PacifiCorp Energy; Notice of Intent To Prepare a Draft and Final Environmental Assessment and Revised Procedural Schedule, 36328 [2015-15490]
Download as PDF
36328
Federal Register / Vol. 80, No. 121 / Wednesday, June 24, 2015 / Notices
Filed Date: 6/1/15.
Accession Number: 20150601–5402.
Comments Due: 5 p.m. ET 6/19/15.
Docket Numbers: RP15–1052–001.
Applicants: Discovery Gas
Transmission LLC.
Description: Compliance filing per
154.203: Substitute Order No. 801
Compliance filing (System Map
Migration to Web site) to be effective 7/
9/2015.
Filed Date: 6/15/15.
Accession Number: 20150615–5128.
Comments Due: 5 p.m. ET 6/29/15.
Docket Numbers: RP15–1053–001.
Applicants: Black Marlin Pipeline
Company.
Description: Compliance filing per
154.203: Substitute Order No. 801
Compliance Filing (System Map
Migration to Web site) to be effective 7/
9/2015.
Filed Date: 6/15/15.
Accession Number: 20150615–5226.
Comments Due: 5 p.m. ET 6/29/15.
Any person desiring to protest in any
of the above proceedings must file in
accordance with Rule 211 of the
Commission’s Regulations (18 CFR
385.211) on or before 5:00 p.m. Eastern
time on the specified comment date.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: June 16, 2015.
Kimberly D. Bose,
Secretary.
for the continued operation of the 1.1megawatt Wallowa Falls Hydroelectric
Project (Wallowa Falls Project) No. 308.
On February 10, 2015, PacifiCorp filed
an updated application that included
modifications to its proposed action. On
March 6, 2015, the Commission issued
a Notice of Application Ready for
Environmental Analysis, and Soliciting
Comments, Recommendations,
Preliminary Terms and Conditions, and
Preliminary Fishway Prescriptions (REA
Notice). The REA notice included a
procedural schedule that included
preparation of a single Environmental
Assessment (EA).
Based on the comments received in
response to the REA notice, Commission
staff has determined that its analysis of
the proposed relicensing action will
require preparation of a Draft and Final
EA. A Draft EA will be issued and
circulated for review by all interested
parties. All comments filed on the Draft
EA will be analyzed by staff and
considered in the Final EA. Staff’s
conclusions and recommendations will
be available for the Commission’s
consideration in reaching its final
licensing decision.
The application will be processed
according to the following revised
procedural schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Issue Draft EA ...........
Comments on Draft
EA due.
Modified terms and
conditions due.
Commission issues
Final EA.
Target date
November 2015.
December 2015.
January 2016.
April 2016.
[FR Doc. 2015–15486 Filed 6–23–15; 8:45 am]
Any questions regarding this notice
may be directed to Matt Cutlip at (503)
552–2762, or by email at matt.cutlip@
ferc.gov.
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Dated: June 18, 2015.
Kimberly D. Bose,
Secretary.
Federal Energy Regulatory
Commission
[Project No. 308–007]
[FR Doc. 2015–15490 Filed 6–23–15; 8:45 am]
tkelley on DSK3SPTVN1PROD with NOTICES
PacifiCorp Energy; Notice of Intent To
Prepare a Draft and Final
Environmental Assessment and
Revised Procedural Schedule
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CD15–18–000]
Soldier Canyon Filter Plant; Notice of
Preliminary Determination of a
Qualifying Conduit Hydropower
Facility and Soliciting Comments and
Motions To Intervene
On January 23, 2015, Soldier Canyon
Filter Plant filed a notice of intent to
construct a qualifying conduit
hydropower facility, pursuant to section
30 of the Federal Power Act (FPA), as
amended by section 4 of the
Hydropower Regulatory Efficiency Act
of 2013 (HREA). The proposed Soldier
Canyon Micro Hydro Facility would
have an installed capacity of 100
kilowatts (kW), and would be located
along the existing 36-inch-diameter
Soldier Canyon Pipeline at the Soldier
Canyon Filter Plant. The project would
be located near Fort Collins in Larimer
County, Colorado.
Applicant Contact: Mr. Chris Harris,
General Manager, 4424 Laporte Avenue,
Fort Collins, CO 80521, Phone No. (970)
482–3143.
FERC Contact: Christopher Chaney,
Phone No. (202) 502–6778, email:
christopher.chaney@ferc.gov.
Qualifying Conduit Hydropower
Facility Description: The proposed
project would consist of: (1) A proposed
140-square-foot buried powerhouse; (2)
an approximately 30-foot-long, 16-inchdiameter intake pipe branching off the
36-inch-diameter Soldier Canyon
Pipeline; (3) one 100-kilowatt turbinegenerating unit; (4) an approximately
60-foot-long, 16-inch-diameter discharge
pipe returning water to the 36-inchdiameter Soldier Canyon Pipeline; and
(5) appurtenant facilities. The proposed
project would have an estimated annual
generating capacity of 880 megawatthours.
A qualifying conduit hydropower
facility is one that is determined or
deemed to meet all of the criteria shown
in the table below.
On February 28, 2014, PacifiCorp
Energy (PacifiCorp) filed an application
VerDate Sep<11>2014
16:43 Jun 23, 2015
Jkt 235001
PO 00000
Frm 00013
Fmt 4703
Sfmt 4703
E:\FR\FM\24JNN1.SGM
24JNN1
Agencies
[Federal Register Volume 80, Number 121 (Wednesday, June 24, 2015)]
[Notices]
[Page 36328]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-15490]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 308-007]
PacifiCorp Energy; Notice of Intent To Prepare a Draft and Final
Environmental Assessment and Revised Procedural Schedule
On February 28, 2014, PacifiCorp Energy (PacifiCorp) filed an
application for the continued operation of the 1.1-megawatt Wallowa
Falls Hydroelectric Project (Wallowa Falls Project) No. 308. On
February 10, 2015, PacifiCorp filed an updated application that
included modifications to its proposed action. On March 6, 2015, the
Commission issued a Notice of Application Ready for Environmental
Analysis, and Soliciting Comments, Recommendations, Preliminary Terms
and Conditions, and Preliminary Fishway Prescriptions (REA Notice). The
REA notice included a procedural schedule that included preparation of
a single Environmental Assessment (EA).
Based on the comments received in response to the REA notice,
Commission staff has determined that its analysis of the proposed
relicensing action will require preparation of a Draft and Final EA. A
Draft EA will be issued and circulated for review by all interested
parties. All comments filed on the Draft EA will be analyzed by staff
and considered in the Final EA. Staff's conclusions and recommendations
will be available for the Commission's consideration in reaching its
final licensing decision.
The application will be processed according to the following
revised procedural schedule. Revisions to the schedule may be made as
appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Draft EA............................ November 2015.
Comments on Draft EA due.................. December 2015.
Modified terms and conditions due......... January 2016.
Commission issues Final EA................ April 2016.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Matt Cutlip
at (503) 552-2762, or by email at matt.cutlip@ferc.gov.
Dated: June 18, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-15490 Filed 6-23-15; 8:45 am]
BILLING CODE 6717-01-P