Information Collection Request Submitted to OMB for Review and Approval; Comment Request; NSPS for Hot Mix Asphalt Facilities (Renewal), 30452-30453 [2015-12945]
Download as PDF
asabaliauskas on DSK5VPTVN1PROD with NOTICES
30452
Federal Register / Vol. 80, No. 102 / Thursday, May 28, 2015 / Notices
Repayment Study: Existing rate
schedules are predicated upon an
August 2011 repayment study and other
supporting data contained in FERC
docket number EF11–13–000. The
annual revenue requirement in this
study is $59,600,000. An updated
repayment study, dated January 2015,
indicates rates are not adequate to
recover cost increases that have been
identified and therefore do not meet
repayment criteria. The additional costs
are due to numerous factors. Corps
Operation & Maintenance expenses have
exceeded estimates and current rate
schedules did not include costs
associated with the dam safety repairs of
the Wolf Creek and Center Hill Projects.
The dam repair costs, after the
application of the Dam Safety Act
(Water Resources Development Act of
1986 section 1203), are a combined
$83,200,000. The Corps has also
provided Southeastern with an updated
plan of major replacements for the
Cumberland System with the total cost
of these planned replacements at
$868,000,000. Also, TVA notified
Southeastern on March 5, 2015 they will
charge $1,009,850 per month for
delivery of capacity and energy to the
outside TVA customers. A revised
repayment study demonstrates that a
revenue increase to $78,500,000 per
year will meet repayment criteria. The
increase in the annual revenue
requirement is $18,900,000 per year, or
about 32 percent.
Applicability of the Dam Safety Act:
Under section 1203 of the Water
Resources Development Act of 1986,
otherwise known as the Dam Safety Act,
Congress capped the percentage of dam
repair costs that may be assigned to
project purposes (such as hydropower)
at 15 percent. This cap applies to dam
modification costs, ‘‘the cause of which
results from new hydrologic or seismic
data or changes in the state-of-the-art
design or construction criteria deemed
necessary for safety purposes’’. 33
U.S.C. 467n(a). When applicable, the
Dam Safety Act requires that dam safety
repair costs be recovered within thirty
years of completion of the work. If the
Dam Safety Act is not applied, 100
percent of all costs are assigned to
project purposes for cost recovery but
the thirty-year cost recovery
requirement does not attach.
Southeastern continues to discuss,
analyze and seek guidance on the issue
from other relevant agencies.
Proposed Rates: Southeastern is
proposing three rate scenarios per rate
schedule. All of the rate scenarios have
an annual revenue requirement of
$78,500,000. This annual revenue
requirement was calculated using the
VerDate Sep<11>2014
18:18 May 27, 2015
Jkt 235001
lower bound of possible costs associated
with the Wolf Creek and Center Hill
Dam repairs: 15 percent assigned to
project purposes and recovered within
thirty years of completion, an amount
that may be adjusted upward pending
final determination of the Dam Safety
Act’s applicability.
The first rate scenario includes the
rates necessary to recover costs under
the Revised Interim Operating Plan.
Under this scenario, the capacity rate at
the TVA border is $2.28 per kilowatt per
month and the energy charge is 14.79
mills per kilowatt-hour. The outside
customers would pay their portion of
the transmission credit provided TVA
for delivery of capacity and energy to
neighboring system interconnection
points, as agreed by contract between
Southeastern and TVA. This rate would
remain in effect under the Revised
Interim Operating Plan.
The second rate scenario would
recover cost from capacity and energy.
The revenue requirement under this
alternative would be $78,500,000 per
year. This scenario would be in effect if
Southeastern changes the Revised
Interim Operating Plan.
The third rate scenario is based on the
original Cumberland Marketing Policy.
All costs are recovered from capacity
and excess energy. The rates under this
alternative would be as follows:
(As of 2/1/2015 and provided for
illustrative purposes)
East Kentucky Power Cooperative:
Capacity: $1.994 per kW/Month
Energy: 13.914 mills per kWh
These rates would go into effect once
the Corps lifts the restrictions on the
operation of the Wolf Creek and Center
Hill Projects and the Revised Interim
Operating Plan and Southeastern
returns to normal operations.
The referenced repayment studies are
available for examination at 1166
Athens Tech Road, Elberton, Georgia
30635–6711. The Proposed Rate
Schedules CBR–1–I, CSI–1–I, CEK–1–I,
CM–1–I, CC–1–J, CK–1–I, CTV–1–I,
CTVI–1–B, and Replacement-3 are also
available.
Dated: May 20, 2015.
Kenneth E. Legg,
Administrator.
[FR Doc. 2015–12888 Filed 5–27–15; 8:45 am]
BILLING CODE 6450–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OECA–2014–0040; FRL–9928–
41–OEI]
Third Scenario—Return to Original
Marketing Policy
Information Collection Request
Submitted to OMB for Review and
Approval; Comment Request; NSPS
for Hot Mix Asphalt Facilities
(Renewal)
Inside TVA Preference Customers
AGENCY:
Capacity and Base Energy: $3.733 per
kW/Month
Additional Energy: 13.914 mills per
kWh
Transmission: Pass-through
SUMMARY:
Cumberland System Rates
Outside TVA Preference Customers
(Excluding Customers served through
Carolina Power & Light Company or
East Kentucky Power Cooperative)
Capacity and Base Energy: $3.733 per
kW/Month
Additional Energy: 13.914 mills per
kWh
Transmission: Monthly TVA
Transmission Charge divided by
545,000
Customers Served Through Carolina
Power & Light Company
Capacity and Base Energy: $4.249 per
kW/Month
TVA Transmission: TVA rate at border
as computed above, adjusted for DEP
delivery.
DEP Transmission: $1.546 per kW/
Month
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
Environmental Protection
Agency (EPA).
ACTION: Notice.
The Environmental Protection
Agency has submitted an information
collection request (ICR), ‘‘NSPS for Hot
Mix Asphalt Facilities (40 CFR part 60,
subpart I) (Renewal)’’ (EPA ICR No.
1127.11, OMB Control No. 2060–0083)
to the Office of Management and Budget
(OMB) for review and approval in
accordance with the Paperwork
Reduction Act (44 U.S.C. 3501 et seq.).
This is a proposed extension of the ICR,
which is currently approved through
May 31, 2015. Public comments were
previously requested via the Federal
Register (79 FR 30117) on May 27, 2014
during a 60-day comment period. This
notice allows for an additional 30 days
for public comments. A fuller
description of the ICR is given below,
including its estimated burden and cost
to the public. An Agency may not
conduct or sponsor and a person is not
required to respond to a collection of
information unless it displays a
currently valid OMB control number.
E:\FR\FM\28MYN1.SGM
28MYN1
Federal Register / Vol. 80, No. 102 / Thursday, May 28, 2015 / Notices
Additional comments may be
submitted on or before June 29, 2015.
ADDRESSES: Submit your comments,
referencing Docket ID Number EPA–
HQ–OECA–2014–0040, to (1) EPA
online using www.regulations.gov (our
preferred method), by email to
docket.oeca@epa.gov, or by mail to: EPA
Docket Center, Environmental
Protection Agency, Mail Code 28221T,
1200 Pennsylvania Ave. NW.,
Washington, DC 20460, and (2) OMB via
email to oira_submission@omb.eop.gov.
Address comments to OMB Desk Officer
for EPA.
EPA’s policy is that all comments
received will be included in the public
docket without change including any
personal information provided, unless
the comment includes profanity, threats,
information claimed to be Confidential
Business Information (CBI) or other
information whose disclosure is
restricted by statute.
FOR FURTHER INFORMATION CONTACT:
Patrick Yellin, Monitoring, Assistance,
and Media Programs Division, Office of
Compliance, Mail Code 2227A,
Environmental Protection Agency, 1200
Pennsylvania Ave. NW., Washington,
DC 20460; telephone number: (202)
564–2970; fax number: (202) 564–0050;
email address: yellin.patrick@epa.gov.
SUPPLEMENTARY INFORMATION:
Supporting documents which explain in
detail the information that the EPA will
be collecting are available in the public
docket for this ICR. The docket can be
viewed online at www.regulations.gov
or in person at the EPA Docket Center,
EPA West, Room 3334, 1301
Constitution Ave. NW., Washington,
DC. The telephone number for the
Docket Center is 202–566–1744. For
additional information about EPA’s
public docket, visit https://www.epa.gov/
dockets.
Abstract: These regulations apply to
hot mix asphalt facilities comprised
only of a combination of the following:
Dryers; systems for screening, handling,
storing, and weighing hot aggregate;
systems for loading, transferring, and
storing mineral filler; systems for
mixing hot mix asphalt; and the loading,
transfer, and storage systems associated
with emission control systems.
Form Numbers: None.
Respondents/affected entities: Hot
mix asphalt facilities.
Respondent’s obligation to respond:
Mandatory (40 CFR part 60, subpart I).
Estimated number of respondents:
4,640 (total).
Frequency of response: Initially and
occasionally.
Total estimated burden: 19,000 hours
(per year). Burden is defined at 5 CFR
1320.3(b).
asabaliauskas on DSK5VPTVN1PROD with NOTICES
DATES:
VerDate Sep<11>2014
18:18 May 27, 2015
Jkt 235001
Total estimated cost: $1,893,000 (per
year), includes $0 annualized capital or
operation & maintenance costs.
Changes in the Estimates: There is an
adjustment increase in the estimated
burden as currently identified in the
OMB Inventory of Approved Burdens.
The increase is not due to any program
changes. The change in burden occurred
because the number of respondents
subject to the standard has increased
since the last ICR renewal period. In
addition, the use of more updated labor
rates results in an increase in total labor
costs.
Courtney Kerwin,
Acting Director, Collection Strategies
Division.
[FR Doc. 2015–12945 Filed 5–27–15; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OECA–2014–0079; FRL–9927–
84–OEI]
Information Collection Request
Submitted to OMB for Review and
Approval; Comment Request; NESHAP
for Wet-Formed Fiberglass Mat
Production (Renewal)
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
The Environmental Protection
Agency has submitted an information
collection request (ICR), ‘‘NESHAP for
Wet-Formed Fiberglass Mat Production
(40 CFR part 63, subpart HHHH)
(Renewal)’’ (EPA ICR No. 1964.06, OMB
Control No. 2060–0496), to the Office of
Management and Budget (OMB) for
review and approval in accordance with
the Paperwork Reduction Act (44 U.S.C.
3501 et seq.). This is a proposed
extension of the ICR, which is currently
approved through May 31, 2015. Public
comments were previously requested
via the Federal Register (79 FR 30117)
on May 27, 2014 during a 60-day
comment period. This notice allows for
an additional 30 days for public
comments. A fuller description of the
ICR is given below, including its
estimated burden and cost to the public.
An Agency may neither conduct nor
sponsor, and a person is not required to
respond to, a collection of information
unless it displays a currently valid OMB
control number.
DATES: Additional comments may be
submitted on or before June 29, 2015.
ADDRESSES: Submit your comments,
referencing Docket ID Number EPA–
HQ–OECA–2014–0079, to: (1) EPA
SUMMARY:
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
30453
online using www.regulations.gov (our
preferred method), or by email to
docket.oeca@epa.gov, or by mail to: EPA
Docket Center, Environmental
Protection Agency, Mail Code 28221T,
1200 Pennsylvania Ave. NW.,
Washington, DC 20460; and (2) OMB via
email to oira_submission@omb.eop.gov.
Address comments to OMB Desk Officer
for EPA.
EPA’s policy is that all comments
received will be included in the public
docket without change including any
personal information provided, unless
the comment includes profanity, threats,
information claimed to be Confidential
Business Information (CBI), or other
information whose disclosure is
restricted by statute.
FOR FURTHER INFORMATION CONTACT:
Patrick Yellin, Monitoring, Assistance,
and Media Programs Division, Office of
Compliance, Mail Code 2227A,
Environmental Protection Agency, 1200
Pennsylvania Ave. NW., Washington,
DC 20460; telephone number: (202)
564–2970; fax number: (202) 564–0050;
email address: yellin.patrick@epa.gov.
SUPPLEMENTARY INFORMATION:
Supporting documents which explain in
detail the information that the EPA will
be collecting are available in the public
docket for this ICR. The docket can be
viewed online at www.regulations.gov
or in person at the EPA Docket Center,
WJC West, Room 3334, 1301
Constitution Ave. NW., Washington,
DC. The telephone number for the
Docket Center is 202–566–1744. For
additional information about EPA’s
public docket, visit: https://
www.epa.gov/dockets.
Abstract: The affected entities are
subject to the General Provisions of the
NESHAP (40 CFR part 63, subpart A),
and any changes, or additions, to the
Provisions specified at 40 CFR part 63,
subpart HHHH. Owners or operators of
the affected facilities must submit an
initial notification report, performance
tests, and periodic reports and results.
Owners or operators are also required to
maintain records of the occurrence and
duration of any startup, shutdown, or
malfunction in the operation of an
affected facility, or any period during
which the monitoring system is
inoperative. Reports, at a minimum, are
required semiannually.
Form Numbers: None.
Respondents/affected entities: Wetformed fiberglass mat production
facilities.
Respondent’s obligation to respond:
Mandatory (40 CFR part 63, subpart
HHHH).
Estimated number of respondents: 14
(total).
E:\FR\FM\28MYN1.SGM
28MYN1
Agencies
[Federal Register Volume 80, Number 102 (Thursday, May 28, 2015)]
[Notices]
[Pages 30452-30453]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-12945]
=======================================================================
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[EPA-HQ-OECA-2014-0040; FRL-9928-41-OEI]
Information Collection Request Submitted to OMB for Review and
Approval; Comment Request; NSPS for Hot Mix Asphalt Facilities
(Renewal)
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: The Environmental Protection Agency has submitted an
information collection request (ICR), ``NSPS for Hot Mix Asphalt
Facilities (40 CFR part 60, subpart I) (Renewal)'' (EPA ICR No.
1127.11, OMB Control No. 2060-0083) to the Office of Management and
Budget (OMB) for review and approval in accordance with the Paperwork
Reduction Act (44 U.S.C. 3501 et seq.). This is a proposed extension of
the ICR, which is currently approved through May 31, 2015. Public
comments were previously requested via the Federal Register (79 FR
30117) on May 27, 2014 during a 60-day comment period. This notice
allows for an additional 30 days for public comments. A fuller
description of the ICR is given below, including its estimated burden
and cost to the public. An Agency may not conduct or sponsor and a
person is not required to respond to a collection of information unless
it displays a currently valid OMB control number.
[[Page 30453]]
DATES: Additional comments may be submitted on or before June 29, 2015.
ADDRESSES: Submit your comments, referencing Docket ID Number EPA-HQ-
OECA-2014-0040, to (1) EPA online using www.regulations.gov (our
preferred method), by email to docket.oeca@epa.gov, or by mail to: EPA
Docket Center, Environmental Protection Agency, Mail Code 28221T, 1200
Pennsylvania Ave. NW., Washington, DC 20460, and (2) OMB via email to
oira_submission@omb.eop.gov. Address comments to OMB Desk Officer for
EPA.
EPA's policy is that all comments received will be included in the
public docket without change including any personal information
provided, unless the comment includes profanity, threats, information
claimed to be Confidential Business Information (CBI) or other
information whose disclosure is restricted by statute.
FOR FURTHER INFORMATION CONTACT: Patrick Yellin, Monitoring,
Assistance, and Media Programs Division, Office of Compliance, Mail
Code 2227A, Environmental Protection Agency, 1200 Pennsylvania Ave.
NW., Washington, DC 20460; telephone number: (202) 564-2970; fax
number: (202) 564-0050; email address: yellin.patrick@epa.gov.
SUPPLEMENTARY INFORMATION: Supporting documents which explain in detail
the information that the EPA will be collecting are available in the
public docket for this ICR. The docket can be viewed online at
www.regulations.gov or in person at the EPA Docket Center, EPA West,
Room 3334, 1301 Constitution Ave. NW., Washington, DC. The telephone
number for the Docket Center is 202-566-1744. For additional
information about EPA's public docket, visit https://www.epa.gov/dockets.
Abstract: These regulations apply to hot mix asphalt facilities
comprised only of a combination of the following: Dryers; systems for
screening, handling, storing, and weighing hot aggregate; systems for
loading, transferring, and storing mineral filler; systems for mixing
hot mix asphalt; and the loading, transfer, and storage systems
associated with emission control systems.
Form Numbers: None.
Respondents/affected entities: Hot mix asphalt facilities.
Respondent's obligation to respond: Mandatory (40 CFR part 60,
subpart I).
Estimated number of respondents: 4,640 (total).
Frequency of response: Initially and occasionally.
Total estimated burden: 19,000 hours (per year). Burden is defined
at 5 CFR 1320.3(b).
Total estimated cost: $1,893,000 (per year), includes $0 annualized
capital or operation & maintenance costs.
Changes in the Estimates: There is an adjustment increase in the
estimated burden as currently identified in the OMB Inventory of
Approved Burdens. The increase is not due to any program changes. The
change in burden occurred because the number of respondents subject to
the standard has increased since the last ICR renewal period. In
addition, the use of more updated labor rates results in an increase in
total labor costs.
Courtney Kerwin,
Acting Director, Collection Strategies Division.
[FR Doc. 2015-12945 Filed 5-27-15; 8:45 am]
BILLING CODE 6560-50-P