Approval and Promulgation of Implementation Plans; Florida Infrastructure Requirements for the 2008 Lead NAAQS, 57538-57540 [2015-24088]

Download as PDF 57538 Federal Register / Vol. 80, No. 185 / Thursday, September 24, 2015 / Rules and Regulations Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and • does not provide EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under Executive Order 12898 (59 FR 7629, February 16, 1994). In addition, the SIP is not approved to apply on any Indian reservation land or in any other area where EPA or an Indian tribe has demonstrated that a tribe has jurisdiction. In those areas of Indian country, the rule does not have tribal implications as specified by Executive Order 13175 (65 FR 67249, November 9, 2000), nor will it impose substantial direct costs on tribal governments or preempt tribal law. The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. EPA will submit a report containing this action and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. A major rule cannot take effect until 60 days after it is published in the Federal Register. This action is not a ‘‘major rule’’ as defined by 5 U.S.C. 804(2). Under section 307(b)(1) of the CAA, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by November 23, 2015. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this action for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. See section 307(b)(2). List of Subjects in 40 CFR Part 52 Environmental protection, Air pollution control, Incorporation by reference, Ozone, Reporting and recordkeeping requirements, Volatile organic compounds. Authority: 42 U.S.C. 7401 et seq. Dated: September 10, 2015. Heather McTeer Toney, Regional Administrator, Region 4. 40 CFR part 52 is amended as follows: PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS 1. The authority citation for part 52 continues to read as follows: ■ Authority: 42 U.S.C. 7401 et seq. Subpart L—Georgia 2. Section 52.570(c) is amended by revising the entry for ‘‘391–3–22’’ to read as follows: ■ § 52.570 * Identification of plan. * * (c) * * * * * EPA APPROVED GEORGIA REGULATIONS State citation Title/subject * 391–3–22 ...... State effective date * Clean Fueled Fleets .... * * * * * BILLING CODE 6560–50–P ENVIRONMENTAL PROTECTION AGENCY 40 CFR Part 52 [EPA–R04–OAR–2013–0040; FRL–9934–41– Region 4] Approval and Promulgation of Implementation Plans; Florida Infrastructure Requirements for the 2008 Lead NAAQS Environmental Protection Agency (EPA). ACTION: Final rule. tkelley on DSK3SPTVN1PROD with RULES AGENCY: The Environmental Protection Agency (EPA) is taking final action to approve portions of the October 14, 2011, State Implementation Plan (SIP) submission, provided by the State of VerDate Sep<11>2014 16:28 Sep 23, 2015 Jkt 235001 Explanation * * 9/24/15 [Insert citation of publication]. * * Clean Fueled Fleets rules moved to the contingency measures portion of the SIP-approved 1997 8-hour ozone Maintenance Plan for the Atlanta Area. Florida, through the Department of Environmental Protection (FL DEP) for inclusion into the Florida SIP. This final submission pertains to the Clean Air Act (CAA or the Act) infrastructure requirements for the 2008 Lead national ambient air quality standards (NAAQS). The CAA requires that each state adopt and submit a SIP for the implementation, maintenance, and enforcement of each NAAQS promulgated by EPA, which is commonly referred to as an ‘‘infrastructure’’ SIP. FL DEP certified that the Florida SIP contains provisions that ensure the 2008 Lead NAAQS is implemented, enforced, and maintained in Florida. With the exception of provisions pertaining to prevention of significant deterioration (PSD) permitting which EPA has already approved, EPA is taking final action to approve Florida’s infrastructure submission, provided to EPA on October 14, 2011, as satisfying the required infrastructure elements for the 2008 Lead NAAQS. DATES: This rule will be effective October 26, 2015 ADDRESSES: EPA has established a docket for this action under Docket Identification No. EPA–R04–OAR– 2013–0040. All documents in the docket are listed on the www.regulations.gov Web site. Although listed in the index, some information is not publicly available, i.e., Confidential Business Information or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the Internet and will be publicly available only in hard copy form. Publicly available docket materials are available either electronically through www.regulations.gov or in hard copy at the Air Regulatory Management Section, Air Planning and Implementation Branch, Air, Pesticides and Toxics Management Division, U.S. * 5/11/14 [FR Doc. 2015–24094 Filed 9–23–15; 8:45 am] SUMMARY: EPA approval date PO 00000 Frm 00030 Fmt 4700 Sfmt 4700 E:\FR\FM\24SER1.SGM 24SER1 Federal Register / Vol. 80, No. 185 / Thursday, September 24, 2015 / Rules and Regulations Environmental Protection Agency, Region 4, 61 Forsyth Street SW., Atlanta, Georgia 30303–8960. EPA requests that if at all possible, you contact the person listed in the FOR FURTHER INFORMATION CONTACT section to schedule your inspection. The Regional Office’s official hours of business are Monday through Friday, 8:30 a.m. to 4:30 p.m., excluding Federal holidays. Zuri Farngalo, Air Regulatory Management Section, Air Planning and Implementation Branch, Air, Pesticides and Toxics Management Division, U.S. Environmental Protection Agency, Region 4, 61 Forsyth Street SW., Atlanta, Georgia 30303–8960. The telephone number is (404) 562–9152. Mr. Farngalo can be reached via electronic mail at farngalo.zuri@ epa.gov. FOR FURTHER INFORMATION CONTACT: SUPPLEMENTARY INFORMATION: tkelley on DSK3SPTVN1PROD with RULES I. Background Upon promulgation of a new or revised NAAQS, sections 110(a)(1) and (2) of the CAA require states to address basic SIP requirements, including emissions inventories, monitoring, and modeling to assure attainment and maintenance for that new NAAQS. Section 110(a) of the CAA generally requires states to make a SIP submission to meet applicable requirements in order to provide for the implementation, maintenance, and enforcement of a new or revised NAAQS within three years following the promulgation of such NAAQS, or within such shorter period as EPA may prescribe. For additional information on the infrastructure SIP requirements, see the proposed rulemaking published on May 22, 2015 (80 FR 29592). On May 22, 2015, EPA proposed to approve portions of Florida’s October 14, 2011, 2008 Lead NAAQS infrastructure SIP submission with the exception of provisions pertaining to PSD permitting in sections 110(a)(2)(C), prong 3 of D(i) and (J). EPA did not receive any comments, adverse or otherwise, on the May 22, 2015, proposed rule. EPA took final action to approve the PSD permitting requirements in sections 110(a)(2)(C), prong 3 of D(i) and (J) on March 18, 2015 (80 FR 14019). EPA is taking final action to approve the remaining portions of Florida’s infrastructure submission as demonstrating that the State meets the applicable requirements of sections 110(a)(1) and (2) of the CAA for the 2008 Lead NAAQS. VerDate Sep<11>2014 16:28 Sep 23, 2015 Jkt 235001 II. Final Action With the exception of provisions pertaining to PSD permitting requirements, EPA is taking final action to approve Florida’s October 14, 2011, infrastructure submission because it addresses the required infrastructure elements for the 2008 Lead NAAQS. FL DEP has addressed the elements of the CAA 110(a)(1) and (2) SIP requirements pursuant to section 110 of the CAA to ensure that the 2008 Lead NAAQS is implemented, enforced, and maintained in Florida. III. Statutory and Executive Order Reviews Under the CAA, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, EPA’s role is to approve state choices, provided that they meet the criteria of the CAA. Accordingly, this action merely approves state law as meeting Federal requirements and does not impose additional requirements beyond those imposed by state law. For that reason, this action: • Is not a significant regulatory action subject to review by the Office of Management and Budget under Executive Orders 12866 (58 FR 51735, October 4, 1993) and 13563 (76 FR 3821, January 21, 2011); • does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.); • is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.); • does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104–4); • does not have Federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999); • is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997); • is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001); • is not subject to requirements of Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the Clean Air Act; and PO 00000 Frm 00031 Fmt 4700 Sfmt 4700 57539 • does not provide EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under Executive Order 12898 (59 FR 7629, February 16, 1994). In addition, the SIP is not approved to apply on any Indian reservation land or in any other area where EPA or an Indian tribe has demonstrated that a tribe has jurisdiction. In those areas of Indian country, the rule does not have tribal implications and will not impose substantial direct costs on tribal governments or preempt tribal law as specified by Executive Order 13175 (65 FR 67249, November 9, 2000). The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. EPA will submit a report containing this action and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. A major rule cannot take effect until 60 days after it is published in the Federal Register. This action is not a ‘‘major rule’’ as defined by 5 U.S.C. 804(2). Under section 307(b)(1) of the CAA, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by November 23, 2015. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this action for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. See section 307(b)(2). List of Subjects in 40 CFR Part 52 Environmental protection, Air pollution control, Incorporation by reference, Intergovernmental relations, Lead, Reporting and recordkeeping requirements, Volatile organic compounds. Dated: September 10, 2015. Heather McTeer Toney, Regional Administrator, Region 4. 40 CFR part 52 is amended as follows: E:\FR\FM\24SER1.SGM 24SER1 57540 Federal Register / Vol. 80, No. 185 / Thursday, September 24, 2015 / Rules and Regulations Authority: 42 U.S.C. 7401 et seq. PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS Subpart K—Florida 2. Section 52.520(e), is amended by adding entry ‘‘110(a)(1) and (2) Infrastructure Requirements for the 2008 ■ 1. The authority citation for part 52 continues to read as follows: ■ Lead National Ambient Air Quality Standards’’ at the end of the table to read as follows: § 52.520 * Identification of plan. * * (e) * * * * * EPA-APPROVED FLORIDA NON-REGULATORY PROVISIONS Provision State effective date EPA approval date Federal Register notice Explanation * * 110(a)(1) and (2) Infrastructure Requirements for the 2008 Lead National Ambient Air Quality Standards. * 10/14/2011 9/24/2015 * * [Insert citation of publication] ......... * * With the exception of provisions pertaining to PSD permitting requirements in sections 110(a)(2)(C), prong 3 of D(i) and (J). approve South Carolina’s infrastructure SIP submission, provided to EPA on September 20, 2011. BILLING CODE 6560–50–P [EPA–R04–OAR–2012–0852; FRL– 9934–40– Region 4] Approval and Promulgation of Implementation Plans; South Carolina; Infrastructure Requirements for the 2008 Lead National Ambient Air Quality Standards Environmental Protection Agency (EPA). ACTION: Final rule. AGENCY: The Environmental Protection Agency (EPA) is taking final action to approve the September 20, 2011, State Implementation Plan (SIP) submission, provided by the South Carolina Department of Health and Environmental Control (SC DHEC) for inclusion into the South Carolina SIP. This final action pertains to the Clean Air Act (CAA or the Act) infrastructure requirements for the 2008 Lead national ambient air quality standards (NAAQS). The CAA requires that each state adopt and submit a SIP for the implementation, maintenance, and enforcement of each NAAQS promulgated by EPA, which is commonly referred to as an ‘‘infrastructure’’ SIP. SC DHEC certified that the South Carolina SIP contains provisions to ensure the 2008 Lead NAAQS is implemented, enforced, and maintained in South Carolina. With the exception of provisions pertaining to prevention of significant deterioration (PSD) permitting which EPA has already approved, EPA is taking final action to SUMMARY: tkelley on DSK3SPTVN1PROD with RULES EPA has established a docket for this action under Docket Identification No. EPA–R04–OAR– 2012–0852. All documents in the docket are listed on the www.regulations.gov Web site. Although listed in the index, some information is not publicly available, i.e., Confidential Business Information or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the Internet and will be publicly available only in hard copy form. Publicly available docket materials are available either electronically through www.regulations.gov or in hard copy at the Air Regulatory Management Section, Air Planning and Implementation Branch, Air, Pesticides and Toxics Management Division, U.S. Environmental Protection Agency, Region 4, 61 Forsyth Street SW., Atlanta, Georgia 30303–8960. EPA requests that if at all possible, you contact the person listed in the FOR FURTHER INFORMATION CONTACT section to schedule your inspection. The Regional Office’s official hours of business are Monday through Friday, 8:30 a.m. to 4:30 p.m., excluding Federal holidays. ADDRESSES: 40 CFR Part 52 16:28 Sep 23, 2015 I. Background Upon promulgation of a new or revised NAAQS, sections 110(a)(1) and (2) of the CAA require states to address basic SIP requirements, including emissions inventories, monitoring, and modeling to assure attainment and maintenance for that new NAAQS. Section 110(a) of the CAA generally requires states to make a SIP submission to meet applicable requirements in order to provide for the implementation, maintenance, and enforcement of a new or revised NAAQS within three years following the promulgation of such NAAQS, or within such shorter period as EPA may prescribe. For additional information on the infrastructure SIP requirements, see the proposed rulemaking published on June 8, 2015. (80 FR 32324) On June 8, 2015, EPA proposed to approve portions of South Carolina’s September 20, 2011, 2008 Lead NAAQS infrastructure SIP submission with the exception of provisions pertaining to PSD permitting in sections 110(a)(2)(C), prong 3 of D(i) and (J). See 80 FR 32324. EPA did not receive any comments, adverse or otherwise, on the June 8, 2015, proposed rule. EPA took final action to approve the PSD permitting requirements in sections 110(a)(2)(C), prong 3 of D(i) and (J) on March 18, 2015. See 80 FR 14019. DATES: ENVIRONMENTAL PROTECTION AGENCY VerDate Sep<11>2014 electronic mail at farngalo.zuri@ epa.gov. SUPPLEMENTARY INFORMATION: This rule will be effective October 26, 2015. [FR Doc. 2015–24088 Filed 9–23–15; 8:45 am] Jkt 235001 Zuri Farngalo, Air Regulatory Management Section, Air Planning and Implementation Branch, Air, Pesticides and Toxics Management Division, U.S. Environmental Protection Agency, Region 4, 61 Forsyth Street SW., Atlanta, Georgia 30303–8960. The telephone number is (404) 562–9152. Mr. Farngalo can be reached via FOR FURTHER INFORMATION CONTACT: PO 00000 Frm 00032 Fmt 4700 Sfmt 4700 II. This Action In this rulemaking, EPA is taking final action to approve the remaining portions of South Carolina’s infrastructure submission as demonstrating that the State meets the applicable requirements of sections 110(a)(1) and (2) of the CAA for the E:\FR\FM\24SER1.SGM 24SER1

Agencies

[Federal Register Volume 80, Number 185 (Thursday, September 24, 2015)]
[Rules and Regulations]
[Pages 57538-57540]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-24088]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Part 52

[EPA-R04-OAR-2013-0040; FRL-9934-41-Region 4]


Approval and Promulgation of Implementation Plans; Florida 
Infrastructure Requirements for the 2008 Lead NAAQS

AGENCY: Environmental Protection Agency (EPA).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Environmental Protection Agency (EPA) is taking final 
action to approve portions of the October 14, 2011, State 
Implementation Plan (SIP) submission, provided by the State of Florida, 
through the Department of Environmental Protection (FL DEP) for 
inclusion into the Florida SIP. This final submission pertains to the 
Clean Air Act (CAA or the Act) infrastructure requirements for the 2008 
Lead national ambient air quality standards (NAAQS). The CAA requires 
that each state adopt and submit a SIP for the implementation, 
maintenance, and enforcement of each NAAQS promulgated by EPA, which is 
commonly referred to as an ``infrastructure'' SIP. FL DEP certified 
that the Florida SIP contains provisions that ensure the 2008 Lead 
NAAQS is implemented, enforced, and maintained in Florida. With the 
exception of provisions pertaining to prevention of significant 
deterioration (PSD) permitting which EPA has already approved, EPA is 
taking final action to approve Florida's infrastructure submission, 
provided to EPA on October 14, 2011, as satisfying the required 
infrastructure elements for the 2008 Lead NAAQS.

DATES: This rule will be effective October 26, 2015

ADDRESSES: EPA has established a docket for this action under Docket 
Identification No. EPA-R04-OAR-2013-0040. All documents in the docket 
are listed on the www.regulations.gov Web site. Although listed in the 
index, some information is not publicly available, i.e., Confidential 
Business Information or other information whose disclosure is 
restricted by statute. Certain other material, such as copyrighted 
material, is not placed on the Internet and will be publicly available 
only in hard copy form. Publicly available docket materials are 
available either electronically through www.regulations.gov or in hard 
copy at the Air Regulatory Management Section, Air Planning and 
Implementation Branch, Air, Pesticides and Toxics Management Division, 
U.S.

[[Page 57539]]

Environmental Protection Agency, Region 4, 61 Forsyth Street SW., 
Atlanta, Georgia 30303-8960. EPA requests that if at all possible, you 
contact the person listed in the FOR FURTHER INFORMATION CONTACT 
section to schedule your inspection. The Regional Office's official 
hours of business are Monday through Friday, 8:30 a.m. to 4:30 p.m., 
excluding Federal holidays.

FOR FURTHER INFORMATION CONTACT: Zuri Farngalo, Air Regulatory 
Management Section, Air Planning and Implementation Branch, Air, 
Pesticides and Toxics Management Division, U.S. Environmental 
Protection Agency, Region 4, 61 Forsyth Street SW., Atlanta, Georgia 
30303-8960. The telephone number is (404) 562-9152. Mr. Farngalo can be 
reached via electronic mail at farngalo.zuri@epa.gov.

SUPPLEMENTARY INFORMATION: 

I. Background

    Upon promulgation of a new or revised NAAQS, sections 110(a)(1) and 
(2) of the CAA require states to address basic SIP requirements, 
including emissions inventories, monitoring, and modeling to assure 
attainment and maintenance for that new NAAQS. Section 110(a) of the 
CAA generally requires states to make a SIP submission to meet 
applicable requirements in order to provide for the implementation, 
maintenance, and enforcement of a new or revised NAAQS within three 
years following the promulgation of such NAAQS, or within such shorter 
period as EPA may prescribe. For additional information on the 
infrastructure SIP requirements, see the proposed rulemaking published 
on May 22, 2015 (80 FR 29592).
    On May 22, 2015, EPA proposed to approve portions of Florida's 
October 14, 2011, 2008 Lead NAAQS infrastructure SIP submission with 
the exception of provisions pertaining to PSD permitting in sections 
110(a)(2)(C), prong 3 of D(i) and (J). EPA did not receive any 
comments, adverse or otherwise, on the May 22, 2015, proposed rule. EPA 
took final action to approve the PSD permitting requirements in 
sections 110(a)(2)(C), prong 3 of D(i) and (J) on March 18, 2015 (80 FR 
14019). EPA is taking final action to approve the remaining portions of 
Florida's infrastructure submission as demonstrating that the State 
meets the applicable requirements of sections 110(a)(1) and (2) of the 
CAA for the 2008 Lead NAAQS.

II. Final Action

    With the exception of provisions pertaining to PSD permitting 
requirements, EPA is taking final action to approve Florida's October 
14, 2011, infrastructure submission because it addresses the required 
infrastructure elements for the 2008 Lead NAAQS. FL DEP has addressed 
the elements of the CAA 110(a)(1) and (2) SIP requirements pursuant to 
section 110 of the CAA to ensure that the 2008 Lead NAAQS is 
implemented, enforced, and maintained in Florida.

III. Statutory and Executive Order Reviews

    Under the CAA, the Administrator is required to approve a SIP 
submission that complies with the provisions of the Act and applicable 
Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in 
reviewing SIP submissions, EPA's role is to approve state choices, 
provided that they meet the criteria of the CAA. Accordingly, this 
action merely approves state law as meeting Federal requirements and 
does not impose additional requirements beyond those imposed by state 
law. For that reason, this action:
     Is not a significant regulatory action subject to review 
by the Office of Management and Budget under Executive Orders 12866 (58 
FR 51735, October 4, 1993) and 13563 (76 FR 3821, January 21, 2011);
     does not impose an information collection burden under the 
provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
     is certified as not having a significant economic impact 
on a substantial number of small entities under the Regulatory 
Flexibility Act (5 U.S.C. 601 et seq.);
     does not contain any unfunded mandate or significantly or 
uniquely affect small governments, as described in the Unfunded 
Mandates Reform Act of 1995 (Pub. L. 104-4);
     does not have Federalism implications as specified in 
Executive Order 13132 (64 FR 43255, August 10, 1999);
     is not an economically significant regulatory action based 
on health or safety risks subject to Executive Order 13045 (62 FR 
19885, April 23, 1997);
     is not a significant regulatory action subject to 
Executive Order 13211 (66 FR 28355, May 22, 2001);
     is not subject to requirements of Section 12(d) of the 
National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 
note) because application of those requirements would be inconsistent 
with the Clean Air Act; and
     does not provide EPA with the discretionary authority to 
address, as appropriate, disproportionate human health or environmental 
effects, using practicable and legally permissible methods, under 
Executive Order 12898 (59 FR 7629, February 16, 1994).
    In addition, the SIP is not approved to apply on any Indian 
reservation land or in any other area where EPA or an Indian tribe has 
demonstrated that a tribe has jurisdiction. In those areas of Indian 
country, the rule does not have tribal implications and will not impose 
substantial direct costs on tribal governments or preempt tribal law as 
specified by Executive Order 13175 (65 FR 67249, November 9, 2000).
    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the 
Small Business Regulatory Enforcement Fairness Act of 1996, generally 
provides that before a rule may take effect, the agency promulgating 
the rule must submit a rule report, which includes a copy of the rule, 
to each House of the Congress and to the Comptroller General of the 
United States. EPA will submit a report containing this action and 
other required information to the U.S. Senate, the U.S. House of 
Representatives, and the Comptroller General of the United States prior 
to publication of the rule in the Federal Register. A major rule cannot 
take effect until 60 days after it is published in the Federal 
Register. This action is not a ``major rule'' as defined by 5 U.S.C. 
804(2).
    Under section 307(b)(1) of the CAA, petitions for judicial review 
of this action must be filed in the United States Court of Appeals for 
the appropriate circuit by November 23, 2015. Filing a petition for 
reconsideration by the Administrator of this final rule does not affect 
the finality of this action for the purposes of judicial review nor 
does it extend the time within which a petition for judicial review may 
be filed, and shall not postpone the effectiveness of such rule or 
action. This action may not be challenged later in proceedings to 
enforce its requirements. See section 307(b)(2).

List of Subjects in 40 CFR Part 52

    Environmental protection, Air pollution control, Incorporation by 
reference, Intergovernmental relations, Lead, Reporting and 
recordkeeping requirements, Volatile organic compounds.

    Dated: September 10, 2015.
Heather McTeer Toney,
Regional Administrator, Region 4.

    40 CFR part 52 is amended as follows:

[[Page 57540]]

PART 52--APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS

0
1. The authority citation for part 52 continues to read as follows:

    Authority:  42 U.S.C. 7401 et seq.

Subpart K--Florida

0
2. Section 52.520(e), is amended by adding entry ``110(a)(1) and (2) 
Infrastructure Requirements for the 2008 Lead National Ambient Air 
Quality Standards'' at the end of the table to read as follows:


Sec.  52.520  Identification of plan.

* * * * *
    (e) * * *

                                 EPA-Approved Florida Non-Regulatory Provisions
----------------------------------------------------------------------------------------------------------------
                                    State effective    EPA approval     Federal Register
             Provision                    date             date              notice              Explanation
----------------------------------------------------------------------------------------------------------------
 
                                                  * * * * * * *
110(a)(1) and (2) Infrastructure        10/14/2011        9/24/2015   [Insert citation of   With the exception
 Requirements for the 2008 Lead                                        publication].         of provisions
 National Ambient Air Quality                                                                pertaining to PSD
 Standards.                                                                                  permitting
                                                                                             requirements in
                                                                                             sections
                                                                                             110(a)(2)(C), prong
                                                                                             3 of D(i) and (J).
----------------------------------------------------------------------------------------------------------------


[FR Doc. 2015-24088 Filed 9-23-15; 8:45 am]
BILLING CODE 6560-50-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.