Anyone is able to search the electronic form of all comments
received into any of our dockets by the name of the individual
submitting the comment (or signing the comment, if submitted on behalf
of an association, business, labor union, etc.). You may review DOT's
complete Privacy Act Statement in the Federal Register published on
April 11, 2000 (65 FR 19477), or at https://www.regulations.gov.
H. Regulation Identifier Number (RIN)
A regulation identifier number (RIN) is assigned to each regulatory
action listed in the Unified Agenda of Federal Regulations. The
Regulatory Information Service Center publishes the Unified Agenda in
April and October of each year. The RIN contained in the heading of
this document may be used to cross-reference this action with the
Unified Agenda.
List of Subjects in 49 CFR Part 195
Incorporation by reference, Integrity management, Pipeline safety.
In consideration of the foregoing, PHMSA proposes to amend 49 CFR
part 195 as follows:
PART 195--TRANSPORTATION OF HAZARDOUS LIQUIDS BY PIPELINE
0
1. The authority citation for part 195 is revised to read as follows:
Authority: 49 U.S.C. 5103, 60101, 60102, 60104, 60108, 60109,
60116, 60118, 60131, 60131, 60137, and 49 CFR 1.97.
0
2. In Sec. 195.1, paragraph (a)(5) is added, paragraph (b)(2) is
removed, and paragraphs (b)(3) through (10) are re-designated as (b)(2)
through (9).
The addition reads as follows:
Sec. 195.1 Which pipelines are covered by this part?
(a) * * *
* * * * *
(5) For purposes of the reporting requirements in subpart B of this
part, any gathering line not already covered under paragraphs (a)(1),
(2), (3) or (4) of this section.
* * * * *
0
3. In section 195.2, the definition for ``Hazardous liquid'' is revised
and a definition of ``Significant stress corrosion cracking'' is added
in alphabetical order to read as follows:
Sec. 195.2 Definitions.
* * * * *
Hazardous liquid means petroleum, petroleum products, anhydrous
ammonia or non-petroleum fuel, including biofuel that is flammable,
toxic, or corrosive or would be harmful to the environment if released
in significant quantities.
* * * * *
Significant stress corrosion cracking means a stress corrosion
cracking (SCC) cluster in which the deepest crack, in a series of
interacting cracks, is greater than 10% of the wall thickness and the
total interacting length of the cracks is equal to or greater than 75%
of the critical length of a 50% through-wall flaw that would fail at a
stress level of 110% of SMYS.
* * * * *
0
4. In section 195.11, add paragraphs (b)(12) and (13) to read as
follows:
Sec. 195.11 What is a regulated rural gathering line and what
requirements apply?
* * * * *
(b) * * *
(12) Perform pipeline assessments and remediation as required under
Sec. Sec. 195.416 and 195.422.
(13) Establish a leak detection system in compliance with
Sec. Sec. 195.134 and 195.444.
* * * * *
0
5. Section 195.13 is added to subpart A to read as follows:
Sec. 195.13 What reporting requirements apply to pipelines
transporting hazardous liquids by gravity?
(a) Scope. This section applies to pipelines transporting hazardous
liquids by gravity as of [effective date of the final rule].
(b) Annual, accident and safety related reporting. Comply with the
reporting requirements in subpart B of this part by [date 6 months
after effective date of the final rule].
0
6. Section 195.120 is revised to read as follows:
Sec. 195.120 Passage of internal inspection devices.
(a) General. Except as provided in paragraphs (b) and (c) of this
section, each new pipeline and each main line section of a pipeline
where the line
[[Page 61639]]
pipe, valve, fitting or other line component is replaced must be
designed and constructed to accommodate the passage of instrumented
internal inspection devices.
(b) Exceptions. This section does not apply to:
(1) Manifolds;
(2) Station piping such as at pump stations, meter stations, or
pressure reducing stations;
(3) Piping associated with tank farms and other storage facilities;
(4) Cross-overs;
(5) Pipe for which an instrumented internal inspection device is
not commercially available; and
(6) Offshore pipelines, other than main lines 10 inches (254
millimeters) or greater in nominal diameter, that transport liquids to
onshore facilities.
(c) Impracticability. An operator may file a petition under Sec.
190.9 for a finding that the requirements in paragraph (a) should not
be applied to a pipeline for reasons of impracticability.
(d) Emergencies. An operator need not comply with paragraph (a) of
this section in constructing a new or replacement segment of a pipeline
in an emergency. Within 30 days after discovering the emergency, the
operator must file a petition under Sec. 190.9 for a finding that
requiring the design and construction of the new or replacement
pipeline segment to accommodate passage of instrumented internal
inspection devices would be impracticable as a result of the emergency.
If the petition is denied, within 1 year after the date of the notice
of the denial, the operator must modify the new or replacement pipeline
segment to allow passage of instrumented internal inspection devices.
0
7. Section 195.134 is revised to read as follow:
Sec. 195.134 Leak detection.
(a) Scope. This section applies to each hazardous liquid pipeline
transporting liquid in single phase (without gas in the liquid).
(b) General. Each pipeline must have a system for detecting leaks
that complies with the requirements in Sec. 195.444.
(c) CPM leak detection systems. A new computational pipeline
monitoring (CPM) leak detection system or replaced component of an
existing CPM system must be designed in accordance with the
requirements in section 4.2 of API RP 1130 (incorporated by reference,
see Sec. 195.3) and any other applicable design criteria in that
standard.
0
8. In Sec. 195.401, the introductory text of paragraph (b) and
paragraph (b)(1) are revised and paragraph (b)(3) is added to read as
follows.
Sec. 195.401 General requirements.
* * * * *
(b) An operator must make repairs on its pipeline system according
to the following requirements:
(1) Non integrity management repairs. Whenever an operator
discovers any condition that could adversely affect the safe operation
of a pipeline not covered under Sec. 195.452, it must correct the
condition as prescribed in Sec. 195.422. However, if the condition is
of such a nature that it presents an immediate hazard to persons or
property, the operator may not operate the affected part of the system
until it has corrected the unsafe condition.
* * * * *
(3) Prioritizing repairs. An operator must consider the risk to
people, property, and the environment in prioritizing the correction of
any conditions referenced in paragraphs (b)(1) and (2) of this section.
* * * * *
0
9. Section 195.414 is added to read as follows:
Sec. 195.414 Inspections of pipelines in areas affected by extreme
weather, a natural disaster, and other similar events.
(a) General. Following an extreme weather event such as a hurricane
or flood, an earthquake, a natural disaster, or other similar event, an
operator must inspect all potentially affected pipeline facilities to
ensure that no conditions exist that could adversely affect the safe
operation of that pipeline.
(b) Inspection method. An operator must consider the nature of the
event and the physical characteristics, operating conditions, location,
and prior history of the affected pipeline in determining the
appropriate method for performing the inspection required under
paragraph (a) of this section.
(c) Time period. The inspection required under paragraph (a) of
this section must occur within 72 hours after the cessation of the
event, or as soon as the affected area can be safely accessed by the
personnel and equipment required to perform the inspection as
determined under paragraph (b) of this section.
(d) Remedial action. An operator must take appropriate remedial
action to ensure the safe operation of a pipeline based on the
information obtained as a result of performing the inspection required
under paragraph (a) of this section. Such actions might include, but
are not limited to:
(1) Reducing the operating pressure or shutting down the pipeline;
(2) Modifying, repairing, or replacing any damaged pipeline
facilities;
(3) Preventing, mitigating, or eliminating any unsafe conditions in
the pipeline right-of-way;
(4) Performing additional patrols, surveys, tests, or inspections;
(5) Implementing emergency response activities with Federal, State,
or local personnel; and
(6) Notifying affected communities of the steps that can be taken
to ensure public safety.
0
10. Section 195.416 is added to read as follows:
Sec. 195.416 Pipeline assessments.
(a) Scope. This section applies to pipelines that are not subject
to the integrity management requirements in Sec. 195.452.
(b) General. An operator must perform an assessment of a pipeline
at least once every 10 years, or as otherwise necessary to ensure
public safety.
(c) Method. The assessment required under paragraph (b) of this
section must be performed with an in-line inspection tool or tools
capable of detecting corrosion and deformation anomalies, including
dents, cracks, gouges, and grooves, unless an operator:
(i) Demonstrates that the pipeline is not capable of accommodating
an inline inspection tool; and that the use of an alternative
assessment method will provide a substantially equivalent understanding
of the condition of the pipeline; and
(ii) Notifies the Office of Pipeline Safety (OPS) 90 days before
conducting the assessment by:
(A) Sending the notification, along with the information required
to demonstrate compliance with paragraph (c)(i) of this section, to the
Information Resources Manager, Office of Pipeline Safety, Pipeline and
Hazardous Materials Safety Administration, 1200 New Jersey Avenue SE.,
Washington, DC 20590; or
(B) Sending the notification, along with the information required
to demonstrate compliance with paragraph (c)(i) of this section, to the
Information Resources Manager by facsimile to (202) 366-7128.
(d) Data analysis. A person qualified by knowledge, training, and
experience must analyze the data obtained from an assessment performed
under paragraph (b) of this section to determine if a condition could
adversely affect the safe operation of the pipeline. Uncertainties in
any reported results (including tool tolerance) must be considered as
part of that analysis.
(e) Discovery of condition. For purposes of Sec. 195.422,
discovery of a
[[Page 61640]]
condition occurs when an operator has adequate information to determine
that a condition exists. An operator must promptly, but no later than
180 days after an assessment, obtain sufficient information about a
condition and make the determination required under paragraph (d) of
this section, unless 180-days is impracticable as determined by PHMSA.
(f) Remediation. An operator must comply with the requirements in
Sec. 195.422 if a condition that could adversely affect the safe
operation of a pipeline is discovered in complying with paragraphs (d)
and (e) of this section.
(g) Consideration of information. An operator must consider all
relevant information about a pipeline in complying with the
requirements in paragraphs (a) through (f) of this section.
0
11. Section 195.422 is revised to read as follows:
Sec. 195.422 Pipeline remediation.
(a) Scope. This section applies to pipelines that are not subject
to the integrity management requirements in Sec. 195.452.
(b) General. Each operator must, in repairing its pipeline systems,
ensure that the repairs are made in a safe manner and are made so as to
prevent damage to persons, property, or the environment.
(c) Replacement. An operator may not use any pipe, valve, or
fitting, for replacement in repairing pipeline facilities, unless it is
designed and constructed as required by this part.
(d) Remediation schedule. An operator must complete the remediation
of a condition according to the following schedule:
(1) Immediate repair conditions. An operator must repair the
following conditions immediately upon discovery:
(i) Metal loss greater than 80% of nominal wall regardless of
dimensions.
(ii) A calculation of the remaining strength of the pipe shows a
burst pressure less than 1.1 times the maximum operating pressure at
the location of the anomaly. Suitable remaining strength calculation
methods include, but are not limited to, ASME/ANSI B31G (``Manual for
Determining the Remaining Strength of Corroded Pipelines'' (1991) or
AGA Pipeline Research Committee Project PR-3-805 (``A Modified
Criterion for Evaluating the Remaining Strength of Corroded Pipe''
(December 1989)) (incorporated by reference, see Sec. 195.3.
(iii) A dent located anywhere on the pipeline that has any
indication of metal loss, cracking or a stress riser.
(iv) A dent located on the top of the pipeline (above the 4 and 8
o'clock positions) with a depth greater than 6% of the nominal pipe
diameter.
(v) An anomaly that in the judgment of the person designated by the
operator to evaluate the assessment results requires immediate action.
(vi) Any indication of significant stress corrosion cracking (SCC).
(vii) Any indication of selective seam weld corrosion (SSWC).
(2) Until the remediation of a condition specified in paragraph
(d)(1) of this section is complete, an operator must:
(i) Reduce the operating pressure of the affected pipeline using
the formula specified in paragraph 195.422(d)(3)(iv) or;
(ii) Shutdown the affected pipeline.
(3) 18-month repair conditions. An operator must repair the
following conditions within 18 months of discovery:
(i) A dent with a depth greater than 2% of the pipeline's diameter
(0.250 inches in depth for a pipeline diameter less than NPS 12) that
affects pipe curvature at a girth weld or a longitudinal seam weld.
(ii) A dent located on the top of the pipeline (above 4 and 8
o'clock position) with a depth greater than 2% of the pipeline's
diameter (0.250 inches in depth for a pipeline diameter less than NPS
12).
(iii) A dent located on the bottom of the pipeline with a depth
greater than 6% of the pipeline's diameter.
(iv) A calculation of the remaining strength of the pipe at the
anomaly shows a safe operating pressure that is less than the MOP at
that location. Provided the safe operating pressure includes the
internal design safety factors in Sec. 195.106 in calculating the pipe
anomaly safe operating pressure, suitable remaining strength
calculation methods include, but are not limited to, ASME/ANSI B31G
(``Manual for Determining the Remaining Strength of Corroded
Pipelines'' (1991)) or AGA Pipeline Research Committee Project PR-3-805
(``A Modified Criterion for Evaluating the Remaining Strength of
Corroded Pipe'' (December 1989)) (incorporated by reference, see Sec.
195.3).
(v) An area of general corrosion with a predicted metal loss
greater than 50% of nominal wall.
(vi) Predicted metal loss greater than 50% of nominal wall that is
located at a crossing of another pipeline, or is in an area with
widespread circumferential corrosion, or is in an area that could
affect a girth weld.
(vii) A potential crack indication that when excavated is
determined to be a crack.
(viii) Corrosion of or along a seam weld.
(ix) A gouge or groove greater than 12.5% of nominal wall.
(e) Other conditions. Unless another timeframe is specified in
paragraph (d) of this section, an operator must take appropriate
remedial action to correct any condition that could adversely affect
the safe operation of a pipeline system within a reasonable time.
0
12. Section 195.444 is revised to read as follows:
Sec. 195.444 Leak detection.
(a) Scope. This section applies to each hazardous liquid pipeline
transporting liquid in single phase (without gas in the liquid).
(b) General. A pipeline must have a system for detecting leaks. An
operator must evaluate and modify, as necessary, the capability of its
leak detection system to protect the public, property, and the
environment. An operator's evaluation must, at least, consider the
following factors--length and size of the pipeline, type of product
carried, the swiftness of leak detection, location of nearest response
personnel, and leak history.
(c) CPM leak detection systems. Each computational pipeline
monitoring (CPM) leak detection system installed on a hazardous liquid
pipeline must comply with API RP 1130 (incorporated by reference, see
Sec. 195.3) in operating, maintaining, testing, record keeping, and
dispatcher training of the system.
0
13. In Sec. 195.452:
0
a. Revise paragraphs (a), (b)(1), introductory text of paragraph
(c)(1)(i), (c)(1)(i)(A), (d), (e)(1)(vii), (g), introductory text of
(h)(1), (h)(2), and (h)(4);
0
b. Revise paragraph (i)(2)(viii) by removing the period at the end of
the last sentence and adding in its place a ``;'' and add paragraph
(i)(2)(ix);
0
c. Revise paragraphs (j)(1) and (2);
0
d. Add paragraph (n).
The revisions and additions read as follows:
Sec. 195.452 Pipeline integrity management in high consequence areas.
(a) Which pipelines are covered by this section? This section
applies to each hazardous liquid pipeline and carbon dioxide pipeline
that could affect a high consequence area, including any pipeline
located in a high consequence area, unless the operator demonstrates
that a worst case discharge from the pipeline could not affect the
area. (Appendix C of this part provides
[[Page 61641]]
guidance on determining if a pipeline could affect a high consequence
area.) Covered pipelines are categorized as follows:
(1) Category 1 includes pipelines existing on May 29, 2001, that
were owned or operated by an operator who owned or operated a total of
500 or more miles of pipeline subject to this part.
(2) Category 2 includes pipelines existing on May 29, 2001, that
were owned or operated by an operator who owned or operated less than
500 miles of pipeline subject to this part.
(3) Category 3 includes pipelines constructed or converted after
May 29, 2001, low-stress pipelines in rural areas under Sec. 195.12.
(b) * * *
(1) Develop a written integrity management program that addresses
the risks on each segment of pipeline in the first column of the
following table not later than the date in the second column:
------------------------------------------------------------------------
Pipeline Date
------------------------------------------------------------------------
Category 1........................ March 31, 2002.
Category 2........................ February 18, 2003.
Category 3........................ Date the pipeline begins operation
or as provided in Sec. 195.12.
------------------------------------------------------------------------
* * * * *
(c) * * *
(1) * * *
(i) The methods selected to assess the integrity of the line pipe.
An operator must assess the integrity of the line pipe by In Line
Inspection tool unless it is impracticable, then use methods (B), (C)
or (D) of this paragraph. The methods an operator selects to assess low
frequency electric resistance welded pipe, or lap welded pipe, or pipe
with a seam factor less than 1.0 as defined in Sec. 195.106(e) or lap
welded pipe susceptible to longitudinal seam failure must be capable of
assessing seam integrity and of detecting corrosion and deformation
anomalies.
(A) Internal inspection tool or tools capable of detecting
corrosion, and deformation anomalies including dents, cracks (pipe body
and weld seams), gouges and grooves. An operator using this method must
explicitly consider uncertainties in reported results (including tool
tolerance, anomaly findings, and unity chart plots or equivalent for
determining uncertainties) in identifying anomalies;
* * * * *
(d) When must operators complete baseline assessments?
(1) All pipelines. An operator must complete the baseline
assessment before the pipeline begins operation.
(2) Newly-identified areas. If an operator obtains information
(whether from the information analysis required under paragraph (g) of
this section, Census Bureau maps, or any other source) demonstrating
that the area around a pipeline segment has changed to meet the
definition of a high consequence area (see Sec. 195.450), that area
must be incorporated into the operator's baseline assessment plan
within one year from the date that the information is obtained. An
operator must complete the baseline assessment of any pipeline segment
that could affect a newly-identified high consequence area within five
years from the date the area is identified.
* * * * *
(e) * * *
(1) * * *
(vii) Local environmental factors that could affect the pipeline
(e.g., seismicity, corrosivity of soil, subsidence, climatic);
* * * * *
(g) What is an information analysis? In periodically evaluating the
integrity of each pipeline segment (see paragraph (j) of this section),
an operator must analyze all available information about the integrity
of its entire pipeline and the consequences of a possible failure along
the pipeline. This analysis must:
(1) Integrate information and attributes about the pipeline which
include, but are not limited to:
(i) Pipe diameter, wall thickness, grade, and seam type;
(ii) Pipe coating including girth weld coating;
(iii) Maximum operating pressure (MOP);
(iv) Endpoints of segments that could affect high consequence areas
(HCAs);
(v) Hydrostatic test pressure including any test failures--if
known;
(vi) Location of casings and if shorted;
(vii) Any in-service ruptures or leaks--including identified
causes;
(viii) Data gathered through integrity assessments required under
this section;
(ix) Close interval survey (CIS) survey results;
(x) Depth of cover surveys;
(xi) Corrosion protection (CP) rectifier readings;
(xii) CP test point survey readings and locations;
(xiii) AC/DC and foreign structure interference surveys;
(xiv) Pipe coating surveys and cathodic protection surveys.
(xv) Results of examinations of exposed portions of buried
pipelines (i.e., pipe and pipe coating condition, see Sec. 195.569);
(xvi) Stress corrosion cracking (SCC) and other cracking (pipe body
or weld) excavations and findings, including in-situ non-destructive
examinations and analysis results for failure stress pressures and
cyclic fatigue crack growth analysis to estimate the remaining life of
the pipeline;
(xvii) Aerial photography;
(xviii) Location of foreign line crossings;
(xix) Pipe exposures resulting from encroachments;
(xx) Seismicity of the area; and
(xxi) Other pertinent information derived from operations and
maintenance activities and any additional tests, inspections, surveys,
patrols, or monitoring required under this part.
(2) Consider information critical to determining the potential for,
and preventing, damage due to excavation, including current and planned
damage prevention activities, and development or planned development
along the pipeline;
(3) Consider how a potential failure would affect high consequence
areas, such as location of a water intake.
(4) Identify spatial relationships among anomalous information
(e.g., corrosion coincident with foreign line crossings; evidence of
pipeline damage where aerial photography shows evidence of
encroachment). Storing the information in a geographic information
system (GIS), alone, is not sufficient. An operator must analyze for
interrelationships among the data.
(h) * * *
(1) General requirements. An operator must take prompt action to
address all anomalous conditions in the pipeline that the operator
discovers through the integrity assessment or information analysis. In
addressing all conditions, an operator must evaluate all anomalous
conditions and remediate those that could reduce a pipeline's
integrity. An operator must be able to demonstrate that the remediation
of the condition will ensure that the condition is unlikely to pose a
threat to the long-term integrity of the pipeline. An operator must
comply with all other applicable requirements in this part in
remediating a condition.
* * * * *
(2) Discovery of condition. Discovery of a condition occurs when an
operator has adequate information to determine that a condition exists.
An operator must promptly, but no later than 180 days after an
assessment, obtain sufficient information about a condition and make
the determination required, unless the operator can demonstrate that
that 180-day is impracticable. If 180-days is impracticable to make a
[[Page 61642]]
determination about a condition found during an assessment, the
pipeline operator must notify PHMSA and provide an expected date when
adequate information will become available.
* * * * *
(4) Special requirements for scheduling remediation--(i) Immediate
repair conditions. An operator's evaluation and remediation schedule
must provide for immediate repair conditions. To maintain safety, an
operator must temporarily reduce the operating pressure or shut down
the pipeline until the operator completes the repair of these
conditions. An operator must calculate the temporary reduction in
operating pressure using the formulas in paragraph (h)(4)(i)(B) of this
section, if applicable, or when the formulas in paragraph (h)(4)(i)(B)
of this section are not applicable by using a pressure reduction
determination in accordance with Sec. 195.106 and the appropriate
remaining pipe wall thickness, or if all of these are unknown a minimum
20 percent or greater operating pressure reduction must be implemented
until the anomaly is repaired. If the formula is not applicable to the
type of anomaly or would produce a higher operating pressure, an
operator must use an alternative acceptable method to calculate a
reduced operating pressure. An operator must treat the following
conditions as immediate repair conditions:
(A) Metal loss greater than 80% of nominal wall regardless of
dimensions.
(B) A calculation of the remaining strength of the pipe shows a
predicted burst pressure less than 1.1 times the maximum operating
pressure at the location of the anomaly. Suitable remaining strength
calculation methods include, but are not limited to, ASME/ANSI B31G
(``Manual for Determining the Remaining Strength of Corroded
Pipelines'' (1991) or AGA Pipeline Research Committee Project PR-3-805
(``A Modified Criterion for Evaluating the Remaining Strength of
Corroded Pipe'' (December 1989)) (incorporated by reference, see Sec.
195.3).
(C) A dent located anywhere on the pipeline that has any indication
of metal loss, cracking or a stress riser.
(D) A dent located on the top of the pipeline (above the 4 and 8
o'clock positions) with a depth greater than 6% of the nominal pipe
diameter.
(E) Any indication of significant stress corrosion cracking (SCC).
(F) Any indication of selective seam weld corrosion (SSWC)
(G) An anomaly that in the judgment of the person designated by the
operator to evaluate the assessment results requires immediate action.
(ii) 270-day conditions. Except for conditions listed in paragraph
(h)(4)(i) of this section, an operator must schedule evaluation and
remediation of the following within 270 days of discovery of the
condition:
(A) A dent with a depth greater than 2% of the pipeline's diameter
(0.250 inches in depth for a pipeline diameter less than NPS 12) that
affects pipe curvature at a girth weld or a longitudinal seam weld.
(B) A dent located on the top of the pipeline (above 4 and 8
o'clock position) with a depth greater than 2% of the pipeline's
diameter (0.250 inches in depth for a pipeline diameter less than NPS
12).
(C) A dent located on the bottom of the pipeline with a depth
greater than 6% of the pipeline's diameter.
(D) A calculation of the remaining strength of the pipe at the
anomaly shows a safe operating pressure that is less than MOP at that
location. Provided the safe operating pressure includes the internal
design safety factors in Sec. 195.106 in calculating the pipe anomaly
safe operating pressure, suitable remaining strength calculation
methods include, but are not limited to, ASME/ANSI B31G (``Manual for
Determining the Remaining Strength of Corroded Pipelines'' (1991)) or
AGA Pipeline Research Committee Project PR-3-805 (``A Modified
Criterion for Evaluating the Remaining Strength of Corroded Pipe''
(December 1989)) (incorporated by reference, see Sec. 195.3).
(E) An area of general corrosion with a predicted metal loss
greater than 50% of nominal wall.
(F) Predicted metal loss greater than 50% of nominal wall that is
located at a crossing of another pipeline, or is in an area with
widespread circumferential corrosion, or is in an area that could
affect a girth weld.
(G) A potential crack indication that when excavated is determined
to be a crack.
(H) Corrosion of or along a longitudinal seam weld.
(I) A gouge or groove greater than 12.5% of nominal wall.
(iii) Other Conditions. In addition to the conditions listed in
paragraphs (h)(4)(i) and (ii) of this section, an operator must
evaluate any condition identified by an integrity assessment or
information analysis that could impair the integrity of the pipeline,
and as appropriate, schedule the condition for remediation. Appendix C
of this part contains guidance concerning other conditions that an
operator should evaluate.
(i) * * *
(2) * * *
(ix) Seismicity of the area.
* * * * *
(j) * * * (1) General. After completing the baseline integrity
assessment, an operator must continue to assess the line pipe at
specified intervals and periodically evaluate the integrity of each
pipeline segment that could affect a high consequence area.
(2) Verifying covered segments. An operator must verify the risk
factors used in identifying pipeline segments that could affect a high
consequence area on at least an annual basis not to exceed 15-months
(Appendix C provides additional guidance on factors that can influence
whether a pipeline segment could affect a high consequence area). If a
change in circumstance indicates that the prior consideration of a risk
factor is no longer valid or that new risk factors should be
considered, an operator must perform a new integrity analysis and
evaluation to establish the endpoints of any previously-identified
covered segments. The integrity analysis and evaluation must include
consideration of the results of any baseline and periodic integrity
assessments (see paragraphs (b), (c), (d), and (e) of this section),
information analyses (see paragraph (g) of this section), and decisions
about remediation and preventive and mitigative actions (see paragraphs
(h) and (i) of this section). An operator must complete the first
annual verification under this paragraph no later than [date one year
after effective date of the final rule].
* * * * *
(n) Accommodation of internal inspection devices--(1) Scope. This
paragraph does not apply to any pipeline facilities listed in Sec.
195.120(b).
(2) General. An operator must ensure that each pipeline is modified
to accommodate the passage of an instrumented internal inspection
device by [date 20 years from effective date of the final rule].
(3) Newly-identified areas. If a pipeline could affect a newly-
identified high consequence area (see paragraph (d)(3) of this section)
after [date 20 years from effective date of the final rule], an
operator must modify the pipeline to accommodate the passage of an
instrumented internal inspection device within five years of the date
of identification or before performing the baseline assessment,
whichever is sooner.
(4) Lack of accommodation. An operator may file a petition under
Sec. 190.9 of this chapter for a finding that
[[Page 61643]]
the basic construction (i.e. length, diameter, operating pressure, or
location) of a pipeline cannot be modified to accommodate the passage
of an internal inspection device.
(5) Emergencies. An operator may file a petition under Sec. 190.9
of this chapter for a finding that a pipeline cannot be modified to
accommodate the passage of an instrumented internal inspection device
as a result of an emergency. Such a petition must be filed within 30
days after discovering the emergency. If the petition is denied, the
operator must modify the pipeline to allow the passage of an
instrumented internal inspection device within one year after the date
of the notice of the denial.
Issued in Washington, DC on October 1, 2015, under authority
delegated in 49 CFR Part 1.97(a).
Linda Daugherty,
Deputy Associate Administrator for Field Operations.
[FR Doc. 2015-25359 Filed 10-9-15; 8:45 am]
BILLING CODE 4910-60-P