Mountain Village, CO; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene, 35340-35341 [2015-15099]
Download as PDF
35340
Federal Register / Vol. 80, No. 118 / Friday, June 19, 2015 / Notices
TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY—Continued
Description
Satisfies
(Y/N)
FPA 30(a)(3)(C)(ii), as amended by HREA
FPA 30(a)(3)(C)(iii), as amended by
HREA.
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Statutory provision
The facility has an installed capacity that does not exceed 5 megawatts .....................
On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA.
Y
Y
Preliminary Determination: Based
upon the above criteria, Commission
staff preliminarily determines that the
proposal satisfies the requirements for a
qualifying conduit hydropower facility,
which is not required to be licensed or
exempted from licensing.
Comments and Motions to Intervene:
Deadline for filing comments contesting
whether the facility meets the qualifying
criteria is 45 days from the issuance
date of this notice.
Deadline for filing motions to
intervene is 30 days from the issuance
date of this notice.
Anyone may submit comments or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210 and
385.214. Any motions to intervene must
be received on or before the specified
deadline date for the particular
proceeding.
Filing and Service of Responsive
Documents: All filings must (1) bear in
all capital letters the ‘‘COMMENTS
CONTESTING QUALIFICATION FOR A
CONDUIT HYDROPOWER FACILITY’’
or ‘‘MOTION TO INTERVENE,’’ as
applicable; (2) state in the heading the
name of the applicant and the project
number of the application to which the
filing responds; (3) state the name,
address, and telephone number of the
person filing; and (4) otherwise comply
with the requirements of sections
385.2001 through 385.2005 of the
Commission’s regulations.1 All
comments contesting Commission staff’s
preliminary determination that the
facility meets the qualifying criteria
must set forth their evidentiary basis.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and comments using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
1 18
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
A copy of all other filings in reference
to this application must be accompanied
by proof of service on all persons listed
in the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Locations of Notice of Intent: Copies
of the notice of intent can be obtained
directly from the applicant or such
copies can be viewed and reproduced at
the Commission in its Public Reference
Room, Room 2A, 888 First Street NE.,
Washington, DC 20426. The filing may
also be viewed on the web at https://
www.ferc.gov/docs-filing/elibrary.asp
using the ‘‘eLibrary’’ link. Enter the
docket number (e.g., CD15–26–000) in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or email
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659.
Dated: June 15, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–15098 Filed 6–18–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CD15–27–000]
Mountain Village, CO; Notice of
Preliminary Determination of a
Qualifying Conduit Hydropower
Facility and Soliciting Comments and
Motions To Intervene
intent to construct a qualifying conduit
hydropower facility, pursuant to section
30 of the Federal Power Act (FPA), as
amended by section 4 of the
Hydropower Regulatory Efficiency Act
of 2013 (HREA). The proposed Double
Cabins PRV Hydro Project would have
an installed capacity of 5 kilowatts (kW)
and would be located on the existing
water supply pipeline for Mountain
Village, which transports water for
municipal consumption. The project
would be located near Mountain Village
in San Miguel County, Colorado.
Applicant Contact: Finn Kjome,
Director of Public Works, 455 Mountain
Village Blvd., Suite A, Mountain
Village, CO 81435, Phone No. (970)
369–8206.
FERC Contact: Robert Bell, Phone No.
(202) 502–6062, email: robert.bell@
ferc.gov.
Qualifying Conduit Hydropower
Facility Description: The proposed
project would consist of: (1) A proposed
short, 2-inch-diameter intake pipe that
connects to a 10-inch-diameter main
water supply pipe; (2) a proposed
powerhouse that contains one turbinegenerator unit with an installed capacity
of 5 kW; (3) a proposed short 2-inchdiameter exit pipe returning flow to the
main water supply pipe, making the
total bypass approximately 10-feet; and
(5) appurtenant facilities. The proposed
project would have an estimated annual
generating capacity of 10 megawatthours.
A qualifying conduit hydropower
facility is one that is determined or
deemed to meet all of the criteria shown
in the table below.
On June 3, 2015, the town of
Mountain Village, CO filed a notice of
CFR 385.2001–2005 (2014).
VerDate Sep<11>2014
19:33 Jun 18, 2015
Jkt 235001
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
E:\FR\FM\19JNN1.SGM
19JNN1
Federal Register / Vol. 80, No. 118 / Friday, June 19, 2015 / Notices
35341
TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
Statutory
provision
FPA 30(a)(3)(A), as amended
by HREA.
asabaliauskas on DSK5VPTVN1PROD with NOTICES
FPA 30(a)(3)(C)(i), as amended
by HREA.
FPA 30(a)(3)(C)(ii), as amended
by HREA.
FPA 30(a)(3)(C)(iii), as amended by HREA.
Description
Satisfies
(Y/N)
The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity.
The facility is constructed, operated, or maintained for the generation of electric power and
uses for such generation only the hydroelectric potential of a non-federally owned conduit.
The facility has an installed capacity that does not exceed 5 megawatts .....................................
Y
On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA.
Preliminary Determination: Based
upon the above criteria, Commission
staff preliminarily determines that the
proposal satisfies the requirements for a
qualifying conduit hydropower facility,
which is not required to be licensed or
exempted from licensing.
Comments and Motions to Intervene:
Deadline for filing comments contesting
whether the facility meets the qualifying
criteria is 45 days from the issuance
date of this notice.
Deadline for filing motions to
intervene is 30 days from the issuance
date of this notice.
Anyone may submit comments or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210 and
385.214. Any motions to intervene must
be received on or before the specified
deadline date for the particular
proceeding.
Filing and Service of Responsive
Documents: All filings must (1) bear in
all capital letters the ‘‘COMMENTS
CONTESTING QUALIFICATION FOR A
CONDUIT HYDROPOWER FACILITY’’
or ‘‘MOTION TO INTERVENE,’’ as
applicable; (2) state in the heading the
name of the applicant and the project
number of the application to which the
filing responds; (3) state the name,
address, and telephone number of the
person filing; and (4) otherwise comply
with the requirements of sections
385.2001 through 385.2005 of the
Commission’s regulations.1 All
comments contesting Commission staff’s
preliminary determination that the
facility meets the qualifying criteria
must set forth their evidentiary basis.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and comments using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
1 18
CFR 385.2001–2005 (2014).
VerDate Sep<11>2014
19:33 Jun 18, 2015
Jkt 235001
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
A copy of all other filings in reference
to this application must be accompanied
by proof of service on all persons listed
in the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Locations of Notice of Intent: Copies
of the notice of intent can be obtained
directly from the applicant or such
copies can be viewed and reproduced at
the Commission in its Public Reference
Room, Room 2A, 888 First Street NE.,
Washington, DC 20426. The filing may
also be viewed on the web at https://
www.ferc.gov/docs-filing/elibrary.asp
using the ‘‘eLibrary’’ link. Enter the
docket number (e.g., CD15–27–000) in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or email
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659.
Dated: June 15, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–15099 Filed 6–18–15; 8:45 am]
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
The Federal Energy Regulatory
Commission (Commission) hereby gives
notice that members of the
Commission’s staff may attend the
following meeting related to the
transmission planning activities of the
Fmt 4703
Sfmt 9990
Y
New York Independent System
Operator, Inc.
The New York Independent System
Operator, Inc. Electric System Planning
Working Group Meeting
June 25, 2015, 10:00 a.m.–4:00 p.m.
(EST)
The above-referenced meeting will be
via web conference and teleconference.
The above-referenced meeting is open
to stakeholders.
Further information may be found at:
https://www.nyiso.com/public/markets_
operations/services/planning/index.jsp.
The discussions at the meeting
described above may address matters at
issue in the following proceedings:
Docket Nos. ER13–102, ER13–1942,
ER13–1946, New York Independent
System Operator, Inc. and New York
Transmission Owners
Docket No. ER13–1926, PJM
Transmission Owners
Docket Nos. ER13–1947, ER13–198, PJM
Interconnection, L.L.C.
Docket Nos. ER13–1957, ER13–193,
ER13–196, ISO New England Inc.
Docket No. ER13–1960, ISO New
England Inc., Participating
Transmission Owners Administrative
Committee, and New England Power
Pool Participants Committee
Dated: June 15, 2015.
Kimberly D. Bose,
Secretary.
Notice of Commission Staff
Attendance
Frm 00043
Y
For more information, contact James
Eason, Office of Energy Market
Regulation, Federal Energy Regulatory
Commission at (202) 502–8622 or
James.Eason@ferc.gov.
DEPARTMENT OF ENERGY
PO 00000
Y
[FR Doc. 2015–15108 Filed 6–18–15; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\19JNN1.SGM
19JNN1
Agencies
[Federal Register Volume 80, Number 118 (Friday, June 19, 2015)]
[Notices]
[Pages 35340-35341]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-15099]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CD15-27-000]
Mountain Village, CO; Notice of Preliminary Determination of a
Qualifying Conduit Hydropower Facility and Soliciting Comments and
Motions To Intervene
On June 3, 2015, the town of Mountain Village, CO filed a notice of
intent to construct a qualifying conduit hydropower facility, pursuant
to section 30 of the Federal Power Act (FPA), as amended by section 4
of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The
proposed Double Cabins PRV Hydro Project would have an installed
capacity of 5 kilowatts (kW) and would be located on the existing water
supply pipeline for Mountain Village, which transports water for
municipal consumption. The project would be located near Mountain
Village in San Miguel County, Colorado.
Applicant Contact: Finn Kjome, Director of Public Works, 455
Mountain Village Blvd., Suite A, Mountain Village, CO 81435, Phone No.
(970) 369-8206.
FERC Contact: Robert Bell, Phone No. (202) 502-6062, email:
robert.bell@ferc.gov.
Qualifying Conduit Hydropower Facility Description: The proposed
project would consist of: (1) A proposed short, 2-inch-diameter intake
pipe that connects to a 10-inch-diameter main water supply pipe; (2) a
proposed powerhouse that contains one turbine-generator unit with an
installed capacity of 5 kW; (3) a proposed short 2-inch-diameter exit
pipe returning flow to the main water supply pipe, making the total
bypass approximately 10-feet; and (5) appurtenant facilities. The
proposed project would have an estimated annual generating capacity of
10 megawatt-hours.
A qualifying conduit hydropower facility is one that is determined
or deemed to meet all of the criteria shown in the table below.
[[Page 35341]]
Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
Satisfies (Y/
Statutory provision Description N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA............ The conduit the facility uses is a tunnel, canal, Y
pipeline, aqueduct, flume, ditch, or similar
manmade water conveyance that is operated for
the distribution of water for agricultural,
municipal, or industrial consumption and not
primarily for the generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA......... The facility is constructed, operated, or Y
maintained for the generation of electric power
and uses for such generation only the
hydroelectric potential of a non-federally owned
conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA........ The facility has an installed capacity that does Y
not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA....... On or before August 9, 2013, the facility is not Y
licensed, or exempted from the licensing
requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------
Preliminary Determination: Based upon the above criteria,
Commission staff preliminarily determines that the proposal satisfies
the requirements for a qualifying conduit hydropower facility, which is
not required to be licensed or exempted from licensing.
Comments and Motions to Intervene: Deadline for filing comments
contesting whether the facility meets the qualifying criteria is 45
days from the issuance date of this notice.
Deadline for filing motions to intervene is 30 days from the
issuance date of this notice.
Anyone may submit comments or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210 and 385.214. Any motions to intervene must be received on or
before the specified deadline date for the particular proceeding.
Filing and Service of Responsive Documents: All filings must (1)
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as
applicable; (2) state in the heading the name of the applicant and the
project number of the application to which the filing responds; (3)
state the name, address, and telephone number of the person filing; and
(4) otherwise comply with the requirements of sections 385.2001 through
385.2005 of the Commission's regulations.\1\ All comments contesting
Commission staff's preliminary determination that the facility meets
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------
\1\ 18 CFR 385.2001-2005 (2014).
---------------------------------------------------------------------------
The Commission strongly encourages electronic filing. Please file
motions to intervene and comments using the Commission's eFiling system
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. A copy of all other filings in
reference to this application must be accompanied by proof of service
on all persons listed in the service list prepared by the Commission in
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
Locations of Notice of Intent: Copies of the notice of intent can
be obtained directly from the applicant or such copies can be viewed
and reproduced at the Commission in its Public Reference Room, Room 2A,
888 First Street NE., Washington, DC 20426. The filing may also be
viewed on the web at https://www.ferc.gov/docs-filing/elibrary.asp using
the ``eLibrary'' link. Enter the docket number (e.g., CD15-27-000) in
the docket number field to access the document. For assistance, call
toll-free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502-8659.
Dated: June 15, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-15099 Filed 6-18-15; 8:45 am]
BILLING CODE 6717-01-P