Guidelines for preparation of power
repayment studies are included in DOE
Order No. RA 6120.2 entitled Power
Marketing Administration Financial
Reporting. Following DOE guidelines,
Southwestern prepared a 2015 Current
Power Repayment Study using the
existing Sam Rayburn Dam Rate
Schedule.1 This study indicates that
Southwestern’s legal requirement to
repay the investment in the power
generating facility for power and energy
marketed by Southwestern will not be
met without an increase in revenues.
The need for increased revenues is
primarily due to increased operations
and maintenance costs and increased
interest expense associated with
investments and replacements in the
Corps hydroelectric generating facilities.
The 2015 Revised Power Repayment
Study shows that additional annual
revenues of $333,672 (a 7.9 percent
increase), beginning January 1, 2016, are
needed to satisfy repayment criteria.
Southwestern will continue to
perform its Power Repayment Studies
annually, and if the 2016 results should
indicate the need for additional
revenues, another rate filing will be
conducted and updated revenue
requirements implemented for fiscal
year 2017 and thereafter.
Procedures for public participation in
power and transmission rate
adjustments of the Power Marketing
Administrations are found at title 10,
part 903, subpart A of the Code of
Federal Regulations (10 CFR part 903).
Southwestern’s customers and other
interested parties may request copies of
the 2015 Sam Rayburn Dam Power
Repayment Studies and the proposed
Rate Schedule. Submit requests to the
Director, Division of Resources and
Rates, Office of Corporate Operations,
Southwestern Power Administration,
One West Third, Tulsa, OK 74103, (918)
595–6684 or via email to swparates@
swpa.gov.
If requested a Public Information and
Comment Forum (Forum) will be held
on October 22, 2015, to explain to
customers and interested parties the
proposed Rate Schedule and supporting
2015 Power Repayment Studies, and to
allow for comment. A chairman, who
will be responsible for orderly
procedure, will conduct the Forum if
requested. Questions concerning the
rates, studies, and information
presented at the Forum will be
answered, to the extent possible, at the
Forum. Questions not answered at the
1 FERC, on February 6, 2014, confirmed and
approved the existing Sam Rayburn Dam rate
schedule for the period October 1 2013 through
September 30, 2017. See 146 FERC ¶ 62,105 (FERC
Docket No. EF14–2–000).
VerDate Sep<11>2014
17:44 Oct 08, 2015
Jkt 238001
Forum will be answered in writing.
Questions involving voluminous data
contained in Southwestern’s records
may best be answered by consultation
and review of pertinent records at
Southwestern’s offices.
Persons requesting that a Forum be
held should indicate in writing to the
Senior Vice President and Chief
Operating Officer (see FOR FURTHER
INFORMATION CONTACT) by letter, email,
or facsimile transmission (918–595–
6646) by October 16, 2015, their request
for such a Forum. If no request is
received, no such Forum will be held.
Persons interested in speaking at the
Forum, if held, should submit a request
to the Senior Vice President and Chief
Operating Officer, Southwestern, at least
seven (7) calendar days prior to the
Forum so that a list of forum
participants can be developed. The
chairman may allow others to speak if
time permits.
A transcript of the Forum, if held, will
be made. Copies of the transcript and all
documents introduced will be available
for review at Southwestern’s offices (see
ADDRESSES) during normal business
hours. Copies of the transcript and all
documents introduced may also be
obtained, for a fee, from the transcribing
service. A copy of all written comments
or an electronic copy in MS Word on
the proposed Sam Rayburn Dam Rate
Schedule is due on or before November
9, 2015. Comments should be submitted
to the Senior Vice President and Chief
Operating Officer, Southwestern, (see
FOR FURTHER INFORMATION CONTACT).
Procedures for the confirmation and
approval of rates for the Federal Power
Marketing Administrations are found at
title 18, part 300, subpart L of the Code
of Federal Regulations (18 CFR part
300). The Acting Administrator will
review and consider oral and written
comments and the information gathered
in the course of the proceeding when
submitting the finalized Sam Rayburn
Dam Power Repayment Studies and
Rate Schedule Proposal in support of
the proposed rate to the Deputy
Secretary of Energy for confirmation and
approval on an interim basis, and
subsequently to the Federal Energy
Regulatory Commission for
confirmation and approval on a final
basis.
Once submitted for final confirmation
and approval, the Commission will
allow the public an opportunity to
provide written comments on the
proposed rate increase before making a
final decision.
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
61207
Dated: September 30, 2015.
Scott Carpenter,
Acting Administrator.
[FR Doc. 2015–25765 Filed 10–8–15; 8:45 am]
BILLING CODE 6450–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–9023–4]
Environmental Impact Statements;
Notice of Availability
Responsible Agency: Office of Federal,
Activities, General Information (202)
564–7146 or https://www2.epa.gov/nepa.
Weekly receipt of Environmental Impact
Statements (EISs)
Filed 09/28/2015 Through 10/02/2015
Pursuant to 40 CFR 1506.9.
Notice
Section 309(a) of the Clean Air Act
requires that EPA make public its
comments on EISs issued by other
Federal agencies. EPA’s comment letters
on EISs are available at: https://
cdxnodengn.epa.gov/cdx-enepa-public/
action/eis/search.
EIS No. 20150284, Draft, NPS, CA,
Scorpion Pier Replacement, Comment
Period Ends: 12/18/2015, Contact:
Karl Bachman 805–658–5700.
EIS No. 20150285, Final, FERC, OR,
Jordan Cove Energy and Pacific
Connector Gas Pipeline Project,
Review Period Ends: 11/08/2015,
Contact: Paul Friedman 202–502–
8059.
EIS No. 20150286, Draft, FERC, ID, Bear
River Narrows Hydroelectric ProjectFERC Project 12486–008, Comment
Period Ends: 11/30/2015, Contact:
Shana Murray 202–502–8333.
EIS No. 20150287, Draft, NGA, MO,
Next NGA West Campus in the
Greater St. Louis Metropolitan Area,
Comment Period Ends: 11/23/2015,
Contact: David Berczek (NGA) 314–
676–1123 and Amy Blair (COE) 816–
389–3393.
EIS No. 20150288, Draft, USACE, NE.,
Nebraska Highway 12 Niobrara East
and West, Comment Period Ends: 11/
23/2015, Contact: Rebecca J. Latka
402–995–2681.
Amended Notices
EIS No. 20150207, Draft, DOE, NH,
Northern Pass Transmission Line
Project, Comment Period Ends: 12/31/
2015, Contact: Brian Mills 202–586–
8267 Revision to FR Notice Published
07/24/2015; Extending Comment
Period from 10/29/2015 to 12/31/
20115.
EIS No. 20150264, Final, FHWA, TN,
Pellissippi Parkway Extension (State
E:\FR\FM\09OCN1.SGM
09OCN1
61208
Federal Register / Vol. 80, No. 196 / Friday, October 9, 2015 / Notices
Route 162) from State Route 33 (Old
Knoxville Highway) to US 321/State
Route 73/Lamar Alexander Parkway,
Review Period Ends: 11/18/2015,
Contact: Theresa Claxton 615–781–
5770. Revision to FR Notice
Published: 09/18/2015; Extending
Comment Period from 10/19/2015 to
11/18/2015.
EIS No. 20150278, Draft, USACE, GA,
Update of the Water Control Manual
for the Apalachicola-ChattahoocheeFlint River Basin in Alabama, Florida,
and Georgia and Water Supply
Storage Assessment, Comment Period
Ends: 12/01/2015, Contact: Lewis C.
Sumner 251–694–3857. Revision to
FR Notice Published 10/02/2015;
Correction to EIS Status should read
’Draft’ and Correcting the Comment
Period from 11/16/2015 to 12/1/2015.
Dated: October 6, 2015.
Karin Leff,
Acting Director, NEPA Compliance Division,
Office of Federal Activities.
[FR Doc. 2015–25795 Filed 10–8–15; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9935–20-Region 5]
Notice of Issuance of Part 71 Federal
Operating Permit to Great Lakes
Transmission Limited Partnership
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
This notice announces that on
August 28, 2015, pursuant to title V of
the Clean Air Act, the Environmental
Protection Agency (EPA) issued a title V
permit to operate (title V permit) to
Great Lakes Transmission Limited
Partnership. This permit authorizes
Great Lakes Transmission Limited
Partnership to operate a natural gas
compressor station at its facility
(Facility) in Deer River, Minnesota. The
compressor station consists of two
stationary natural gas-fired turbines,
which in turn drive two natural gas
compressors for the Deer River
Compressor Station No.4, which is
located on the Leech Lake Band of
Ojibwe Indian Reservation.
DATES: During the public comment
period, which ended June 1, 2015, EPA
received comments on the draft title V
permit. Therefore, in accordance with
40 CFR 71.11(i)(2), this permit is
effective 30 days after service of notice
of the decision to issue the permit,
October 2, 2015. 40 CFR 71.11(i)(2)
provides that the final permit decision
tkelley on DSK3SPTVN1PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:44 Oct 08, 2015
Jkt 238001
becomes effective 30 days after the
service of notice of the decision unless
a later effective date is specified, review
is requested, or no comments requested
a change in the draft permit, in which
case the permit becomes effective
immediately upon issuance. The
exceptions noted above to the 30 days
after notice of permit issuance date did
not apply in this permitting action. EPA
received comments on the draft permit
from the Leech Lake Band of Ojibwe
and the Minnesota Historical Society
State Historic Preservation Office during
the public comment period, and
changes were made to the final permit.
ADDRESSES: The final signed permit is
available for public inspection online at
https://yosemite.epa.gov/r5/r5ard.nsf/
Tribal+Permits!OpenView, or during
normal business hours at the following
address: EPA, Region 5, 77 West Jackson
Boulevard (AR–18J), Chicago, Illinois
60604.
FOR FURTHER INFORMATION CONTACT:
Constantine Blathras, Environmental
Engineer, EPA, Region 5, 77 W. Jackson
Boulevard (AR–18J), Chicago, Illinois
60604, (312) 886–0671, or
blathras.constantine@epa.gov.
SUPPLEMENTARY INFORMATION: This
supplemental information is organized
as follows:
A. What is the background information?
B. What is the purpose of this notice?
A. What Is the background
information?
The Deer River Compressor Station
No. 4 is owned by Great Lakes
Transmission Limited Partnership. Deer
River Compressor Station No. 4 consists
of two stationary natural gas-fired
turbines which, in turn, drive two
natural gas compressors. EPA received
the permit application on April 25,
2014.
On April 29, 2015, EPA made
available for a 30-day public comment
a draft Federal title V permit to operate
(V–LL–2706100011–14–01) in
accordance with the requirements of 40
CFR 71.11(d). This title V permit
incorporated all applicable air quality
requirements for the Deer River
Compressor Station No.4, including the
monitoring necessary to ensure
compliance with these requirements.
EPA received written comments,
responded to those comments, finalized
the permit and provided copies to the
applicant pursuant to 40 CFR 71.11(i).
B. What is the purpose of this notice?
EPA is notifying the public of the
issuance of the title V permit to Great
Lakes Transmission Limited Partnership
on August 28, 2015. Because EPA
PO 00000
Frm 00054
Fmt 4703
Sfmt 4703
received comments on the draft title V
permit, it is effective 30 days after
notice of permit issuance, October 2,
2015, pursuant to 40 CFR 71.11(i)(2).
Dated: September 25, 2015.
Susan Hedman,
Regional Administrator, Region 5.
[FR Doc. 2015–25838 Filed 10–8–15; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPPT–2014–0734; FRL 9933–60–
OEI]
Agency Information Collection
Activities; Information Collection
Request Submitted to OMB for Review
and Approval; Comment Request;
Health and Safety Data Reporting,
Submission of Lists and Copies of
Health and Safety Studies
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
EPA has submitted the
following information collection request
(ICR) to the Office of Management and
Budget (OMB) for review and approval
in accordance with the Paperwork
Reduction Act (PRA): ‘‘Health and
Safety Data Reporting, Submission of
Lists and Copies of Health and Safety
Studies’’ and identified by EPA ICR No.
0575.15 and OMB Control No. 2070–
0004. The ICR, which is available in the
docket along with other related
materials, provides a detailed
explanation of the collection activities
and the burden estimate that is only
briefly summarized in this document.
EPA did not receive any comments in
response to the previously provided
public review opportunity issued in the
Federal Register on March 30, 2015 (80
FR 16672). With this submission, EPA is
providing an additional 30 days for
public review.
DATES: Comments must be received on
or before November 9, 2015.
ADDRESSES: Submit your comments,
identified by docket identification (ID)
number EPA–HQ–OPPT–2014–0734, to
both EPA and OMB as follows:
• To EPA online using https://
www.regulations.gov (our preferred
method) or by mail to: EPA Docket
Center, Environmental Protection
Agency, Mail Code 28221T, 1200
Pennsylvania Ave. NW., Washington,
DC 20460.
• To OMB via email to oira_
submission@omb.eop.gov. Address
comments to OMB Desk Officer for EPA.
SUMMARY:
E:\FR\FM\09OCN1.SGM
09OCN1
Agencies
[Federal Register Volume 80, Number 196 (Friday, October 9, 2015)]
[Notices]
[Pages 61207-61208]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-25795]
=======================================================================
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[ER-FRL-9023-4]
Environmental Impact Statements; Notice of Availability
Responsible Agency: Office of Federal, Activities, General
Information (202) 564-7146 or https://www2.epa.gov/nepa.
Weekly receipt of Environmental Impact Statements (EISs)
Filed 09/28/2015 Through 10/02/2015
Pursuant to 40 CFR 1506.9.
Notice
Section 309(a) of the Clean Air Act requires that EPA make public
its comments on EISs issued by other Federal agencies. EPA's comment
letters on EISs are available at: https://cdxnodengn.epa.gov/cdx-enepa-public/action/eis/search.
EIS No. 20150284, Draft, NPS, CA, Scorpion Pier Replacement, Comment
Period Ends: 12/18/2015, Contact: Karl Bachman 805-658-5700.
EIS No. 20150285, Final, FERC, OR, Jordan Cove Energy and Pacific
Connector Gas Pipeline Project, Review Period Ends: 11/08/2015,
Contact: Paul Friedman 202-502-8059.
EIS No. 20150286, Draft, FERC, ID, Bear River Narrows Hydroelectric
Project-FERC Project 12486-008, Comment Period Ends: 11/30/2015,
Contact: Shana Murray 202-502-8333.
EIS No. 20150287, Draft, NGA, MO, Next NGA West Campus in the Greater
St. Louis Metropolitan Area, Comment Period Ends: 11/23/2015, Contact:
David Berczek (NGA) 314-676-1123 and Amy Blair (COE) 816-389-3393.
EIS No. 20150288, Draft, USACE, NE., Nebraska Highway 12 Niobrara East
and West, Comment Period Ends: 11/23/2015, Contact: Rebecca J. Latka
402-995-2681.
Amended Notices
EIS No. 20150207, Draft, DOE, NH, Northern Pass Transmission Line
Project, Comment Period Ends: 12/31/2015, Contact: Brian Mills 202-586-
8267 Revision to FR Notice Published 07/24/2015; Extending Comment
Period from 10/29/2015 to 12/31/20115.
EIS No. 20150264, Final, FHWA, TN, Pellissippi Parkway Extension (State
[[Page 61208]]
Route 162) from State Route 33 (Old Knoxville Highway) to US 321/State
Route 73/Lamar Alexander Parkway, Review Period Ends: 11/18/2015,
Contact: Theresa Claxton 615-781-5770. Revision to FR Notice Published:
09/18/2015; Extending Comment Period from 10/19/2015 to 11/18/2015.
EIS No. 20150278, Draft, USACE, GA, Update of the Water Control Manual
for the Apalachicola-Chattahoochee-Flint River Basin in Alabama,
Florida, and Georgia and Water Supply Storage Assessment, Comment
Period Ends: 12/01/2015, Contact: Lewis C. Sumner 251-694-3857.
Revision to FR Notice Published 10/02/2015; Correction to EIS Status
should read 'Draft' and Correcting the Comment Period from 11/16/2015
to 12/1/2015.
Dated: October 6, 2015.
Karin Leff,
Acting Director, NEPA Compliance Division, Office of Federal
Activities.
[FR Doc. 2015-25795 Filed 10-8-15; 8:45 am]
BILLING CODE 6560-50-P