In the Matter of All Power Reactor Licensees Owned and Operated by Entergy Nuclear Operations, Inc.; Entergy Operations, Inc.; and Entergy Nuclear Generation Company, 48343-48348 [2015-19853]
Download as PDF
Federal Register / Vol. 80, No. 155 / Wednesday, August 12, 2015 / Notices
of Docketing included an opportunity to
request a hearing and to petition for
leave to intervene. No requests for a
hearing or leave to intervene were
submitted.
The NRC prepared a safety evaluation
report (SER) (ADAMS Accession No.
ML15050A428) to document its review
and evaluation of the amendment
request. Also in connection with this
action, the Commission prepared an
Environmental Assessment (EA)
(ADAMS Accession No. ML15022A575)
and a Finding of No Significant Impact
(FONSI) (ADAMS Accession No.
ML15026A683). The Notice of
Availability of the EA and FONSI for the
NA ISFSI was published in the Federal
Register on February 27, 2015 (80 FR
10726).
As required by the Act and the NRC’s
rules and regulations in 10 CFR Chapter
1, the staff made the appropriate
findings which are contained in the
SER. The NRC approved and issued
Amendment No. 4 to SNM–2507, held
by Dominion for the receipt, possession,
transfer, and storage of spent fuel and
associated radioactive materials at the
NA ISFSI. Pursuant to 10 CFR 72.46(d),
the NRC is providing notice of the
action taken. Amendment No. 4 was
effective as of the date of issuance,
August 3, 2015.
Dated at Rockville, Maryland, this 3rd day
of August, 2015.
For the Nuclear Regulatory Commission.
Michele Sampson,
Chief, Licensing Branch, Division of Spent
Fuel Management, Office of Nuclear Material
Safety and Safeguards.
[FR Doc. 2015–19807 Filed 8–11–15; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. (as Shown in the Attachment);
License Nos. (as Shown in the Attachment):
EA–14–009; NRC–2015–0135]
In the Matter of All Power Reactor
Licensees Owned and Operated by
Entergy Nuclear Operations, Inc.;
Entergy Operations, Inc.; and Entergy
Nuclear Generation Company
Nuclear Regulatory
Commission.
ACTION: Confirmatory order; issuance.
mstockstill on DSK4VPTVN1PROD with NOTICES
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing a
confirmatory order to Entergy
Operations, Inc. (Entergy), confirming
an agreement reached in an Alternative
Dispute Resolution mediation session
held on September 22, 2014. As part of
this agreement, Entergy will take actions
SUMMARY:
VerDate Sep<11>2014
18:16 Aug 11, 2015
Jkt 235001
to review and evaluate its security
procedures; strengthen its procedures
and set expectations regarding the
conduct of security personnel; and
conduct a presentation describing the
event that formed the bases for the
violation and the lessons learned, to its
employees and the industry. Entergy is
required to have an independent safety
culture assessment conducted of the
security organization at its River Bend
Station. Entergy is also required to
notify the NRC periodically of the status
of its efforts.
The confirmatory order was
issued on December 3, 2014.
DATES:
Please refer to Docket ID
NRC–2015–0135 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this action by the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2015–0135. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
questions about the Order, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
NRC: ADAMS Public Documents and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if that document
is publicly available in ADAMS) is
provided the first time that a document
is referenced.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
ADDRESSES:
FOR FURTHER INFORMATION CONTACT:
Christi Maier, Region IV, U.S. Nuclear
Regulatory Commission, Washington DC
20555–001; 817–200–1217; or by email
to Christi.Maier@nrc.gov.
SUPPLEMENTARY INFORMATION:
The text of
the Order is attached.
Dated this 3rd day of December 2014.
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
48343
For The Nuclear Regulatory Commission.
Marc L. Dapas,
Regional Administrator.
Editorial Note: This document was
received for publication by the Office of the
Federal Register on August 7, 2015.
ATTACHMENT—CONFIRMATORY
ORDER MODIFYING LICENSE
UNITED STATES OF AMERICA
NUCLEAR REGULATORY
COMMISSION
In the Matter of All Power Reactor
Licensees Owned and Operated by
Entergy Nuclear Operations, Inc.;
Entergy Operations, Inc. and Entergy
Nuclear Generation Company [Docket
Nos. (as shown in Attachment); License
Nos. (as shown in Attachment)]
EA–14–009
Confirmatory Order Modifying License
I.
The licensees identified in
Attachment 1 to this Order hold licenses
issued by the U.S. Nuclear Regulatory
Commission (NRC or Commission)
pursuant to Title 10 of the Code of
Federal Regulations (10 CFR) Part 50,
‘‘Domestic Licensing of Production and
Utilization Facilities.’’ The licenses
authorize the operation of the listed
facilities in accordance with conditions
specified therein.
This Confirmatory Order is the result
of an agreement reached during an
alternative dispute resolution (ADR)
mediation session conducted on
September 22, 2014, in Arlington,
Texas.
II.
On March 21, 2012, the NRC initiated
a special inspection to determine the
circumstances surrounding a security
event, which occurred on March 18,
2012, at Entergy Operations, Inc.’s
(Entergy or Licensee), River Bend
Station (RBS or facility). In addition, on
March 21, 2012, the NRC’s Office of
Investigations (OI), Region IV Field
Office, initiated an investigation at RBS
to determine if Entergy employees
willfully violated NRC security
requirements at RBS. The investigation
was completed on December 31, 2013,
and was documented in OI Report 4–
2012–022. Based on the evidence
developed during the investigation, OI’s
Region IV Field Office concluded that
the willful actions of an unidentified
individual caused Entergy to be in
violation of 10 CFR part 73, ‘‘Physical
Protection of Plants and Materials.’’
While the NRC investigation did not
identify the individual responsible for
the security-related violation, the OI
E:\FR\FM\12AUN1.SGM
12AUN1
48344
Federal Register / Vol. 80, No. 155 / Wednesday, August 12, 2015 / Notices
mstockstill on DSK4VPTVN1PROD with NOTICES
Region IV Field Office did establish
several facts that are germane to the
conclusion of the investigation. Details
of the security event and the subsequent
inspection and investigation are
described in Attachment 2 to this Order.
Attachment 2 includes Security-Related
Information (SRI); therefore, it is not
publicly available.
The NRC determined that as the result
of the willful actions of an unidentified
individual, Entergy failed to comply
with 10 CFR part 73. The NRC described
the results of the inspection and
investigation in a letter to Entergy dated
July 16, 2014. In response to the NRC’s
letter, Entergy requested ADR to resolve
this matter. This confirmatory order is
issued pursuant to the agreement
reached during the ADR process.
III.
On September 22, 2014, the NRC and
Entergy met in an ADR session
mediated by a professional mediator,
arranged through the Cornell University
Scheinman Institute on Conflict
Resolution. ADR is a process in which
a neutral mediator, with no decisionmaking authority, assists the parties in
reaching an agreement on resolving any
differences regarding the dispute.
During the ADR session, a preliminary
settlement agreement was reached. The
elements of that preliminary agreement,
with the exception of the section that
includes SRI, are described below. The
portions of the agreement that contain
SRI, as well as the sections of this
Confirmatory Order that address SRI,
are described in the aforementioned
non-public Attachment. The following
description of the preliminary ADR
agreement, and the required actions
described in Section V of this
Confirmatory Order, include references
to the non-public Attachment to allow
for public release of this Confirmatory
Order. The publicly available elements
of the agreement consist of the
following:
The NRC recognizes the corrective
actions that Entergy has already
implemented associated with the
apparent violation and preliminary
finding. Entergy’s corrective actions are
described in the non-public Attachment.
A. The NRC and Entergy agree that a
willful violation of Title 10 Code of
Federal Regulations (10 CFR) Part 73
occurred on March 18, 2012, at River
Bend Station. However, the NRC and
Entergy disagree on the specific aspects
of that willful characterization of the
violation. The details regarding these
aspects are described in the non-public
Attachment.
1. The NRC concluded that the
security-related violation occurred
VerDate Sep<11>2014
18:16 Aug 11, 2015
Jkt 235001
because of the deliberate misconduct of
an unidentified security officer at River
Bend Station.
2. Entergy does not believe that
willful intent was involved in all
aspects of the violation.
B. Within 4 months from the date of
this Confirmatory Order, Entergy will
revise its security procedures.
C. Within 3 months from the date of
this Confirmatory Order, Entergy will, at
each of its nuclear plants, conduct a
review of its controls for SRI and
communicate to the NRC the results of
the review. Within 6 months from the
date of this Confirmatory Order, Entergy
will establish new controls and will
provide its proposed controls to the
NRC for its review. The NRC will
communicate to Entergy any concerns
regarding the controls within 60 days of
submittal for resolution in a manner
acceptable to both parties. Entergy will
implement the controls within 15
months from the date of this
Confirmatory Order. The details
regarding these controls are described in
the non-public Attachment.
D. Within 9 months from the date of
this Confirmatory Order, Entergy will
review and evaluate the location and
storage of SRI at each of its nuclear
plants. The details are described in the
non-public Attachment.
E. Entergy will develop a
‘‘commitment to compliance’’ statement
or a similar document highlighting the
special responsibilities of nuclear
security personnel. This document will
explain that nuclear security personnel
need to comply with regulations and
procedures, and it will describe the
potential consequences if compliance
does not occur. Within 12 months from
the date of this Confirmatory Order,
Entergy will require at each of its
nuclear plants that nuclear security
personnel read and sign the statement
(subject to any collective bargaining
obligations it may have). Entergy will
include the reading and signing of this
statement in the initial qualification
process of nuclear security personnel.
The details are described in the nonpublic Attachment.
F. Within 6 months from the date of
this Confirmatory Order, Entergy will
identify those security posts in each of
its nuclear plants that should be subject
to certain decorum standards that will
ensure a professional environment in
those areas. Once identified, Entergy
will establish decorum protocols for
those security posts. In addition, within
6 months of the date of this
Confirmatory Order, Entergy will
provide its proposed decorum protocols
to the NRC for its review. The NRC will
communicate to Entergy any concerns
PO 00000
Frm 00058
Fmt 4703
Sfmt 4703
regarding the proposed decorum
protocols within 60 days of submittal
for resolution in a manner acceptable to
both parties. Entergy will implement the
decorum protocols within 12 months
from the date of this Confirmatory
Order.
G. Within 4 months from the date of
this Confirmatory Order, Entergy will
prepare a ‘‘lessons learned’’
presentation to be delivered to Entergy
nuclear employees at each of its nuclear
plants describing the event that formed
the basis for this violation. Prior to
making the presentation, Entergy will
provide its proposed presentation to the
NRC for its review. The NRC will
communicate to Entergy any concerns
regarding the presentation within 30
days of submittal. Entergy will deliver
the presentation to Entergy nuclear
employees within 12 months of this
Confirmatory Order.
H. Within 4 months from the date of
this Confirmatory Order, Entergy will
prepare a presentation describing the
event that formed the basis for this
violation. The presentation will be
delivered to the Nuclear Security
Working Group and the National
Nuclear Security Conference (subject to
acceptance of the conference-organizing
committees). This presentation will
include, among other subjects, the
subjects covered in the non-public
Attachment to this Confirmatory Order.
Prior to making the presentation,
Entergy will provide its proposed
presentation to the NRC for its review.
The NRC will communicate to Entergy
any concerns regarding the presentation
within 30 days of submittal. Entergy
will deliver the presentation within 12
months of this Confirmatory Order.
I. Within 6 months from the date of
this Confirmatory Order, Entergy will
ensure that an independent third party
conducts a safety culture assessment of
the Security organization at River Bend
Station. The results will be incorporated
into Entergy’s corrective action program
as appropriate. A copy of the completed
assessment will be made available for
NRC review.
J. Within 4 months from the date of
this Confirmatory Order, Entergy will
prepare refresher training on the
provisions of 10 CFR 50.5 and 50.9 for
Entergy employees at each of its nuclear
plants. Prior to conducting the training,
Entergy will provide its proposed
refresher training plan to the NRC for its
review. The NRC will communicate to
Entergy any concerns regarding the plan
within 30 days of submittal for
resolution in a manner acceptable to
both parties. Entergy will complete
administration of this refresher training
E:\FR\FM\12AUN1.SGM
12AUN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 155 / Wednesday, August 12, 2015 / Notices
within 12 months of this Confirmatory
Order.
K. Notification to the NRC When
Actions Are Completed
1. Unless otherwise specified, Entergy
will submit written notification to the
Director, Division of Reactor Safety,
USNRC Region IV, 1600 East Lamar
Blvd., Arlington, Texas 76011–4511, at
intervals not to exceed 6 months, 1 year,
and annually thereafter until the terms
of the Confirmatory Order are
completed, providing a status of each
item in the Order.
2. Entergy will provide its basis for
concluding that the terms of the
Confirmatory Order have been satisfied,
to the NRC, in writing
L. Inspection Follow-up
Based on the corrective actions and
enhancements described above, the NRC
will conduct follow-up inspections
using NRC Inspection Procedure 92702,
‘‘Followup on Corrective Actions for
Violations and Deviations.’’
M. Administrative Items
1. The NRC and Entergy Operations,
Inc., agree that the above elements will
be incorporated into this Confirmatory
Order and that the NRC will consider
the order an escalated enforcement
action.
2. The NRC and Entergy agree that the
issues described in the NRC’s Inspection
Report and Investigation Report to
Entergy Operations, Inc., of July 16,
2014 (EA–14–009) resulted in a
violation of NRC security requirements.
The details regarding the violation are
described in the non-public Attachment.
3. In consideration of the significant
corrective actions Entergy has already
taken and the additional actions Entergy
has committed to taking to enhance its
security program, the NRC agrees to
reduce the severity level of the escalated
enforcement sanction. The NRC agrees
to issue a Notice of Violation for a
security-related violation and impose a
$70,000 civil penalty for the matter
discussed in the NRC’s Inspection
Report and Investigation Report to
Entergy Operations, Inc., of July 16,
2014 (EA–14–009). The issuance of the
Notice of Violation and civil penalty is
considered escalated enforcement. The
NRC communicates, in the non-public
Attachment, the basis for its original
conclusion regarding the
characterization of the violation.
4. This agreement is binding upon
successors and assigns of Entergy
Operations, Inc.
N. Within thirty days of the date of
the Confirmatory Order, Entergy shall
pay a civil penalty of $70,000.
O. Entergy agrees that this
Confirmatory Order is to be effective
VerDate Sep<11>2014
18:16 Aug 11, 2015
Jkt 235001
upon issuance and waives its right to a
hearing in connection with this Order.
P. If Entergy fulfills its commitments
under this Order, the NRC will not take
further enforcement action based on the
violations of NRC requirements
described in Enclosure 2 of the letter
transmitting this Order.
On November 21, 2014, Entergy
consented to issuing this Confirmatory
Order with the commitments, as
described in Section V below.
IV.
Since the Licensee has agreed to take
additional actions to address NRC
concerns, as set forth in Section III
above, the NRC has concluded that its
concerns can be resolved through
issuance of this Confirmatory Order.
I find that Entergy’s commitments as
set forth in Section V are acceptable and
necessary and conclude that with these
commitments public health and safety
are reasonably assured. In view of the
foregoing, I have determined that public
health and safety require that Entergy’s
commitments be confirmed by this
Confirmatory Order. Based on the above
and Entergy’s consent, this
Confirmatory Order is effective 30 days
after its issuance.
V.
Accordingly, pursuant to Sections
104b, 161b, 161i, 161o, 182 and 186 of
the Atomic Energy Act of 1954, as
amended, and the Commission’s
regulations in 10 CFR 2.202 and 10 CFR
parts 50 and 73, IT IS HEREBY
ORDERED THAT THE ACTIONS
DESCRIBED BELOW WILL BE TAKEN
AT RIVER BEND STATION AND
OTHER NUCLEAR POWER PLANTS IN
ENTERGY’S FLEET AND THAT
REACTOR OPERATING LICENSE NO.
NPF–47 IS MODIFIED AS FOLLOWS
WITH RESPECT TO THE ACTIONS TO
BE TAKEN AT THE RIVER BEND
STATION:
A. The NRC and Entergy agree that a
willful violation of Title 10 Code of
Federal Regulations (10 CFR) Part 73
occurred on March 18, 2012, at River
Bend Station. However, the NRC and
Entergy disagree on the specific aspects
of that willful characterization of the
violation. The details regarding these
aspects are described in the non-public
Attachment.
1. The NRC concluded that the
security-related violation occurred
because of the deliberate misconduct of
an unidentified security officer at River
Bend Station.
2. However, Entergy does not believe
that willful intent was involved in all
aspects of the violation.
PO 00000
Frm 00059
Fmt 4703
Sfmt 4703
48345
B. Within 4 months from the date of
this Confirmatory Order, Entergy will
revise its security procedures.
C. Within 3 months from the date of
this Confirmatory Order, Entergy will, at
each of its nuclear plants, conduct a
review of its controls for SRI and
communicate to the NRC the results of
the review. Within 6 months from the
date of this Confirmatory Order, Entergy
will establish new controls and will
provide its proposed controls to the
NRC for its review. The NRC will
communicate to Entergy any concerns
regarding the controls within 60 days of
submittal for resolution in a manner
acceptable to both parties. Entergy will
implement the controls within 15
months from the date of this
Confirmatory Order. The details
regarding these controls are described in
the non-public Attachment.
D. Within 9 months from the date of
this Confirmatory Order, Entergy will
review and evaluate the location and
storage of SRI at each of its nuclear
plants. The details are described in the
non-public Attachment.
E. Entergy will develop a
‘‘commitment to compliance’’ statement
or a similar document highlighting the
special responsibilities of nuclear
security personnel. This document will
explain that nuclear security personnel
need to comply with regulations and
procedures, and it will describe the
potential consequences if compliance
does not occur. Within 12 months from
the date of this Confirmatory Order,
Entergy will require at each of its
nuclear plants that nuclear security
personnel read and sign the statement
(subject to any collective bargaining
obligations it may have). Entergy will
include the reading and signing of this
statement in the initial qualification
process of nuclear security personnel.
The details are described in the nonpublic Attachment.
F. Within 6 months from the date of
this Confirmatory Order, Entergy will
identify those security posts in each of
its nuclear plants that should be subject
to certain decorum standards that will
ensure a professional environment in
those areas. Once identified, Entergy
will establish decorum protocols for
those security posts. In addition, within
6 months of the date of this
Confirmatory Order, Entergy will
provide its proposed decorum protocols
to the NRC for its review. The NRC will
communicate to Entergy any concerns
regarding the proposed decorum
protocols within 60 days of submittal
for resolution in a manner acceptable to
both parties. Entergy will implement the
decorum protocols within 12 months
E:\FR\FM\12AUN1.SGM
12AUN1
mstockstill on DSK4VPTVN1PROD with NOTICES
48346
Federal Register / Vol. 80, No. 155 / Wednesday, August 12, 2015 / Notices
from the date of this Confirmatory
Order.
G. Within 4 months from the date of
this Confirmatory Order, Entergy will
prepare a ‘‘lessons learned’’
presentation to be delivered to Entergy
nuclear employees at each of its nuclear
plants describing the event that formed
the basis for this violation. Prior to
making the presentation, Entergy will
provide its proposed presentation to the
NRC for its review. The NRC will
communicate to Entergy any concerns
regarding the presentation within 30
days of submittal. Entergy will deliver
the presentation to Entergy nuclear
employees within 12 months of this
Confirmatory Order.
H. Within 4 months from the date of
this Confirmatory Order, Entergy will
prepare a presentation describing the
event that formed the basis for this
violation. The presentation will be
delivered to the Nuclear Security
Working Group and the National
Nuclear Security Conference (subject to
acceptance of the conference-organizing
committees). This presentation will
include, among other subjects, the
subjects covered by the non-public
Attachment to this Confirmatory Order.
Prior to making the presentation,
Entergy will provide its proposed
presentation to the NRC for its review.
The NRC will communicate to Entergy
any concerns regarding the presentation
within 30 days of submittal. Entergy
will deliver the presentation within 12
months of this Confirmatory Order.
I. Within 6 months from the date of
this Confirmatory Order, Entergy will
ensure that an independent, third party
conducts a safety culture assessment of
the Security organization at River Bend
Station. The results will be incorporated
into Entergy’s corrective action program
as appropriate. A copy of the completed
assessment will be made available for
NRC review.
J. Within 4 months from the date of
this Confirmatory Order, Entergy will
prepare refresher training on the
provisions of 10 CFR 50.5 and 50.9 for
Entergy employees at each of its nuclear
plants. Prior to conducting the training,
Entergy will provide its proposed
refresher training plan to the NRC for its
review. The NRC will communicate to
Entergy any concerns regarding the plan
within 30 days of submittal for
resolution in a manner acceptable to
both parties. Entergy will complete
administration of this refresher training
within 12 months of this Confirmatory
Order.
K. Notification to the NRC When
Actions Are Completed
1. Unless otherwise specified, Entergy
will submit written notification to the
VerDate Sep<11>2014
18:16 Aug 11, 2015
Jkt 235001
Director, Division of Reactor Safety,
USNRC Region IV, 1600 East Lamar
Blvd., Arlington, Texas 76011–4511, at
intervals not to exceed 6 months, 1 year,
and annually thereafter until the terms
of the Confirmatory Order are
completed, providing a status of each
item in the Order.
2. Entergy will provide its basis for
concluding that the terms of the
Confirmatory Order have been satisfied,
to the NRC, in writing
L. Inspection Follow-up
Based on the corrective actions and
enhancements described above, the NRC
will conduct follow-up inspections
using NRC Inspection Procedure 92702,
‘‘Followup on Corrective Actions for
Violations and Deviations.’’
M. Administrative Items
1. The NRC and Entergy Operations,
Inc., agree that the above elements will
be incorporated into this Confirmatory
Order and that the NRC will consider
the order an escalated enforcement
action.
2. The NRC and Entergy agree that the
issues in the NRC’s Inspection Report
and Investigation Report (EA–14–009)
described in a July 16, 2014, letter to
Entergy Operations, Inc., resulted in a
violation of NRC security requirements.
The details regarding the violation are
described in the non-public Attachment.
3. In consideration of the significant
corrective actions Entergy has already
taken and the additional actions Entergy
has committed to taking to enhance its
security program, the NRC agrees to
reduce the severity level of the escalated
enforcement sanction. The NRC agrees
to issue a Notice of Violation for a
security-related violation and impose a
$70,000 civil penalty for the matter
discussed in the July 16, 2014, letter to
Entergy Operations, Inc., regarding the
NRC’s Inspection Report and
Investigation Report (EA–14–009). The
issuance of the Notice of Violation and
civil penalty is considered escalated
enforcement. The NRC communicates,
in the non-public Attachment, the basis
for its original conclusion regarding the
characterization of the violation.
4. This agreement is binding upon
successors and assigns of Entergy
Operations, Inc.
N. Within 30 days of the date of the
Confirmatory Order, Entergy shall pay a
civil penalty of $70,000.
O. Entergy agrees that this
Confirmatory Order is to be effective
upon issuance and waives its right to a
hearing in connection with this Order
P. If Entergy fulfills its commitments
under this Order, the NRC will not take
further enforcement action based on the
violations of NRC requirements
PO 00000
Frm 00060
Fmt 4703
Sfmt 4703
described in Enclosure 2 of the letter
transmitting this Order.
The Regional Administrator, Region
IV, may, in writing, relax or rescind any
of the above conditions upon
demonstration by Entergy of good cause.
VI.
Any person adversely affected by this
Confirmatory Order, other than Entergy,
may request a hearing within 30 days of
its publication in the Federal Register.
Where good cause is shown,
consideration will be given to extending
the time to request a hearing. A request
for extension of time must be made in
writing to the Director, Office of
Enforcement, U.S. Nuclear Regulatory
Commission, Washington, DC 20555,
and include a statement of good cause
for the extension.
This Order and its Attachments
contain information up to the SecurityRelated Information designation, as
defined in 10 CFR 73.2, and its
disclosure to unauthorized individuals
is prohibited by 10 CFR 73.21 and 10
CFR 73.22. Therefore, any redacted
material will not be made available for
public inspection in the NRC Public
Document Room or electronically in the
NRC’s Agencywide Documents Access
and Management System. Any person
requesting to obtain a copy of this order
or portions thereof will be required to
demonstrate their trust and reliability
through a Federal Bureau of
Investigation background check and
criminal history check, as well as
demonstrate a ‘‘need to know’’ such
information.
If a person other than the licensee
requests a hearing, that person shall set
forth with particularity the manner in
which his interest is adversely affected
by this Confirmatory Order and shall
address the criteria set forth in 10 CFR
2.309(d) and (f).
If a hearing is requested by a person
whose interest is adversely affected, the
Commission will issue an order
designating the time and place of any
hearing. If a hearing is held, the issue to
be considered at such hearing shall be
whether this Confirmatory Order should
be sustained.
In the absence of any request for
hearing, or written approval of an
extension of time in which to request a
hearing, the provisions specified in
Section V above shall be effective and
final thirty days after issuance of this
Confirmatory Order without further
order or proceedings. If an extension of
time for requesting a hearing has been
approved, the provisions specified in
Section V shall be final when the
extension expires if a hearing request
has not been received.
E:\FR\FM\12AUN1.SGM
12AUN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 155 / Wednesday, August 12, 2015 / Notices
A REQUEST FOR HEARING SHALL
NOT STAY THE EFFECTIVENESS OF
THIS ORDER.
All documents filed in NRC
adjudicatory proceedings, including a
request for hearing, a petition for leave
to intervene, any motion or other
document filed in the proceeding prior
to the submission of a request for
hearing or petition to intervene, and
documents filed by interested
governmental entities participating
under 10 CFR 2.315(c), must be filed in
accordance with the NRC E-Filing rule
(72 FR 49139, August 28, 2007), as
amended by 77 FR 46562; August 3,
2012 (codified in pertinent part at 10
CFR part 2, subpart C). The E-Filing
process requires participants to submit
and serve all adjudicatory documents
over the internet, or in some cases to
mail copies on electronic storage media.
Participants may not submit paper
copies of their filings unless they seek
an exemption in accordance with the
procedures described below.
To comply with the procedural
requirements of E-Filing, at least 10
days prior to the filing deadline, the
participant should contact the Office of
the Secretary by email at
hearing.docket@nrc.gov, or by telephone
at (301) 415–1677, to request (1) a
digital ID certificate, which allows the
participant (or its counsel or
representative) to digitally sign
documents and access the E-Submittal
server for any proceeding in which it is
participating; and (2) advise the
Secretary that the participant will be
submitting a request or petition for
hearing (even in instances in which the
participant, or its counsel or
representative, already holds an NRCissued digital ID certificate). Based upon
this information, the Secretary will
establish an electronic docket for the
hearing in this proceeding if the
Secretary has not already established an
electronic docket.
Information about applying for a
digital ID certificate is available on
NRC’s public Web site at https://
www.nrc.gov/site-help/esubmittals.html. System requirements
for accessing the E-Submittal server are
detailed in NRC’s ‘‘Guidance for
Electronic Submission,’’ which is
available on the agency’s public Web
site at https://www.nrc.gov/site-help/esubmittals.html. Participants may
attempt to use other software not listed
on the Web site, but should note that the
NRC’s E-Filing system does not support
unlisted software, and the NRC Meta
System Help Desk will not be able to
offer assistance in using unlisted
software.
VerDate Sep<11>2014
18:16 Aug 11, 2015
Jkt 235001
If a participant is electronically
submitting a document to the NRC in
accordance with the E-Filing rule, the
participant must file the document
using the NRC’s online, Web-based
submission form. In order to serve
documents through the Electronic
Information Exchange (EIE), users will
be required to install a Web browser
plug-in from the NRC Web site. Further
information on the Web-based
submission form, including the
installation of the Web browser plug-in,
is available on the NRC’s public Web
site at https://www.nrc.gov/site-help/esubmittals.html.
Once a participant has obtained a
digital ID certificate and a docket has
been created, the participant can then
submit a request for hearing or petition
for leave to intervene through the EIE.
Submissions should be in Portable
Document Format (PDF) in accordance
with NRC guidance available on the
NRC public Web site at https://
www.nrc.gov/site-help/esubmittals.html. A filing is considered
complete at the time the documents are
submitted through the NRC’s E-Filing
system. To be timely, an electronic
filing must be submitted to the E-Filing
system no later than 11:59 p.m. Eastern
Time on the due date. Upon receipt of
a transmission, the E-Filing system
time-stamps the document and sends
the submitter an email notice
confirming receipt of the document. The
E-Filing system also distributes an email
notice that provides access to the
document to the NRC’s Office of the
General Counsel and any others who
have advised the Office of the Secretary
that they wish to participate in the
proceeding, so that the filer need not
serve the documents on those
participants separately. Therefore, any
others who wish to participate in the
proceeding (or their counsel or
representative) must apply for and
receive a digital ID certificate before a
hearing request/petition to intervene is
filed so that they can obtain access to
the document via the E-Filing system.
A person filing electronically using
the agency’s adjudicatory E-Filing
system may seek assistance by
contacting the NRC Meta System Help
Desk through the ‘‘Contact Us’’ link
located on the NRC Web site at https://
www.nrc.gov/site-help/esubmittals.html, by email at
MSHD.Resource@nrc.gov, or by a tollfree call at (866) 672–7640. The NRC
Meta System Help Desk is available
between 8 a.m. and 8 p.m., Eastern
Time, Monday through Friday,
excluding government holidays.
Participants who believe that they
have a good cause for not submitting
PO 00000
Frm 00061
Fmt 4703
Sfmt 4703
48347
documents electronically must file an
exemption request, in accordance with
10 CFR 2.302(g), with their initial paper
filing requesting authorization to
continue to submit documents in paper
format. Such filings must be submitted
by: (1) First class mail addressed to the
Office of the Secretary of the
Commission, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, Attention: Rulemaking and
Adjudications Staff; or (2) courier,
express mail, or expedited delivery
service to the Office of the Secretary,
Sixteenth Floor, One White Flint North,
11555 Rockville Pike, Rockville,
Maryland, 20852, Attention:
Rulemaking and Adjudications Staff.
Participants filing a document in this
manner are responsible for serving the
document on all other participants.
Filing is considered complete by firstclass mail as of the time of deposit in
the mail, or by courier, express mail, or
expedited delivery service upon
depositing the document with the
provider of the service. A presiding
officer, having granted an exemption
request from using E-Filing, may require
a participant or party to use E-Filing if
the presiding officer subsequently
determines that the reason for granting
the exemption from use of E-Filing no
longer exists.
Documents submitted in adjudicatory
proceedings will appear in NRC’s
electronic hearing docket which is
available to the public at https://
ehd1.nrc.gov/ehd/, unless excluded
pursuant to an order of the Commission,
or the presiding officer. Participants are
requested not to include personal
privacy information, such as social
security numbers, home addresses, or
home phone numbers in their filings,
unless an NRC regulation or other law
requires submission of such
information. With respect to
copyrighted works, except for limited
excerpts that serve the purpose of the
adjudicatory filings and would
constitute a Fair Use application,
participants are requested not to include
copyrighted materials in their
submission.
For The Nuclear Regulatory Commission
Dated this 3rd day of December 2014.
Marc L. Dapas,
Regional Administrator.
Attachments: as stated
E:\FR\FM\12AUN1.SGM
12AUN1
48348
Federal Register / Vol. 80, No. 155 / Wednesday, August 12, 2015 / Notices
Attachment 1
All Power Reactor Licensees Owned
and Operated By Entergy Nuclear
Operations, Inc.; Entergy Operations,
Inc.; and Entergy Nuclear Generation
Company
Arkansas Nuclear One, Units 1 and 2
Entergy Operations, Inc.
Docket Nos. 50–313, 50–368
License Nos. DRP–51; NPF–6
Mr. Jeremy Browning, Site Vice
President
Arkansas Nuclear One
Entergy Operations, Inc.
1448 SR 333
Russellville, AR 72802–0967
Grand Gulf Nuclear Station
Entergy Operations, Inc.
Docket No. 50–416
License No. NPF–29
Mr. Kevin J. Mulligan, Site Vice
President
Entergy Operations, Inc.
Grand Gulf Nuclear Station
P.O. Box 756
Port Gibson, MS 39150
Indian Point Nuclear Generating Unit
Nos. 2 and 3
Entergy Nuclear Operations, Inc.
Docket Nos. 50–247 and 50–286
License Nos. DPR–26 and DPR–64
John Ventosa, Vice President,
Operations
Entergy Nuclear Operations, Inc.
Indian Point Energy Center
450 Broadway, GSB
P.O. Box 249
Buchanan, NY 10511–0249
James A. FitzPatrick Nuclear Power
Plant
John Dent, Jr., Vice President—Site Vice
President
Entergy Nuclear Operations
Pilgrim Nuclear Power Station
600 Rocky Hill Road
Plymouth, MA 02360–5508
River Bend Station
Entergy Operations, Inc.
Docket No. 50–458
License No. NPF–47
Mr. Eric W. Olson, Site Vice President
Entergy Operations, Inc.
River Bend Station
5485 US Highway 61N
St. Francisville, LA 70775
Vermont Yankee Nuclear Power Station
Entergy Nuclear Operations, Inc.
Docket No. 50–271
License No. DPR–28
Christopher J. Wamser, Site Vice
President
Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station
320 Governor Hunt Road
Vernon, VT 05354
Waterford Steam Electric Station, Unit 3
Entergy Operations, Inc.
Docket No. 50–382
License No. NPF–38
Mr. Michael R. Chisum, Site Vice
President
Entergy Operations, Inc.
Waterford Steam Electric Station
17265 River Road
Killona, LA 70057–0751
Attachment 2—Redacted
Editorial Note: This document was
received for publication by the Office of the
Federal Register on August 7, 2015.
[FR Doc. 2015–19853 Filed 8–11–15; 8:45 am]
BILLING CODE 7590–01–P
Palisades Nuclear Plant
mstockstill on DSK4VPTVN1PROD with NOTICES
Entergy Nuclear Operations, Inc.
Docket No. 50–333
License No. DPR–59
Lawrence Coyle, Executive Vice
President
Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power
Plant
P.O. Box 110
Lycoming, NY 13093
AGENCY:
Entergy Nuclear Operations, Inc.
Docket No. 50–255
License No. DPR–20
Anthony J. Vitale, Site Vice President
Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant
27780 Blue Star Memorial Highway
Covert, MI 49043
Pilgrim Nuclear Power Station
Entergy Nuclear Generation Company
Docket No. 50–293
License No. DPR–35
VerDate Sep<11>2014
18:16 Aug 11, 2015
Jkt 235001
NUCLEAR REGULATORY
COMMISSION
[NRC–2014–0253]
Fitness-for-Duty Programs for New
Nuclear Power Plant Construction
Sites
NRC about the availability of
information regarding this document.
You may access information related to
this document, which the NRC
possesses and is publicly available,
using the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2014–0253. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced in this notice (if
that document is available in ADAMS)
is provided the first time that a
document is referenced. Revision 0 of
Regulatory Guide 5.84, is available in
ADAMS under Accession No.
ML15083A412. The regulatory analysis
may be found in ADAMS under
Accession No. ML14218A861.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
Regulatory guides are not
copyrighted, and NRC approval is not
required to reproduce them.
FOR FURTHER INFORMATION CONTACT:
Wesley W. Held, Office of Nuclear
Security and Incident Response,
telephone: 301–415–1583, email:
wesley.held@nrc.gov, or Richard A.
Jervey, Office of Nuclear Regulatory
Research, telephone: 301–415–6201,
email: richard.jervey@nrc.gov. Both are
staff of the U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
Nuclear Regulatory
Commission.
ACTION: Regulatory guide; issuance.
I. Introduction
The U.S. Nuclear Regulatory
Commission (NRC) is issuing a new
regulatory guide (RG), RG 5.84,
‘‘Fitness-for-Duty Programs at New
Reactor Construction Sites.’’ This RG
provides guidance for implementing
fitness-for-duty (FFD) requirements at
nuclear power plant construction sites.
ADDRESSES: Please refer to Docket ID
NRC–2014–0253 when contacting the
The NRC is issuing a new guide in the
NRC’s ‘‘Regulatory Guide’’ series. This
series was developed to describe and
make available to the public information
regarding methods that are acceptable to
the NRC staff for implementing specific
parts of the agency’s regulations,
techniques that the staff uses in
evaluating specific issues or postulated
events, and data that the staff needs in
SUMMARY:
PO 00000
Frm 00062
Fmt 4703
Sfmt 4703
SUPPLEMENTARY INFORMATION:
E:\FR\FM\12AUN1.SGM
12AUN1
Agencies
[Federal Register Volume 80, Number 155 (Wednesday, August 12, 2015)]
[Notices]
[Pages 48343-48348]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-19853]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. (as Shown in the Attachment); License Nos. (as Shown in
the Attachment): EA-14-009; NRC-2015-0135]
In the Matter of All Power Reactor Licensees Owned and Operated
by Entergy Nuclear Operations, Inc.; Entergy Operations, Inc.; and
Entergy Nuclear Generation Company
AGENCY: Nuclear Regulatory Commission.
ACTION: Confirmatory order; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing a
confirmatory order to Entergy Operations, Inc. (Entergy), confirming an
agreement reached in an Alternative Dispute Resolution mediation
session held on September 22, 2014. As part of this agreement, Entergy
will take actions to review and evaluate its security procedures;
strengthen its procedures and set expectations regarding the conduct of
security personnel; and conduct a presentation describing the event
that formed the bases for the violation and the lessons learned, to its
employees and the industry. Entergy is required to have an independent
safety culture assessment conducted of the security organization at its
River Bend Station. Entergy is also required to notify the NRC
periodically of the status of its efforts.
DATES: The confirmatory order was issued on December 3, 2014.
ADDRESSES: Please refer to Docket ID NRC-2015-0135 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this action by the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2015-0135. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For questions about the Order,
contact the individual listed in the FOR FURTHER INFORMATION CONTACT
section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select NRC: ADAMS Public Documents and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if that document
is publicly available in ADAMS) is provided the first time that a
document is referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Christi Maier, Region IV, U.S. Nuclear
Regulatory Commission, Washington DC 20555-001; 817-200-1217; or by
email to Christi.Maier@nrc.gov.
SUPPLEMENTARY INFORMATION: The text of the Order is attached.
Dated this 3rd day of December 2014.
For The Nuclear Regulatory Commission.
Marc L. Dapas,
Regional Administrator.
Editorial Note: This document was received for publication by
the Office of the Federal Register on August 7, 2015.
ATTACHMENT--CONFIRMATORY ORDER MODIFYING LICENSE
UNITED STATES OF AMERICA
NUCLEAR REGULATORY COMMISSION
In the Matter of All Power Reactor Licensees Owned and Operated by
Entergy Nuclear Operations, Inc.; Entergy Operations, Inc. and Entergy
Nuclear Generation Company [Docket Nos. (as shown in Attachment);
License Nos. (as shown in Attachment)]
EA-14-009
Confirmatory Order Modifying License
I.
The licensees identified in Attachment 1 to this Order hold
licenses issued by the U.S. Nuclear Regulatory Commission (NRC or
Commission) pursuant to Title 10 of the Code of Federal Regulations (10
CFR) Part 50, ``Domestic Licensing of Production and Utilization
Facilities.'' The licenses authorize the operation of the listed
facilities in accordance with conditions specified therein.
This Confirmatory Order is the result of an agreement reached
during an alternative dispute resolution (ADR) mediation session
conducted on September 22, 2014, in Arlington, Texas.
II.
On March 21, 2012, the NRC initiated a special inspection to
determine the circumstances surrounding a security event, which
occurred on March 18, 2012, at Entergy Operations, Inc.'s (Entergy or
Licensee), River Bend Station (RBS or facility). In addition, on March
21, 2012, the NRC's Office of Investigations (OI), Region IV Field
Office, initiated an investigation at RBS to determine if Entergy
employees willfully violated NRC security requirements at RBS. The
investigation was completed on December 31, 2013, and was documented in
OI Report 4-2012-022. Based on the evidence developed during the
investigation, OI's Region IV Field Office concluded that the willful
actions of an unidentified individual caused Entergy to be in violation
of 10 CFR part 73, ``Physical Protection of Plants and Materials.''
While the NRC investigation did not identify the individual
responsible for the security-related violation, the OI
[[Page 48344]]
Region IV Field Office did establish several facts that are germane to
the conclusion of the investigation. Details of the security event and
the subsequent inspection and investigation are described in Attachment
2 to this Order. Attachment 2 includes Security-Related Information
(SRI); therefore, it is not publicly available.
The NRC determined that as the result of the willful actions of an
unidentified individual, Entergy failed to comply with 10 CFR part 73.
The NRC described the results of the inspection and investigation in a
letter to Entergy dated July 16, 2014. In response to the NRC's letter,
Entergy requested ADR to resolve this matter. This confirmatory order
is issued pursuant to the agreement reached during the ADR process.
III.
On September 22, 2014, the NRC and Entergy met in an ADR session
mediated by a professional mediator, arranged through the Cornell
University Scheinman Institute on Conflict Resolution. ADR is a process
in which a neutral mediator, with no decision-making authority, assists
the parties in reaching an agreement on resolving any differences
regarding the dispute. During the ADR session, a preliminary settlement
agreement was reached. The elements of that preliminary agreement, with
the exception of the section that includes SRI, are described below.
The portions of the agreement that contain SRI, as well as the sections
of this Confirmatory Order that address SRI, are described in the
aforementioned non-public Attachment. The following description of the
preliminary ADR agreement, and the required actions described in
Section V of this Confirmatory Order, include references to the non-
public Attachment to allow for public release of this Confirmatory
Order. The publicly available elements of the agreement consist of the
following:
The NRC recognizes the corrective actions that Entergy has already
implemented associated with the apparent violation and preliminary
finding. Entergy's corrective actions are described in the non-public
Attachment.
A. The NRC and Entergy agree that a willful violation of Title 10
Code of Federal Regulations (10 CFR) Part 73 occurred on March 18,
2012, at River Bend Station. However, the NRC and Entergy disagree on
the specific aspects of that willful characterization of the violation.
The details regarding these aspects are described in the non-public
Attachment.
1. The NRC concluded that the security-related violation occurred
because of the deliberate misconduct of an unidentified security
officer at River Bend Station.
2. Entergy does not believe that willful intent was involved in all
aspects of the violation.
B. Within 4 months from the date of this Confirmatory Order,
Entergy will revise its security procedures.
C. Within 3 months from the date of this Confirmatory Order,
Entergy will, at each of its nuclear plants, conduct a review of its
controls for SRI and communicate to the NRC the results of the review.
Within 6 months from the date of this Confirmatory Order, Entergy will
establish new controls and will provide its proposed controls to the
NRC for its review. The NRC will communicate to Entergy any concerns
regarding the controls within 60 days of submittal for resolution in a
manner acceptable to both parties. Entergy will implement the controls
within 15 months from the date of this Confirmatory Order. The details
regarding these controls are described in the non-public Attachment.
D. Within 9 months from the date of this Confirmatory Order,
Entergy will review and evaluate the location and storage of SRI at
each of its nuclear plants. The details are described in the non-public
Attachment.
E. Entergy will develop a ``commitment to compliance'' statement or
a similar document highlighting the special responsibilities of nuclear
security personnel. This document will explain that nuclear security
personnel need to comply with regulations and procedures, and it will
describe the potential consequences if compliance does not occur.
Within 12 months from the date of this Confirmatory Order, Entergy will
require at each of its nuclear plants that nuclear security personnel
read and sign the statement (subject to any collective bargaining
obligations it may have). Entergy will include the reading and signing
of this statement in the initial qualification process of nuclear
security personnel. The details are described in the non-public
Attachment.
F. Within 6 months from the date of this Confirmatory Order,
Entergy will identify those security posts in each of its nuclear
plants that should be subject to certain decorum standards that will
ensure a professional environment in those areas. Once identified,
Entergy will establish decorum protocols for those security posts. In
addition, within 6 months of the date of this Confirmatory Order,
Entergy will provide its proposed decorum protocols to the NRC for its
review. The NRC will communicate to Entergy any concerns regarding the
proposed decorum protocols within 60 days of submittal for resolution
in a manner acceptable to both parties. Entergy will implement the
decorum protocols within 12 months from the date of this Confirmatory
Order.
G. Within 4 months from the date of this Confirmatory Order,
Entergy will prepare a ``lessons learned'' presentation to be delivered
to Entergy nuclear employees at each of its nuclear plants describing
the event that formed the basis for this violation. Prior to making the
presentation, Entergy will provide its proposed presentation to the NRC
for its review. The NRC will communicate to Entergy any concerns
regarding the presentation within 30 days of submittal. Entergy will
deliver the presentation to Entergy nuclear employees within 12 months
of this Confirmatory Order.
H. Within 4 months from the date of this Confirmatory Order,
Entergy will prepare a presentation describing the event that formed
the basis for this violation. The presentation will be delivered to the
Nuclear Security Working Group and the National Nuclear Security
Conference (subject to acceptance of the conference-organizing
committees). This presentation will include, among other subjects, the
subjects covered in the non-public Attachment to this Confirmatory
Order. Prior to making the presentation, Entergy will provide its
proposed presentation to the NRC for its review. The NRC will
communicate to Entergy any concerns regarding the presentation within
30 days of submittal. Entergy will deliver the presentation within 12
months of this Confirmatory Order.
I. Within 6 months from the date of this Confirmatory Order,
Entergy will ensure that an independent third party conducts a safety
culture assessment of the Security organization at River Bend Station.
The results will be incorporated into Entergy's corrective action
program as appropriate. A copy of the completed assessment will be made
available for NRC review.
J. Within 4 months from the date of this Confirmatory Order,
Entergy will prepare refresher training on the provisions of 10 CFR
50.5 and 50.9 for Entergy employees at each of its nuclear plants.
Prior to conducting the training, Entergy will provide its proposed
refresher training plan to the NRC for its review. The NRC will
communicate to Entergy any concerns regarding the plan within 30 days
of submittal for resolution in a manner acceptable to both parties.
Entergy will complete administration of this refresher training
[[Page 48345]]
within 12 months of this Confirmatory Order.
K. Notification to the NRC When Actions Are Completed
1. Unless otherwise specified, Entergy will submit written
notification to the Director, Division of Reactor Safety, USNRC Region
IV, 1600 East Lamar Blvd., Arlington, Texas 76011-4511, at intervals
not to exceed 6 months, 1 year, and annually thereafter until the terms
of the Confirmatory Order are completed, providing a status of each
item in the Order.
2. Entergy will provide its basis for concluding that the terms of
the Confirmatory Order have been satisfied, to the NRC, in writing
L. Inspection Follow-up
Based on the corrective actions and enhancements described above,
the NRC will conduct follow-up inspections using NRC Inspection
Procedure 92702, ``Followup on Corrective Actions for Violations and
Deviations.''
M. Administrative Items
1. The NRC and Entergy Operations, Inc., agree that the above
elements will be incorporated into this Confirmatory Order and that the
NRC will consider the order an escalated enforcement action.
2. The NRC and Entergy agree that the issues described in the NRC's
Inspection Report and Investigation Report to Entergy Operations, Inc.,
of July 16, 2014 (EA-14-009) resulted in a violation of NRC security
requirements. The details regarding the violation are described in the
non-public Attachment.
3. In consideration of the significant corrective actions Entergy
has already taken and the additional actions Entergy has committed to
taking to enhance its security program, the NRC agrees to reduce the
severity level of the escalated enforcement sanction. The NRC agrees to
issue a Notice of Violation for a security-related violation and impose
a $70,000 civil penalty for the matter discussed in the NRC's
Inspection Report and Investigation Report to Entergy Operations, Inc.,
of July 16, 2014 (EA-14-009). The issuance of the Notice of Violation
and civil penalty is considered escalated enforcement. The NRC
communicates, in the non-public Attachment, the basis for its original
conclusion regarding the characterization of the violation.
4. This agreement is binding upon successors and assigns of Entergy
Operations, Inc.
N. Within thirty days of the date of the Confirmatory Order,
Entergy shall pay a civil penalty of $70,000.
O. Entergy agrees that this Confirmatory Order is to be effective
upon issuance and waives its right to a hearing in connection with this
Order.
P. If Entergy fulfills its commitments under this Order, the NRC
will not take further enforcement action based on the violations of NRC
requirements described in Enclosure 2 of the letter transmitting this
Order.
On November 21, 2014, Entergy consented to issuing this
Confirmatory Order with the commitments, as described in Section V
below.
IV.
Since the Licensee has agreed to take additional actions to address
NRC concerns, as set forth in Section III above, the NRC has concluded
that its concerns can be resolved through issuance of this Confirmatory
Order.
I find that Entergy's commitments as set forth in Section V are
acceptable and necessary and conclude that with these commitments
public health and safety are reasonably assured. In view of the
foregoing, I have determined that public health and safety require that
Entergy's commitments be confirmed by this Confirmatory Order. Based on
the above and Entergy's consent, this Confirmatory Order is effective
30 days after its issuance.
V.
Accordingly, pursuant to Sections 104b, 161b, 161i, 161o, 182 and
186 of the Atomic Energy Act of 1954, as amended, and the Commission's
regulations in 10 CFR 2.202 and 10 CFR parts 50 and 73, IT IS HEREBY
ORDERED THAT THE ACTIONS DESCRIBED BELOW WILL BE TAKEN AT RIVER BEND
STATION AND OTHER NUCLEAR POWER PLANTS IN ENTERGY'S FLEET AND THAT
REACTOR OPERATING LICENSE NO. NPF-47 IS MODIFIED AS FOLLOWS WITH
RESPECT TO THE ACTIONS TO BE TAKEN AT THE RIVER BEND STATION:
A. The NRC and Entergy agree that a willful violation of Title 10
Code of Federal Regulations (10 CFR) Part 73 occurred on March 18,
2012, at River Bend Station. However, the NRC and Entergy disagree on
the specific aspects of that willful characterization of the violation.
The details regarding these aspects are described in the non-public
Attachment.
1. The NRC concluded that the security-related violation occurred
because of the deliberate misconduct of an unidentified security
officer at River Bend Station.
2. However, Entergy does not believe that willful intent was
involved in all aspects of the violation.
B. Within 4 months from the date of this Confirmatory Order,
Entergy will revise its security procedures.
C. Within 3 months from the date of this Confirmatory Order,
Entergy will, at each of its nuclear plants, conduct a review of its
controls for SRI and communicate to the NRC the results of the review.
Within 6 months from the date of this Confirmatory Order, Entergy will
establish new controls and will provide its proposed controls to the
NRC for its review. The NRC will communicate to Entergy any concerns
regarding the controls within 60 days of submittal for resolution in a
manner acceptable to both parties. Entergy will implement the controls
within 15 months from the date of this Confirmatory Order. The details
regarding these controls are described in the non-public Attachment.
D. Within 9 months from the date of this Confirmatory Order,
Entergy will review and evaluate the location and storage of SRI at
each of its nuclear plants. The details are described in the non-public
Attachment.
E. Entergy will develop a ``commitment to compliance'' statement or
a similar document highlighting the special responsibilities of nuclear
security personnel. This document will explain that nuclear security
personnel need to comply with regulations and procedures, and it will
describe the potential consequences if compliance does not occur.
Within 12 months from the date of this Confirmatory Order, Entergy will
require at each of its nuclear plants that nuclear security personnel
read and sign the statement (subject to any collective bargaining
obligations it may have). Entergy will include the reading and signing
of this statement in the initial qualification process of nuclear
security personnel. The details are described in the non-public
Attachment.
F. Within 6 months from the date of this Confirmatory Order,
Entergy will identify those security posts in each of its nuclear
plants that should be subject to certain decorum standards that will
ensure a professional environment in those areas. Once identified,
Entergy will establish decorum protocols for those security posts. In
addition, within 6 months of the date of this Confirmatory Order,
Entergy will provide its proposed decorum protocols to the NRC for its
review. The NRC will communicate to Entergy any concerns regarding the
proposed decorum protocols within 60 days of submittal for resolution
in a manner acceptable to both parties. Entergy will implement the
decorum protocols within 12 months
[[Page 48346]]
from the date of this Confirmatory Order.
G. Within 4 months from the date of this Confirmatory Order,
Entergy will prepare a ``lessons learned'' presentation to be delivered
to Entergy nuclear employees at each of its nuclear plants describing
the event that formed the basis for this violation. Prior to making the
presentation, Entergy will provide its proposed presentation to the NRC
for its review. The NRC will communicate to Entergy any concerns
regarding the presentation within 30 days of submittal. Entergy will
deliver the presentation to Entergy nuclear employees within 12 months
of this Confirmatory Order.
H. Within 4 months from the date of this Confirmatory Order,
Entergy will prepare a presentation describing the event that formed
the basis for this violation. The presentation will be delivered to the
Nuclear Security Working Group and the National Nuclear Security
Conference (subject to acceptance of the conference-organizing
committees). This presentation will include, among other subjects, the
subjects covered by the non-public Attachment to this Confirmatory
Order. Prior to making the presentation, Entergy will provide its
proposed presentation to the NRC for its review. The NRC will
communicate to Entergy any concerns regarding the presentation within
30 days of submittal. Entergy will deliver the presentation within 12
months of this Confirmatory Order.
I. Within 6 months from the date of this Confirmatory Order,
Entergy will ensure that an independent, third party conducts a safety
culture assessment of the Security organization at River Bend Station.
The results will be incorporated into Entergy's corrective action
program as appropriate. A copy of the completed assessment will be made
available for NRC review.
J. Within 4 months from the date of this Confirmatory Order,
Entergy will prepare refresher training on the provisions of 10 CFR
50.5 and 50.9 for Entergy employees at each of its nuclear plants.
Prior to conducting the training, Entergy will provide its proposed
refresher training plan to the NRC for its review. The NRC will
communicate to Entergy any concerns regarding the plan within 30 days
of submittal for resolution in a manner acceptable to both parties.
Entergy will complete administration of this refresher training within
12 months of this Confirmatory Order.
K. Notification to the NRC When Actions Are Completed
1. Unless otherwise specified, Entergy will submit written
notification to the Director, Division of Reactor Safety, USNRC Region
IV, 1600 East Lamar Blvd., Arlington, Texas 76011-4511, at intervals
not to exceed 6 months, 1 year, and annually thereafter until the terms
of the Confirmatory Order are completed, providing a status of each
item in the Order.
2. Entergy will provide its basis for concluding that the terms of
the Confirmatory Order have been satisfied, to the NRC, in writing
L. Inspection Follow-up
Based on the corrective actions and enhancements described above,
the NRC will conduct follow-up inspections using NRC Inspection
Procedure 92702, ``Followup on Corrective Actions for Violations and
Deviations.''
M. Administrative Items
1. The NRC and Entergy Operations, Inc., agree that the above
elements will be incorporated into this Confirmatory Order and that the
NRC will consider the order an escalated enforcement action.
2. The NRC and Entergy agree that the issues in the NRC's
Inspection Report and Investigation Report (EA-14-009) described in a
July 16, 2014, letter to Entergy Operations, Inc., resulted in a
violation of NRC security requirements. The details regarding the
violation are described in the non-public Attachment.
3. In consideration of the significant corrective actions Entergy
has already taken and the additional actions Entergy has committed to
taking to enhance its security program, the NRC agrees to reduce the
severity level of the escalated enforcement sanction. The NRC agrees to
issue a Notice of Violation for a security-related violation and impose
a $70,000 civil penalty for the matter discussed in the July 16, 2014,
letter to Entergy Operations, Inc., regarding the NRC's Inspection
Report and Investigation Report (EA-14-009). The issuance of the Notice
of Violation and civil penalty is considered escalated enforcement. The
NRC communicates, in the non-public Attachment, the basis for its
original conclusion regarding the characterization of the violation.
4. This agreement is binding upon successors and assigns of Entergy
Operations, Inc.
N. Within 30 days of the date of the Confirmatory Order, Entergy
shall pay a civil penalty of $70,000.
O. Entergy agrees that this Confirmatory Order is to be effective
upon issuance and waives its right to a hearing in connection with this
Order
P. If Entergy fulfills its commitments under this Order, the NRC
will not take further enforcement action based on the violations of NRC
requirements described in Enclosure 2 of the letter transmitting this
Order.
The Regional Administrator, Region IV, may, in writing, relax or
rescind any of the above conditions upon demonstration by Entergy of
good cause.
VI.
Any person adversely affected by this Confirmatory Order, other
than Entergy, may request a hearing within 30 days of its publication
in the Federal Register. Where good cause is shown, consideration will
be given to extending the time to request a hearing. A request for
extension of time must be made in writing to the Director, Office of
Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555,
and include a statement of good cause for the extension.
This Order and its Attachments contain information up to the
Security-Related Information designation, as defined in 10 CFR 73.2,
and its disclosure to unauthorized individuals is prohibited by 10 CFR
73.21 and 10 CFR 73.22. Therefore, any redacted material will not be
made available for public inspection in the NRC Public Document Room or
electronically in the NRC's Agencywide Documents Access and Management
System. Any person requesting to obtain a copy of this order or
portions thereof will be required to demonstrate their trust and
reliability through a Federal Bureau of Investigation background check
and criminal history check, as well as demonstrate a ``need to know''
such information.
If a person other than the licensee requests a hearing, that person
shall set forth with particularity the manner in which his interest is
adversely affected by this Confirmatory Order and shall address the
criteria set forth in 10 CFR 2.309(d) and (f).
If a hearing is requested by a person whose interest is adversely
affected, the Commission will issue an order designating the time and
place of any hearing. If a hearing is held, the issue to be considered
at such hearing shall be whether this Confirmatory Order should be
sustained.
In the absence of any request for hearing, or written approval of
an extension of time in which to request a hearing, the provisions
specified in Section V above shall be effective and final thirty days
after issuance of this Confirmatory Order without further order or
proceedings. If an extension of time for requesting a hearing has been
approved, the provisions specified in Section V shall be final when the
extension expires if a hearing request has not been received.
[[Page 48347]]
A REQUEST FOR HEARING SHALL NOT STAY THE EFFECTIVENESS OF THIS
ORDER.
All documents filed in NRC adjudicatory proceedings, including a
request for hearing, a petition for leave to intervene, any motion or
other document filed in the proceeding prior to the submission of a
request for hearing or petition to intervene, and documents filed by
interested governmental entities participating under 10 CFR 2.315(c),
must be filed in accordance with the NRC E-Filing rule (72 FR 49139,
August 28, 2007), as amended by 77 FR 46562; August 3, 2012 (codified
in pertinent part at 10 CFR part 2, subpart C). The E-Filing process
requires participants to submit and serve all adjudicatory documents
over the internet, or in some cases to mail copies on electronic
storage media. Participants may not submit paper copies of their
filings unless they seek an exemption in accordance with the procedures
described below.
To comply with the procedural requirements of E-Filing, at least 10
days prior to the filing deadline, the participant should contact the
Office of the Secretary by email at hearing.docket@nrc.gov, or by
telephone at (301) 415-1677, to request (1) a digital ID certificate,
which allows the participant (or its counsel or representative) to
digitally sign documents and access the E-Submittal server for any
proceeding in which it is participating; and (2) advise the Secretary
that the participant will be submitting a request or petition for
hearing (even in instances in which the participant, or its counsel or
representative, already holds an NRC-issued digital ID certificate).
Based upon this information, the Secretary will establish an electronic
docket for the hearing in this proceeding if the Secretary has not
already established an electronic docket.
Information about applying for a digital ID certificate is
available on NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html. System requirements for accessing the E-Submittal
server are detailed in NRC's ``Guidance for Electronic Submission,''
which is available on the agency's public Web site at https://www.nrc.gov/site-help/e-submittals.html. Participants may attempt to
use other software not listed on the Web site, but should note that the
NRC's E-Filing system does not support unlisted software, and the NRC
Meta System Help Desk will not be able to offer assistance in using
unlisted software.
If a participant is electronically submitting a document to the NRC
in accordance with the E-Filing rule, the participant must file the
document using the NRC's online, Web-based submission form. In order to
serve documents through the Electronic Information Exchange (EIE),
users will be required to install a Web browser plug-in from the NRC
Web site. Further information on the Web-based submission form,
including the installation of the Web browser plug-in, is available on
the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a request for
hearing or petition for leave to intervene through the EIE. Submissions
should be in Portable Document Format (PDF) in accordance with NRC
guidance available on the NRC public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the
time the documents are submitted through the NRC's E-Filing system. To
be timely, an electronic filing must be submitted to the E-Filing
system no later than 11:59 p.m. Eastern Time on the due date. Upon
receipt of a transmission, the E-Filing system time-stamps the document
and sends the submitter an email notice confirming receipt of the
document. The E-Filing system also distributes an email notice that
provides access to the document to the NRC's Office of the General
Counsel and any others who have advised the Office of the Secretary
that they wish to participate in the proceeding, so that the filer need
not serve the documents on those participants separately. Therefore,
any others who wish to participate in the proceeding (or their counsel
or representative) must apply for and receive a digital ID certificate
before a hearing request/petition to intervene is filed so that they
can obtain access to the document via the E-Filing system.
A person filing electronically using the agency's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System
Help Desk through the ``Contact Us'' link located on the NRC Web site
at https://www.nrc.gov/site-help/e-submittals.html, by email at
MSHD.Resource@nrc.gov, or by a toll-free call at (866) 672-7640. The
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m.,
Eastern Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, Sixteenth
Floor, One White Flint North, 11555 Rockville Pike, Rockville,
Maryland, 20852, Attention: Rulemaking and Adjudications Staff.
Participants filing a document in this manner are responsible for
serving the document on all other participants. Filing is considered
complete by first-class mail as of the time of deposit in the mail, or
by courier, express mail, or expedited delivery service upon depositing
the document with the provider of the service. A presiding officer,
having granted an exemption request from using E-Filing, may require a
participant or party to use E-Filing if the presiding officer
subsequently determines that the reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in
NRC's electronic hearing docket which is available to the public at
https://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the
Commission, or the presiding officer. Participants are requested not to
include personal privacy information, such as social security numbers,
home addresses, or home phone numbers in their filings, unless an NRC
regulation or other law requires submission of such information. With
respect to copyrighted works, except for limited excerpts that serve
the purpose of the adjudicatory filings and would constitute a Fair Use
application, participants are requested not to include copyrighted
materials in their submission.
For The Nuclear Regulatory Commission
Dated this 3rd day of December 2014.
Marc L. Dapas,
Regional Administrator.
Attachments: as stated
[[Page 48348]]
Attachment 1
All Power Reactor Licensees Owned and Operated By Entergy Nuclear
Operations, Inc.; Entergy Operations, Inc.; and Entergy Nuclear
Generation Company
Arkansas Nuclear One, Units 1 and 2
Entergy Operations, Inc.
Docket Nos. 50-313, 50-368
License Nos. DRP-51; NPF-6
Mr. Jeremy Browning, Site Vice President
Arkansas Nuclear One
Entergy Operations, Inc.
1448 SR 333
Russellville, AR 72802-0967
Grand Gulf Nuclear Station
Entergy Operations, Inc.
Docket No. 50-416
License No. NPF-29
Mr. Kevin J. Mulligan, Site Vice President
Entergy Operations, Inc.
Grand Gulf Nuclear Station
P.O. Box 756
Port Gibson, MS 39150
Indian Point Nuclear Generating Unit Nos. 2 and 3
Entergy Nuclear Operations, Inc.
Docket Nos. 50-247 and 50-286
License Nos. DPR-26 and DPR-64
John Ventosa, Vice President, Operations
Entergy Nuclear Operations, Inc.
Indian Point Energy Center
450 Broadway, GSB
P.O. Box 249
Buchanan, NY 10511-0249
James A. FitzPatrick Nuclear Power Plant
Entergy Nuclear Operations, Inc.
Docket No. 50-333
License No. DPR-59
Lawrence Coyle, Executive Vice President
Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant
P.O. Box 110
Lycoming, NY 13093
Palisades Nuclear Plant
Entergy Nuclear Operations, Inc.
Docket No. 50-255
License No. DPR-20
Anthony J. Vitale, Site Vice President
Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant
27780 Blue Star Memorial Highway
Covert, MI 49043
Pilgrim Nuclear Power Station
Entergy Nuclear Generation Company
Docket No. 50-293
License No. DPR-35
John Dent, Jr., Vice President--Site Vice President
Entergy Nuclear Operations
Pilgrim Nuclear Power Station
600 Rocky Hill Road
Plymouth, MA 02360-5508
River Bend Station
Entergy Operations, Inc.
Docket No. 50-458
License No. NPF-47
Mr. Eric W. Olson, Site Vice President
Entergy Operations, Inc.
River Bend Station
5485 US Highway 61N
St. Francisville, LA 70775
Vermont Yankee Nuclear Power Station
Entergy Nuclear Operations, Inc.
Docket No. 50-271
License No. DPR-28
Christopher J. Wamser, Site Vice President
Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station
320 Governor Hunt Road
Vernon, VT 05354
Waterford Steam Electric Station, Unit 3
Entergy Operations, Inc.
Docket No. 50-382
License No. NPF-38
Mr. Michael R. Chisum, Site Vice President
Entergy Operations, Inc.
Waterford Steam Electric Station
17265 River Road
Killona, LA 70057-0751
Attachment 2--Redacted
Editorial Note: This document was received for publication by
the Office of the Federal Register on August 7, 2015.
[FR Doc. 2015-19853 Filed 8-11-15; 8:45 am]
BILLING CODE 7590-01-P