Standard Format and Content of Transportation Security Plans for Classified Matter Shipments, 32622-32623 [2015-14018]
Download as PDF
32622
Federal Register / Vol. 80, No. 110 / Tuesday, June 9, 2015 / Notices
granting or denying access) is governed
by 10 CFR 2.311.3
I. The Commission expects that the
NRC staff and presiding officers (and
any other reviewing officers) will
consider and resolve requests for access
to SUNSI, and motions for protective
orders, in a timely fashion in order to
minimize any unnecessary delays in
identifying those petitioners who have
standing and who have propounded
contentions meeting the specificity and
basis requirements in 10 CFR part 2.
Attachment 1 to this Order summarizes
the general target schedule for
processing and resolving requests under
these procedures.
It is so ordered.
Dated at Rockville, Maryland, this 20th day
of May, 2015.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE
UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING
Day
Event/Activity
0 ...............
Publication of Federal Register notice of hearing and opportunity to petition for leave to intervene, including order with instructions
for access requests.
Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information: Supporting the standing of a potential party identified by name and address; describing the need for the information in order for the
potential party to participate meaningfully in an adjudicatory proceeding.
Deadline for submitting petition for intervention containing: (i) Demonstration of standing; and (ii) all contentions whose formulation
does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply).
U.S. Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for access
provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs any
party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If
NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation
of redactions or review of redacted documents).
If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party to the
proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a motion
seeking a ruling to reverse the NRC staff’s grant of access.
Deadline for NRC staff reply to motions to reverse NRC staff determination(s).
(Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file
motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure Agreement
for SUNSI.
If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse
determination by the NRC staff.
Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective
order.
Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline.
(Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.
(Answer receipt +7) Petitioner/Intervenor reply to answers.
Decision on contention admission.
10 .............
60 .............
20 .............
25 .............
30 .............
40 .............
A ..............
A + 3 ........
A + 28 ......
A + 53 ......
A + 60 ......
>A + 60 ....
Security Plans for Classified Matter
Shipments.’’ The guide describes a
method that NRC staff considers
acceptable for compliance with the
agency’s regulations with regard to the
development of classified matter
transportation security plans, which
identify the correct measures to protect
classified matter while in transport.
[FR Doc. 2015–12783 Filed 6–8–15; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2014–0081]
Standard Format and Content of
Transportation Security Plans for
Classified Matter Shipments
Nuclear Regulatory
Commission.
ACTION: Regulatory guide; issuance.
tkelley on DSK3SPTVN1PROD with NOTICES
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing a new
Regulatory Guide (RG) 7.13, ‘‘Standard
Format and Content of Transportation
SUMMARY:
3 Requesters should note that the filing
requirements of the NRC’s E-Filing Rule (72 FR
49139; August 28, 2007) apply to appeals of NRC
VerDate Sep<11>2014
17:12 Jun 08, 2015
Jkt 235001
The document will be
available for those who have established
a ‘‘need-to-know’’ and possess access
permission to Official Use Only—
Security Related Information (OUO–
SRI). To obtain the document, contact:
Al Tardiff, Office of Nuclear Security
and Incident Response, telephone: 301–
287–3616 or email: Al.Tardiff@nrc.gov.
ADDRESSES:
staff determinations (because they must be served
on a presiding officer or the Commission, as
PO 00000
Frm 00099
Fmt 4703
Sfmt 4703
Al
Tardiff, Office of Nuclear Security and
Incident Response, telephone: 301–287–
3616, email: Al.Tardiff@nrc.gov, or
Mekonen Bayssie, Office of Nuclear
Regulatory Research, telephone: 301–
251–7489, email: Mekonen.Bayssie@
nrc.gov. U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
FOR FURTHER INFORMATION CONTACT:
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is issuing a new guide in the
NRC’s ‘‘Regulatory Guide’’ series. This
series was developed to describe and
make available to the public information
regarding methods that are acceptable to
the NRC staff for implementing specific
applicable), but not to the initial SUNSI request
submitted to the NRC staff under these procedures.
E:\FR\FM\09JNN1.SGM
09JNN1
Federal Register / Vol. 80, No. 110 / Tuesday, June 9, 2015 / Notices
parts of the agency’s regulations,
techniques that the staff uses in
evaluating specific issues or postulated
events, and data that the staff needs in
its review of applications for permits
and licenses.
Regulatory guide RG 7.13 is withheld
from public disclosure but is available
to those affected licensees and cleared
stakeholders who can or have
demonstrated a need to know. The
‘‘Backfitting and Issue Finality’’ section
describes previously issued guidance on
this subject, which is entitled, Interim
Staff Guidance (ISG) DSP–ISG–01, Staff
Review Procedure for Transportation
Security Plans for Classified Matter
Shipments (July 7, 2006). This
document also contains OUO–SRI
information.
II. Additional Information
DG–7005, was published in the
Federal Register on April 25, 2014 (79
FR 23015) for a 60-day stakeholders’
comment period. The stakeholders’
comment period closed on June 24,
2014. Stakeholders’ comments on DG–
7005 and the staff responses to the
stakeholders’ comments can be obtained
the individuals listed in the FOR
FURTHER INFORMATION section of this
document.
tkelley on DSK3SPTVN1PROD with NOTICES
III. Congressional Review Act
This regulatory guide is a rule as
defined in the Congressional Review
Act (5 U.S.C. 801–808). However, the
Office of Management and Budget has
not found it to be a major rule as
defined in the Congressional Review
Act.
III. Backfitting and Issue Finality
Issuance of this final regulatory guide
does not constitute backfitting as
defined in 10 CFR 50.109 (the Backfit
Rule) and is not otherwise inconsistent
with the issue finality provisions in 10
CFR part 52. This RG provides guidance
on development of transportation
security plans to protect classified
information while such information is
in transport, in order to meet the
requirements of 10 CFR part 95. The
staff has previously issued guidance on
this subject in DSP–ISG–01, Staff
Review Procedure for Transportation
Security Plans for Classified Matter
Shipments (July 7, 2006). The staff will
use the guidance in the review and
approval of new and amended
transportation security plans submitted
to the NRC. Current licensees with NRCapproved transportation security plans
may continue to use DSP–ISG–01,
which the NRC has found acceptable for
complying with 10 CFR part 95
regulations as long as the licensees do
VerDate Sep<11>2014
17:12 Jun 08, 2015
Jkt 235001
not change their NRC-approved
transportation security plans.
This regulatory guide does not
constitute backfitting as described
above, would not constitute backfitting
under any of the backfitting provisions
in 10 CFR Chapter I, nor would it be
regarded as backfitting under
Commission and Executive Director for
Operations guidance. In addition,
issuance of the RG would not otherwise
be inconsistent with the issue finality
provisions in 10 CFR part 52. The staff’s
position is based upon the following
considerations.
1. Part 95 applies to materials
licensees and other entities transporting
(or placing into transport) classified
security information, and contains
requirements governing such transport.
Although some of these materials
licensees are protected by backfitting or
issue finality provisions in 10 CFR part
52, these backfitting and issue finality
protections do not extend to the
procedures governing transport of
classified information. For example,
under the definition of backfitting in 10
CFR 50.109(a)(1), protection is afforded
to nuclear power plant licensees against
changes in, or new requirements and
guidance on, inter alia, ‘‘procedures or
organization required to . . . operate a
facility.’’ Procedures governing the
transportation of materials off of the
facility site cannot reasonably be viewed
as constituting such facility operating
procedures. The backfitting and issue
finality provisions applicable to other
materials licensees are written in an
analogous fashion. Therefore, changes to
the guidance on compliance with 10
CFR part 95—even if imposed on these
materials licensees who are protected by
backfitting or issue protection
provisions in 10 CFR part 52 (see the
discussion in item 2)—would not
constitute backfitting or a violation of
issue finality provisions under 10 CFR
part 52.
2. Even if the NRC were to conclude
that materials licensees are afforded
backfitting protection with respect to
procedures governing transportation of
classified information, changes in
guidance would not constitute
backfitting as defined in the various
NRC backfitting provisions unless
imposed on materials licensees. As
described earlier, the NRC staff does not
intend to impose or apply the guidance
in this RG to existing licensees who
already have NRC-approved
transportation security plans (the
exception is where a licensee makes
changes to or proposes to amend such
plans; the backfitting and issue finality
implications are discussed in item 3
below). Given this current lack of staff
PO 00000
Frm 00100
Fmt 4703
Sfmt 9990
32623
intention to impose the guidance in this
RG, this would not constitute backfitting
or a violation of issue finality provisions
under 10 CFR part 52. If the staff seeks
to impose a position in the RG 7.13 on
holders of already issued licenses in a
manner which constitutes backfitting or
does not provide issue finality as
described in the applicable issue finality
provision then the staff must make the
showing as set forth in the applicable
backfitting provision or address the
criteria for avoiding issue finality as
described applicable issue finality
provision.
3. A licensing basis change
voluntarily initiated by a licensee is not
considered to be backfitting. In such
cases, the policy considerations
underlying the NRC’s backfitting
provisions, viz. regulatory stability and
predictability concerning the terms of
an NRC approval, are not applicable
where the licensee itself voluntarily
seeks a change to its licensing basis.
This rationale is reflected in a July 14,
2010, letter from the NRC General
Counsel to NEI’s General Counsel
(ADAMS Accession No. ML101960180)
4. Even if the NRC were to conclude
that materials licensees are afforded
backfitting protection with respect to
procedures governing transportation of
classified information, applicants and
potential/future applicants for such
materials licenses are not, with certain
exceptions not relevant here, protected
under either the various NRC backfitting
provisions or the issue finality
provisions under 10 CFR part 52. This
is because neither the backfitting
provisions nor the issue finality
provisions under 10 CFR part 52 were
intended for every NRC action which
substantially changes the expectations
of current and future applicants.
Dated at Rockville, Maryland, this 3rd day
of June, 2015.
For the Nuclear Regulatory Commission.
Harriet Karagiannis,
Acting Chief, Regulatory Guidance and
Generic Issues Branch, Division of
Engineering, Office of Nuclear Regulatory
Research.
[FR Doc. 2015–14018 Filed 6–8–15; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\09JNN1.SGM
09JNN1
Agencies
[Federal Register Volume 80, Number 110 (Tuesday, June 9, 2015)]
[Notices]
[Pages 32622-32623]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-14018]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2014-0081]
Standard Format and Content of Transportation Security Plans for
Classified Matter Shipments
AGENCY: Nuclear Regulatory Commission.
ACTION: Regulatory guide; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing a new
Regulatory Guide (RG) 7.13, ``Standard Format and Content of
Transportation Security Plans for Classified Matter Shipments.'' The
guide describes a method that NRC staff considers acceptable for
compliance with the agency's regulations with regard to the development
of classified matter transportation security plans, which identify the
correct measures to protect classified matter while in transport.
ADDRESSES: The document will be available for those who have
established a ``need-to-know'' and possess access permission to
Official Use Only--Security Related Information (OUO-SRI). To obtain
the document, contact: Al Tardiff, Office of Nuclear Security and
Incident Response, telephone: 301-287-3616 or email:
Al.Tardiff@nrc.gov.
FOR FURTHER INFORMATION CONTACT: Al Tardiff, Office of Nuclear Security
and Incident Response, telephone: 301-287-3616, email:
Al.Tardiff@nrc.gov, or Mekonen Bayssie, Office of Nuclear Regulatory
Research, telephone: 301-251-7489, email: Mekonen.Bayssie@nrc.gov. U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is issuing a new guide in the NRC's ``Regulatory Guide''
series. This series was developed to describe and make available to the
public information regarding methods that are acceptable to the NRC
staff for implementing specific
[[Page 32623]]
parts of the agency's regulations, techniques that the staff uses in
evaluating specific issues or postulated events, and data that the
staff needs in its review of applications for permits and licenses.
Regulatory guide RG 7.13 is withheld from public disclosure but is
available to those affected licensees and cleared stakeholders who can
or have demonstrated a need to know. The ``Backfitting and Issue
Finality'' section describes previously issued guidance on this
subject, which is entitled, Interim Staff Guidance (ISG) DSP-ISG-01,
Staff Review Procedure for Transportation Security Plans for Classified
Matter Shipments (July 7, 2006). This document also contains OUO-SRI
information.
II. Additional Information
DG-7005, was published in the Federal Register on April 25, 2014
(79 FR 23015) for a 60-day stakeholders' comment period. The
stakeholders' comment period closed on June 24, 2014. Stakeholders'
comments on DG-7005 and the staff responses to the stakeholders'
comments can be obtained the individuals listed in the FOR FURTHER
INFORMATION section of this document.
III. Congressional Review Act
This regulatory guide is a rule as defined in the Congressional
Review Act (5 U.S.C. 801-808). However, the Office of Management and
Budget has not found it to be a major rule as defined in the
Congressional Review Act.
III. Backfitting and Issue Finality
Issuance of this final regulatory guide does not constitute
backfitting as defined in 10 CFR 50.109 (the Backfit Rule) and is not
otherwise inconsistent with the issue finality provisions in 10 CFR
part 52. This RG provides guidance on development of transportation
security plans to protect classified information while such information
is in transport, in order to meet the requirements of 10 CFR part 95.
The staff has previously issued guidance on this subject in DSP-ISG-01,
Staff Review Procedure for Transportation Security Plans for Classified
Matter Shipments (July 7, 2006). The staff will use the guidance in the
review and approval of new and amended transportation security plans
submitted to the NRC. Current licensees with NRC-approved
transportation security plans may continue to use DSP-ISG-01, which the
NRC has found acceptable for complying with 10 CFR part 95 regulations
as long as the licensees do not change their NRC-approved
transportation security plans.
This regulatory guide does not constitute backfitting as described
above, would not constitute backfitting under any of the backfitting
provisions in 10 CFR Chapter I, nor would it be regarded as backfitting
under Commission and Executive Director for Operations guidance. In
addition, issuance of the RG would not otherwise be inconsistent with
the issue finality provisions in 10 CFR part 52. The staff's position
is based upon the following considerations.
1. Part 95 applies to materials licensees and other entities
transporting (or placing into transport) classified security
information, and contains requirements governing such transport.
Although some of these materials licensees are protected by backfitting
or issue finality provisions in 10 CFR part 52, these backfitting and
issue finality protections do not extend to the procedures governing
transport of classified information. For example, under the definition
of backfitting in 10 CFR 50.109(a)(1), protection is afforded to
nuclear power plant licensees against changes in, or new requirements
and guidance on, inter alia, ``procedures or organization required to .
. . operate a facility.'' Procedures governing the transportation of
materials off of the facility site cannot reasonably be viewed as
constituting such facility operating procedures. The backfitting and
issue finality provisions applicable to other materials licensees are
written in an analogous fashion. Therefore, changes to the guidance on
compliance with 10 CFR part 95--even if imposed on these materials
licensees who are protected by backfitting or issue protection
provisions in 10 CFR part 52 (see the discussion in item 2)--would not
constitute backfitting or a violation of issue finality provisions
under 10 CFR part 52.
2. Even if the NRC were to conclude that materials licensees are
afforded backfitting protection with respect to procedures governing
transportation of classified information, changes in guidance would not
constitute backfitting as defined in the various NRC backfitting
provisions unless imposed on materials licensees. As described earlier,
the NRC staff does not intend to impose or apply the guidance in this
RG to existing licensees who already have NRC-approved transportation
security plans (the exception is where a licensee makes changes to or
proposes to amend such plans; the backfitting and issue finality
implications are discussed in item 3 below). Given this current lack of
staff intention to impose the guidance in this RG, this would not
constitute backfitting or a violation of issue finality provisions
under 10 CFR part 52. If the staff seeks to impose a position in the RG
7.13 on holders of already issued licenses in a manner which
constitutes backfitting or does not provide issue finality as described
in the applicable issue finality provision then the staff must make the
showing as set forth in the applicable backfitting provision or address
the criteria for avoiding issue finality as described applicable issue
finality provision.
3. A licensing basis change voluntarily initiated by a licensee is
not considered to be backfitting. In such cases, the policy
considerations underlying the NRC's backfitting provisions, viz.
regulatory stability and predictability concerning the terms of an NRC
approval, are not applicable where the licensee itself voluntarily
seeks a change to its licensing basis. This rationale is reflected in a
July 14, 2010, letter from the NRC General Counsel to NEI's General
Counsel (ADAMS Accession No. ML101960180)
4. Even if the NRC were to conclude that materials licensees are
afforded backfitting protection with respect to procedures governing
transportation of classified information, applicants and potential/
future applicants for such materials licenses are not, with certain
exceptions not relevant here, protected under either the various NRC
backfitting provisions or the issue finality provisions under 10 CFR
part 52. This is because neither the backfitting provisions nor the
issue finality provisions under 10 CFR part 52 were intended for every
NRC action which substantially changes the expectations of current and
future applicants.
Dated at Rockville, Maryland, this 3rd day of June, 2015.
For the Nuclear Regulatory Commission.
Harriet Karagiannis,
Acting Chief, Regulatory Guidance and Generic Issues Branch, Division
of Engineering, Office of Nuclear Regulatory Research.
[FR Doc. 2015-14018 Filed 6-8-15; 8:45 am]
BILLING CODE 7590-01-P