Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information, 53897-53902 [2015-21795]
Download as PDF
Federal Register / Vol. 80, No. 173 / Tuesday, September 8, 2015 / Notices
1. Persons who wish to provide a
written statement should submit an
electronic copy to Ms. Holiday at the
contact information listed above. All
submittals must be received by October
23, 2015, three business days prior to
the meeting, and must pertain to the
topic on the agenda for the meeting.
2. Questions and comments from
members of the public will be permitted
during the meetings, at the discretion of
the Vice Chairman.
3. The draft transcript and meeting
summary will be available on ACMUI’s
Web site https://www.nrc.gov/readingrm/doc-collections/acmui/meetings/
2015.html on or about December 11,
2015.
This meeting will be held in
accordance with the Atomic Energy Act
of 1954, as amended (primarily section
161a); the Federal Advisory Committee
Act (5 U.S.C. App); and the
Commission’s regulations in title 10 of
the Code of Federal Regulations, part 7.
Dated at Rockville, Maryland, this 31st day
of August, 2015.
For the Nuclear Regulatory Commission.
Andrew L. Bates,
Advisory Committee Management Officer.
[FR Doc. 2015–22552 Filed 9–4–15; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2015–0193]
Applications and Amendments to
Facility Operating Licenses and
Combined Licenses Involving
Proposed No Significant Hazards
Considerations and Containing
Sensitive Unclassified Non-Safeguards
Information and Order Imposing
Procedures for Access to Sensitive
Unclassified Non-Safeguards
Information
Nuclear Regulatory
Commission.
ACTION: License amendment request;
opportunity to comment, request a
hearing, and petition for leave to
intervene; order.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) received and is
considering approval of one amendment
request. The amendment request is for
Vermont Yankee Nuclear Power Station.
For this amendment request, the NRC
proposes to determine that it involves
no significant hazards consideration. In
addition, the amendment request
contains sensitive unclassified nonsafeguards information (SUNSI).
asabaliauskas on DSK5VPTVN1PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:18 Sep 04, 2015
Jkt 235001
Comments must be filed by
October 8, 2015. A request for a hearing
must be filed by November 9, 2015. Any
potential party as defined in § 2.4 of
Title 10 of the Code of Federal
Regulations (10 CFR), who believes
access to SUNSI is necessary to respond
to this notice must request document
access by September 18, 2015.
ADDRESSES: You may submit comments
by any of the following methods (unless
this document describes a different
method for submitting comments on a
specific subject):
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2015–0193. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• Mail comments to: Cindy Bladey,
Office of Administration, Mail Stop:
OWFN–12–H08, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
For additional direction on obtaining
information and submitting comments,
see ‘‘Obtaining Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
FOR FURTHER INFORMATION CONTACT:
Janet Burkhardt, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington DC
20555–0001; telephone: 301–415–1384,
email: Janet.Burkhardt@nrc.gov.
SUPPLEMENTARY INFORMATION:
DATES:
I. Obtaining Information and
Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC–2015–
0193 when contacting the NRC about
the availability of information for this
action. You may obtain publiclyavailable information related to this
action by any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2015–0193.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
PO 00000
Frm 00139
Fmt 4703
Sfmt 4703
53897
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in the SUPPLEMENTARY
INFORMATION section.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC–2015–
0193, facility name, unit number(s),
application date, and subject in your
comment submission.
The NRC cautions you not to include
identifying or contact information that
you do not want to be publicly
disclosed in your comment submission.
The NRC will post all comment
submissions at https://
www.regulations.gov as well as enter the
comment submissions into ADAMS.
The NRC does not routinely edit
comment submissions to remove
identifying or contact information.
If you are requesting or aggregating
comments from other persons for
submission to the NRC, then you should
inform those persons not to include
identifying or contact information that
they do not want to be publicly
disclosed in their comment submission.
Your request should state that the NRC
does not routinely edit comment
submissions to remove such information
before making the comment
submissions available to the public or
entering the comment submissions into
ADAMS.
II. Background
Pursuant to Section 189a.(2) of the
Atomic Energy Act of 1954, as amended
(the Act), the NRC is publishing this
notice. The Act requires the
Commission to publish notice of any
amendments issued, or proposed to be
issued and grants the Commission the
authority to issue and make
immediately effective any amendment
to an operating license or combined
license, as applicable, upon a
determination by the Commission that
such amendment involves no significant
hazards consideration, notwithstanding
the pendency before the Commission of
a request for a hearing from any person.
This notice includes notice of an
amendment containing SUNSI.
E:\FR\FM\08SEN1.SGM
08SEN1
53898
Federal Register / Vol. 80, No. 173 / Tuesday, September 8, 2015 / Notices
III. Notice of Consideration of Issuance
of Amendment to Facility Operating
Licenses and Combined Licenses,
Proposed No Significant Hazards
Consideration Determination, and
Opportunity for a Hearing
asabaliauskas on DSK5VPTVN1PROD with NOTICES
The Commission has made a
proposed determination that the
following amendment request involves
no significant hazards consideration.
Under the Commission’s regulations in
10 CFR 50.92, this means that operation
of the facility in accordance with the
proposed amendment would not (1)
involve a significant increase in the
probability or consequences of an
accident previously evaluated, or (2)
create the possibility of a new or
different kind of accident from any
accident previously evaluated, or (3)
involve a significant reduction in a
margin of safety. The basis for this
proposed determination for the
amendment request is shown below.
The Commission is seeking public
comments on this proposed
determination. Any comments received
within 30 days after the date of
publication of this notice will be
considered in making any final
determination.
Normally, the Commission will not
issue the amendment until the
expiration of 60 days after the date of
publication of this notice. The
Commission may issue the license
amendment before expiration of the 60day period provided that its final
determination is that the amendment
involves no significant hazards
consideration. In addition, the
Commission may issue the amendment
prior to the expiration of the 30-day
comment period should circumstances
change during the 30-day comment
period such that failure to act in a
timely way would result, for example,
in derating or shutdown of the facility.
Should the Commission take action
prior to the expiration of either the
comment period or the notice period, it
will publish a notice of issuance in the
Federal Register. Should the
Commission make a final No Significant
Hazards Consideration Determination,
any hearing will take place after
issuance. The Commission expects that
the need to take this action will occur
very infrequently.
A. Opportunity To Request a Hearing
and Petition for Leave To Intervene
Within 60 days after the date of
publication of this notice, any person(s)
whose interest may be affected by this
action may file a request for a hearing
and a petition to intervene with respect
to issuance of the amendment to the
VerDate Sep<11>2014
17:18 Sep 04, 2015
Jkt 235001
subject facility operating license or
combined license. Requests for a
hearing and a petition for leave to
intervene shall be filed in accordance
with the Commission’s ‘‘Agency Rules
of Practice and Procedure’’ in 10 CFR
part 2. Interested person(s) should
consult a current copy of 10 CFR 2.309,
which is available at the NRC’s PDR,
located at One White Flint North, Room
O1–F21, 11555 Rockville Pike (first
floor), Rockville, Maryland 20852. The
NRC’s regulations are accessible
electronically from the NRC Library on
the NRC’s Web site at https://
www.nrc.gov/reading-rm/doccollections/cfr/. If a request for a hearing
or petition for leave to intervene is filed
within 60 days, the Commission or a
presiding officer designated by the
Commission or by the Chief
Administrative Judge of the Atomic
Safety and Licensing Board Panel, will
rule on the request and/or petition; and
the Secretary or the Chief
Administrative Judge of the Atomic
Safety and Licensing Board will issue a
notice of a hearing or an appropriate
order.
As required by 10 CFR 2.309, a
petition for leave to intervene shall set
forth with particularity the interest of
the petitioner in the proceeding, and
how that interest may be affected by the
results of the proceeding. The petition
should specifically explain the reasons
why intervention should be permitted
with particular reference to the
following general requirements: (1) The
name, address, and telephone number of
the requestor or petitioner; (2) the
nature of the requestor’s/petitioner’s
right under the Act to be made a party
to the proceeding; (3) the nature and
extent of the requestor’s/petitioner’s
property, financial, or other interest in
the proceeding; and (4) the possible
effect of any decision or order which
may be entered in the proceeding on the
requestor’s/petitioner’s interest. The
petition must also set forth the specific
contentions which the requestor/
petitioner seeks to have litigated at the
proceeding.
Each contention must consist of a
specific statement of the issue of law or
fact to be raised or controverted. In
addition, the requestor/petitioner shall
provide a brief explanation of the bases
for the contention and a concise
statement of the alleged facts or expert
opinion which support the contention
and on which the requestor/petitioner
intends to rely in proving the contention
at the hearing. The requestor/petitioner
must also provide references to those
specific sources and documents of
which the petitioner is aware and on
which the requestor/petitioner intends
PO 00000
Frm 00140
Fmt 4703
Sfmt 4703
to rely to establish those facts or expert
opinion. The petition must include
sufficient information to show that a
genuine dispute exists with the
applicant on a material issue of law or
fact. Contentions shall be limited to
matters within the scope of the
amendment under consideration. The
contention must be one which, if
proven, would entitle the requestor/
petitioner to relief. A requestor/
petitioner who fails to satisfy these
requirements with respect to at least one
contention will not be permitted to
participate as a party.
Those permitted to intervene become
parties to the proceeding, subject to any
limitations in the order granting leave to
intervene, and have the opportunity to
participate fully in the conduct of the
hearing.
If a hearing is requested, and the
Commission has not made a final
determination on the issue of no
significant hazards consideration, the
Commission will make a final
determination on the issue of no
significant hazards consideration. The
final determination will serve to decide
when the hearing is held. If the final
determination is that the amendment
request involves no significant hazards
consideration, the Commission may
issue the amendment and make it
immediately effective, notwithstanding
the request for a hearing. Any hearing
held would take place after issuance of
the amendment. If the final
determination is that the amendment
request involves a significant hazards
consideration, then any hearing held
would take place before the issuance of
any amendment unless the Commission
finds an imminent danger to the health
or safety of the public, in which case it
will issue an appropriate order or rule
under 10 CFR part 2.
B. Electronic Submissions (E-Filing)
All documents filed in NRC
adjudicatory proceedings, including a
request for hearing, a petition for leave
to intervene, any motion or other
document filed in the proceeding prior
to the submission of a request for
hearing or petition to intervene, and
documents filed by interested
governmental entities participating
under 10 CFR 2.315(c), must be filed in
accordance with the NRC’s E-Filing rule
(72 FR 49139; August 28, 2007). The EFiling process requires participants to
submit and serve all adjudicatory
documents over the internet, or in some
cases to mail copies on electronic
storage media. Participants may not
submit paper copies of their filings
unless they seek an exemption in
E:\FR\FM\08SEN1.SGM
08SEN1
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 173 / Tuesday, September 8, 2015 / Notices
accordance with the procedures
described below.
To comply with the procedural
requirements of E-Filing, at least 10
days prior to the filing deadline, the
participant should contact the Office of
the Secretary by email at
hearing.docket@nrc.gov, or by telephone
at 301–415–1677, to request (1) a digital
identification (ID) certificate, which
allows the participant (or its counsel or
representative) to digitally sign
documents and access the E-Submittal
server for any proceeding in which it is
participating; and (2) advise the
Secretary that the participant will be
submitting a request or petition for
hearing (even in instances in which the
participant, or its counsel or
representative, already holds an NRCissued digital ID certificate). Based upon
this information, the Secretary will
establish an electronic docket for the
hearing in this proceeding if the
Secretary has not already established an
electronic docket.
Information about applying for a
digital ID certificate is available on the
NRC’s public Web site at https://
www.nrc.gov/site-help/e-submittals/
getting-started.html. System
requirements for accessing the ESubmittal server are detailed in the
NRC’s ‘‘Guidance for Electronic
Submission,’’ which is available on the
agency’s public Web site at https://
www.nrc.gov/site-help/esubmittals.html. Participants may
attempt to use other software not listed
on the Web site, but should note that the
NRC’s E-Filing system does not support
unlisted software, and the NRC Meta
System Help Desk will not be able to
offer assistance in using unlisted
software.
If a participant is electronically
submitting a document to the NRC in
accordance with the E-Filing rule, the
participant must file the document
using the NRC’s online, Web-based
submission form. In order to serve
documents through the Electronic
Information Exchange System, users
will be required to install a Web
browser plug-in from the NRC’s Web
site. Further information on the Webbased submission form, including the
installation of the Web browser plug-in,
is available on the NRC’s public Web
site at https://www.nrc.gov/site-help/esubmittals.html.
Once a participant has obtained a
digital ID certificate and a docket has
been created, the participant can then
submit a request for hearing or petition
for leave to intervene. Submissions
should be in Portable Document Format
(PDF) in accordance with NRC guidance
available on the NRC’s public Web site
VerDate Sep<11>2014
17:18 Sep 04, 2015
Jkt 235001
at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered
complete at the time the documents are
submitted through the NRC’s E-Filing
system. To be timely, an electronic
filing must be submitted to the E-Filing
system no later than 11:59 p.m. Eastern
Time on the due date. Upon receipt of
a transmission, the E-Filing system
time-stamps the document and sends
the submitter an email notice
confirming receipt of the document. The
E-Filing system also distributes an email
notice that provides access to the
document to the NRC’s Office of the
General Counsel and any others who
have advised the Office of the Secretary
that they wish to participate in the
proceeding, so that the filer need not
serve the documents on those
participants separately. Therefore,
applicants and other participants (or
their counsel or representative) must
apply for and receive a digital ID
certificate before a hearing request/
petition to intervene is filed so that they
can obtain access to the document via
the E-Filing system.
A person filing electronically using
the NRC’s adjudicatory E-Filing system
may seek assistance by contacting the
NRC Meta System Help Desk through
the ‘‘Contact Us’’ link located on the
NRC’s public Web site at https://
www.nrc.gov/site-help/esubmittals.html, by email to
MSHD.Resource@nrc.gov, or by a tollfree call at 1–866–672–7640. The NRC
Meta System Help Desk is available
between 8 a.m. and 8 p.m., Eastern
Time, Monday through Friday,
excluding government holidays.
Participants who believe that they
have a good cause for not submitting
documents electronically must file an
exemption request, in accordance with
10 CFR 2.302(g), with their initial paper
filing requesting authorization to
continue to submit documents in paper
format. Such filings must be submitted
by: (1) First class mail addressed to the
Office of the Secretary of the
Commission, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, Attention: Rulemaking and
Adjudications Staff; or (2) courier,
express mail, or expedited delivery
service to the Office of the Secretary,
Sixteenth Floor, One White Flint North,
11555 Rockville Pike, Rockville,
Maryland 20852, Attention: Rulemaking
and Adjudications Staff. Participants
filing a document in this manner are
responsible for serving the document on
all other participants. Filing is
considered complete by first-class mail
as of the time of deposit in the mail, or
by courier, express mail, or expedited
delivery service upon depositing the
PO 00000
Frm 00141
Fmt 4703
Sfmt 4703
53899
document with the provider of the
service. A presiding officer, having
granted an exemption request from
using E-Filing, may require a participant
or party to use E-Filing if the presiding
officer subsequently determines that the
reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory
proceedings will appear in the NRC’s
electronic hearing docket which is
available to the public at https://
ehd1.nrc.gov/ehd/, unless excluded
pursuant to an order of the Commission,
or the presiding officer. Participants are
requested not to include personal
privacy information, such as social
security numbers, home addresses, or
home phone numbers in their filings,
unless an NRC regulation or other law
requires submission of such
information. However, in some
instances, a request to intervene will
require including information on local
residence in order to demonstrate a
proximity assertion of interest in the
proceeding. With respect to copyrighted
works, except for limited excerpts that
serve the purpose of the adjudicatory
filings and would constitute a Fair Use
application, participants are requested
not to include copyrighted materials in
their submission.
Petitions for leave to intervene must
be filed no later than 60 days from the
date of publication of this notice.
Requests for hearing, petitions for leave
to intervene, and motions for leave to
file new or amended contentions that
are filed after the 60-day deadline will
not be entertained absent a
determination by the presiding officer
that the filing demonstrates good cause
by satisfying the three factors in 10 CFR
2.309(c)(1)(i)–(iii).
For further details with respect to this
amendment action, see the application
for amendment which is available for
public inspection at the NRC’s PDR,
located at One White Flint North, Room
O1–F21, 11555 Rockville Pike (first
floor), Rockville, Maryland 20852.
Publicly available documents created or
received at the NRC are accessible
electronically through ADAMS in the
NRC Library at https://www.nrc.gov/
reading-rm/adams.html. If you do not
have access to ADAMS or if there are
problems in accessing the documents
located in ADAMS, contact the PDR’s
Reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov.
E:\FR\FM\08SEN1.SGM
08SEN1
53900
Federal Register / Vol. 80, No. 173 / Tuesday, September 8, 2015 / Notices
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Entergy Nuclear Vermont Yankee, LLC
and Entergy Nuclear Operations, Inc.,
Docket No. 50–271, Vermont Yankee
Nuclear Power Station (VY), Vernon,
Vermont
Date of amendment request: June 24,
2015. A publicly-available version is in
ADAMS under Accession No.
ML15177A016.
Description of amendment request:
This amendment request contains
sensitive unclassified non-safeguards
information (SUNSI). The amendment
would revise the VY Cyber Security
Plan (CSP) Milestone 8 Implementation
Schedule, full implementation date
from June 30, 2016, to December 15,
2017. The proposed amendment would
also revise the existing facility operating
license Security Plan license condition.
Basis for proposed no significant
hazards consideration determination:
As required by 10 CFR 50.91(a), the
licensee has provided its analysis of the
issue of no significant hazards
consideration which is presented below:
1. Does the proposed change involve a
significant increase in the probability or
consequences of an accident previously
evaluated?
Response: No.
The proposed change to the CSP
Implementation Schedule is administrative
in nature. This change does not alter accident
analysis assumptions, add any initiators, or
affect the function of plant systems or the
manner in which systems are operated,
maintained, modified, tested, or inspected.
The proposed change does not require any
plant modifications which affect the
performance capability of the structures,
systems, and components (SSCs) relied upon
to mitigate the consequences of postulated
accidents and has no impact on the
probability or consequences of an accident
previously evaluated.
Therefore, the proposed change does not
involve a significant increase in the
probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the
possibility of a new or different kind of
accident from any accident previously
evaluated?
Response: No.
The proposed change to the CSP
Implementation Schedule is administrative
in nature. This change does not alter accident
analysis assumptions, add any initiators, or
affect the function of plant systems or the
manner in which systems are operated,
maintained, modified, tested, or inspected.
The proposed change does not require any
plant modifications which affect the
performance capability of the SSCs relied
upon to mitigate the consequences of
postulated accidents and does not create the
possibility of a new or different kind of
accident previously evaluated.
Therefore, the proposed change does not
create the possibility of a new or different
kind of accident from any accident
previously evaluated.
VerDate Sep<11>2014
17:18 Sep 04, 2015
Jkt 235001
3. Does the proposed change involve a
significant reduction in a margin of safety?
Response: No.
Plant safety margins are established
through limiting conditions for operation,
limiting safety system settings, and safety
limits specified in the Technical
Specifications. The proposed change to the
CSP Implementation Schedule is
administrative in nature. In addition, the
milestone date delay for full implementation
of the CSP has no substantive impact because
other measures have been taken which
provide adequate protection during this
period of time. Because there is no change to
established safety margins as a result of this
change, the proposed change does not
involve a significant reduction in a margin of
safety.
Therefore, the proposed change does not
involve a significant reduction in a margin of
safety.
The NRC staff has reviewed the
licensee’s analysis and, based on this
review, it appears that the three
standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff
proposes to determine that the
amendment request involves no
significant hazards consideration.
Attorney for licensee: Ms. Susan
Raimo, Senior Counsel, Entergy
Services, Inc., 101 Constitution Avenue
NW., Suite 200 East, Washington DC
20001.
NRC Branch Chief: Meena K. Khanna.
Entergy Nuclear Vermont Yankee, LLC
and Entergy Nuclear Operations, Inc.,
Docket No. 50–271, Vermont Yankee
Nuclear Power Station, Vernon,
Vermont
Order Imposing Procedures for Access
to Sensitive Unclassified NonSafeguards Information for Contention
Preparation
A. This Order contains instructions
regarding how potential parties to this
proceeding may request access to
documents containing SUNSI.
B. Within 10 days after publication of
this notice of hearing and opportunity to
petition for leave to intervene, any
potential party who believes access to
SUNSI is necessary to respond to this
notice may request such access. A
‘‘potential party’’ is any person who
intends to participate as a party by
demonstrating standing and filing an
admissible contention under 10 CFR
2.309. Requests for access to SUNSI
submitted later than 10 days after
publication of this notice will not be
considered absent a showing of good
cause for the late filing, addressing why
the request could not have been filed
earlier.
C. The requester shall submit a letter
requesting permission to access SUNSI
to the Office of the Secretary, U.S.
PO 00000
Frm 00142
Fmt 4703
Sfmt 4703
Nuclear Regulatory Commission,
Washington, DC 20555–0001, Attention:
Rulemakings and Adjudications Staff,
and provide a copy to the Associate
General Counsel for Hearings,
Enforcement and Administration, Office
of the General Counsel, Washington, DC
20555–0001. The expedited delivery or
courier mail address for both offices is:
U.S. Nuclear Regulatory Commission,
11555 Rockville Pike, Rockville,
Maryland 20852. The email address for
the Office of the Secretary and the
Office of the General Counsel are
Hearing.Docket@nrc.gov and
OGCmailcenter@nrc.gov, respectively.1
The request must include the following
information:
(1) A description of the licensing
action with a citation to this Federal
Register notice;
(2) The name and address of the
potential party and a description of the
potential party’s particularized interest
that could be harmed by the action
identified in C.(1); and
(3) The identity of the individual or
entity requesting access to SUNSI and
the requester’s basis for the need for the
information in order to meaningfully
participate in this adjudicatory
proceeding. In particular, the request
must explain why publicly-available
versions of the information requested
would not be sufficient to provide the
basis and specificity for a proffered
contention.
D. Based on an evaluation of the
information submitted under paragraph
C.(3) the NRC staff will determine
within 10 days of receipt of the request
whether:
(1) There is a reasonable basis to
believe the petitioner is likely to
establish standing to participate in this
NRC proceeding; and
(2) The requestor has established a
legitimate need for access to SUNSI.
E. If the NRC staff determines that the
requestor satisfies both D.(1) and D.(2)
above, the NRC staff will notify the
requestor in writing that access to
SUNSI has been granted. The written
notification will contain instructions on
how the requestor may obtain copies of
the requested documents, and any other
conditions that may apply to access to
those documents. These conditions may
include, but are not limited to, the
signing of a Non-Disclosure Agreement
or Affidavit, or Protective Order 2 setting
1 While a request for hearing or petition to
intervene in this proceeding must comply with the
filing requirements of the NRC’s ‘‘E-Filing Rule,’’
the initial request to access SUNSI under these
procedures should be submitted as described in this
paragraph.
2 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SUNSI must
E:\FR\FM\08SEN1.SGM
08SEN1
Federal Register / Vol. 80, No. 173 / Tuesday, September 8, 2015 / Notices
forth terms and conditions to prevent
the unauthorized or inadvertent
disclosure of SUNSI by each individual
who will be granted access to SUNSI.
F. Filing of Contentions. Any
contentions in these proceedings that
are based upon the information received
as a result of the request made for
SUNSI must be filed by the requestor no
later than 25 days after the requestor is
granted access to that information.
However, if more than 25 days remain
between the date the petitioner is
granted access to the information and
the deadline for filing all other
contentions (as established in the notice
of hearing or opportunity for hearing),
the petitioner may file its SUNSI
contentions by that later deadline. This
provision does not extend the time for
filing a request for a hearing and
petition to intervene, which must
comply with the requirements of 10 CFR
2.309.
G. Review of Denials of Access.
(1) If the request for access to SUNSI
is denied by the NRC staff after a
determination on standing and need for
access, the NRC staff shall immediately
notify the requestor in writing, briefly
stating the reason or reasons for the
denial.
(2) The requester may challenge the
NRC staff’s adverse determination by
filing a challenge within 5 days of
receipt of that determination with: (a)
The presiding officer designated in this
proceeding; (b) if no presiding officer
has been appointed, the Chief
Administrative Judge, or if he or she is
unavailable, another administrative
judge, or an administrative law judge
with jurisdiction pursuant to 10 CFR
2.318(a); or (c) officer if that officer has
been designated to rule on information
access issues.
H. Review of Grants of Access. A
party other than the requester may
challenge an NRC staff determination
granting access to SUNSI whose release
would harm that party’s interest
independent of the proceeding. Such a
challenge must be filed with the Chief
Administrative Judge within 5 days of
the notification by the NRC staff of its
grant of access.
If challenges to the NRC staff
determinations are filed, these
procedures give way to the normal
process for litigating disputes
53901
concerning access to information. The
availability of interlocutory review by
the Commission of orders ruling on
such NRC staff determinations (whether
granting or denying access) is governed
by 10 CFR 2.311.3
I. The Commission expects that the
NRC staff and presiding officers (and
any other reviewing officers) will
consider and resolve requests for access
to SUNSI, and motions for protective
orders, in a timely fashion in order to
minimize any unnecessary delays in
identifying those petitioners who have
standing and who have propounded
contentions meeting the specificity and
basis requirements in 10 CFR part 2.
Attachment 1 to this Order summarizes
the general target schedule for
processing and resolving requests under
these procedures.
It is so ordered.
Dated at Rockville, Maryland, this 27th day
of August, 2015.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO
SENSITIVE UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING
Day
0
10
60
20
25
30
40
A
A+3
asabaliauskas on DSK5VPTVN1PROD with NOTICES
A + 28
A + 53
A + 60
Event/activity
Publication of Federal Register notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests.
Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information:
supporting the standing of a potential party identified by name and address; describing the need for the information in order
for the potential party to participate meaningfully in an adjudicatory proceeding.
Deadline for submitting petition for intervention containing: (i) demonstration of standing; and (ii) all contentions whose formulation does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply).
U.S. Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for access provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs
any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing
(preparation of redactions or review of redacted documents).
If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling to
reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party
to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a
motion seeking a ruling to reverse the NRC staff’s grant of access.
Deadline for NRC staff reply to motions to reverse NRC staff determination(s).
(Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and
file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure
Agreement for SUNSI.
If access granted: issuance of presiding officer or other designated officer decision on motion for protective order for access to
sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse determination by the NRC staff.
Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective
order.
Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline.
(Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.
(Answer receipt +7) Petitioner/Intervenor reply to answers.
be filed with the presiding officer or the Chief
Administrative Judge if the presiding officer has not
yet been designated, within 30 days of the deadline
for the receipt of the written access request.
VerDate Sep<11>2014
17:18 Sep 04, 2015
Jkt 235001
3 Requesters should note that the filing
requirements of the NRC’s E-Filing Rule (72 FR
49139; August 28, 2007) apply to appeals of NRC
staff determinations (because they must be served
PO 00000
Frm 00143
Fmt 4703
Sfmt 4703
on a presiding officer or the Commission, as
applicable), but not to the initial SUNSI request
submitted to the NRC staff under these procedures.
E:\FR\FM\08SEN1.SGM
08SEN1
53902
Federal Register / Vol. 80, No. 173 / Tuesday, September 8, 2015 / Notices
ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO
SENSITIVE UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING—Continued
Day
>A + 60
Event/activity
Decision on contention admission.
[FR Doc. 2015–21795 Filed 9–4–15; 8:45 am]
Week of September 28, 2015—Tentative
BILLING CODE 7590–01–P
Monday, September 28, 2015
1:30 p.m. NRC All Employees Meeting
(Public Meeting), Marriott Bethesda
North Hotel, 5701 Marinelli Road,
Rockville, MD 20852
NUCLEAR REGULATORY
COMMISSION
[NRC–2015–0001]
Sunshine Act Meeting Notice
September 7, 14, 21, 28, October
5, 12, 2015.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public and Closed.
DATE:
Week of September 7, 2015
Tuesday, September 8, 2015
9:25 a.m. Affirmation Session (Public
Meeting)—Tentative
(a) Final Rule: Hearing on Challenges
to the Immediate Effectiveness of
Orders (10 CFR parts 2 and 150;
RIN 3150–AJ27). (Tentative)
(b) DTE Electric Co. (Fermi Nuclear
Power Plant, Unit 2), Applicant’s
Appeal of LBP–15–5 (Mar. 3, 2015).
(Tentative)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
9:30 a.m. Briefing on Project AIM 2020
(Public Meeting) (Contact: Karen
Fitch: 301–415–7358)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Thursday, September 10, 2015
9:30 a.m. Briefing on NRC International
Activities (Closed—Ex. 1 & 9)
Week of September 14, 2015—Tentative
There are no meetings scheduled for
the week of September 14, 2015.
Week of September 21, 2015—Tentative
Tuesday, September 22, 2015
asabaliauskas on DSK5VPTVN1PROD with NOTICES
9:30 a.m. Discussion of Management
and Personnel Issues (Closed—Ex. 2
& 6)
Thursday, September 24, 2015
9:30 a.m. Strategic Programmatic
Overview of the New Reactors
Business Line (Public Meeting)
(Contact: Donna Williams: 301–
415–1322)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
VerDate Sep<11>2014
17:18 Sep 04, 2015
Jkt 235001
Thursday, October 1, 2015
9:00 a.m. Strategic Programmatic
Overview of the Decommissioning
and Low-Level Waste and Spent
Fuel Storage and Transportation
Business Lines (Public Meeting)
(Contact: Damaris Marcano: 301–
415–7328)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Week of October 5, 2015—Tentative
There are no meetings scheduled for
the week of October 5, 2015.
Week of October 12, 2015—Tentative
There are no meetings scheduled for
the week of October 12, 2015.
*
*
*
*
*
The schedule for Commission
meetings is subject to change on short
notice. For more information or to verify
the status of meetings, contact Glenn
Ellmers at 301–415–0442 or via email at
Glenn.Ellmers@nrc.gov.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.
braille, large print), please notify
Kimberly Meyer, NRC Disability
Program Manager, at 301–287–0727, by
videophone at 240–428–3217, or by
email at Kimberly.Meyer-Chambers@
nrc.gov. Determinations on requests for
reasonable accommodation will be
made on a case-by-case basis.
*
*
*
*
*
Members of the public may request to
receive this information electronically.
If you would like to be added to the
distribution, please contact the Nuclear
PO 00000
Frm 00144
Fmt 4703
Sfmt 4703
Regulatory Commission, Office of the
Secretary, Washington, DC 20555 (301–
415–1969), or email
Brenda.Akstulewicz@nrc.gov or
Patricia.Jimenez@nrc.gov.
Dated: September 2, 2015.
Glenn Ellmers,
Policy Coordinator, Office of the Secretary.
[FR Doc. 2015–22613 Filed 9–3–15; 11:15 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2014–0204]
Quality Assurance Program
Description—Design Certification,
Early Site Permit and New License
Applicants
Nuclear Regulatory
Commission.
ACTION: Standard review plan-final
section; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing a final
revision to NUREG–0800, ‘‘Standard
Review Plan for the Review of Safety
Analysis Reports for Nuclear Power
Plants: LWR Edition,’’ Section 17.5,
‘‘Quality Assurance Program
Description—Design Certification, Early
Site Permit and New License
Applicants.’’
DATES: The effective date of this
Standard Review Plan (SRP) update is
October 8, 2015.
ADDRESSES: Please refer to Docket ID
NRC–2014–0204 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2014–0204. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
SUMMARY:
E:\FR\FM\08SEN1.SGM
08SEN1
Agencies
[Federal Register Volume 80, Number 173 (Tuesday, September 8, 2015)]
[Notices]
[Pages 53897-53902]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-21795]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2015-0193]
Applications and Amendments to Facility Operating Licenses and
Combined Licenses Involving Proposed No Significant Hazards
Considerations and Containing Sensitive Unclassified Non-Safeguards
Information and Order Imposing Procedures for Access to Sensitive
Unclassified Non-Safeguards Information
AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment request; opportunity to comment, request a
hearing, and petition for leave to intervene; order.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) received and is
considering approval of one amendment request. The amendment request is
for Vermont Yankee Nuclear Power Station. For this amendment request,
the NRC proposes to determine that it involves no significant hazards
consideration. In addition, the amendment request contains sensitive
unclassified non-safeguards information (SUNSI).
DATES: Comments must be filed by October 8, 2015. A request for a
hearing must be filed by November 9, 2015. Any potential party as
defined in Sec. 2.4 of Title 10 of the Code of Federal Regulations (10
CFR), who believes access to SUNSI is necessary to respond to this
notice must request document access by September 18, 2015.
ADDRESSES: You may submit comments by any of the following methods
(unless this document describes a different method for submitting
comments on a specific subject):
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2015-0193. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
Mail comments to: Cindy Bladey, Office of Administration,
Mail Stop: OWFN-12-H08, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
For additional direction on obtaining information and submitting
comments, see ``Obtaining Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Janet Burkhardt, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC
20555-0001; telephone: 301-415-1384, email: Janet.Burkhardt@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2015-0193 when contacting the NRC
about the availability of information for this action. You may obtain
publicly-available information related to this action by any of the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2015-0193.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if it is available
in ADAMS) is provided the first time that it is mentioned in the
SUPPLEMENTARY INFORMATION section.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2015-0193, facility name, unit
number(s), application date, and subject in your comment submission.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC will post all comment submissions at https://www.regulations.gov as well as enter the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Background
Pursuant to Section 189a.(2) of the Atomic Energy Act of 1954, as
amended (the Act), the NRC is publishing this notice. The Act requires
the Commission to publish notice of any amendments issued, or proposed
to be issued and grants the Commission the authority to issue and make
immediately effective any amendment to an operating license or combined
license, as applicable, upon a determination by the Commission that
such amendment involves no significant hazards consideration,
notwithstanding the pendency before the Commission of a request for a
hearing from any person.
This notice includes notice of an amendment containing SUNSI.
[[Page 53898]]
III. Notice of Consideration of Issuance of Amendment to Facility
Operating Licenses and Combined Licenses, Proposed No Significant
Hazards Consideration Determination, and Opportunity for a Hearing
The Commission has made a proposed determination that the following
amendment request involves no significant hazards consideration. Under
the Commission's regulations in 10 CFR 50.92, this means that operation
of the facility in accordance with the proposed amendment would not (1)
involve a significant increase in the probability or consequences of an
accident previously evaluated, or (2) create the possibility of a new
or different kind of accident from any accident previously evaluated,
or (3) involve a significant reduction in a margin of safety. The basis
for this proposed determination for the amendment request is shown
below.
The Commission is seeking public comments on this proposed
determination. Any comments received within 30 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of 60 days after the date of publication of this notice. The
Commission may issue the license amendment before expiration of the 60-
day period provided that its final determination is that the amendment
involves no significant hazards consideration. In addition, the
Commission may issue the amendment prior to the expiration of the 30-
day comment period should circumstances change during the 30-day
comment period such that failure to act in a timely way would result,
for example, in derating or shutdown of the facility. Should the
Commission take action prior to the expiration of either the comment
period or the notice period, it will publish a notice of issuance in
the Federal Register. Should the Commission make a final No Significant
Hazards Consideration Determination, any hearing will take place after
issuance. The Commission expects that the need to take this action will
occur very infrequently.
A. Opportunity To Request a Hearing and Petition for Leave To Intervene
Within 60 days after the date of publication of this notice, any
person(s) whose interest may be affected by this action may file a
request for a hearing and a petition to intervene with respect to
issuance of the amendment to the subject facility operating license or
combined license. Requests for a hearing and a petition for leave to
intervene shall be filed in accordance with the Commission's ``Agency
Rules of Practice and Procedure'' in 10 CFR part 2. Interested
person(s) should consult a current copy of 10 CFR 2.309, which is
available at the NRC's PDR, located at One White Flint North, Room O1-
F21, 11555 Rockville Pike (first floor), Rockville, Maryland 20852. The
NRC's regulations are accessible electronically from the NRC Library on
the NRC's Web site at https://www.nrc.gov/reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to intervene is
filed within 60 days, the Commission or a presiding officer designated
by the Commission or by the Chief Administrative Judge of the Atomic
Safety and Licensing Board Panel, will rule on the request and/or
petition; and the Secretary or the Chief Administrative Judge of the
Atomic Safety and Licensing Board will issue a notice of a hearing or
an appropriate order.
As required by 10 CFR 2.309, a petition for leave to intervene
shall set forth with particularity the interest of the petitioner in
the proceeding, and how that interest may be affected by the results of
the proceeding. The petition should specifically explain the reasons
why intervention should be permitted with particular reference to the
following general requirements: (1) The name, address, and telephone
number of the requestor or petitioner; (2) the nature of the
requestor's/petitioner's right under the Act to be made a party to the
proceeding; (3) the nature and extent of the requestor's/petitioner's
property, financial, or other interest in the proceeding; and (4) the
possible effect of any decision or order which may be entered in the
proceeding on the requestor's/petitioner's interest. The petition must
also set forth the specific contentions which the requestor/petitioner
seeks to have litigated at the proceeding.
Each contention must consist of a specific statement of the issue
of law or fact to be raised or controverted. In addition, the
requestor/petitioner shall provide a brief explanation of the bases for
the contention and a concise statement of the alleged facts or expert
opinion which support the contention and on which the requestor/
petitioner intends to rely in proving the contention at the hearing.
The requestor/petitioner must also provide references to those specific
sources and documents of which the petitioner is aware and on which the
requestor/petitioner intends to rely to establish those facts or expert
opinion. The petition must include sufficient information to show that
a genuine dispute exists with the applicant on a material issue of law
or fact. Contentions shall be limited to matters within the scope of
the amendment under consideration. The contention must be one which, if
proven, would entitle the requestor/petitioner to relief. A requestor/
petitioner who fails to satisfy these requirements with respect to at
least one contention will not be permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing.
If a hearing is requested, and the Commission has not made a final
determination on the issue of no significant hazards consideration, the
Commission will make a final determination on the issue of no
significant hazards consideration. The final determination will serve
to decide when the hearing is held. If the final determination is that
the amendment request involves no significant hazards consideration,
the Commission may issue the amendment and make it immediately
effective, notwithstanding the request for a hearing. Any hearing held
would take place after issuance of the amendment. If the final
determination is that the amendment request involves a significant
hazards consideration, then any hearing held would take place before
the issuance of any amendment unless the Commission finds an imminent
danger to the health or safety of the public, in which case it will
issue an appropriate order or rule under 10 CFR part 2.
B. Electronic Submissions (E-Filing)
All documents filed in NRC adjudicatory proceedings, including a
request for hearing, a petition for leave to intervene, any motion or
other document filed in the proceeding prior to the submission of a
request for hearing or petition to intervene, and documents filed by
interested governmental entities participating under 10 CFR 2.315(c),
must be filed in accordance with the NRC's E-Filing rule (72 FR 49139;
August 28, 2007). The E-Filing process requires participants to submit
and serve all adjudicatory documents over the internet, or in some
cases to mail copies on electronic storage media. Participants may not
submit paper copies of their filings unless they seek an exemption in
[[Page 53899]]
accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least 10
days prior to the filing deadline, the participant should contact the
Office of the Secretary by email at hearing.docket@nrc.gov, or by
telephone at 301-415-1677, to request (1) a digital identification (ID)
certificate, which allows the participant (or its counsel or
representative) to digitally sign documents and access the E-Submittal
server for any proceeding in which it is participating; and (2) advise
the Secretary that the participant will be submitting a request or
petition for hearing (even in instances in which the participant, or
its counsel or representative, already holds an NRC-issued digital ID
certificate). Based upon this information, the Secretary will establish
an electronic docket for the hearing in this proceeding if the
Secretary has not already established an electronic docket.
Information about applying for a digital ID certificate is
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/getting-started.html. System requirements for accessing
the E-Submittal server are detailed in the NRC's ``Guidance for
Electronic Submission,'' which is available on the agency's public Web
site at https://www.nrc.gov/site-help/e-submittals.html. Participants
may attempt to use other software not listed on the Web site, but
should note that the NRC's E-Filing system does not support unlisted
software, and the NRC Meta System Help Desk will not be able to offer
assistance in using unlisted software.
If a participant is electronically submitting a document to the NRC
in accordance with the E-Filing rule, the participant must file the
document using the NRC's online, Web-based submission form. In order to
serve documents through the Electronic Information Exchange System,
users will be required to install a Web browser plug-in from the NRC's
Web site. Further information on the Web-based submission form,
including the installation of the Web browser plug-in, is available on
the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a request for
hearing or petition for leave to intervene. Submissions should be in
Portable Document Format (PDF) in accordance with NRC guidance
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the
documents are submitted through the NRC's E-Filing system. To be
timely, an electronic filing must be submitted to the E-Filing system
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of
a transmission, the E-Filing system time-stamps the document and sends
the submitter an email notice confirming receipt of the document. The
E-Filing system also distributes an email notice that provides access
to the document to the NRC's Office of the General Counsel and any
others who have advised the Office of the Secretary that they wish to
participate in the proceeding, so that the filer need not serve the
documents on those participants separately. Therefore, applicants and
other participants (or their counsel or representative) must apply for
and receive a digital ID certificate before a hearing request/petition
to intervene is filed so that they can obtain access to the document
via the E-Filing system.
A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System
Help Desk through the ``Contact Us'' link located on the NRC's public
Web site at https://www.nrc.gov/site-help/e-submittals.html, by email to
MSHD.Resource@nrc.gov, or by a toll-free call at 1-866-672-7640. The
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m.,
Eastern Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, Sixteenth
Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland
20852, Attention: Rulemaking and Adjudications Staff. Participants
filing a document in this manner are responsible for serving the
document on all other participants. Filing is considered complete by
first-class mail as of the time of deposit in the mail, or by courier,
express mail, or expedited delivery service upon depositing the
document with the provider of the service. A presiding officer, having
granted an exemption request from using E-Filing, may require a
participant or party to use E-Filing if the presiding officer
subsequently determines that the reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in the
NRC's electronic hearing docket which is available to the public at
https://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the
Commission, or the presiding officer. Participants are requested not to
include personal privacy information, such as social security numbers,
home addresses, or home phone numbers in their filings, unless an NRC
regulation or other law requires submission of such information.
However, in some instances, a request to intervene will require
including information on local residence in order to demonstrate a
proximity assertion of interest in the proceeding. With respect to
copyrighted works, except for limited excerpts that serve the purpose
of the adjudicatory filings and would constitute a Fair Use
application, participants are requested not to include copyrighted
materials in their submission.
Petitions for leave to intervene must be filed no later than 60
days from the date of publication of this notice. Requests for hearing,
petitions for leave to intervene, and motions for leave to file new or
amended contentions that are filed after the 60-day deadline will not
be entertained absent a determination by the presiding officer that the
filing demonstrates good cause by satisfying the three factors in 10
CFR 2.309(c)(1)(i)-(iii).
For further details with respect to this amendment action, see the
application for amendment which is available for public inspection at
the NRC's PDR, located at One White Flint North, Room O1-F21, 11555
Rockville Pike (first floor), Rockville, Maryland 20852. Publicly
available documents created or received at the NRC are accessible
electronically through ADAMS in the NRC Library at https://www.nrc.gov/reading-rm/adams.html. If you do not have access to ADAMS or if there
are problems in accessing the documents located in ADAMS, contact the
PDR's Reference staff at 1-800-397-4209, 301-415-4737, or by email to
pdr.resource@nrc.gov.
[[Page 53900]]
Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations,
Inc., Docket No. 50-271, Vermont Yankee Nuclear Power Station (VY),
Vernon, Vermont
Date of amendment request: June 24, 2015. A publicly-available
version is in ADAMS under Accession No. ML15177A016.
Description of amendment request: This amendment request contains
sensitive unclassified non-safeguards information (SUNSI). The
amendment would revise the VY Cyber Security Plan (CSP) Milestone 8
Implementation Schedule, full implementation date from June 30, 2016,
to December 15, 2017. The proposed amendment would also revise the
existing facility operating license Security Plan license condition.
Basis for proposed no significant hazards consideration
determination: As required by 10 CFR 50.91(a), the licensee has
provided its analysis of the issue of no significant hazards
consideration which is presented below:
1. Does the proposed change involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
The proposed change to the CSP Implementation Schedule is
administrative in nature. This change does not alter accident
analysis assumptions, add any initiators, or affect the function of
plant systems or the manner in which systems are operated,
maintained, modified, tested, or inspected. The proposed change does
not require any plant modifications which affect the performance
capability of the structures, systems, and components (SSCs) relied
upon to mitigate the consequences of postulated accidents and has no
impact on the probability or consequences of an accident previously
evaluated.
Therefore, the proposed change does not involve a significant
increase in the probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the possibility of a new or
different kind of accident from any accident previously evaluated?
Response: No.
The proposed change to the CSP Implementation Schedule is
administrative in nature. This change does not alter accident
analysis assumptions, add any initiators, or affect the function of
plant systems or the manner in which systems are operated,
maintained, modified, tested, or inspected. The proposed change does
not require any plant modifications which affect the performance
capability of the SSCs relied upon to mitigate the consequences of
postulated accidents and does not create the possibility of a new or
different kind of accident previously evaluated.
Therefore, the proposed change does not create the possibility
of a new or different kind of accident from any accident previously
evaluated.
3. Does the proposed change involve a significant reduction in a
margin of safety?
Response: No.
Plant safety margins are established through limiting conditions
for operation, limiting safety system settings, and safety limits
specified in the Technical Specifications. The proposed change to
the CSP Implementation Schedule is administrative in nature. In
addition, the milestone date delay for full implementation of the
CSP has no substantive impact because other measures have been taken
which provide adequate protection during this period of time.
Because there is no change to established safety margins as a result
of this change, the proposed change does not involve a significant
reduction in a margin of safety.
Therefore, the proposed change does not involve a significant
reduction in a margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
Attorney for licensee: Ms. Susan Raimo, Senior Counsel, Entergy
Services, Inc., 101 Constitution Avenue NW., Suite 200 East, Washington
DC 20001.
NRC Branch Chief: Meena K. Khanna.
Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations,
Inc., Docket No. 50-271, Vermont Yankee Nuclear Power Station, Vernon,
Vermont
Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation
A. This Order contains instructions regarding how potential parties
to this proceeding may request access to documents containing SUNSI.
B. Within 10 days after publication of this notice of hearing and
opportunity to petition for leave to intervene, any potential party who
believes access to SUNSI is necessary to respond to this notice may
request such access. A ``potential party'' is any person who intends to
participate as a party by demonstrating standing and filing an
admissible contention under 10 CFR 2.309. Requests for access to SUNSI
submitted later than 10 days after publication of this notice will not
be considered absent a showing of good cause for the late filing,
addressing why the request could not have been filed earlier.
C. The requester shall submit a letter requesting permission to
access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, Attention: Rulemakings and
Adjudications Staff, and provide a copy to the Associate General
Counsel for Hearings, Enforcement and Administration, Office of the
General Counsel, Washington, DC 20555-0001. The expedited delivery or
courier mail address for both offices is: U.S. Nuclear Regulatory
Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The email
address for the Office of the Secretary and the Office of the General
Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov,
respectively.\1\ The request must include the following information:
---------------------------------------------------------------------------
\1\ While a request for hearing or petition to intervene in this
proceeding must comply with the filing requirements of the NRC's
``E-Filing Rule,'' the initial request to access SUNSI under these
procedures should be submitted as described in this paragraph.
---------------------------------------------------------------------------
(1) A description of the licensing action with a citation to this
Federal Register notice;
(2) The name and address of the potential party and a description
of the potential party's particularized interest that could be harmed
by the action identified in C.(1); and
(3) The identity of the individual or entity requesting access to
SUNSI and the requester's basis for the need for the information in
order to meaningfully participate in this adjudicatory proceeding. In
particular, the request must explain why publicly-available versions of
the information requested would not be sufficient to provide the basis
and specificity for a proffered contention.
D. Based on an evaluation of the information submitted under
paragraph C.(3) the NRC staff will determine within 10 days of receipt
of the request whether:
(1) There is a reasonable basis to believe the petitioner is likely
to establish standing to participate in this NRC proceeding; and
(2) The requestor has established a legitimate need for access to
SUNSI.
E. If the NRC staff determines that the requestor satisfies both
D.(1) and D.(2) above, the NRC staff will notify the requestor in
writing that access to SUNSI has been granted. The written notification
will contain instructions on how the requestor may obtain copies of the
requested documents, and any other conditions that may apply to access
to those documents. These conditions may include, but are not limited
to, the signing of a Non-Disclosure Agreement or Affidavit, or
Protective Order \2\ setting
[[Page 53901]]
forth terms and conditions to prevent the unauthorized or inadvertent
disclosure of SUNSI by each individual who will be granted access to
SUNSI.
---------------------------------------------------------------------------
\2\ Any motion for Protective Order or draft Non-Disclosure
Affidavit or Agreement for SUNSI must be filed with the presiding
officer or the Chief Administrative Judge if the presiding officer
has not yet been designated, within 30 days of the deadline for the
receipt of the written access request.
---------------------------------------------------------------------------
F. Filing of Contentions. Any contentions in these proceedings that
are based upon the information received as a result of the request made
for SUNSI must be filed by the requestor no later than 25 days after
the requestor is granted access to that information. However, if more
than 25 days remain between the date the petitioner is granted access
to the information and the deadline for filing all other contentions
(as established in the notice of hearing or opportunity for hearing),
the petitioner may file its SUNSI contentions by that later deadline.
This provision does not extend the time for filing a request for a
hearing and petition to intervene, which must comply with the
requirements of 10 CFR 2.309.
G. Review of Denials of Access.
(1) If the request for access to SUNSI is denied by the NRC staff
after a determination on standing and need for access, the NRC staff
shall immediately notify the requestor in writing, briefly stating the
reason or reasons for the denial.
(2) The requester may challenge the NRC staff's adverse
determination by filing a challenge within 5 days of receipt of that
determination with: (a) The presiding officer designated in this
proceeding; (b) if no presiding officer has been appointed, the Chief
Administrative Judge, or if he or she is unavailable, another
administrative judge, or an administrative law judge with jurisdiction
pursuant to 10 CFR 2.318(a); or (c) officer if that officer has been
designated to rule on information access issues.
H. Review of Grants of Access. A party other than the requester may
challenge an NRC staff determination granting access to SUNSI whose
release would harm that party's interest independent of the proceeding.
Such a challenge must be filed with the Chief Administrative Judge
within 5 days of the notification by the NRC staff of its grant of
access.
If challenges to the NRC staff determinations are filed, these
procedures give way to the normal process for litigating disputes
concerning access to information. The availability of interlocutory
review by the Commission of orders ruling on such NRC staff
determinations (whether granting or denying access) is governed by 10
CFR 2.311.\3\
---------------------------------------------------------------------------
\3\ Requesters should note that the filing requirements of the
NRC's E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals
of NRC staff determinations (because they must be served on a
presiding officer or the Commission, as applicable), but not to the
initial SUNSI request submitted to the NRC staff under these
procedures.
---------------------------------------------------------------------------
I. The Commission expects that the NRC staff and presiding officers
(and any other reviewing officers) will consider and resolve requests
for access to SUNSI, and motions for protective orders, in a timely
fashion in order to minimize any unnecessary delays in identifying
those petitioners who have standing and who have propounded contentions
meeting the specificity and basis requirements in 10 CFR part 2.
Attachment 1 to this Order summarizes the general target schedule for
processing and resolving requests under these procedures.
It is so ordered.
Dated at Rockville, Maryland, this 27th day of August, 2015.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
ATTACHMENT 1--General Target Schedule for Processing and Resolving
Requests for Access to Sensitive Unclassified Non-Safeguards Information
in This Proceeding
------------------------------------------------------------------------
Day Event/activity
------------------------------------------------------------------------
0 Publication of Federal Register notice of
hearing and opportunity to petition for leave
to intervene, including order with
instructions for access requests.
10 Deadline for submitting requests for access to
Sensitive Unclassified Non-Safeguards
Information (SUNSI) with information:
supporting the standing of a potential party
identified by name and address; describing the
need for the information in order for the
potential party to participate meaningfully in
an adjudicatory proceeding.
60 Deadline for submitting petition for
intervention containing: (i) demonstration of
standing; and (ii) all contentions whose
formulation does not require access to SUNSI
(+25 Answers to petition for intervention; +7
petitioner/requestor reply).
20 U.S. Nuclear Regulatory Commission (NRC) staff
informs the requester of the staff's
determination whether the request for access
provides a reasonable basis to believe
standing can be established and shows need for
SUNSI. (NRC staff also informs any party to
the proceeding whose interest independent of
the proceeding would be harmed by the release
of the information.) If NRC staff makes the
finding of need for SUNSI and likelihood of
standing, NRC staff begins document processing
(preparation of redactions or review of
redacted documents).
25 If NRC staff finds no ``need'' or no likelihood
of standing, the deadline for petitioner/
requester to file a motion seeking a ruling to
reverse the NRC staff's denial of access; NRC
staff files copy of access determination with
the presiding officer (or Chief Administrative
Judge or other designated officer, as
appropriate). If NRC staff finds ``need'' for
SUNSI, the deadline for any party to the
proceeding whose interest independent of the
proceeding would be harmed by the release of
the information to file a motion seeking a
ruling to reverse the NRC staff's grant of
access.
30 Deadline for NRC staff reply to motions to
reverse NRC staff determination(s).
40 (Receipt +30) If NRC staff finds standing and
need for SUNSI, deadline for NRC staff to
complete information processing and file
motion for Protective Order and draft Non-
Disclosure Affidavit. Deadline for applicant/
licensee to file Non-Disclosure Agreement for
SUNSI.
A If access granted: issuance of presiding
officer or other designated officer decision
on motion for protective order for access to
sensitive information (including schedule for
providing access and submission of
contentions) or decision reversing a final
adverse determination by the NRC staff.
A + 3 Deadline for filing executed Non-Disclosure
Affidavits. Access provided to SUNSI
consistent with decision issuing the
protective order.
A + 28 Deadline for submission of contentions whose
development depends upon access to SUNSI.
However, if more than 25 days remain between
the petitioner's receipt of (or access to) the
information and the deadline for filing all
other contentions (as established in the
notice of hearing or opportunity for hearing),
the petitioner may file its SUNSI contentions
by that later deadline.
A + 53 (Contention receipt +25) Answers to contentions
whose development depends upon access to
SUNSI.
A + 60 (Answer receipt +7) Petitioner/Intervenor reply
to answers.
[[Page 53902]]
>A + 60 Decision on contention admission.
------------------------------------------------------------------------
[FR Doc. 2015-21795 Filed 9-4-15; 8:45 am]
BILLING CODE 7590-01-P