Millennium Pipeline Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Valley Lateral Project, and Request for Comments on Environmental Issues, 40058-40060 [2015-16998]
Download as PDF
40058
Federal Register / Vol. 80, No. 133 / Monday, July 13, 2015 / Notices
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
Motions to intervene, protests and
comments may be filed electronically
via the internet in lieu of paper; see, 18
CFR 385.2001(a) (1) (iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link. The
Commission strongly encourages
electronic filings.
Comment Date: July 22, 2015.
Dated: July 1, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–16999 Filed 7–10–15; 8:45 am]
asabaliauskas on DSK5VPTVN1PROD with NOTICES
BILLING CODE 6717–01P
VerDate Sep<11>2014
19:27 Jul 10, 2015
Jkt 235001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF15–23–000]
Millennium Pipeline Company, LLC;
Notice of Intent To Prepare an
Environmental Assessment for the
Planned Valley Lateral Project, and
Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Valley Lateral Project involving
construction and operation of facilities
by Millennium Pipeline Company, LLC
(Millennium) in Orange County, New
York. The Commission will use this EA
in its decision-making process to
determine whether the project is in the
public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before August 5,
2015.
If you sent comments on this project
to the Commission before the opening of
this docket on April 30, 2015, you will
need to file those comments in Docket
No. PF15–23–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (www.ferc.gov). This
fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings.
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov. Please carefully
follow these instructions so that your
comments are properly recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (PF15–23–
000) with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Room 1A, Washington, DC 20426.
Summary of the Planned Project
Millennium plans to construct and
operate approximately 7.8 miles of new
pipeline lateral in Orange County, New
York. The planned pipeline lateral
would provide about 130 million cubic
feet per day of natural gas per day to the
Competitive Power Ventures (CPV)
Valley Energy Center in the Town of
Wawayanda, New York from
Millennium’s existing mainline
pipeline. According to Millennium, the
Valley Lateral Project would supply
E:\FR\FM\13JYN1.SGM
13JYN1
Federal Register / Vol. 80, No. 133 / Monday, July 13, 2015 / Notices
natural gas for generation of up to 650
megawatts of power at the CPV Valley
Energy Center (in development).
The planned Valley Lateral Project
would consist of the following facilities:
• 7.8 miles of pipeline lateral
originating at Millennium’s existing
mainline that would deliver gas to the
CPV Valley Energy Center;
• a pig 1 launcher at the pipeline
origin located wholly within the
permanent pipeline right-of-way; and
• a pig receiver and metering
facilities at the pipeline terminus and
located entirely within the area to be
developed for the CPV Valley Energy
Center.
The general location of the project
facilities is shown in appendix 1.2
Land Requirements for Construction
Construction of the planned pipeline
lateral facilities would occur within a
75- to 135-foot right-of-way. Following
construction, Millennium would
maintain a 50-foot right-of-way for
permanent operation of the project’s
facilities; the remaining acreage would
be restored and revert to former uses.
About 24 percent of the planned
pipeline route parallels existing
pipeline, utility, or road rights-of-way.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us3 to
discover and address concerns the
public may have about proposals. This
process is referred to as scoping. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
asabaliauskas on DSK5VPTVN1PROD with NOTICES
1A
‘‘pig’’ is a tool that the pipeline company
inserts into and pushes through the pipeline for
cleaning the pipeline, conducting internal
inspections, or other purposes.
2 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
VerDate Sep<11>2014
19:27 Jul 10, 2015
Jkt 235001
planned project under these general
headings:
• geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts.
We will also evaluate possible
alternatives to the planned project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Although no formal application has
been filed, we have already initiated our
NEPA review under the Commission’s
pre-filing process. The purpose of the
pre-filing process is to encourage early
involvement of interested stakeholders
and to identify and resolve issues before
the FERC receives an application. As
part of our pre-filing review, we have
begun to contact some federal and state
agencies to discuss their involvement in
the scoping process and the preparation
of the EA.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. We will also publish and
distribute the EA to the public for an
allotted comment period. We will
consider all comments on the EA before
we make our recommendations to the
Commission. To ensure we have the
opportunity to consider and address
your comments, please carefully follow
the instructions in the Public
Participation section, beginning on page
2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues related to this
project to formally cooperate with us in
the preparation of the EA.4 Agencies
that would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
4 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
40059
notice to initiate consultation with the
applicable State Historic Preservation
Office, and to solicit their views and
those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.5 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned project.
Copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
the mailing list, please return the
attached Information Request (appendix
2).
Becoming an Intervenor
Once Millennium files its application
with the Commission, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
5 The Advisory Council on Historic Preservation
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
E:\FR\FM\13JYN1.SGM
13JYN1
40060
Federal Register / Vol. 80, No. 133 / Monday, July 13, 2015 / Notices
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the User’s Guide under
the ‘‘e-filing’’ link on the Commission’s
Web site. Please note that the
Commission will not accept requests for
intervenor status at this time. You must
wait until the Commission receives a
formal application for the project.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search’’ and enter the docket
number, excluding the last three digits
in the Docket Number field (i.e., PF15–
23). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: July 6, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–16998 Filed 7–10–15; 8:45 am]
BILLING CODE 6717–01–P
asabaliauskas on DSK5VPTVN1PROD with NOTICES
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice Of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Numbers: RP15–1077–000.
VerDate Sep<11>2014
19:27 Jul 10, 2015
Jkt 235001
Applicants: Texas Gas Transmission,
LLC.
Description: § 4(d) rate filing per
154.204: Remove References to Expired
Operating Lease to be effective 4/1/
2015.
Filed Date: 6/24/15.
Accession Number: 20150624–5059.
Comments Due: 5 p.m. ET 7/6/15.
Docket Numbers: RP15–1078–000.
Applicants: Barclays Bank PLC.
Description: Petition for Temporary
Waiver of Commission Capacity Release
Regulations and Related Tariff
Provisions and Request for Expedited
Action of Barclays Bank PLC under
RP15–1078.
Filed Date: 6/24/15.
Accession Number: 20150624–5160.
Comments Due: 5 p.m. ET 7/1/15.
Docket Numbers: RP15–1079–000.
Applicants: Algonquin Gas
Transmission, LLC.
Description: § 4(d) rate filing per
154.204: BBPC 2015–07–01 Releases to
EDF Trading to be effective 7/1/2015.
Filed Date: 6/25/15.
Accession Number: 20150625–5022.
Comments Due: 5 p.m. ET 7/7/15.
Docket Numbers: RP15–1080–000.
Applicants: Northern Natural Gas
Company.
Description: § 4(d) rate filing per
154.204: 20150625 Negotiated Rate to be
effective 7/1/2015.
Filed Date: 6/25/15.
Accession Number: 20150625–5025.
Comments Due: 5 p.m. ET 7/7/15.
Docket Numbers: RP15–1081–000.
Applicants: Kern River Gas
Transmission Company.
Description: § 4(d) rate filing per
154.204: 2015 Enserco to Twin Eagle to
be effective 7/1/2015.
Filed Date: 6/25/15.
Accession Number: 20150625–5034.
Comments Due: 5 p.m. ET 7/7/15.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
§ 385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
Dated: June 25, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–16989 Filed 7–10–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–499–000]
Texas Eastern Transmission, LP;
Notice of Intent to Prepare An
Environmental Assessment for the
Proposed South Texas Expansion
Project, And Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the South Texas Expansion Project
(Project) involving construction and
operation of facilities by Texas Eastern
Transmission, LP (Texas Eastern) in
Nueces, Matagorda, Brazoria, Chambers,
and Orange Counties, Texas. The
Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
You can make a difference by providing
us with your specific comments or
concerns about the Project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before July 30,
2015.
If you sent comments on this project
to the Commission before the opening of
this docket on May 22, 2015, you will
need to file those comments in Docket
No. CP15–499–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this Project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a Texas Eastern representative
E:\FR\FM\13JYN1.SGM
13JYN1
Agencies
[Federal Register Volume 80, Number 133 (Monday, July 13, 2015)]
[Notices]
[Pages 40058-40060]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-16998]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF15-23-000]
Millennium Pipeline Company, LLC; Notice of Intent To Prepare an
Environmental Assessment for the Planned Valley Lateral Project, and
Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Valley Lateral Project
involving construction and operation of facilities by Millennium
Pipeline Company, LLC (Millennium) in Orange County, New York. The
Commission will use this EA in its decision-making process to determine
whether the project is in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before August 5, 2015.
If you sent comments on this project to the Commission before the
opening of this docket on April 30, 2015, you will need to file those
comments in Docket No. PF15-23-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses
a number of typically asked questions, including the use of eminent
domain and how to participate in the Commission's proceedings.
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(PF15-23-000) with your submission: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A,
Washington, DC 20426.
Summary of the Planned Project
Millennium plans to construct and operate approximately 7.8 miles
of new pipeline lateral in Orange County, New York. The planned
pipeline lateral would provide about 130 million cubic feet per day of
natural gas per day to the Competitive Power Ventures (CPV) Valley
Energy Center in the Town of Wawayanda, New York from Millennium's
existing mainline pipeline. According to Millennium, the Valley Lateral
Project would supply
[[Page 40059]]
natural gas for generation of up to 650 megawatts of power at the CPV
Valley Energy Center (in development).
The planned Valley Lateral Project would consist of the following
facilities:
7.8 miles of pipeline lateral originating at Millennium's
existing mainline that would deliver gas to the CPV Valley Energy
Center;
a pig \1\ launcher at the pipeline origin located wholly
within the permanent pipeline right-of-way; and
---------------------------------------------------------------------------
\1\ A ``pig'' is a tool that the pipeline company inserts into
and pushes through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------
a pig receiver and metering facilities at the pipeline
terminus and located entirely within the area to be developed for the
CPV Valley Energy Center.
The general location of the project facilities is shown in appendix
1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned pipeline lateral facilities would occur
within a 75- to 135-foot right-of-way. Following construction,
Millennium would maintain a 50-foot right-of-way for permanent
operation of the project's facilities; the remaining acreage would be
restored and revert to former uses. About 24 percent of the planned
pipeline route parallels existing pipeline, utility, or road rights-of-
way.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires
us\3\ to discover and address concerns the public may have about
proposals. This process is referred to as scoping. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the planned project under these
general headings:
geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
We will also evaluate possible alternatives to the planned project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before
the FERC receives an application. As part of our pre-filing review, we
have begun to contact some federal and state agencies to discuss their
involvement in the scoping process and the preparation of the EA.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. We will also
publish and distribute the EA to the public for an allotted comment
period. We will consider all comments on the EA before we make our
recommendations to the Commission. To ensure we have the opportunity to
consider and address your comments, please carefully follow the
instructions in the Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues
related to this project to formally cooperate with us in the
preparation of the EA.\4\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\4\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office, and to solicit
their views and those of other government agencies, interested Indian
tribes, and the public on the project's potential effects on historic
properties.\5\ We will define the project-specific Area of Potential
Effects (APE) in consultation with the SHPO as the project develops. On
natural gas facility projects, the APE at a minimum encompasses all
areas subject to ground disturbance (examples include construction
right-of-way, contractor/pipe storage yards, compressor stations, and
access roads). Our EA for this project will document our findings on
the impacts on historic properties and summarize the status of
consultations under section 106.
---------------------------------------------------------------------------
\5\ The Advisory Council on Historic Preservation regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
planned project.
Copies of the EA will be sent to the environmental mailing list for
public review and comment. If you would prefer to receive a paper copy
of the document instead of the CD version or would like to remove your
name from the mailing list, please return the attached Information
Request (appendix 2).
Becoming an Intervenor
Once Millennium files its application with the Commission, you may
want to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able
[[Page 40060]]
to file briefs, appear at hearings, and be heard by the courts if they
choose to appeal the Commission's final ruling. An intervenor formally
participates in the proceeding by filing a request to intervene.
Instructions for becoming an intervenor are in the User's Guide under
the ``e-filing'' link on the Commission's Web site. Please note that
the Commission will not accept requests for intervenor status at this
time. You must wait until the Commission receives a formal application
for the project.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., PF15-
23). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: July 6, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-16998 Filed 7-10-15; 8:45 am]