FirstLight Hydro Generating Company; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, 60375-60376 [2015-25390]
Download as PDF
Federal Register / Vol. 80, No. 193 / Tuesday, October 6, 2015 / Notices
Dated: September 30, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–25381 Filed 10–5–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 9842–006]
tkelley on DSK3SPTVN1PROD with NOTICES
Mr. Ray F. Ward; Notice of Application
Ready for Environmental Analysis and
Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Minor New
License.
b. Project No.: 9842–006.
c. Date filed: August 28, 2014.
d. Applicant: Mr. Ray F. Ward.
e. Name of Project: Ward Mill
Hydroelectric Project.
f. Location: On the Watauga River, in
the Township of Laurel Creek, Watauga
County, North Carolina. The project
does not occupy lands of the United
States.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Andrew C.
Givens, Cardinal Energy Service, Inc.,
620 N. West St., Suite 103, Raleigh,
North Carolina 27603, (919) 834–0909.
i. FERC Contact: Adam Peer (202)
502–8449, adam.peer@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
VerDate Sep<11>2014
18:31 Oct 05, 2015
Jkt 238001
The first page of any filing should
include docket number P–9842–006.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted,
and is ready for environmental analysis
at this time.
l. The Ward Mill Project consists of:
(1) A 4.6 acre reservoir with an
estimated gross storage capacity of 16.3
acre-feet; (2) a 130-foot-long by 20-foothigh dam; (3) a 14-footlong, 5-foot-wide,
and 7.5-foot-tall penstock made of rock,
concrete and reinforced steel; (4) a
powerhouse containing two generating
units for a total installed capacity of 168
kilowatts; (5) interconnection with the
utility at the meter point on the
southwest, exterior wall of the
powerhouse; and (6) appurtenant
facilities. The project is estimated to
generate from about 290,000 to about
599,000 kilowatt-hours annually. The
dam and existing facilities are owned by
the applicant. No new project facilities
are proposed.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies should indicate which
recommendations are being submitted
pursuant to section 10(j) of the Federal
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
60375
Power Act (16 U.S.C. 803(j)). Agencies
may obtain copies of the application
directly from the applicant. Each filing
must be accompanied by proof of
service on all persons listed on the
service list prepared by the Commission
in this proceeding, in accordance with
18 CFR 4.34(b) and 385.2010.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: September 30, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–25389 Filed 10–5–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2485–070]
FirstLight Hydro Generating Company;
Notice of Application Accepted for
Filing, Soliciting Comments, Motions
To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Application
for Amendment of Minimum and
Maximum Reservoir Elevation
Requirement.
b. Project No.: 2485–070.
c. Date Filed: September 1, 2015.
d. Applicant: FirstLight Hydro
Generating Company (Firstlight).
e. Name of Project: Northfield
Mountain Pumped Storage Project.
f. Location: The project is located on
the east side of the Connecticut River,
in the towns of Northfield and Erving,
in Franklin County, Massachusetts.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. John S.
Howard, Director FERC Compliance,
FirstLight Hydro Generating Company,
Northfield Mountain Station, 99 Millers
Falls Road, Northfield, MA 01360.
Phone (413) 659–4489.
E:\FR\FM\06OCN1.SGM
06OCN1
tkelley on DSK3SPTVN1PROD with NOTICES
60376
Federal Register / Vol. 80, No. 193 / Tuesday, October 6, 2015 / Notices
i. FERC Contact: Mr. Christopher
Chaney, (202) 502–6778, or
christopher.chaney@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests is 30
days from the issuance date of this
notice by the Commission. The
Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, or comments using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
Please include the project number (P–
2485–070) on any comments, motions to
intervene, or protests filed.
k. Description of Request: FirstLight is
seeking authorization to modify the
upper reservoir’s upper and lower water
surface elevation limits from 1,000.5
feet mean sea level (msl) and 938 feet
msl, to 1,004.5 feet msl and 920 feet
msl, respectively. FirstLight proposes to
use the additional storage capacity
annually between December 1 and
March 31, beginning December 1, 2015,
and continuing until the Commission
issues a new license for the project.
According to FirstLight, approval of
changes in the water surface elevation
limits would result in an increase in the
maximum daily generation from 8,475
megawatt-hours (MWh) to 10,645 MWh,
and provide Independent System
Operator-New England with additional
resources to address winter reliability
needs.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
excluding the last three digits in the
docket number field to access the
document (i.e. P–2485). You may also
register online at https://www.ferc.gov/
docs-filing/esubscription.asp to be
notified via email of new filings and
issuances related to this or other
pending projects. For assistance, call 1–
VerDate Sep<11>2014
18:31 Oct 05, 2015
Jkt 238001
866–208–3676 or email
FERCOnlineSupport@ferc.gov, for TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene, or
protests should relate to the amendment
request. Agencies may obtain copies of
the application directly from the
applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
Dated: September 29, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–25390 Filed 10–5–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–132–000]
Kern River Transmission Company;
Notice of Availability of the
Environmental Assessment for the
Proposed Summerlin Pipe
Replacement Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared an
environmental assessment (EA) for the
Summerlin Pipe Replacement Project,
proposed by Kern River Transmission
Company (Kern River) in the abovereferenced docket. Kern River requests
authorization to construct, operate, and
maintain a new natural gas pipeline and
associated facilities in Clark County,
Nevada, and remove a corresponding
segment of existing pipeline.
The EA assesses the potential
environmental effects of the
construction and operation of the
Summerlin Pipe Replacement Project in
accordance with the requirements of the
National Environmental Policy Act
(NEPA). The FERC staff concludes that
approval of the proposed project, with
appropriate mitigating measures, would
not constitute a major federal action
significantly affecting the quality of the
human environment.
The U.S. Bureau of Land Management
(BLM) participated as a cooperating
agency in the preparation of the EA.
Cooperating agencies have jurisdiction
by law or special expertise with respect
to resources potentially affected by the
proposal and participate in the NEPA
analysis. The BLM will adopt and use
the EA to consider the issuance of a
right-of-way grant for the portion of the
project on BLM lands.
The proposed Summerlin Pipe
Replacement Project includes replacing
a 1.56-mile-long segment of its existing
36-inch-diameter A-Line pipeline and
expanding an existing 0.22-acre valve
and pig launcher yard to 0.37 acre to
accommodate a new crossover valve and
crossover piping.
The FERC staff mailed CD copies of
the EA to federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American tribes;
E:\FR\FM\06OCN1.SGM
06OCN1
Agencies
[Federal Register Volume 80, Number 193 (Tuesday, October 6, 2015)]
[Notices]
[Pages 60375-60376]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-25390]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2485-070]
FirstLight Hydro Generating Company; Notice of Application
Accepted for Filing, Soliciting Comments, Motions To Intervene, and
Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Application for Amendment of Minimum and
Maximum Reservoir Elevation Requirement.
b. Project No.: 2485-070.
c. Date Filed: September 1, 2015.
d. Applicant: FirstLight Hydro Generating Company (Firstlight).
e. Name of Project: Northfield Mountain Pumped Storage Project.
f. Location: The project is located on the east side of the
Connecticut River, in the towns of Northfield and Erving, in Franklin
County, Massachusetts.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. John S. Howard, Director FERC Compliance,
FirstLight Hydro Generating Company, Northfield Mountain Station, 99
Millers Falls Road, Northfield, MA 01360. Phone (413) 659-4489.
[[Page 60376]]
i. FERC Contact: Mr. Christopher Chaney, (202) 502-6778, or
christopher.chaney@ferc.gov.
j. Deadline for filing comments, motions to intervene, and protests
is 30 days from the issuance date of this notice by the Commission. The
Commission strongly encourages electronic filing. Please file motions
to intervene, protests, or comments using the Commission's eFiling
system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. Please include the project number (P-
2485-070) on any comments, motions to intervene, or protests filed.
k. Description of Request: FirstLight is seeking authorization to
modify the upper reservoir's upper and lower water surface elevation
limits from 1,000.5 feet mean sea level (msl) and 938 feet msl, to
1,004.5 feet msl and 920 feet msl, respectively. FirstLight proposes to
use the additional storage capacity annually between December 1 and
March 31, beginning December 1, 2015, and continuing until the
Commission issues a new license for the project. According to
FirstLight, approval of changes in the water surface elevation limits
would result in an increase in the maximum daily generation from 8,475
megawatt-hours (MWh) to 10,645 MWh, and provide Independent System
Operator-New England with additional resources to address winter
reliability needs.
l. Locations of the Application: A copy of the application is
available for inspection and reproduction at the Commission's Public
Reference Room, located at 888 First Street NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits
in the docket number field to access the document (i.e. P-2485). You
may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, call 1-866-
208-3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-
8659. A copy is also available for inspection and reproduction at the
address in item (h) above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
o. Filing and Service of Responsive Documents: Any filing must (1)
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis and otherwise comply with the requirements of 18 CFR
4.34(b). All comments, motions to intervene, or protests should relate
to the amendment request. Agencies may obtain copies of the application
directly from the applicant. A copy of any protest or motion to
intervene must be served upon each representative of the applicant
specified in the particular application. If an intervener files
comments or documents with the Commission relating to the merits of an
issue that may affect the responsibilities of a particular resource
agency, they must also serve a copy of the document on that resource
agency. A copy of all other filings in reference to this application
must be accompanied by proof of service on all persons listed in the
service list prepared by the Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and 385.2010.
Dated: September 29, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-25390 Filed 10-5-15; 8:45 am]