Notice of Availability of Supplemental Information Report for Berryessa Creek Element, Coyote and Berryessa Creek, Flood Control Project, Santa Clara County, CA, 61187-61188 [2015-25859]
Download as PDF
tkelley on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 196 / Friday, October 9, 2015 / Notices
Needs and Uses: Executive Order
12829, ‘‘National Industrial Security
Program’’ requires the Department of
Defense to account each year for the
costs associated with implementation of
the National Industrial Security Program
and report those costs to the Director of
the Information Security Oversight
Office (ISOO). In furtherance of this
requirement, and pursuant with 32 CFR,
Subpart F, section 2001.61(b); Classified
National Security Information; Final
Rule, the Secretary of Defense, acting as
executive agent for NISP, is obligated to
collect cost estimates for classificationrelated activities of contractors,
licensees, certificate holders, and
grantees and report them to ISOO
annually. The cost collection
methodology employed since 1996 was
validated with the ISOO in December
2007. Participation in the survey is
strictly voluntary. Input is integrated
into total cost figure for the President
and is never associated with a specific
facility.
Affected Public: A statistical sample
of active and cleared businesses, or
other profit and non-profit organizations
under Department of Defense Security
Cognizance, approved for storage of
classified materials.
Annual Burden Hours: 125 hours.
Number of Respondents: 749.
Responses per Respondent: 1.
Annual Responses: 749.
Average Burden per Response: 10
minutes.
Frequency: Annually.
Collection of this data is required to
comply with the reporting requirements
of Executive Order 12829, ‘‘National
Industrial Security Program.’’ This
collection of information requests the
assistance of the Facility Security
Officer to provide estimates of annual
security labor cost in burdened, current
year dollars and the estimated
percentage of security labor dollars to
the total security costs for the facility.
Security labor is defined as personnel
whose positions exist to support
operations and staff in the
implementation of government security
requirements for the protection of
classified information. Guards who are
required as supplemental controls are
included in security labor. This data
will be incorporated into a report
produced to ISOO for the estimated cost
of securing classified information
within industry. The survey will be
distributed electronically via a Webbased commercial survey tool.
VerDate Sep<11>2014
17:44 Oct 08, 2015
Jkt 238001
Dated: October 5, 2015.
Aaron Siegel,
Alternate OSD Federal Register Liaison
Officer, Department of Defense.
[FR Doc. 2015–25797 Filed 10–8–15; 8:45 am]
BILLING CODE 5001–06–P
DEPARTMENT OF DEFENSE
Department of the Army, U.S. Army
Corps of Engineers
Notice of Availability of Supplemental
Information Report for Berryessa
Creek Element, Coyote and Berryessa
Creek, Flood Control Project, Santa
Clara County, CA
Department of the Army, U.S.
Army Corps of Engineers, DOD.
ACTION: Public notice.
AGENCY:
The U.S. Army Corps of
Engineers (Corps) has prepared a
Supplemental Information Report (SIR)
to provide an update to the General Reevaluation Report/Environmental
Impact Statement (GRR/EIS) for the
Berryessa Creek Element of the Coyote
and Berryessa Creek, California, Flood
Control Project (Project), that the Corps
may be invoking the Clean Water Act
(CWA) § 404(r) exemption. The Project
initially sought to obtain a water quality
certification from the Regional Water
Quality Control Board, San Francisco
Region (RWQCB) pursuant to the CWA
§ 401(a) (401 Certification). During the
course of extensive coordination over
the last six months, the RWQCB has
stated that it may be unable or unwilling
to issue a 401 Certification for the
Project. Therefore, in an effort to
preserve the ability to improve flood
risk management in this area without
excessive delay, the Corps may invoke
404(r) exemption in lieu of obtaining a
401 Certification from the RWQCB.
FOR FURTHER INFORMATION CONTACT:
Amanda Cruz, U.S. Army Corps of
Engineers, San Francisco District, Plan
Formulation Section, 1455 Market
Street, 17th Floor, San Francisco, CA
94103–1398, (415) 503–6955,
Amanda.b.cruz@usace.army.mil.
SUPPLEMENTARY INFORMATION: The
March 2014 Final GRR/EIS of the
Project, and its accompanying CWA
§ 404(b)(1) alternatives analysis,
recommended the proposed design of a
earthen trapezoidal channel section
with varying bottom width and 2H:1V
side slopes that provides protection
against the one-percent annual chance
exceedance flood event from I–680 in
San Jose to Calaveras Boulevard in
Milpitas (hereinafter ‘‘Project’’). These
environmental analyses determined the
SUMMARY:
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
61187
Project to be the National Economic
Development Plan (NED), the National
Environmental Policy Act (NEPA)
environmentally preferable alternative,
the California Environmental Quality
Act (CEQA) § 15126.6(e)(2)
environmentally superior alternative,
and the CWA § 404 Least Environmental
Damaging Practicable Alternative
(LEDPA). The Corps’ Director of Civil
Works signed the Record of Decision
(ROD) on May 29, 2014.
With the goal of promoting
partnership, it has been the Corps’
position to obtain 401 Certification for
all its projects, regardless of the
availability of 404(r) exemption.
However, if the RWQCB is unable or
unwilling to provide such a certification
then the Corps will initiate 404(r)
exemption procedures and acknowledge
this in the appropriate NEPA document,
which has been determined to be an
SIR.
Section 404(r) creates an exemption
from the water quality certification
requirement under Section 401(a) for
projects (1) specifically authorized by
Congress for which (2) an
environmental impact statement has
been created that (3) includes
consideration of the 404(b)(1)
guidelines, which (4) has been
transmitted to Congress prior to the
appropriation of construction funds.
Congress authorized construction of the
Project in the Water Resources
Development Act of 1990, Public Law
101–640, § 101(a)(5), 103 Stat. 4604
(1990) and as stated above, the Corps
completed the GRR/EIS in March 2014.
The 404(b)(1) Alternatives Analysis was
included in the GRR/EIS as Appendix
A: Part V. With the completion of this
SIR, the Corps will officially transmit
the updated GRR/EIS to Congress prior
to the appropriation of construction
funding. Once done, the Corps will have
met all the requirements to utilize 404(r)
exemption.
The Corps is confident that the Project
is fully conforming to all Federal and
State laws, regulations, and
requirements. In the absence of RWQCB
issuing a 401 Certification, the Corps
may use 404(r) exemption. In light of
the fact that the Project meets all
requirements of 404(r) exemption
without any modifications, there are no
substantial changes or new significant
circumstances or information that
would trigger the need for a supplement
E:\FR\FM\09OCN1.SGM
09OCN1
61188
Federal Register / Vol. 80, No. 196 / Friday, October 9, 2015 / Notices
to the GRR/EIS, as defined in section
1502.9(c) of the CEQ Regulations.
John C. Morrow,
Lieutenant Colonel, U.S. Army, District
Engineer.
[FR Doc. 2015–25859 Filed 10–8–15; 8:45 am]
BILLING CODE 3720–58–P
DEPARTMENT OF DEFENSE
Department of the Army, Corps of
Engineers
Notice of Availability of the Draft
Environmental Impact Statement for
the Nebraska Highway 12 Niobrara
East and West Project, Knox County,
NE
AGENCY:
U.S. Army Corps of Engineers,
DoD.
ACTION:
Notice of availability.
The U.S. Army Corps of
Engineers (Corps), Omaha District, has
prepared a Draft Environmental Impact
Statement (EIS) to analyze the direct,
indirect and cumulative effects of a
proposed Nebraska State Highway
project, Nebraska Highway 12 Niobrara
East and West Project by the Nebraska
Department of Roads (NDOR). The
Applied-for Project is the relocation and
elevation (including additional bridges)
of two segments of existing Nebraska
Highway 12 (N–12) that are frequently
flooded and have incurred damage due
to high water levels associated with the
Missouri River.
DATES: Written comments on the Draft
EIS will be accepted on or after October
9, 2015, through November 23, 2015.
Oral and/or written comments may also
be presented at the Public Hearing to be
held at 6:00 p.m. on Monday, November
9, 2015, at the Niobrara Secondary
School, located at 247 NE–12, Niobrara,
NE 68760.
ADDRESSES: Send written comments
regarding the Applied-for Project and
Draft EIS to Rebecca J. Latka, Project
Manager, U.S. Army Corps of Engineers,
Omaha District, Regulatory Branch,
1616 Capitol Avenue, Omaha, NE
68102–4901, or via email at
Rebecca.J.Latka@usace.army.mil.
Requests to be placed on or removed
from the mailing list should also be sent
to this address.
Copies of the Draft EIS will be
available for review at the addresses
listed in the SUPPLEMENTARY
INFORMATION section.
Electronic copies of the Draft EIS may
be obtained from the Nebraska
Regulatory Office or its Web site at
https://www.nwo.usace.army.mil/
tkelley on DSK3SPTVN1PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:44 Oct 08, 2015
Jkt 238001
Missions/RegulatoryProgram/Nebraska/
EISHighway12.aspx.
FOR FURTHER INFORMATION CONTACT:
Rebecca J. Latka, Project Manager, U.S.
Army Corps of Engineers, at 402–995–
2681; fax 402–996–3842.
SUPPLEMENTARY INFORMATION: The
purpose of the Draft EIS is to provide a
full and fair discussion of the Appliedfor Project and other reasonable
alternatives to inform decision makers
and the public of the environmental
impacts of the Applied-for Project and
the reasonable alternatives. NDOR has
submitted a Section 404 (Clean Water
Act) permit application containing a
roadway design for Alternative A7 (the
Applied-for Project) to the U.S. Army
Corps of Engineers (Corps). NDOR
proposes to relocate N–12 east and west
of Niobrara, NE., south of its existing
location and construct a new roadway at
a higher elevation with enhanced
bridged sections to withstand existing
and future flood events. The segment of
N–12 that is in the bluffs, including the
segment that goes through the Village of
Niobrara, will remain the same. Two
segments of N–12 within the existing
Missouri River floodplain would be
relocated. The west segment is
approximately 6.2 miles long and
extends from just east of Verdel,
Nebraska, on the west end to 2 miles
west of the bridge over the Niobrara
River. The Applied-for Project would
deviate from the existing alignment just
east of Ponca Creek and would rejoin
the existing alignment just north of
County Road 892. The east segment is
approximately 6 miles long and extends
from just east of Spruce Avenue in
Niobrara, NE., to approximately 1 mile
east of Spur 54D (S–54D). In the east
segment, the alignment would deviate
from the existing alignment east of 4th
Avenue in Niobrara, NE., and would
reconnect with existing N–12 at
approximately S–54D. A new
connection to the Chief Standing Bear
Memorial Bridge (N–14) and SD–37
would be developed, tying into the
existing Highway 14 connection (which
will be elevated as part of the project).
Once the roads are completed, the
existing N–12 roadway would be
removed to the existing ground level. In
addition to the Applied-for Project, the
Draft EIS analyzes three alternatives: (1)
Elevation Raise on Existing Alignment,
(2) Elevation Raise on Parallel
Alignment, (3) Base of Bluffs Alignment.
The National Park Service, U.S.
Environmental Protection Agency, U.S.
Fish and Wildlife Service, Federal
Highway Administration, and Knox
County are serving as cooperating
agencies. The Nebraska Game and Parks
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
Commission and Nebraska Department
of Environmental Quality are
participating as review agencies. Copies
of the document are available at the
following addresses:
1. Niobrara Public Library/Niobrara Civic
Center, 25414 Park Avenue Ste 3,
Niobrara, NE 68760–0015
2. Tyndall City Library, 110 W 17th Avenue,
Tyndall, SD 57066
3. Verdel City Office, 202 Second St., Verdel,
NE 68760
4. Verdigre City Public Library, 101 E 3rd
Street, Verdigre, NE 68783
5. Springfield City Library, 605 8th Street,
Springfield, SD 57062
6. Knox County Extension Office, 308 Bridge
Street, Center, NE 68724
7. U.S. Army Corps of Engineers, Lewis and
Clark Visitor Center, 55245 Hwy 121,
Croften, NE 68730
8. U.S. Army Corps of Engineers, Nebraska
Regulatory Office, Lake Wehrspann Field
Office, 8901 S. 154th Street, Omaha, NE
68138–3621
9. Corps of Discovery Welcome Center, 89705
Highway 81, Crofton, NE 68730
Dated: September 30, 2015.
Joseph McMahan,
Chief Regulatory Field Support, Omaha
District.
[FR Doc. 2015–25845 Filed 10–8–15; 8:45 am]
BILLING CODE 3720–58–P
DEPARTMENT OF DEFENSE
Department of the Army, Corps of
Engineers
Notice of Intent To Prepare an
Integrated Feasibility Report & Draft
Environmental Impact Statement for
the Yuba River, California, Ecosystem
Restoration Feasibility Study
Department of the Army, U.S.
Army Corps of Engineers; DOD.
ACTION: Notice of intent.
AGENCY:
The U.S. Army Corps of
Engineers, Sacramento District (Corps),
intends to prepare an integrated
Feasibility Report & Draft
Environmental Impact Statement (DEIS)
for the Yuba River Ecosystem
Restoration Feasibility Study. The Corps
will serve as the lead agency for
compliance with the National
Environmental Policy Act. The Yuba
County Water Agency (YCWA) will
serve as the non-federal sponsor. The
feasibility study is evaluating
opportunities for ecosystem restoration
in the Yuba River watershed, located in
portions of Sierra, Placer, Yuba, and
Nevada counties.
DATES: Written comments should be
submitted by November 9, 2015.
ADDRESSES: Written comments should
be sent to U.S. Army Corps of Engineers,
SUMMARY:
E:\FR\FM\09OCN1.SGM
09OCN1
Agencies
[Federal Register Volume 80, Number 196 (Friday, October 9, 2015)]
[Notices]
[Pages 61187-61188]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-25859]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army, U.S. Army Corps of Engineers
Notice of Availability of Supplemental Information Report for
Berryessa Creek Element, Coyote and Berryessa Creek, Flood Control
Project, Santa Clara County, CA
AGENCY: Department of the Army, U.S. Army Corps of Engineers, DOD.
ACTION: Public notice.
-----------------------------------------------------------------------
SUMMARY: The U.S. Army Corps of Engineers (Corps) has prepared a
Supplemental Information Report (SIR) to provide an update to the
General Re-evaluation Report/Environmental Impact Statement (GRR/EIS)
for the Berryessa Creek Element of the Coyote and Berryessa Creek,
California, Flood Control Project (Project), that the Corps may be
invoking the Clean Water Act (CWA) Sec. 404(r) exemption. The Project
initially sought to obtain a water quality certification from the
Regional Water Quality Control Board, San Francisco Region (RWQCB)
pursuant to the CWA Sec. 401(a) (401 Certification). During the course
of extensive coordination over the last six months, the RWQCB has
stated that it may be unable or unwilling to issue a 401 Certification
for the Project. Therefore, in an effort to preserve the ability to
improve flood risk management in this area without excessive delay, the
Corps may invoke 404(r) exemption in lieu of obtaining a 401
Certification from the RWQCB.
FOR FURTHER INFORMATION CONTACT: Amanda Cruz, U.S. Army Corps of
Engineers, San Francisco District, Plan Formulation Section, 1455
Market Street, 17th Floor, San Francisco, CA 94103-1398, (415) 503-
6955, Amanda.b.cruz@usace.army.mil.
SUPPLEMENTARY INFORMATION: The March 2014 Final GRR/EIS of the Project,
and its accompanying CWA Sec. 404(b)(1) alternatives analysis,
recommended the proposed design of a earthen trapezoidal channel
section with varying bottom width and 2H:1V side slopes that provides
protection against the one-percent annual chance exceedance flood event
from I-680 in San Jose to Calaveras Boulevard in Milpitas (hereinafter
``Project''). These environmental analyses determined the Project to be
the National Economic Development Plan (NED), the National
Environmental Policy Act (NEPA) environmentally preferable alternative,
the California Environmental Quality Act (CEQA) Sec. 15126.6(e)(2)
environmentally superior alternative, and the CWA Sec. 404 Least
Environmental Damaging Practicable Alternative (LEDPA). The Corps'
Director of Civil Works signed the Record of Decision (ROD) on May 29,
2014.
With the goal of promoting partnership, it has been the Corps'
position to obtain 401 Certification for all its projects, regardless
of the availability of 404(r) exemption. However, if the RWQCB is
unable or unwilling to provide such a certification then the Corps will
initiate 404(r) exemption procedures and acknowledge this in the
appropriate NEPA document, which has been determined to be an SIR.
Section 404(r) creates an exemption from the water quality
certification requirement under Section 401(a) for projects (1)
specifically authorized by Congress for which (2) an environmental
impact statement has been created that (3) includes consideration of
the 404(b)(1) guidelines, which (4) has been transmitted to Congress
prior to the appropriation of construction funds. Congress authorized
construction of the Project in the Water Resources Development Act of
1990, Public Law 101-640, Sec. 101(a)(5), 103 Stat. 4604 (1990) and as
stated above, the Corps completed the GRR/EIS in March 2014. The
404(b)(1) Alternatives Analysis was included in the GRR/EIS as Appendix
A: Part V. With the completion of this SIR, the Corps will officially
transmit the updated GRR/EIS to Congress prior to the appropriation of
construction funding. Once done, the Corps will have met all the
requirements to utilize 404(r) exemption.
The Corps is confident that the Project is fully conforming to all
Federal and State laws, regulations, and requirements. In the absence
of RWQCB issuing a 401 Certification, the Corps may use 404(r)
exemption. In light of the fact that the Project meets all requirements
of 404(r) exemption without any modifications, there are no substantial
changes or new significant circumstances or information that would
trigger the need for a supplement
[[Page 61188]]
to the GRR/EIS, as defined in section 1502.9(c) of the CEQ Regulations.
John C. Morrow,
Lieutenant Colonel, U.S. Army, District Engineer.
[FR Doc. 2015-25859 Filed 10-8-15; 8:45 am]
BILLING CODE 3720-58-P