PacifiCorp; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, 60888 [2015-25639]

Download as PDF 60888 Federal Register / Vol. 80, No. 195 / Thursday, October 8, 2015 / Notices Dated: October 2, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–25636 Filed 10–7–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 4580–006] mstockstill on DSK4VPTVN1PROD with NOTICES PacifiCorp; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Types of Application: Amendment of Exemption. b. Project Nos.: 4580–006. c. Date Filed: September 21, 2015. d. Applicant: PacifiCorp. e. Name of Projects: Last Chance Canal Hydroelectric Project. f. Location: The project is located at the Last Chance Canal, a diversion from the Bear River in Caribou County, Idaho. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Roger L. Raeburn, Chief Dam Safety Engineer, PacifiCorp, 825 NE. Multnomah Street, Suite 1500, Portland, OR 97232; (503) 813–6667 or roger.raeburn@ pacificorp.com. i. FERC Contact: B. Peter Yarrington, (202) 502–6129 or peter.yarrington@ ferc.gov. j. Deadline for filing comments, motions to intervene, and protests is 15 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, or comments using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Please include the project number (P– VerDate Sep<11>2014 16:41 Oct 07, 2015 Jkt 238001 4580–006) on any comments, motions to intervene, or protests filed. k. Description of Request: The applicant proposes to replace the project’s wood-crib diversion dam, and parts of the canal intake structure. An engineering inspection in April 2015 found significant deterioration of the diversion dam, which is over 100 years old, in addition to seepage where the intake structure meets the dam. The existing diversion dam would be replaced with a new structure of reinforced concrete and rollercompacted concrete. The work would not result in any changes to dam height, dam width, associated water levels, or project operation. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1 (866) 208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the amendment application. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: October 2, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–25639 Filed 10–7–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 77–276] Pacific Gas and Electric Company; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Application for Temporary Variance of Minimum Flow Requirement. b. Project No.: 77–276. c. Date Filed: September 30, 2015. d. Applicant: Pacific Gas and Electric Company (licensee). e. Name of Project: Potter Valley Project. f. Location: Eel River and East Fork Russian River in Lake and Mendocino Counties, California. E:\FR\FM\08OCN1.SGM 08OCN1

Agencies

[Federal Register Volume 80, Number 195 (Thursday, October 8, 2015)]
[Notices]
[Page 60888]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-25639]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 4580-006]


PacifiCorp; Notice of Application Accepted for Filing, Soliciting 
Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Types of Application: Amendment of Exemption.
    b. Project Nos.: 4580-006.
    c. Date Filed: September 21, 2015.
    d. Applicant: PacifiCorp.
    e. Name of Projects: Last Chance Canal Hydroelectric Project.
    f. Location: The project is located at the Last Chance Canal, a 
diversion from the Bear River in Caribou County, Idaho.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Roger L. Raeburn, Chief Dam Safety Engineer, 
PacifiCorp, 825 NE. Multnomah Street, Suite 1500, Portland, OR 97232; 
(503) 813-6667 or roger.raeburn@pacificorp.com.
    i. FERC Contact: B. Peter Yarrington, (202) 502-6129 or 
peter.yarrington@ferc.gov.
    j. Deadline for filing comments, motions to intervene, and protests 
is 15 days from the issuance date of this notice by the Commission. The 
Commission strongly encourages electronic filing. Please file motions 
to intervene, protests, or comments using the Commission's eFiling 
system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. Please include the project number (P-
4580-006) on any comments, motions to intervene, or protests filed.
    k. Description of Request: The applicant proposes to replace the 
project's wood-crib diversion dam, and parts of the canal intake 
structure. An engineering inspection in April 2015 found significant 
deterioration of the diversion dam, which is over 100 years old, in 
addition to seepage where the intake structure meets the dam. The 
existing diversion dam would be replaced with a new structure of 
reinforced concrete and roller-compacted concrete. The work would not 
result in any changes to dam height, dam width, associated water 
levels, or project operation.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits 
in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1 (866) 208-3676 or email 
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or 
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis and otherwise comply with the requirements of 18 CFR 
4.34(b). All comments, motions to intervene, or protests should relate 
to project works which are the subject of the amendment application. 
Agencies may obtain copies of the application directly from the 
applicant. A copy of any protest or motion to intervene must be served 
upon each representative of the applicant specified in the particular 
application. If an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 
385.2010.

    Dated: October 2, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-25639 Filed 10-7-15; 8:45 am]
 BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.