Download as PDF 32184 ACTION: Federal Register / Vol. 80, No. 108 / Friday, June 5, 2015 / Notices Notice of availability. The U.S. Nuclear Regulatory Commission (NRC) is making available NUREG–0090, Volume 37, ‘‘Report to Congress on Abnormal Occurrences: Fiscal Year 2014.’’ The report describes those events that the NRC or an Agreement State identified as abnormal occurrences (AOs) during fiscal year (FY) 2014, based on the criteria defined in this report’s Appendix A, ‘‘Abnormal Occurrence Criteria and Guidelines for Other Events of Interest.’’ The report describes 12 events at Agreement Statelicensed facilities and 1 event at an NRC-licensed facility. DATES: NUREG–0090, Volume 37, is available June 5, 2015. ADDRESSES: Please refer to Docket ID NRC–2015–0137 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods: • Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC–2015–0137. Address questions about NRC dockets to Carol Gallagher; telephone: 301–415–3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact the individuals listed in the FOR FURTHER INFORMATION CONTACT section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publiclyavailable documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘ADAMS Public Documents’’ and then select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301–415–4737, or by email to pdr.resource@nrc.gov. • NRC’s PDR: You may examine and purchase copies of public documents at the NRC’s PDR, Room O1–F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. FOR FURTHER INFORMATION CONTACT: Katie Tapp, Office of Nuclear Regulatory Research, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, telephone: 301–252–7520, email: Katherine.Tapp@nrc.gov. SUPPLEMENTARY INFORMATION: Section 208 of the Energy Reorganization Act of 1974, as amended (Pub. L. 93–438), defines an ‘‘abnormal occurrence’’ as an unscheduled incident or event that the NRC determines to be significant from the standpoint of public health or safety. asabaliauskas on DSK5VPTVN1PROD with NOTICES SUMMARY: VerDate Sep<11>2014 18:31 Jun 04, 2015 Jkt 235001 The report describes those events that the NRC identified as AOs during FY 2014, based on the criteria defined in this report’s Appendix A, ‘‘Abnormal Occurrence Criteria and Guidelines for Other Events of Interest.’’ The report describes 12 events at Agreement State-licensed facilities and one event at an NRC-licensed facility. One Agreement State-licensee event involved radiation exposure to an embryo/fetus. The NRC-licensee and the other 11 Agreement State-licensee events were medical events as defined in part 35 of Title 10 of the Code of Federal Regulations, and occurred at medical institutions. Agreement States are the 37 States that currently have entered into formal agreements with the NRC pursuant to Section 274 of the Atomic Energy Act of 1954 (AEA) (Pub. L. 83–703) to regulate certain quantities of AEA-licensed material at facilities located within their borders. The Federal Reports Elimination and Sunset Act of 1995 (Pub. L. 104–68) requires that the NRC report AOs to Congress annually. The full report, NUREG–0090, Volume 37, ‘‘Report to Congress on Abnormal Occurrences: Fiscal Year 2014’’ is available electronically at the NRC’s Web site at https://www.nrc.gov/reading-rm/doccollections/nuregs/staff/, and in ADAMS under Accession No. ML15140A285. Dated at Rockville, Maryland, this 1st day of June, 2015. For the Nuclear Regulatory Commission. Annette Vietti-Cook, Secretary of the Commission. [FR Doc. 2015–13825 Filed 6–4–15; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket No. 70–3103; NRC–2010–0264] Louisiana Energy Services, URENCO USA Facility Nuclear Regulatory Commission. ACTION: Inspection reports; issuance. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) staff has conducted inspections of the Louisiana Energy Services, LLC, URENCO USA (UUSA) Facility in Eunice, New Mexico, and has authorized the Uranium Byproduct Cylinder Storage Pad Crane for use with non-enriched uranic material; the introduction of uranium hexafluoride (UF6) into cascades 5.1, 5.2, 5.3, 5.4, 5.5, 5.6, and 5.7; and the commencement of UF6 re-feed operations in cascades 5.1 SUMMARY: PO 00000 Frm 00103 Fmt 4703 Sfmt 4703 through 5.7 in Separation Building Module-1005. DATES: June 5, 2015. ADDRESSES: Please refer to Docket ID NRC–2010–0264 when contacting the NRC about the availability of information regarding this document. You may access publicly-available information related to this document using any of the following methods: • Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC–2010–0264. Address questions about NRC dockets to Carol Gallagher; telephone: 301–415–3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publiclyavailable documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘ADAMS Public Documents’’ and then select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301–415–4737, or by email to pdr.resource@nrc.gov. For the convenience of the reader, the ADAMS accession numbers are provided in a table in the ‘‘Availability of Documents’’ section of this document. • NRC’s PDR: You may examine and purchase copies of public documents at the NRC’s PDR, Room O1–F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. FOR FURTHER INFORMATION CONTACT: Tilda Liu, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001; telephone: 404–997– 4730; email: Tilda.Liu@nrc.gov. SUPPLEMENTARY INFORMATION: I. Further Information The NRC staff has prepared inspection reports documenting its findings in accordance with the requirements of the NRC’s Inspection Manual, and these reports are available for review as specified in Section II of this notice. The publication of this notice satisfies the requirements of Section 70.32(k) of Title 10 of the Code of Federal Regulations (10 CFR), and Section 193(c) of the Atomic Energy Act of 1954, as amended. The introduction of UF6 into any separation building module (SBM) at the UUSA uranium enrichment facility is not permitted until the NRC E:\FR\FM\05JNN1.SGM 05JNN1 32185 Federal Register / Vol. 80, No. 108 / Friday, June 5, 2015 / Notices completes an operational readiness and management measures verification review, to verify that management measures that ensure compliance with the performance requirements of 10 CFR 70.61 have been implemented, and confirms that the SBM has been constructed in accordance with the license and will be operated safely. Subsequent operational readiness and management measures verification reviews will continue throughout the planned future phases of construction and, upon completion of these subsequent phases, additional notices of the operation approval letters will be published in the Federal Register in accordance with 10 CFR 70.32(k). II. Availability of Documents The authorization letters and inspection reports identified in the following table are available to interested persons. NRC Authorization Letters Authorization letters Date ADAMS accession No. Cascade 5.1 ................................................................................................... Uranium Byproduct Cylinder Storage Pad Crane .......................................... Cascade 5.2 ................................................................................................... Cascade 5.3 ................................................................................................... Cascade 5.4 ................................................................................................... Cascade 5.5 ................................................................................................... Re-Feed Operations in Cascades 5.1 through 5.5 ........................................ Cascade 5.6 ................................................................................................... Cascade 5.7 and Re-Feed Operations .......................................................... February 6, 2015 ................................................... February 19, 2015 ................................................. February 20, 2015 ................................................. March 2, 2015 ........................................................ March 12, 2015 ...................................................... April 7, 2015 .......................................................... April 9, 2015 .......................................................... April 29, 2015 ........................................................ May 26, 2015 ......................................................... ML15037A054 ML15050A282 ML15051A028 ML15063A003 ML15071A364 ML15097A278 ML15099A487 ML15119A189 ML15146A123 Inspection Report No. Date ADAMS accession No. 2014–005 ....................................................................................................... 2015–002 ....................................................................................................... 2015–006 ....................................................................................................... January 29, 2015 ................................................... April 21, 2015 ........................................................ February 27, 2015 ................................................. ML15029A031 ML15111A280 ML15058A712 NRC Inspection Reports Dated at Rockville, Maryland, this 26th day of May, 2015. For the Nuclear Regulatory Commission. Thomas A. Grice, Acting Chief, Enrichment and Conversion Branch, Division of Fuel Cycle Safety, Safeguards, and Environmental Review, Office of Nuclear Material Safety, and Safeguards. [FR Doc. 2015–13810 Filed 6–4–15; 8:45 am] POSTAL REGULATORY COMMISSION [Docket Nos. MC2015–52 and CP2015–80; Order No. 2522] New Postal Product Postal Regulatory Commission. Notice. AGENCY: The Commission is noticing a recent Postal Service filing concerning an addition of Priority Mail Contract 123 to the competitive product list. This notice informs the public of the filing, invites public comment, and takes other administrative steps. DATES: Comments are due: June 8, 2015. ADDRESSES: Submit comments electronically via the Commission’s Filing Online system at https:// www.prc.gov. Those who cannot submit comments electronically should contact the person identified in the FOR FURTHER asabaliauskas on DSK5VPTVN1PROD with NOTICES SUMMARY: VerDate Sep<11>2014 18:31 Jun 04, 2015 Jkt 235001 FOR FURTHER INFORMATION CONTACT: David A. Trissell, General Counsel, at 202–789–6820. SUPPLEMENTARY INFORMATION: Table of Contents I. Introduction II. Notice of Commission Action III. Ordering Paragraphs BILLING CODE 7590–01–P ACTION: section by telephone for advice on filing alternatives. INFORMATION CONTACT I. Introduction In accordance with 39 U.S.C. 3642 and 39 CFR 3020.30 et seq., the Postal Service filed a formal request and associated supporting information to add Priority Mail Contract 123 to the competitive product list.1 The Postal Service contemporaneously filed a redacted contract related to the proposed new product under 39 U.S.C. 3632(b)(3) and 39 CFR 3015.5. Id. Attachment B. To support its Request, the Postal Service filed a copy of the contract, a copy of the Governors’ Decision authorizing the product, proposed changes to the product list, a Statement of Supporting Justification, a 1 Request of the United States Postal Service to Add Priority Mail Contract 123 to Competitive Product List and Notice of Filing (Under Seal) of Unredacted Governors’ Decision, Contract, and Supporting Data, May 29, 2015 (Request). PO 00000 Frm 00104 Fmt 4703 Sfmt 4703 certification of compliance with 39 U.S.C. 3633(a), and an application for non-public treatment of certain materials. It also filed supporting financial workpapers. II. Notice of Commission Action The Commission establishes Docket Nos. MC2015–52 and CP2015–80 to consider the Request pertaining to the proposed Priority Mail Contract 123 product and the related contract, respectively. The Commission invites comments on whether the Postal Service’s filings in the captioned dockets are consistent with the policies of 39 U.S.C. 3632, 3633, or 3642, 39 CFR part 3015, and 39 CFR part 3020, subpart B. Comments are due no later than June 8, 2015. The public portions of these filings can be accessed via the Commission’s Web site (https://www.prc.gov). The Commission appoints Curtis Kidd to serve as Public Representative in these dockets. III. Ordering Paragraphs It is ordered: 1. The Commission establishes Docket Nos. MC2015–52 and CP2015–80 to consider the matters raised in each docket. 2. Pursuant to 39 U.S.C. 505, Curtis Kidd is appointed to serve as an officer of the Commission to represent the E:\FR\FM\05JNN1.SGM 05JNN1

Agencies

[Federal Register Volume 80, Number 108 (Friday, June 5, 2015)]
[Notices]
[Pages 32184-32185]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-13810]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 70-3103; NRC-2010-0264]


Louisiana Energy Services, URENCO USA Facility

AGENCY: Nuclear Regulatory Commission.

ACTION: Inspection reports; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) staff has 
conducted inspections of the Louisiana Energy Services, LLC, URENCO USA 
(UUSA) Facility in Eunice, New Mexico, and has authorized the Uranium 
Byproduct Cylinder Storage Pad Crane for use with non-enriched uranic 
material; the introduction of uranium hexafluoride (UF6) 
into cascades 5.1, 5.2, 5.3, 5.4, 5.5, 5.6, and 5.7; and the 
commencement of UF6 re-feed operations in cascades 5.1 
through 5.7 in Separation Building Module-1005.

DATES: June 5, 2015.

ADDRESSES: Please refer to Docket ID NRC-2010-0264 when contacting the 
NRC about the availability of information regarding this document. You 
may access publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2010-0264. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. For 
the convenience of the reader, the ADAMS accession numbers are provided 
in a table in the ``Availability of Documents'' section of this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Tilda Liu, Office of Nuclear Material 
Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, 
DC 20555-0001; telephone: 404-997-4730; email: Tilda.Liu@nrc.gov.

SUPPLEMENTARY INFORMATION: 

I. Further Information

    The NRC staff has prepared inspection reports documenting its 
findings in accordance with the requirements of the NRC's Inspection 
Manual, and these reports are available for review as specified in 
Section II of this notice. The publication of this notice satisfies the 
requirements of Section 70.32(k) of Title 10 of the Code of Federal 
Regulations (10 CFR), and Section 193(c) of the Atomic Energy Act of 
1954, as amended.
    The introduction of UF6 into any separation building 
module (SBM) at the UUSA uranium enrichment facility is not permitted 
until the NRC

[[Page 32185]]

completes an operational readiness and management measures verification 
review, to verify that management measures that ensure compliance with 
the performance requirements of 10 CFR 70.61 have been implemented, and 
confirms that the SBM has been constructed in accordance with the 
license and will be operated safely. Subsequent operational readiness 
and management measures verification reviews will continue throughout 
the planned future phases of construction and, upon completion of these 
subsequent phases, additional notices of the operation approval letters 
will be published in the Federal Register in accordance with 10 CFR 
70.32(k).

II. Availability of Documents

    The authorization letters and inspection reports identified in the 
following table are available to interested persons.

NRC Authorization Letters

------------------------------------------------------------------------
     Authorization letters              Date        ADAMS  accession No.
------------------------------------------------------------------------
Cascade 5.1....................  February 6, 2015.  ML15037A054
Uranium Byproduct Cylinder       February 19, 2015  ML15050A282
 Storage Pad Crane.
Cascade 5.2....................  February 20, 2015  ML15051A028
Cascade 5.3....................  March 2, 2015....  ML15063A003
Cascade 5.4....................  March 12, 2015...  ML15071A364
Cascade 5.5....................  April 7, 2015....  ML15097A278
Re-Feed Operations in Cascades   April 9, 2015....  ML15099A487
 5.1 through 5.5.
Cascade 5.6....................  April 29, 2015...  ML15119A189
Cascade 5.7 and Re-Feed          May 26, 2015.....  ML15146A123
 Operations.
------------------------------------------------------------------------

NRC Inspection Reports

------------------------------------------------------------------------
     Inspection Report No.              Date        ADAMS  accession No.
------------------------------------------------------------------------
2014-005.......................  January 29, 2015.  ML15029A031
2015-002.......................  April 21, 2015...  ML15111A280
2015-006.......................  February 27, 2015  ML15058A712
------------------------------------------------------------------------


    Dated at Rockville, Maryland, this 26th day of May, 2015.

    For the Nuclear Regulatory Commission.
Thomas A. Grice,
Acting Chief, Enrichment and Conversion Branch, Division of Fuel Cycle 
Safety, Safeguards, and Environmental Review, Office of Nuclear 
Material Safety, and Safeguards.
[FR Doc. 2015-13810 Filed 6-4-15; 8:45 am]