Dominion Transmission, Inc.; Notice of Availability of the Environmental Assessment for the Proposed St. Charles Transportation and Keys Energy Projects, 36803 [2015-15650]

Download as PDF Federal Register / Vol. 80, No. 123 / Friday, June 26, 2015 / Notices necessary to make any changes to the collection at this time. Comments: Comments are invited on: (1) whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: June 19, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–15652 Filed 6–25–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. CP15–22–000; CP15–24–000] tkelley on DSK3SPTVN1PROD with NOTICES Dominion Transmission, Inc.; Notice of Availability of the Environmental Assessment for the Proposed St. Charles Transportation and Keys Energy Projects The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the St. Charles Transportation and Keys Energy Projects (Projects), proposed by Dominion Transmission, Inc. (Dominion) in the above-referenced docket. The projects involve installation of two new compressors at the Pleasant Valley Compressor Station in Fairfax County, VA and appurtenant facilities that would provide incremental firm transportation to proposed power plants in Charles and Prince George’s Counties, Maryland, respectively. The EA assesses the potential environmental effects of the construction and operation of the Projects in accordance with the requirements of the National Environmental Policy Act (NEPA). The FERC staff concludes that approval of the proposed project, with appropriate mitigating measures, would not constitute a major federal action significantly affecting the quality of the human environment. The FERC staff mailed copies of the EA to federal, state, and local VerDate Sep<11>2014 18:15 Jun 25, 2015 Jkt 235001 government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; newspapers and libraries in the project area; and parties to this proceeding. In addition, the EA is available for public viewing on the FERC’s Web site (www.ferc.gov) using the eLibrary link. A limited number of copies of the EA are available for distribution and public inspection at: Federal Energy Regulatory Commission, Public Reference Room, 888 First Street NE., Room 2A, Washington, DC 20426, (202) 502–8371. Any person wishing to comment on the EA may do so. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that the Commission has the opportunity to consider your comments prior to making its decision on this project, it is important that we receive your comments in Washington, DC on or before July 20, 2015. For your convenience, there are three methods you can use to file your comments to the Commission. In all instances, please reference the project docket numbers (CP15–22–000 or CP15– 24–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can also file your comments electronically using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. PO 00000 Frm 00047 Fmt 4703 Sfmt 4703 36803 Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission’s Rules of Practice and Procedures (18 CFR 385.214).1 Only intervenors have the right to seek rehearing of the Commission’s decision. The Commission grants affected landowners and others with environmental concerns intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which no other party can adequately represent. Simply filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search,’’ and enter the docket number excluding the last three digits in the Docket Number field (i.e., CP15–22– 000 or CP15–24–000). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Dated: June 19, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–15650 Filed 6–25–15; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [ER–FRL–9021–6] Environmental Impact Statements; Notice of Availability Responsible Agency: Office of Federal Activities, General Information (202) 1 See the previous discussion on the methods for filing comments. E:\FR\FM\26JNN1.SGM 26JNN1

Agencies

[Federal Register Volume 80, Number 123 (Friday, June 26, 2015)]
[Notices]
[Page 36803]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-15650]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP15-22-000; CP15-24-000]


Dominion Transmission, Inc.; Notice of Availability of the 
Environmental Assessment for the Proposed St. Charles Transportation 
and Keys Energy Projects

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the St. 
Charles Transportation and Keys Energy Projects (Projects), proposed by 
Dominion Transmission, Inc. (Dominion) in the above-referenced docket. 
The projects involve installation of two new compressors at the 
Pleasant Valley Compressor Station in Fairfax County, VA and 
appurtenant facilities that would provide incremental firm 
transportation to proposed power plants in Charles and Prince George's 
Counties, Maryland, respectively.
    The EA assesses the potential environmental effects of the 
construction and operation of the Projects in accordance with the 
requirements of the National Environmental Policy Act (NEPA). The FERC 
staff concludes that approval of the proposed project, with appropriate 
mitigating measures, would not constitute a major federal action 
significantly affecting the quality of the human environment.
    The FERC staff mailed copies of the EA to federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners and other interested individuals and 
groups; newspapers and libraries in the project area; and parties to 
this proceeding. In addition, the EA is available for public viewing on 
the FERC's Web site (www.ferc.gov) using the eLibrary link. A limited 
number of copies of the EA are available for distribution and public 
inspection at: Federal Energy Regulatory Commission, Public Reference 
Room, 888 First Street NE., Room 2A, Washington, DC 20426, (202) 502-
8371.
    Any person wishing to comment on the EA may do so. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
The more specific your comments, the more useful they will be. To 
ensure that the Commission has the opportunity to consider your 
comments prior to making its decision on this project, it is important 
that we receive your comments in Washington, DC on or before July 20, 
2015.
    For your convenience, there are three methods you can use to file 
your comments to the Commission. In all instances, please reference the 
project docket numbers (CP15-22-000 or CP15-24-000) with your 
submission. The Commission encourages electronic filing of comments and 
has expert staff available to assist you at (202) 502-8258 or 
efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.
    Any person seeking to become a party to the proceeding must file a 
motion to intervene pursuant to Rule 214 of the Commission's Rules of 
Practice and Procedures (18 CFR 385.214).\1\ Only intervenors have the 
right to seek rehearing of the Commission's decision. The Commission 
grants affected landowners and others with environmental concerns 
intervenor status upon showing good cause by stating that they have a 
clear and direct interest in this proceeding which no other party can 
adequately represent. Simply filing environmental comments will not 
give you intervenor status, but you do not need intervenor status to 
have your comments considered.
---------------------------------------------------------------------------

    \1\ See the previous discussion on the methods for filing 
comments.
---------------------------------------------------------------------------

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP15-
22-000 or CP15-24-000). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: June 19, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-15650 Filed 6-25-15; 8:45 am]
 BILLING CODE 6717-01-P