Southern Company Services, Inc.; KCP&L Greater Missouri Operations Company; The Empire District Electric Company; Associated Electric Cooperative, Inc.; v. Midcontinent Independent System Operator, Inc.; Notice of Complaint, 30451 [2015-12862]
Download as PDF
Federal Register / Vol. 80, No. 102 / Thursday, May 28, 2015 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL15–66–000]
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Southern Company Services, Inc.;
KCP&L Greater Missouri Operations
Company; The Empire District Electric
Company; Associated Electric
Cooperative, Inc.; v. Midcontinent
Independent System Operator, Inc.;
Notice of Complaint
Take notice that on May 20, 2015,
pursuant to sections 309, 205, and 206
of the Federal Power Act (FPA), 16
U.S.C. 824(e), 824(d), and 825(h) and
Rule 206 of the Federal Energy
Regulatory Commission’s (Commission)
Rules of Practice and Procedure, 18 CFR
385.206, Southern Company Services,
Inc., as agent for Alabama Power
Company, Georgia Power Company,
Gulf Power Company, Mississippi
Power Company, and Southern Power
Company (Southern Companies),
KCP&L Greater Missouri Operations
Company, The Empire District Electric
Company, and Associated Electric
Cooperative, Inc. (collectively,
Complainants), filed a formal complaint
against Midcontinent Independent
System Operator, Inc., as agent and tariff
administrator of the MISO Open-Access
Transmission Tariff (MISO or
Respondent), alleging that: (1)
Respondent has levied unlawful charges
upon Complainants in violation of
section 205 of the FPA, and; (2)
Respondent’s rates for transmission
service are unjust, unreasonable, unduly
discriminatory and preferential and in
violation of established precedent under
FPA sections 205 and 206.
The Complainants certify that a copy
of the complaint has been served on the
Respondent.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
VerDate Sep<11>2014
18:18 May 27, 2015
Jkt 235001
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an ‘‘eSubscription’’ link on
the Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on June 9, 2015.
Dated: May 21, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–12862 Filed 5–27–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Southeastern Power Administration
Cumberland System of Projects
Southeastern Power
Administration, DOE.
ACTION: Notice of proposed rates, public
forum, and opportunities for public
review and comment.
AGENCY:
Southeastern Power
Administration (Southeastern) proposes
to revise existing schedules of rates and
charges applicable to the sale of power
from the Cumberland System of Projects
effective for a one-year period, October
1, 2015, through September 30, 2016.
Interested persons may review the rates
and supporting studies and submit
written comments. Southeastern will
evaluate all comments received in this
process.
DATES: Written comments are due on or
before August 26, 2015. A public
information and comment forum will be
held at 2:00 p.m., on June 30, 2015.
Persons desiring to attend the forum
should notify Southeastern at least
seven (7) days before the scheduled
forum date. Persons desiring to speak at
the forum should notify Southeastern at
least three (3) days before the scheduled
forum date, so that a list of forum
participants can be prepared. Others
may speak if time permits.
ADDRESSES: The forum will be held at:
The Inn at Opryland, 2401 Music Valley
SUMMARY:
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
30451
Drive, Nashville, TN 37214–1002.
Written comments should be submitted
to: Administrator, Southeastern Power
Administration, Department of Energy,
1166 Athens Tech Road, Elberton, GA
30635–6711.
FOR FURTHER INFORMATION CONTACT:
Virgil G. Hobbs III, Southeastern Power
Administration, Department of Energy,
1166 Athens Tech Road, Elberton, GA
30635–6711, (706) 213–3800.
SUPPLEMENTARY INFORMATION:
Background of Existing Rates: The
existing schedules of rates and charges
applicable to the sale of power from the
Cumberland System of Projects are
effective through September 30, 2015.
On December 22, 2011, the Federal
Energy Regulatory Commission (FERC)
confirmed and approved on a final
basis, Wholesale Power Rate Schedules
CBR–1–H, CSI–1–H, CEK–1–H, CM–1–
H, CC–1–I, CK–1–H, CTV–1–H, CTVI–
1–A, and Replacement-3 applicable to
Cumberland System of Projects power
for a period ending September 30, 2013
(137 FERC ¶ 62,249). On July 10, 2013,
the Deputy Secretary approved an
extension of the rate schedules to
September 30, 2015 (78 FR 42764).
Operational Impact of Dam Safety
Issues: In February 2007, the U.S. Army
Corps of Engineers (Corps) lowered pool
levels at the Wolf Creek and Center Hill
Projects to reduce the risk of imminent
failure of the dams due to seepage
issues. At that time the Corps also began
the process of mitigating the seepage
issues at the Wolf Creek and Center Hill
Projects. Under normal pool levels, the
marketing policy for the Cumberland
System provides peaking capacity, along
with 1500 or 1800 hours of energy
annually with each kilowatt of capacity,
to customers outside the Tennessee
Valley Authority (TVA) transmission
system. All remaining energy is
scheduled by TVA for the benefit of
customers inside the TVA system. As a
consequence of lowered pool levels due
to dam repairs, Southeastern was not
able to provide peaking capacity and
firm energy to the outside customers
due to operational restrictions.
Southeastern implemented an Interim
Operating Plan for the Cumberland
System to provide these customers with
energy that did not include capacity.
In March 2014, the Corps lifted
operating restrictions on the Wolf Creek
Project. The operating restrictions on
the Center Hill Project remain in effect.
As a consequence, Southeastern
implemented a Revised Interim
Operating Plan that provides reduced
capacity and schedulable energy to the
outside customers.
E:\FR\FM\28MYN1.SGM
28MYN1
Agencies
[Federal Register Volume 80, Number 102 (Thursday, May 28, 2015)]
[Notices]
[Page 30451]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-12862]
[[Page 30451]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL15-66-000]
Southern Company Services, Inc.; KCP&L Greater Missouri
Operations Company; The Empire District Electric Company; Associated
Electric Cooperative, Inc.; v. Midcontinent Independent System
Operator, Inc.; Notice of Complaint
Take notice that on May 20, 2015, pursuant to sections 309, 205,
and 206 of the Federal Power Act (FPA), 16 U.S.C. 824(e), 824(d), and
825(h) and Rule 206 of the Federal Energy Regulatory Commission's
(Commission) Rules of Practice and Procedure, 18 CFR 385.206, Southern
Company Services, Inc., as agent for Alabama Power Company, Georgia
Power Company, Gulf Power Company, Mississippi Power Company, and
Southern Power Company (Southern Companies), KCP&L Greater Missouri
Operations Company, The Empire District Electric Company, and
Associated Electric Cooperative, Inc. (collectively, Complainants),
filed a formal complaint against Midcontinent Independent System
Operator, Inc., as agent and tariff administrator of the MISO Open-
Access Transmission Tariff (MISO or Respondent), alleging that: (1)
Respondent has levied unlawful charges upon Complainants in violation
of section 205 of the FPA, and; (2) Respondent's rates for transmission
service are unjust, unreasonable, unduly discriminatory and
preferential and in violation of established precedent under FPA
sections 205 and 206.
The Complainants certify that a copy of the complaint has been
served on the Respondent.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. The Respondent's
answer and all interventions, or protests must be filed on or before
the comment date. The Respondent's answer, motions to intervene, and
protests must be served on the Complainants.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 5 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for electronic review in the
Commission's Public Reference Room in Washington, DC. There is an
``eSubscription'' link on the Web site that enables subscribers to
receive email notification when a document is added to a subscribed
docket(s). For assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5:00 p.m. Eastern Time on June 9, 2015.
Dated: May 21, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-12862 Filed 5-27-15; 8:45 am]
BILLING CODE 6717-01-P