American Midstream, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Natchez Pipeline Project and Request for Comments on Environmental Issues, 46259-46261 [2015-19055]
Download as PDF
Federal Register / Vol. 80, No. 149 / Tuesday, August 4, 2015 / Notices
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: July 29, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–19057 Filed 8–3–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL15–86–000]
tkelley on DSK3SPTVN1PROD with NOTICES
ITC Grid Development LLC; Notice of
Petition for Declaratory Order
Take notice that on July 28, 2015,
pursuant to rule 207(a) of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure and sections 366.3(d) and
366.4(b)(3) of the Commission’s
regulations, 18 CFR 385.207(a), 366.3(d),
and 366.4(b)(3), ITC Grid Development
LLC (ITC Grid), filed a petition for
declaratory order (petition) seeking a
Commission ruling: (1) That binding
revenue requirement bids selected as
the result of Commission-approved,
Order No. 1000-compliant, and
demonstrably competitive transmission
project selection processes will be
deemed just and reasonable when filed
at the Commission as a stated rate
pursuant to Federal Power Act (FPA)
section 205; and (2) that such binding
bids are entitled to protection under the
Mobile-Sierra standard, and may not
subsequently be changed by means of a
complaint filed under FPA section 206
unless required by the public interest.
ITC Grid requests that the Commission
rule on this petition within 90 days of
when its petition was filed, or by
October 26, 2015, in order to facilitate
ITC Grid’s participation in upcoming
competitive project solicitations, as
more fully explained in its petition. .
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
VerDate Sep<11>2014
18:45 Aug 03, 2015
Jkt 235001
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Petitioner.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern time
on August 27, 2015.
Dated: July 29, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–19060 Filed 8–3–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–523–000]
American Midstream, LLC; Notice of
Intent To Prepare an Environmental
Assessment for the Proposed Natchez
Pipeline Project and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Natchez Pipeline Project involving
construction and operation of facilities
by American Midstream, LLC (Midla) in
Franklin, Catahoula, and Concordia
Parishes, Louisiana, and Adams County,
Mississippi. The Commission will use
this EA in its decision-making process
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
46259
to determine whether the project is in
the public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before August 24,
2015.
If you sent comments on this project
to the Commission before the opening of
this docket on June 29, 2015, you will
need to file those comments in Docket
No. CP15–523–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
Midla provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
This fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC Web site
(www.ferc.gov).
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
E:\FR\FM\04AUN1.SGM
04AUN1
46260
Federal Register / Vol. 80, No. 149 / Tuesday, August 4, 2015 / Notices
tkelley on DSK3SPTVN1PROD with NOTICES
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (CP15–523–
000) with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Room 1A, Washington, DC 20426.
Summary of the Proposed Project
Midla proposes to construct, own,
maintain, and operate the Natchez
Pipeline Project consisting of 51.97
miles of 12-inch-diameter pipeline
traversing portions of Franklin,
Catahoula, and Concordia Parishes,
Louisiana and Adams County,
Mississippi, pursuant to Section 7(c) of
the Natural Gas Act and Section 2.1 of
the Stipulation and Agreement
(Settlement) approved in Docket Nos.
RP14–638, et al. on April 16, 2015. The
Natchez Pipeline would have three
anchor shippers: Atmos Energy
Corporation, which serves the cities of
Ferriday, Gilbert, and Wisner,
Louisiana, and the city of Natchez,
Mississippi; the Louisiana Municipal
Gas Authority, serving the municipal
gas systems of Clayton, Jonesville, Sicily
Island, and Vidalia, Louisiana; and
BASF, which has an industrial facility
located near Vidalia, Louisiana.
As part of the Commission Order of
the Settlement, the Commission
approved Midla to abandon about 370
miles of varying diameter pipeline along
with associated laterals from the Desiard
Compressor Station in Ouachita Parish,
Louisiana to a point near Scottlandville
in East Baton Rogue Parish, Louisiana,
either in place, by removal, or by
transfer, subject to certain conditions.
Among the conditions, Midla would
need to continue to serve customers
VerDate Sep<11>2014
18:45 Aug 03, 2015
Jkt 235001
with delivery points from Winnsboro,
Louisiana to the Natchez, Mississippi
area through the Natchez pipeline,
which the Natchez Pipeline Project
would accomplish. Once the Natchez
pipeline is in service, Midla would be
able to abandon its existing pipeline
system.
The Natchez Pipeline Project would
consist of the following facilities:
• 51.97 miles of 12-inch-diameter
pipeline;
• 0.50 mile of 4-inch-diameter
delivery lateral at milepost 46.83 in
Concordia Parish to serve the City of
Vidalia, Louisiana;
• 4 aboveground valve sites;
• 12 meter stations; and
• 2 pig launcher/receivers.1
The general location of the project
facilities is shown in appendix 1.2
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 516.55 acres of
land for the aboveground facilities and
the pipeline, which includes the
pipeline permanent right-of-way,
temporary workspaces, additional
temporary workspaces, above-ground
facilities, contractor yards, and access
roads. Following construction, Midla
would maintain about 193.68 acres for
permanent operation of the project’s
pipeline, aboveground facilities and
access roads; the remaining acreage
would be restored and revert to former
uses. About 41 miles (or 79 percent) of
the proposed pipeline route parallels
existing pipeline, utility, or road rightsof-way.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 3 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
1A
‘‘pig’’ is a tool that the pipeline company
inserts into and pushes through the pipeline for
cleaning the pipeline, conducting internal
inspections, or other purposes.
2 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts.
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.4 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office(s) (SHPO), and to solicit their
4 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
E:\FR\FM\04AUN1.SGM
04AUN1
Federal Register / Vol. 80, No. 149 / Tuesday, August 4, 2015 / Notices
views and those of other government
agencies, interested Indian tribes, and
the public on the project’s potential
effects on historic properties.5 We will
define the project-specific Area of
Potential Effects (APE) in consultation
with the SHPO(s) as the project
develops. On natural gas facility
projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
proposed facilities and the
environmental information provided by
Midla. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Potential impacts on lands under
the Conservation Reserve Program,
administered by the U.S. Department of
Agriculture;
• potential impacts on the Louisiana
black bear; and
• crossing of the Mississippi River.
tkelley on DSK3SPTVN1PROD with NOTICES
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
5 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
18:45 Aug 03, 2015
Jkt 235001
If we publish and distribute the EA,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the ‘‘Document-less
Intervention Guide’’ under the ‘‘e-filing’’
link on the Commission’s Web site.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP15–523). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
46261
Dated: July 24, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–19055 Filed 8–3–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF15–24–000]
WBI Energy Transmission, Inc.; Notice
of Intent To Prepare an Environmental
Assessment for the Planned Demicks
Lake Pipeline Project and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Demicks Lake Pipeline Project
(Project) involving construction and
operation of facilities by WBI Energy
Transmission, Inc (WBI Energy) in
McKenzie County, North Dakota. The
Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before August 27,
2015.
If you sent comments on this project
to the Commission before the opening of
this docket on May 13, 2015, you will
need to file those comments in Docket
No. PF15–24–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
E:\FR\FM\04AUN1.SGM
04AUN1
Agencies
[Federal Register Volume 80, Number 149 (Tuesday, August 4, 2015)]
[Notices]
[Pages 46259-46261]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-19055]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-523-000]
American Midstream, LLC; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Natchez Pipeline Project and
Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Natchez Pipeline Project
involving construction and operation of facilities by American
Midstream, LLC (Midla) in Franklin, Catahoula, and Concordia Parishes,
Louisiana, and Adams County, Mississippi. The Commission will use this
EA in its decision-making process to determine whether the project is
in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before August 24, 2015.
If you sent comments on this project to the Commission before the
opening of this docket on June 29, 2015, you will need to file those
comments in Docket No. CP15-523-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
Midla provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' This fact sheet addresses a number of typically asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff
[[Page 46260]]
available to assist you at (202) 502-8258 or efiling@ferc.gov. Please
carefully follow these instructions so that your comments are properly
recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(CP15-523-000) with your submission: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A,
Washington, DC 20426.
Summary of the Proposed Project
Midla proposes to construct, own, maintain, and operate the Natchez
Pipeline Project consisting of 51.97 miles of 12-inch-diameter pipeline
traversing portions of Franklin, Catahoula, and Concordia Parishes,
Louisiana and Adams County, Mississippi, pursuant to Section 7(c) of
the Natural Gas Act and Section 2.1 of the Stipulation and Agreement
(Settlement) approved in Docket Nos. RP14-638, et al. on April 16,
2015. The Natchez Pipeline would have three anchor shippers: Atmos
Energy Corporation, which serves the cities of Ferriday, Gilbert, and
Wisner, Louisiana, and the city of Natchez, Mississippi; the Louisiana
Municipal Gas Authority, serving the municipal gas systems of Clayton,
Jonesville, Sicily Island, and Vidalia, Louisiana; and BASF, which has
an industrial facility located near Vidalia, Louisiana.
As part of the Commission Order of the Settlement, the Commission
approved Midla to abandon about 370 miles of varying diameter pipeline
along with associated laterals from the Desiard Compressor Station in
Ouachita Parish, Louisiana to a point near Scottlandville in East Baton
Rogue Parish, Louisiana, either in place, by removal, or by transfer,
subject to certain conditions. Among the conditions, Midla would need
to continue to serve customers with delivery points from Winnsboro,
Louisiana to the Natchez, Mississippi area through the Natchez
pipeline, which the Natchez Pipeline Project would accomplish. Once the
Natchez pipeline is in service, Midla would be able to abandon its
existing pipeline system.
The Natchez Pipeline Project would consist of the following
facilities:
51.97 miles of 12-inch-diameter pipeline;
0.50 mile of 4-inch-diameter delivery lateral at milepost
46.83 in Concordia Parish to serve the City of Vidalia, Louisiana;
4 aboveground valve sites;
12 meter stations; and
2 pig launcher/receivers.\1\
---------------------------------------------------------------------------
\1\ A ``pig'' is a tool that the pipeline company inserts into
and pushes through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------
The general location of the project facilities is shown in appendix
1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 516.55
acres of land for the aboveground facilities and the pipeline, which
includes the pipeline permanent right-of-way, temporary workspaces,
additional temporary workspaces, above-ground facilities, contractor
yards, and access roads. Following construction, Midla would maintain
about 193.68 acres for permanent operation of the project's pipeline,
aboveground facilities and access roads; the remaining acreage would be
restored and revert to former uses. About 41 miles (or 79 percent) of
the proposed pipeline route parallels existing pipeline, utility, or
road rights-of-way.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\3\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\4\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\4\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office(s) (SHPO), and
to solicit their
[[Page 46261]]
views and those of other government agencies, interested Indian tribes,
and the public on the project's potential effects on historic
properties.\5\ We will define the project-specific Area of Potential
Effects (APE) in consultation with the SHPO(s) as the project develops.
On natural gas facility projects, the APE at a minimum encompasses all
areas subject to ground disturbance (examples include construction
right-of-way, contractor/pipe storage yards, compressor stations, and
access roads). Our EA for this project will document our findings on
the impacts on historic properties and summarize the status of
consultations under section 106.
---------------------------------------------------------------------------
\5\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the proposed facilities and
the environmental information provided by Midla. This preliminary list
of issues may be changed based on your comments and our analysis.
Potential impacts on lands under the Conservation Reserve
Program, administered by the U.S. Department of Agriculture;
potential impacts on the Louisiana black bear; and
crossing of the Mississippi River.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the ``Document-less Intervention Guide'' under the ``e-filing'' link on
the Commission's Web site. Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP15-
523). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: July 24, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-19055 Filed 8-3-15; 8:45 am]