Drawbridge Operation Regulation; Reynolds Channel, Nassau, NY, 32312 [2015-13920]
Download as PDF
32312
Federal Register / Vol. 80, No. 109 / Monday, June 8, 2015 / Rules and Regulations
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2015–0401]
Drawbridge Operation Regulation;
Reynolds Channel, Nassau, NY
Coast Guard, DHS.
Notice of deviation from
drawbridge regulation.
AGENCY:
ACTION:
The Coast Guard has issued a
temporary deviation from the operating
schedule that governs the Long Beach
Bridge, across Reynolds Channel, mile
4.7, at Nassau, New York. This
temporary deviation is necessary to
facilitate the Annual Salute to Veterans
and Fireworks Display. This deviation
allows the bridge to remain in the
closed position during this public event.
DATES: This deviation is effective from
9:30 p.m. on June 27, 2015 to 12 a.m.
on June 28, 2015.
ADDRESSES: The docket for this
deviation, [USCG–2015–0401] is
available at https://www.regulations.gov.
Type the docket number in the
‘‘SEARCH’’ box and click ‘‘SEARCH.’’
Click on Open Docket Folder on the line
associated with this deviation. You may
also visit the Docket Management
Facility in Room W12–140, on the
ground floor of the Department of
Transportation West Building, 1200
New Jersey Avenue SE., Washington,
DC, 20590, between 9 a.m. and 5 p.m.,
Monday through Friday, except Federal
holidays.
FOR FURTHER INFORMATION CONTACT: If
you have questions on this temporary
deviation, contact Ms. Judy K. LeungYee, Project Officer, First Coast Guard
District, telephone (212) 514–4330,
email judy.k.leung-yee@uscg.mil. If you
have questions on viewing the docket,
call Ms. Cheryl Collins, Program
SUMMARY:
Manager, Docket Operations, telephone
(202) 366–9826.
SUPPLEMENTARY INFORMATION: The Long
Beach Bridge, mile 4.7, across Reynolds
Channel has a vertical clearance in the
closed position of 22 feet at mean high
water and 24 feet at mean low water.
The existing bridge operating
regulations are found at 33 CFR
117.799(g).
Reynolds Channel is transited by
commercial fishing and recreational
vessel traffic.
Nassau County Department of Public
Works requested this temporary
deviation from the normal operating
schedule to facilitate a public event, the
City of Long Beach Annual Fireworks
Display.
Under this temporary deviation, the
Long Beach Bridge may remain in the
closed position between 9:30 p.m. on
June 27, 2015 and 12:00 a.m. on June 28,
2015 (rain date June 28, 2015).
There is no alternate route for vessel
traffic; however, vessels that can pass
under the closed draws during this
closure may do so at any time. The
bridge will be able to open in the event
of an emergency.
The Coast Guard will inform the users
of the waterway through our Local and
Broadcast Notice to Mariners of the
change in operating schedule for the
bridge so that vessels can arrange their
transits to minimize any impact caused
by the temporary deviation.
In accordance with 33 CFR 117.35(e),
the drawbridge must return to its regular
operating schedule immediately at the
end of the effective period of this
temporary deviation. This deviation
from the operating regulations is
authorized under 33 CFR 117.35.
Dated: May 27, 2015.
C.J. Bisignano,
Supervisory Bridge Management Specialist,
First Coast Guard District.
[FR Doc. 2015–13920 Filed 6–5–15; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 165
[Docket No. USCG–2015–0362]
Safety Zones; Recurring Events in
Captain of the Port Boston Zone
AGENCY:
Coast Guard, DHS.
Notice of enforcement of
regulation.
ACTION:
The Coast Guard will enforce
the safety zones in the Captain of the
Port Boston Zone on the specified dates
and times listed below. This action is
necessary to ensure the protection of the
maritime public and event participants
from the hazards associated with these
annual recurring events. Under the
provisions in the CFR, no person or
vessel, except for the safety vessels
assisting with these events may enter
the safety zones unless given permission
from the COTP or the designated onscene representative. The Coast Guard
may be assisted by other Federal, State,
or local law enforcement agencies in
enforcing this regulation.
SUMMARY:
The regulation for these safety
zones described in 33 CFR 165.118 will
be enforced on the dates and times
listed in the table below.
DATES:
If
you have questions on this document,
call or email Mr. Mark Cutter, Coast
Guard Sector Boston Waterways
Management Division, telephone 617–
223–4000, email Mark.E.Cutter@
uscg.mil.
FOR FURTHER INFORMATION CONTACT:
The Coast
Guard will enforce the safety zones
listed in 33 CFR 165.118 on the
specified dates and times as indicated in
Table 1 below.
SUPPLEMENTARY INFORMATION:
TABLE 1
Surfside Fireworks ..................
•
•
•
•
•
6.5 Hull Youth Football Carnival
Fireworks.
•
•
•
•
•
wreier-aviles on DSK5TPTVN1PROD with RULES
6.3
VerDate Sep<11>2014
15:05 Jun 05, 2015
Event Type: Fireworks Display.
Sponsor: Salisbury Beach Partnership and Chamber of Commerce.
Date: Every Saturday from June 27, 2015 through September 5, 2015.
Time: 9:00 p.m. to 11:00 p.m.
Location: All waters of the Atlantic Ocean near Salisbury Beach, MA, within a 350-yard radius of the fireworks barge located at position 42°50.6′ N., 070°48.4′ W. (NAD 83).
Event Type: Fireworks Display.
Sponsor: Hull Youth Football.
Date: June 20, 2015.
Time: 9:30 p.m. to 10:30 p.m.
Location: All waters within a 450-foot radius of the fireworks barge located approximately 500 feet of off
Nantasket Beach, Hull MA located at position 42°16.6′ N., 070°51.7′ W. (NAD 83).
Jkt 235001
PO 00000
Frm 00046
Fmt 4700
Sfmt 4700
E:\FR\FM\08JNR1.SGM
08JNR1
Agencies
[Federal Register Volume 80, Number 109 (Monday, June 8, 2015)]
[Rules and Regulations]
[Page 32312]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-13920]
[[Page 32312]]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG-2015-0401]
Drawbridge Operation Regulation; Reynolds Channel, Nassau, NY
AGENCY: Coast Guard, DHS.
ACTION: Notice of deviation from drawbridge regulation.
-----------------------------------------------------------------------
SUMMARY: The Coast Guard has issued a temporary deviation from the
operating schedule that governs the Long Beach Bridge, across Reynolds
Channel, mile 4.7, at Nassau, New York. This temporary deviation is
necessary to facilitate the Annual Salute to Veterans and Fireworks
Display. This deviation allows the bridge to remain in the closed
position during this public event.
DATES: This deviation is effective from 9:30 p.m. on June 27, 2015 to
12 a.m. on June 28, 2015.
ADDRESSES: The docket for this deviation, [USCG-2015-0401] is available
at https://www.regulations.gov. Type the docket number in the ``SEARCH''
box and click ``SEARCH.'' Click on Open Docket Folder on the line
associated with this deviation. You may also visit the Docket
Management Facility in Room W12-140, on the ground floor of the
Department of Transportation West Building, 1200 New Jersey Avenue SE.,
Washington, DC, 20590, between 9 a.m. and 5 p.m., Monday through
Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If you have questions on this
temporary deviation, contact Ms. Judy K. Leung-Yee, Project Officer,
First Coast Guard District, telephone (212) 514-4330, email
judy.k.leung-yee@uscg.mil. If you have questions on viewing the docket,
call Ms. Cheryl Collins, Program Manager, Docket Operations, telephone
(202) 366-9826.
SUPPLEMENTARY INFORMATION: The Long Beach Bridge, mile 4.7, across
Reynolds Channel has a vertical clearance in the closed position of 22
feet at mean high water and 24 feet at mean low water. The existing
bridge operating regulations are found at 33 CFR 117.799(g).
Reynolds Channel is transited by commercial fishing and
recreational vessel traffic.
Nassau County Department of Public Works requested this temporary
deviation from the normal operating schedule to facilitate a public
event, the City of Long Beach Annual Fireworks Display.
Under this temporary deviation, the Long Beach Bridge may remain in
the closed position between 9:30 p.m. on June 27, 2015 and 12:00 a.m.
on June 28, 2015 (rain date June 28, 2015).
There is no alternate route for vessel traffic; however, vessels
that can pass under the closed draws during this closure may do so at
any time. The bridge will be able to open in the event of an emergency.
The Coast Guard will inform the users of the waterway through our
Local and Broadcast Notice to Mariners of the change in operating
schedule for the bridge so that vessels can arrange their transits to
minimize any impact caused by the temporary deviation.
In accordance with 33 CFR 117.35(e), the drawbridge must return to
its regular operating schedule immediately at the end of the effective
period of this temporary deviation. This deviation from the operating
regulations is authorized under 33 CFR 117.35.
Dated: May 27, 2015.
C.J. Bisignano,
Supervisory Bridge Management Specialist, First Coast Guard District.
[FR Doc. 2015-13920 Filed 6-5-15; 8:45 am]
BILLING CODE 9110-04-P