Application to Export Electric Energy; Elan Energy Services, LLC, 41029-41030 [2015-17082]
Download as PDF
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 134 / Tuesday, July 14, 2015 / Notices
outside of the Scenic Area as is the case
with the Wind Project—warrants
thoughtful and careful consideration of
its potential to impact scenic resources.
BPA believes that such consideration
has been amply demonstrated in this
case, and that definite and effective
action has been taken by the State of
Washington to reasonably help protect
views as a result of this consideration.
Furthermore, BPA agrees with the
Governor that the state-approved Wind
Project strikes an effective balance
between minimizing visual impacts
while still carrying out the public
interest of the State of Washington in
approving sites for alternative energy
facilities.
The total cost of the BPA
interconnection facilities is estimated at
$12.6 million. All costs associated with
these facilities will be advance funded
by WRE and administration of contracts
with WRE will follow normal,
established procedures. In accordance
with BPA’s open access transmission
tariff, WRE will be eligible to receive
transmission credits for any portion of
the interconnection facilities that
constitute network upgrades. BPA
believes that this approach provides for
both cost and administrative
efficiencies.
Finally, in deciding to grant the
requested interconnection, BPA believes
it is being appropriately respectful of
state authorities concerning the siting of
non-federal generation projects. As has
been mentioned previously in this
Record of Decision, BPA does not have
siting authority or regulatory
jurisdiction over these facilities. That is
the purview of appropriate state and
local entities, in this case Washington
EFSEC and, ultimately, the Washington
Governor. BPA notes that the siting
process conducted by the State of
Washington for the Wind Project was
both lengthy and extremely thorough,
and addressed many of the same
environmental issues also considered in
the Final EIS for the Project. BPA also
notes that the State of Washington
decided to approve construction and
operation of the Wind Project on the
basis of the siting process and Final EIS.
Finally, BPA notes that this approval
was upheld by the Washington Supreme
Court in a legal challenge of the siting
process brought against the State of
Washington. In light of this, granting the
requested interconnection provides the
appropriate comity to the State of
Washington’s legally executed overall
authorities concerning the siting of the
Wind Project.
VerDate Sep<11>2014
19:09 Jul 13, 2015
Jkt 235001
Mitigation
41029
electronic mail to Electricity.Exports@
All the mitigation measures described hq.doe.gov, or by facsimile to 202–586–
in the Draft EIS and updated in the Final 8008.
SUPPLEMENTARY INFORMATION: Exports of
EIS have been adopted. A complete list
electricity from the United States to a
of these measures can be found in the
foreign country are regulated by the
Mitigation Action Plan. WRE will be
Department of Energy (DOE) pursuant to
responsible for executing mitigation
sections 301(b) and 402(f) of the
measures identified for the Wind
Department of Energy Organization Act
Project, while BPA will be responsible
(42 U.S.C. 7151(b), 7172(f)) and require
for executing the mitigation measures
authorization under section 202(e) of
associated with the BPA
the Federal Power Act (16 U.S.C.
interconnection facilities.
824a(e)).
In addition to identifying mitigation
On June 5, 2015, DOE received an
measures in the EIS, the State of
application from the Applicant for
Washington has included numerous
authority to transmit electric energy
conditions in the Final SCA for the
Wind Project that are intended to ensure from the United States to Mexico as a
power marketer for a five-year term
that the Wind Project is built and
using existing international
operated in a way that preserves and
protects the quality of the environment. transmission facilities. The Applicant
will register as a Power Marketer with
As environmental mitigation,
Washington EFSEC has found that these the Texas Public Utilities Commission
(PUCT.) The Applicant will also register
conditions will ensure that the Project
as a Purchasing Selling Entity with the
will produce minimal adverse
Texas Reliability Entity (TRE) and the
environmental effects. WRE will be
North American Electric Reliability
required to comply with these Final
Corporation (NERC).
SCA conditions. As discussed above,
In its application, the Applicant states
the Final SCA is available at https://
that it does not own or control any
www.efsec.wa.gov/whistling
electric generation or transmission
%20ridge.shtml.
facilities, and it does not have a
Issued in Portland, Oregon.
franchised service area. The electric
Dated: June 24, 2015.
energy that the Applicant proposes to
Elliot E. Mainzer,
export to Mexico would be surplus
Administrator and Chief Executive Officer.
energy purchased from third parties
[FR Doc. 2015–17087 Filed 7–13–15; 8:45 am]
such as electric utilities and Federal
power marketing agencies pursuant to
BILLING CODE 6450–01–P
voluntary agreements. The existing
international transmission facilities to
DEPARTMENT OF ENERGY
be utilized by the Applicant have
previously been authorized by
[OE Docket No. EA–413]
Presidential permits issued pursuant to
Executive Order 10485, as amended,
Application to Export Electric Energy;
and are appropriate for open access
Elan Energy Services, LLC
transmission by third parties.
AGENCY: Office of Electricity Delivery
Procedural Matters: Any person
and Energy Reliability, DOE.
desiring to be heard in this proceeding
ACTION: Notice of application.
should file a comment or protest to the
application at the address provided
SUMMARY: Elan Energy Services, LLC
above. Protests should be filed in
(Applicant) has applied for authority to
accordance with Rule 211 of the Federal
transmit electric energy from the United Energy Regulatory Commission’s (FERC)
States to Mexico pursuant to section
Rules of Practice and Procedures (18
202(e) of the Federal Power Act.
CFR 385.211). Any person desiring to
DATES: Comments, protests, or motions
become a party to these proceedings
to intervene must be submitted on or
should file a motion to intervene at the
before August 13, 2015.
above address in accordance with FERC
Rule 214 (18 CFR 385.214). Five copies
ADDRESSES: Comments, protests,
of such comments, protests, or motions
motions to intervene, or requests for
to intervene should be sent to the
more information should be addressed
address provided above on or before the
to: Office of Electricity Delivery and
date listed above.
Energy Reliability, Mail Code: OE–20,
Comments and other filings
U.S. Department of Energy, 1000
concerning the Applicant’s application
Independence Avenue SW.,
to export electric energy to Mexico
Washington, DC 20585–0350. Because
of delays in handling conventional mail, should be clearly marked with OE
Docket No. EA–413. An additional copy
it is recommended that documents be
is to be provided directly to Andrew B.
transmitted by overnight mail, by
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
E:\FR\FM\14JYN1.SGM
14JYN1
41030
Federal Register / Vol. 80, No. 134 / Tuesday, July 14, 2015 / Notices
Young, Mayer Brown LLP, 1999 K Street
NW., Washington, DC 20006.
A final decision will be made on this
application after the environmental
impacts have been evaluated pursuant
to DOE’s National Environmental Policy
Act Implementing Procedures (10 CFR
part 1021) and after a determination is
made by DOE that the proposed action
will not have an adverse impact on the
sufficiency of supply or reliability of the
U.S. electric power supply system.
Copies of this application will be
made available, upon request, for public
inspection and copying at the address
provided above, by accessing the
program Web site at https://energy.gov/
node/11845, or by emailing Angela Troy
at Angela.Troy@hq.doe.gov.
Issued in Washington, DC, on July 7, 2015.
Christopher Lawrence,
Electricity Policy Analyst, Office of Electricity
Delivery and Energy Reliability.
[FR Doc. 2015–17082 Filed 7–13–15; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2464–000]
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Gresham Municipal Utilities; Notice Of
Authorization for Continued Project
Operation
On June 10, 2013 Gresham Municipal
Utilities, licensee for the Weed Dam
Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Weed Dam Hydroelectric Project is
located on Red River, in Shawano
County, Wisconsin.
The license for Project No. 2464 was
issued for a period ending June 30,
2015. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
VerDate Sep<11>2014
19:09 Jul 13, 2015
Jkt 235001
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2464
is issued to the licensee for a period
effective July 1, 2015 through June 30,
2016 or until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before June 30, 2016, notice
is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, Gresham Municipal
Utilities, is authorized to continue
operation of the Weed Dam
Hydroelectric Project, until such time as
the Commission acts on its application
for a subsequent license.
Dated: July 8, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–17223 Filed 7–13–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–524–000]
Florida Gas Transmission Company,
LLC; Notice of Request Under Blanket
Authorization
Take notice that on June 29, 2015,
Florida Gas Transmission Company,
LLC (FGT), 1300 Main St., Houston,
Texas 77002, filed in Docket No. CP15–
524–000, a prior notice request pursuant
to sections 157.205, 157.208(b)/(c), and
157.211(b) of the Commission’s
regulations under the Natural Gas Act
(NGA). FGT seeks authorization to
construct, own and operate a new bidirectional measurement and regulation
station and an interconnection with
Gulfstream Natural Gas System, LLC,
located in Martin County, Florida. FGT
proposes to perform these activities
under its blanket certificate issued in
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
Docket No. CP82–553–000 [21 FERC
¶ 62,235 (1982)], all as more fully set
forth in the application which is on file
with the Commission and open to
public inspection.
The filing may be viewed on the web
at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this
application should be directed to
Stephen Veatch, Senior Director of
Certificates, Florida Gas Transmission
Company, LLC, 1300 Main St., Houston,
Texas, 77002, or by calling (713) 989–
2024 (telephone) or (713) 989–1205 (fax)
stephen.veatch@energytransfer.com.
Any person or the Commission’s Staff
may, within 60 days after the issuance
of the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and, pursuant to section
157.205 of the Commission’s
Regulations under the NGA (18 CFR
157.205) a protest to the request. If no
protest is filed within the time allowed
therefore, the proposed activity shall be
deemed to be authorized effective the
day after the time allowed for protest. If
a protest is filed and not withdrawn
within 30 days after the time allowed
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
E:\FR\FM\14JYN1.SGM
14JYN1
Agencies
[Federal Register Volume 80, Number 134 (Tuesday, July 14, 2015)]
[Notices]
[Pages 41029-41030]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-17082]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[OE Docket No. EA-413]
Application to Export Electric Energy; Elan Energy Services, LLC
AGENCY: Office of Electricity Delivery and Energy Reliability, DOE.
ACTION: Notice of application.
-----------------------------------------------------------------------
SUMMARY: Elan Energy Services, LLC (Applicant) has applied for
authority to transmit electric energy from the United States to Mexico
pursuant to section 202(e) of the Federal Power Act.
DATES: Comments, protests, or motions to intervene must be submitted on
or before August 13, 2015.
ADDRESSES: Comments, protests, motions to intervene, or requests for
more information should be addressed to: Office of Electricity Delivery
and Energy Reliability, Mail Code: OE-20, U.S. Department of Energy,
1000 Independence Avenue SW., Washington, DC 20585-0350. Because of
delays in handling conventional mail, it is recommended that documents
be transmitted by overnight mail, by electronic mail to
Electricity.Exports@hq.doe.gov, or by facsimile to 202-586-8008.
SUPPLEMENTARY INFORMATION: Exports of electricity from the United
States to a foreign country are regulated by the Department of Energy
(DOE) pursuant to sections 301(b) and 402(f) of the Department of
Energy Organization Act (42 U.S.C. 7151(b), 7172(f)) and require
authorization under section 202(e) of the Federal Power Act (16 U.S.C.
824a(e)).
On June 5, 2015, DOE received an application from the Applicant for
authority to transmit electric energy from the United States to Mexico
as a power marketer for a five-year term using existing international
transmission facilities. The Applicant will register as a Power
Marketer with the Texas Public Utilities Commission (PUCT.) The
Applicant will also register as a Purchasing Selling Entity with the
Texas Reliability Entity (TRE) and the North American Electric
Reliability Corporation (NERC).
In its application, the Applicant states that it does not own or
control any electric generation or transmission facilities, and it does
not have a franchised service area. The electric energy that the
Applicant proposes to export to Mexico would be surplus energy
purchased from third parties such as electric utilities and Federal
power marketing agencies pursuant to voluntary agreements. The existing
international transmission facilities to be utilized by the Applicant
have previously been authorized by Presidential permits issued pursuant
to Executive Order 10485, as amended, and are appropriate for open
access transmission by third parties.
Procedural Matters: Any person desiring to be heard in this
proceeding should file a comment or protest to the application at the
address provided above. Protests should be filed in accordance with
Rule 211 of the Federal Energy Regulatory Commission's (FERC) Rules of
Practice and Procedures (18 CFR 385.211). Any person desiring to become
a party to these proceedings should file a motion to intervene at the
above address in accordance with FERC Rule 214 (18 CFR 385.214). Five
copies of such comments, protests, or motions to intervene should be
sent to the address provided above on or before the date listed above.
Comments and other filings concerning the Applicant's application
to export electric energy to Mexico should be clearly marked with OE
Docket No. EA-413. An additional copy is to be provided directly to
Andrew B.
[[Page 41030]]
Young, Mayer Brown LLP, 1999 K Street NW., Washington, DC 20006.
A final decision will be made on this application after the
environmental impacts have been evaluated pursuant to DOE's National
Environmental Policy Act Implementing Procedures (10 CFR part 1021) and
after a determination is made by DOE that the proposed action will not
have an adverse impact on the sufficiency of supply or reliability of
the U.S. electric power supply system.
Copies of this application will be made available, upon request,
for public inspection and copying at the address provided above, by
accessing the program Web site at https://energy.gov/node/11845, or by
emailing Angela Troy at Angela.Troy@hq.doe.gov.
Issued in Washington, DC, on July 7, 2015.
Christopher Lawrence,
Electricity Policy Analyst, Office of Electricity Delivery and Energy
Reliability.
[FR Doc. 2015-17082 Filed 7-13-15; 8:45 am]
BILLING CODE 6450-01-P