Eastern Shore Natural Gas Company; Notice of Intent To Prepare an Environmental Assessment For the Proposed System Reliability Project and Request for Comments on Environmental Issues, 54781-54783 [2015-22915]
Download as PDF
Federal Register / Vol. 80, No. 176 / Friday, September 11, 2015 / Notices
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: September 4, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–22916 Filed 9–10–15; 8:45 pm]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–498–000]
rmajette on DSK7SPTVN1PROD with NOTICES
Eastern Shore Natural Gas Company;
Notice of Intent To Prepare an
Environmental Assessment For the
Proposed System Reliability Project
and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the System Reliability Project involving
construction and operation of facilities
by Eastern Shore Natural Gas Company
(Eastern Shore) in Kent, New Castle, and
Sussex Counties, Delaware. The
Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before October 5,
2015.
VerDate Sep<11>2014
15:14 Sep 10, 2015
Jkt 235001
If you sent comments on this project
to the Commission before the opening of
this docket on May 22, 2015, you will
need to file those comments in Docket
No. CP15–498–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
Eastern Shore provided landowners
with a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility on My Land? What Do I Need
to Know?’’ This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
54781
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (CP15–498–
000) with your submission:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Room 1A,
Washington, DC 20426.
Summary of the Proposed Project
Eastern Shore proposes to construct
and operate 10.1 miles of new natural
gas pipeline loops 1 in New Castle and
Kent County, Delaware, and modify its
existing Bridgeville Compressor Station
in Sussex County, Delaware. According
to Eastern Shore, its project would
increase the reliability of natural gas to
Eastern Shore’s existing customers
during high demand winter months; this
need was not fully met in 2014 and
2015 and resulted in gas service ‘‘brown
outs.’’
The Eastern Shore System Reliability
Project would consist of the following
facilities:
• 2.5 miles of 16-inch-diameter
looping pipeline in New Castle County;
• pigging facilities 2 at the existing
Glasgow Control Station in New Castle
County;
• about 7.6 miles of 16-inch diameter
looping pipeline, one mainline valve
assembly, pigging facilities, and one
permanent access road in Kent County;
and
• an additional 1,775 horsepower of
compression, a new operations control
station, and one permanent access road
at the existing Bridgeville Compressor
Station in Sussex County.
The general location of the project
facilities is shown in appendix 1.3
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 156.7 acres of land
for the aboveground facilities and the
pipeline. Following construction,
Eastern Shore would maintain about
1 A pipeline loop is a segment of pipe constructed
parallel to an existing pipeline to increase capacity.
2 A ‘‘pig’’ is a tool that the pipeline company
inserts into and pushes through the pipeline for
cleaning the pipeline, conducting internal
inspections, or other purposes. A pipeline loop is
a segment of pipe constructed parallel to an existing
pipeline to increase capacity.
3 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
E:\FR\FM\11SEN1.SGM
11SEN1
54782
Federal Register / Vol. 80, No. 176 / Friday, September 11, 2015 / Notices
11.8 acres for permanent operation of
the project’s facilities; the remaining
acreage would be restored and revert to
former uses. All of the proposed
pipeline route would parallel existing
pipeline, utility, or road rights-of-way;
about 3 percent of the proposed project
would be contained within Eastern
Shore’s existing right-of-way and the
rest of the project (97%) would be
constructed on adjacent property.
rmajette on DSK7SPTVN1PROD with NOTICES
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 4 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts.
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
4 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
VerDate Sep<11>2014
15:14 Sep 10, 2015
Jkt 235001
in the Public Participation section,
beginning on page 2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.5 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.6 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
5 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
6 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP15–498). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
E:\FR\FM\11SEN1.SGM
11SEN1
Federal Register / Vol. 80, No. 176 / Friday, September 11, 2015 / Notices
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: September 4, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–22915 Filed 9–10–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP15–539–000; CP15–514–
000]
Columbia Gulf Transmission, LLC;
Columbia Gas Transmission, LLC;
Notice of Intent To Prepare an
Environmental Impact Statement for
the Rayne Xpress Expansion Project,
and Request for Comments on
Environmental Issues
rmajette on DSK7SPTVN1PROD with NOTICES
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will evaluate the
environmental impacts of the Rayne
XPress Expansion Project (project) in an
environmental impact statement (EIS)
being prepared for the related Leach
XPress Project filed by Columbia Gas
Transmission (Columbia Gas) in Docket
No. CP15–514.1 The Rayne XPress
Expansion Project involves construction
and operation of facilities by Columbia
Gulf Transmission, LLC (Columbia Gulf)
in Carter, Menifee and Montgomery
Counties, Kentucky. The Commission
will use this EIS in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EIS. To ensure that your
comments are timely and properly
1A
Notice of Application was issued on June 22,
2015 for the Leach XPress Project. The NOI stated
that Columbia Gulf, one of Columbia Gas’s
affiliates, may be proposing a project which may
have some connection to the Leach XPress Project.
The Leach XPress Project was in the pre-filing
phase until filed on June 8, 2015 under Docket No.
PF14–023.
VerDate Sep<11>2014
15:14 Sep 10, 2015
Jkt 235001
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before October 5,
2015.
If you sent comments on this project
to the Commission before the opening of
this docket on July 29, 2015, you will
need to file those comments in Docket
No. CP15–539–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
Columbia Gulf provided landowners
with a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
54783
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (CP15–539–
000) with your submission:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Room 1A,
Washington, DC 20426.
Summary of the Proposed Project
Columbia Gulf plans to construct and
operate 51,800 horsepower (hp) of new
compression in Carter, Menifee and
Montgomery Counties, Kentucky, and
modification of the existing Means
Measurement and Regulation Station in
Montgomery County, Kentucky. The
project would provide about 621,000
Dekatherms per day of firm
transportation on its system.
The project would consist of the
following facilities:
• A new 36,400 hp Grayson
Compressor Station consisting of two
gas-driven compressor units at Milepost
(MP) 68 on Columbia Gulf’s existing
Mainline 100, 200 and 300 pipelines in
in Carter County, Kentucky;
• a new 15,400 hp Means Compressor
Station consisting of two gas-driven
compressor units at MP 6.5 on Columbia
Gulf’s existing Mainline 100, 200 and
300 pipelines in in Menifee and
Montgomery Counties, Kentucky; and
• modifications to station piping and
Supervisory Control and Data
Acquisition systems at the existing
Means Measurement and Regulation
Station in Montgomery County,
Kentucky.
The general location of the project
facilities is shown in appendix 2.
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 34 acres of land,
converting about 17 acres of land to
industrial land use under permanent
operation of the project’s facilities.
Columbia Gulf would restore the
remaining acreage to former uses.
The EIS Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
E:\FR\FM\11SEN1.SGM
11SEN1
Agencies
[Federal Register Volume 80, Number 176 (Friday, September 11, 2015)]
[Notices]
[Pages 54781-54783]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-22915]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-498-000]
Eastern Shore Natural Gas Company; Notice of Intent To Prepare an
Environmental Assessment For the Proposed System Reliability Project
and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the System Reliability Project
involving construction and operation of facilities by Eastern Shore
Natural Gas Company (Eastern Shore) in Kent, New Castle, and Sussex
Counties, Delaware. The Commission will use this EA in its decision-
making process to determine whether the project is in the public
convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before October 5, 2015.
If you sent comments on this project to the Commission before the
opening of this docket on May 22, 2015, you will need to file those
comments in Docket No. CP15-498-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
Eastern Shore provided landowners with a fact sheet prepared by the
FERC entitled ``An Interstate Natural Gas Facility on My Land? What Do
I Need to Know?'' This fact sheet addresses a number of typically asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(CP15-498-000) with your submission:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE., Room 1A, Washington, DC 20426.
Summary of the Proposed Project
Eastern Shore proposes to construct and operate 10.1 miles of new
natural gas pipeline loops \1\ in New Castle and Kent County, Delaware,
and modify its existing Bridgeville Compressor Station in Sussex
County, Delaware. According to Eastern Shore, its project would
increase the reliability of natural gas to Eastern Shore's existing
customers during high demand winter months; this need was not fully met
in 2014 and 2015 and resulted in gas service ``brown outs.''
---------------------------------------------------------------------------
\1\ A pipeline loop is a segment of pipe constructed parallel to
an existing pipeline to increase capacity.
---------------------------------------------------------------------------
The Eastern Shore System Reliability Project would consist of the
following facilities:
2.5 miles of 16-inch-diameter looping pipeline in New
Castle County;
pigging facilities \2\ at the existing Glasgow Control
Station in New Castle County;
---------------------------------------------------------------------------
\2\ A ``pig'' is a tool that the pipeline company inserts into
and pushes through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes. A pipeline loop
is a segment of pipe constructed parallel to an existing pipeline to
increase capacity.
---------------------------------------------------------------------------
about 7.6 miles of 16-inch diameter looping pipeline, one
mainline valve assembly, pigging facilities, and one permanent access
road in Kent County; and
an additional 1,775 horsepower of compression, a new
operations control station, and one permanent access road at the
existing Bridgeville Compressor Station in Sussex County.
The general location of the project facilities is shown in appendix
1.\3\
---------------------------------------------------------------------------
\3\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 156.7
acres of land for the aboveground facilities and the pipeline.
Following construction, Eastern Shore would maintain about
[[Page 54782]]
11.8 acres for permanent operation of the project's facilities; the
remaining acreage would be restored and revert to former uses. All of
the proposed pipeline route would parallel existing pipeline, utility,
or road rights-of-way; about 3 percent of the proposed project would be
contained within Eastern Shore's existing right-of-way and the rest of
the project (97%) would be constructed on adjacent property.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\4\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\4\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\5\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\5\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\6\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\6\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the ``Document-less Intervention Guide'' under the ``e-filing'' link on
the Commission's Web site. Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP15-
498). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
[[Page 54783]]
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: September 4, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-22915 Filed 9-10-15; 8:45 am]
BILLING CODE 6717-01-P