Natural Gas Pipeline Company of America, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Chicago Market Expansion Project, and Request for Comments on Environmental Issues, 43074-43076 [2015-17806]

Download as PDF asabaliauskas on DSK5VPTVN1PROD with NOTICES 43074 Federal Register / Vol. 80, No. 139 / Tuesday, July 21, 2015 / Notices near the City of Easton, Northampton County, Pennsylvania. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Chain Dam Hydroelectric Project would consist of the following: (1) An existing 20-foothigh concrete gravity dam with a 690foot-long spillway; (2) an existing impoundment having a surface area of approximately 300 acres and a storage capacity of 1,200 acre-feet at an elevation of 190 feet mean sea level (msl); (2) three channels, each with a very low head (VLH) 500-kilowatt (kW) turbine-generator unit, with a maximum generating capacity of 1,500 kW, with a maximum hydraulic capacity of 2,300 cubic feet per second under a net head of 13.5 feet, (3) three new, heavy flotsam racks; (4) a crest-mounted walkway carrying hydraulic and electrical conduits from the VLH turbines to a new powerhouse; and (5) a 280-footlong 12.42/7.2 kilovolt primary transmission line. The estimated annual generation of the proposed project would be 7,880,000 kilowatt-hours. Applicant Contact: Mr. Ralph J. Jones, Siting Renewables, LLC, 1800 Rt. 34, Suite 101, Wall, NJ 07719; phone: (855) 946–7652. FERC Contact: Monir Chowdhury; phone: (202) 502–6736. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. VerDate Sep<11>2014 17:58 Jul 20, 2015 Jkt 235001 The first page of any filing should include docket number P–14675–000. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14675) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: July 14, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–17790 Filed 7–20–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–505–000] Natural Gas Pipeline Company of America, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Chicago Market Expansion Project, and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Chicago Market Expansion Project (Project) involving construction and operation of facilities by Natural Gas Pipeline Company of America, LLC (Natural) in Livingston County, Illinois. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the Project. You can make a difference by providing us with your specific comments or concerns about the Project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before August 9, 2015. If you sent comments on this Project to the Commission before the opening of this docket on June 1, 2015, you will need to file those comments in Docket PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 No. CP15–505–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this Project. State and local government representatives should notify their constituents of this proposed Project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a Natural representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the Project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. Natural provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). Public Participation For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’ as the filing type; or (3) You can file a paper copy of your comments by mailing them to the E:\FR\FM\21JYN1.SGM 21JYN1 Federal Register / Vol. 80, No. 139 / Tuesday, July 21, 2015 / Notices following address. Be sure to reference the Project docket number (CP15–505– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Summary of the Proposed Project Natural proposes to construct and operate a new compressor station and associated facilities in Livingston County, Illinois. Specifically, Natural proposes to construct and operate one new 30,000 horsepower compressor station with suction and discharge station interconnect piping; and ancillary facilities. The Project would provide about 238,000 dekatherms of incremental northbound firm transportation capacity to the city of Chicago, Illinois and neighboring areas. The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction Construction of the proposed facilities would disturb about 21 acres of land of which 19.2 acres would remain as the permanent facility following construction. The remaining 1.8 acres consists of temporary workspace necessary to accommodate construction of the Project. The temporary workspace would be restored to its previous land use and maintained in its preconstruction condition. The EA Process asabaliauskas on DSK5VPTVN1PROD with NOTICES The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. The NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. VerDate Sep<11>2014 17:58 Jul 20, 2015 Jkt 235001 In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed Project under these general headings: • Geology and soils; • land use; • water resources, fisheries, and wetlands; • cultural resources; • vegetation and wildlife; • air quality and noise; • endangered and threatened species; • public safety; and • cumulative impacts. We will also evaluate reasonable alternatives to the proposed Project or portions of the Project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary (for directions on the use of eLibrary, please see the additional Information Section on page 6). Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this Project to formally cooperate with us in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultations with the Illinois State Historic Preservation Office (SHPO), and to solicit its views and those of other government agencies, interested Indian tribes, and the public on the Project’s potential effects on 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, part 1501.6. PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 43075 historic properties.4 We will define the Project-specific Area of Potential Effects (APE) in consultation with the SHPO as the Project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this Project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Indian tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for Project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed Project. Copies of the EA will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. E:\FR\FM\21JYN1.SGM 21JYN1 43076 Federal Register / Vol. 80, No. 139 / Tuesday, July 21, 2015 / Notices intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘Document’s & Filings’’ link. Click on the eLibrary link, click on General Search and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP15–505). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: July 9, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–17806 Filed 7–20–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission asabaliauskas on DSK5VPTVN1PROD with NOTICES [Docket No. CP15–18–000] Eastern Shore Natural Gas Company; Supplemental Notice of Intent To Prepare an Environmental Assessment for the Proposed White Oak Mainline Expansion Project and Request for Comments on Environmental Issues On January 22, 2015, the Federal Energy Regulatory Commission (FERC or Commission) issued in Docket No. CP15–18–000 a Notice of Intent to Prepare an Environmental Assessment for the Proposed White Oak Mainline Expansion Project and Request for VerDate Sep<11>2014 17:58 Jul 20, 2015 Jkt 235001 Comments on Environmental Issues (NOI). Since its application in the above-referenced docket, FERC staff has requested information regarding the proposed facilities, as well as alternative routes to the proposed Kemblesville Loop 1 in Chester County, Pennsylvania. On June 2, 2015, FERC staff also conducted an onsite environmental review of the proposed pipeline and several alternative routes. In response to data requested by FERC staff, Eastern Shore Natural Gas Company (Eastern Shore) provided information on four alternative pipeline routes. FERC staff is further evaluating Alternative Route 2 as described in Eastern Shore’s April 21, 2015 response. This Supplemental Notice is being issued to seek comments on Alternative Route 2 and opens a new scoping period for interested parties to file comments on environmental issues specific to this alternative route. The January 22, 2015 NOI announced that the FERC staff will prepare an environmental assessment (EA) to address the environmental impacts of the White Oak Mainline Expansion Project (Project). Please refer to the NOI for more information about the overall facilities proposed by Eastern Shore in Pennsylvania and Delaware, and FERC staff’s EA process. The Commission will use the EA in its decision-making process to determine whether the Project is in the public convenience and necessity. The Commission previously solicited public input on the Project in the beginning of 2015. We 2 are now specifically seeking comments on the Kemblesville Loop Alternative Route 2 to help the Commission staff evaluate the environmental impact associated with the alternative and how that compares to the currently proposed route. Please note that this special scoping period will close on August 8, 2015. This Supplemental Notice is being sent to the Commission’s current environmental mailing list for this Project, including new landowners that would be affected by the alternative pipeline route. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission 1 A pipeline loop is constructed parallel to an existing pipeline to increase capacity. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 approves the Project, that approval conveys with it the right of eminent domain. Therefore, if the easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility on My Land? What Do I Need To Know?’’ is available for viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. Public Participation For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission will provide equal consideration to all comments received, whether filed in written form or provided verbally. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing;’’ or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Summary of Kemblesville Loop Alternative Route 2 The Kemblesville Loop Alternative Route 2 would be collocated entirely with the existing right-of-way for Eastern Shore’s White Oak mainline E:\FR\FM\21JYN1.SGM 21JYN1

Agencies

[Federal Register Volume 80, Number 139 (Tuesday, July 21, 2015)]
[Notices]
[Pages 43074-43076]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-17806]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-505-000]


Natural Gas Pipeline Company of America, LLC; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Chicago Market 
Expansion Project, and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Chicago Market Expansion 
Project (Project) involving construction and operation of facilities by 
Natural Gas Pipeline Company of America, LLC (Natural) in Livingston 
County, Illinois. The Commission will use this EA in its decision-
making process to determine whether the project is in the public 
convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the Project. You can make a difference by providing us with 
your specific comments or concerns about the Project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before August 9, 2015.
    If you sent comments on this Project to the Commission before the 
opening of this docket on June 1, 2015, you will need to file those 
comments in Docket No. CP15-505-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this Project. State and local government 
representatives should notify their constituents of this proposed 
Project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a Natural 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the Project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Natural provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the

[[Page 43075]]

following address. Be sure to reference the Project docket number 
(CP15-505-000) with your submission:
    Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
888 First Street NE., Room 1A, Washington, DC 20426.

Summary of the Proposed Project

    Natural proposes to construct and operate a new compressor station 
and associated facilities in Livingston County, Illinois. Specifically, 
Natural proposes to construct and operate one new 30,000 horsepower 
compressor station with suction and discharge station interconnect 
piping; and ancillary facilities. The Project would provide about 
238,000 dekatherms of incremental northbound firm transportation 
capacity to the city of Chicago, Illinois and neighboring areas.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 21 
acres of land of which 19.2 acres would remain as the permanent 
facility following construction. The remaining 1.8 acres consists of 
temporary workspace necessary to accommodate construction of the 
Project. The temporary workspace would be restored to its previous land 
use and maintained in its pre-construction condition.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. The NEPA also requires 
us \2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed Project under these 
general headings:
 Geology and soils;
 land use;
 water resources, fisheries, and wetlands;
 cultural resources;
 vegetation and wildlife;
 air quality and noise;
 endangered and threatened species;
 public safety; and
 cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
Project or portions of the Project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary (for directions 
on the use of eLibrary, please see the additional Information Section 
on page 6). Depending on the comments received during the scoping 
process, we may also publish and distribute the EA to the public for an 
allotted comment period. We will consider all comments on the EA before 
making our recommendations to the Commission. To ensure we have the 
opportunity to consider and address your comments, please carefully 
follow the instructions in the Public Participation section, beginning 
on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this Project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultations 
with the Illinois State Historic Preservation Office (SHPO), and to 
solicit its views and those of other government agencies, interested 
Indian tribes, and the public on the Project's potential effects on 
historic properties.\4\ We will define the Project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the Project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this Project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Indian tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for Project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed Project.
    Copies of the EA will be sent to the environmental mailing list for 
public review and comment. If you would prefer to receive a paper copy 
of the document instead of the CD version or would like to remove your 
name from the mailing list, please return the attached Information 
Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an

[[Page 43076]]

intervenor are in the User's Guide under the ``e-filing'' link on the 
Commission's Web site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``Document's & Filings'' link. 
Click on the eLibrary link, click on General Search and enter the 
docket number, excluding the last three digits in the Docket Number 
field (i.e., CP15-505). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: July 9, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-17806 Filed 7-20-15; 8:45 am]
 BILLING CODE 6717-01-P