DBM Pipeline, LLC; Notice of Staff Protest to Proposed Blanket Certificate Activity, 60895 [2015-25634]

Download as PDF mstockstill on DSK4VPTVN1PROD with NOTICES Federal Register / Vol. 80, No. 195 / Thursday, October 8, 2015 / Notices Applicants: Southwest Power Pool, Inc. Description: Report Filing: Seams Transmission Projects-Re-Submission of Transmittal Letter in ER15–2705 to be effective N/A. Filed Date: 10/2/15. Accession Number: 20151002–5080. Comments Due: 5 p.m. ET 10/23/15. Docket Numbers: ER16–3–000. Applicants: Southwest Power Pool, Inc. Description: Southwest Power Pool, Inc.’s Informational Filing to Notify the Commission of Implementation of YearFour Reallocation of Revenue Requirements Pursuant to Attachments J and O for the Balanced Portfolio. Filed Date: 10/1/15. Accession Number: 20151001–5136. Comments Due: 5 p.m. ET 10/22/15. Docket Numbers: ER16–11–000. Applicants: Sierra Pacific Power Company. Description: § 205(d) Rate Filing: Rate Schedule No. 27—Annual BPA–GTA Update 2015 to be effective 10/31/2015. Filed Date: 10/1/15. Accession Number: 20151001–5407. Comments Due: 5 p.m. ET 10/22/15. Docket Numbers: ER16–12–000. Applicants: LRI Renewable Energy LLC. Description: § 205(d) Rate Filing: Emerald City Amendment to LRI to be effective 10/2/2015. Filed Date: 10/2/15. Accession Number: 20151002–5083. Comments Due: 5 p.m. ET 10/23/15. Docket Numbers: ER16–13–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: Revisions to Attach AE Regarding Annual Auction Revenue Right Allocation to be effective 1/28/2016. Filed Date: 10/2/15. Accession Number: 20151002–5106. Comments Due: 5 p.m. ET 10/23/15. Docket Numbers: ER16–14–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2015–10–02_MISO–SPP JOA Section 8.1.2 Amendment M2M to be effective 3/1/2015. Filed Date: 10/2/15. Accession Number: 20151002–5124. Comments Due: 5 p.m. ET 10/23/15. Docket Numbers: ER16–15–000. Applicants: R.E. Ginna Nuclear Power Plant, LLC. Description: § 205(d) Rate Filing: 2015 normal Oct to be effective 10/2/2015. Filed Date: 10/2/15. Accession Number: 20151002–5125. Comments Due: 5 p.m. ET 10/23/15. VerDate Sep<11>2014 16:41 Oct 07, 2015 Jkt 238001 The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: October 2, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. 60895 historic properties. Mitigation plans do not comply with the National Historic Preservation Act under the Commission’s regulations for blanket projects. DBM Pipeline must file with the Commission construction plan to avoid historic properties (exceed 25 feet from any of the historic properties). In addition, DBM Pipeline must file with the FERC complete responses to the FERC Environmental Data Request dated September 23, 2015. Without this information, environmental concerns cannot be adequately addressed within the 30 day period after the protest deadline. Dated: October 2, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–25634 Filed 10–7–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY [FR Doc. 2015–25616 Filed 10–7–15; 8:45 am] BILLING CODE 6717–01–P Federal Energy Regulatory Commission [Docket No. CP15–553–000] DEPARTMENT OF ENERGY Equitrans, L.P.; Notice of Application Federal Energy Regulatory Commission Take notice that on September 18, 2015, Equitrans, L.P. (‘‘Equitrans’’), pursuant to section 7(c) of the Federal Energy Regulatory Commission’s (FERC) regulations under the Natural Gas Act (NGA), filed in Docket No. CP15–553– 000, application for all authorizations necessary for it to restate the certificated capacities for the Allegheny Valley Connector (AVC) storage facilities located in Cambria, Clarion, Allegheny and Westmoreland Counties, Pennsylvania to reflect actual operations. The new collective storage deliverability will be adjusted to 246 MMcf/d from 260 MMcf/d and the new working gas capacity will be adjusted to 11.2 Bcf from 15.1 Bcf. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions concerning this application may be directed to Matthew Eggerding, Counsel—Midstream, EQT Corporation, 625 Liberty Avenue, Suite 1700, Pittsburgh, PA 15222 by calling (412) 553–5786; by faxing (412) 553– 7781; or by emailing MEggerding@ eqt.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, [Docket No. CP15–537–000] DBM Pipeline, LLC; Notice of Staff Protest to Proposed Blanket Certificate Activity Commission staff (Protestor) hereby protests the prior notice request filed under the provisions of part 157, subpart F, of the Commission’s regulations, by DBM Pipeline, LLC (DBM Pipeline) on July 27, 2015 in the above referenced docket. Pursuant to its part 157, subpart F, blanket certificate authority, DBM Pipeline proposes to construction and operate approximately 9 miles of 20-inch-diameter pipeline in Reeves and Culberson Counties, Texas, and Eddy County, New Mexico. Protestor seeks to have this prior notice request processed as a case-specific application filed under section 7(c) of the Natural Gas Act and part 157, subpart A, of the Commission’s regulations.1 Protestor notes that on September 28, 2015, DBM Pipeline filed a data response which described a mitigation plan instead of an avoidance plan for 1 Section 157.205(f) provides that a protested prior notice filing shall be treated as though it had filed a case-specific application under National Gas Act section 7, unless, pursuant to section 157.205(g) the protestor withdraws its protest within 30 days after protests were due. PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 E:\FR\FM\08OCN1.SGM 08OCN1

Agencies

[Federal Register Volume 80, Number 195 (Thursday, October 8, 2015)]
[Notices]
[Page 60895]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-25634]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-537-000]


DBM Pipeline, LLC; Notice of Staff Protest to Proposed Blanket 
Certificate Activity

    Commission staff (Protestor) hereby protests the prior notice 
request filed under the provisions of part 157, subpart F, of the 
Commission's regulations, by DBM Pipeline, LLC (DBM Pipeline) on July 
27, 2015 in the above referenced docket. Pursuant to its part 157, 
subpart F, blanket certificate authority, DBM Pipeline proposes to 
construction and operate approximately 9 miles of 20-inch-diameter 
pipeline in Reeves and Culberson Counties, Texas, and Eddy County, New 
Mexico. Protestor seeks to have this prior notice request processed as 
a case-specific application filed under section 7(c) of the Natural Gas 
Act and part 157, subpart A, of the Commission's regulations.\1\
---------------------------------------------------------------------------

    \1\ Section 157.205(f) provides that a protested prior notice 
filing shall be treated as though it had filed a case-specific 
application under National Gas Act section 7, unless, pursuant to 
section 157.205(g) the protestor withdraws its protest within 30 
days after protests were due.
---------------------------------------------------------------------------

    Protestor notes that on September 28, 2015, DBM Pipeline filed a 
data response which described a mitigation plan instead of an avoidance 
plan for historic properties. Mitigation plans do not comply with the 
National Historic Preservation Act under the Commission's regulations 
for blanket projects. DBM Pipeline must file with the Commission 
construction plan to avoid historic properties (exceed 25 feet from any 
of the historic properties). In addition, DBM Pipeline must file with 
the FERC complete responses to the FERC Environmental Data Request 
dated September 23, 2015.
    Without this information, environmental concerns cannot be 
adequately addressed within the 30 day period after the protest 
deadline.

    Dated: October 2, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-25634 Filed 10-7-15; 8:45 am]
 BILLING CODE 6717-01-P