Kern River Gas Transmission Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Summerlin Pipe Replacement Project and Request for Comments on Environmental Issues, 28259-28261 [2015-11922]

Download as PDF Federal Register / Vol. 80, No. 95 / Monday, May 18, 2015 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission asabaliauskas on DSK5VPTVN1PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG15–82–000. Applicants: Balko Wind Transmission, LLC. Description: Self-Certification of Exempt Wholesale Generator Status of Balko Wind Transmission, LLC. Filed Date: 5/5/15. Accession Number: 20150505–5095. Comments Due: 5 p.m. ET 5/26/15. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER15–958–002. Applicants: Transource Kansas, LLC. Description: Compliance filing per 35: Transource Kansas Compliance Filing to be effective 4/3/2015. Filed Date: 5/4/15. Accession Number: 20150504–5195. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1466–001. Applicants: ISO New England Inc., New England Power Company. Description: Tariff Amendment per 35.17(b): Errata to Filing of First Rev Service Agreement Nos. TSA–NEP–83 and TSA–NEP–86 to be effective 6/7/201. Filed Date: 5/4/15. Accession Number: 20150504–5201. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1665–000. Applicants: Greenleaf Power Management LLC. Description: Initial rate filing per 35.12 Baseline new to be effective 6/30/2015. Filed Date: 5/4/15. Accession Number: 20150504–5208. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1666–000. Applicants: Southwest Power Pool, Inc. Description: Compliance Filing for Order No. 1000, Regarding Interregional Coordination and Cost Allocation of Transmission Projects with the MidContinent Area Power Pool and NorthWestern Corporation of Southwest Power Pool, Inc. Filed Date: 5/4/15. Accession Number: 20150504–5253. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1667–000. Applicants: Northwestern Corporation. Description: Compliance Filing for Order No. 1000, Regarding Interregional VerDate Sep<11>2014 18:52 May 15, 2015 Jkt 235001 Coordination and Cost Allocation of Transmission Projects with the MidContinent Area Power Pool and Southwest Power Pool, Inc. of Northwestern Corporation. Filed Date: 5/4/15. Accession Number: 20150504–5256. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1668–000. Applicants: Phoenix Energy Group, LLC. Description: Initial rate filing per 35.12 Application for MBR Authority to be effective 6/5/2015. Filed Date: 5/5/15. Accession Number: 20150505–5092. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1669–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Original Service Agreement No. 4104; Queue No. U2– 045/W4–063 to be effective 4/7/2015. Filed Date: 5/5/15. Accession Number: 20150505–5154. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1670–000. Applicants: Southern California Edison Company. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Amended Desert Harvest LGIA to be effective 5/6/2015. Filed Date: 5/5/15. Accession Number: 20150505–5157. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1671–000. Applicants: Public Service Company of Colorado. Description: § 205(d) rate filing per 35.13(a)(2)(iii): 2015–5–5_TSGT-Blue River E&P–405–0.0.0-Filing to be effective 7/4/2015. Filed Date: 5/5/15. Accession Number: 20150505–5159. Comments Due: 5 p.m. ET 5/26/15. Docket Numbers: ER15–1672–000. Applicants: Evergreen Wind Power II, LLC. Description: Initial rate filing per 35.12 Application for Market-Based Rate Authority to be effective 7/5/2015. Filed Date: 5/5/15. Accession Number: 20150505–5168. Comments Due: 5 p.m. ET 5/26/15. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but PO 00000 Frm 00041 Fmt 4703 Sfmt 4703 28259 intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: May 5, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–11811 Filed 5–15–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–132–000] Kern River Gas Transmission Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Summerlin Pipe Replacement Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Summerlin Pipe Replacement Project involving construction and operation of facilities by Kern River Gas Transmission Company (Kern River) in Clark County, Nevada. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before June 11, 2015. If you sent comments on this project to the Commission before the opening of this docket on March 26, 2015, you will need to file those comments in Docket E:\FR\FM\18MYN1.SGM 18MYN1 28260 Federal Register / Vol. 80, No. 95 / Monday, May 18, 2015 / Notices No. CP15–132–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. Kern River provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). asabaliauskas on DSK5VPTVN1PROD with NOTICES Public Participation For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’ as the filing type; or VerDate Sep<11>2014 18:52 May 15, 2015 Jkt 235001 (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP15–132– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Summary of the Proposed Project Kern River proposes the Summerlin Pipe Replacement Project to replace a 1.56-mile-long segment of its existing 36-inch-diameter A-line pipeline from milepost 543.63 to 545.19 in Clark County, Nevada. When originally constructed, this portion of the A-line was designed as pipeline located in a Class I location. This pipe segment must be upgraded with thicker-walled pipe to satisfy U.S. Department of Transportation safety regulations for a Class 3 location as a result of a planned residential development in the vicinity of the existing pipeline. In order to maintain delivery to Kern River’s customers, the pipeline segment would remain in service until the new pipeline segment is constructed and placed into service, after which the old segment would be removed. Due to a crossover of two existing pipelines, the new pipeline segment would be installed at a 25-foot offset from another existing Kern River line (B-line) for 1.15 miles and at a 25-foot offset from the existing A-line for 0.41 mile. To allow for uninterrupted service during the project, Kern River would install a new 24-inch-diameter crossover valve near milepost 0 of the project by hot tapping the 36-inch-diameter A-line and installing crossover piping to the 24inch-diameter B-line crossover piping. An existing 0.22-acre valve and pig 1 launcher yard would be expanded by 0.37 acre to accommodate the new crossover valve and crossover piping. The general location of the project facilities is shown in appendix 1.2 Pipeline facilities are proposed to be installed and removed between October 2015 and December 2015. Kern River expects the new pipeline segment to be placed into service by December 29, 2015. 1 A ‘‘pig’’ is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes. 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 Land Requirements for Construction Construction of the proposed facilities would disturb about 39.30 acres of land, which includes 9.74 acres of permanent right-of-way, 22.23 acres of construction right-of-way (i.e., additional temporary workspace, contractor staging yards), and 7.33 acres of access roads. Kern River proposes to use a 100-foot-wide construction right-of-way to install the replacement pipeline and remove the existing pipeline segment. Of the 31.97 acres used for construction along the pipeline route, 26.12 acres was previously disturbed by construction of the existing A-line and B-line. Following construction, Kern River would maintain 9.74 acres for permanent operation of the project’s facilities with only 1.10 acres of new disturbance, accounting for overlapping rights-of-way with A-line and B-line and previously disturbed land. The remaining acreage used during construction would be restored according to Kern River’s projectspecific Reclamation Plan and revert to former uses. The proposed pipeline crosses 0.44 mile (9.22 acres) of land owned and managed by the Bureau of Land Management (BLM), 1.06 miles (27.34 acres) of private property, and 0.06 mile (2.74 acres) owned by Clark County. The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 3 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • land use; • water resources, fisheries, and wetlands; • cultural resources; • vegetation and wildlife; 3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\18MYN1.SGM 18MYN1 Federal Register / Vol. 80, No. 95 / Monday, May 18, 2015 / Notices • air quality and noise; • endangered and threatened species; • public safety; and • cumulative impacts. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA.4 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Currently, the BLM has expressed its intention to participate as a cooperating agency in the preparation of the EA to satisfy its NEPA responsibilities related to this project. asabaliauskas on DSK5VPTVN1PROD with NOTICES Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.5 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas 4 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 5 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. VerDate Sep<11>2014 18:52 May 15, 2015 Jkt 235001 facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Currently Identified Environmental Issues We have already identified issues that we think deserve attention based on a preliminary review of the proposed facilities and the environmental information provided by Kern River, namely the impact on federally listed threatened and endangered species as well as BLM identified species. Other issues may be added based on your comments and our analysis. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies of the EA will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 28261 An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP15–132). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: May 12, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–11922 Filed 5–15–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–348–000] Southern Star Central Gas Pipeline, Inc.; Notice of Request Under Blanket Authorization Take notice that on April 30, 2015, Southern Star Central Gas Pipeline, Inc. (Southern Star), 4700 State Highway 56, Owensboro, Kentucky 42301, filed a prior notice application pursuant to sections 157.205, 157.208, 157.211, and 157.216 of the Federal Energy Regulatory Commission’s (Commission) E:\FR\FM\18MYN1.SGM 18MYN1

Agencies

[Federal Register Volume 80, Number 95 (Monday, May 18, 2015)]
[Notices]
[Pages 28259-28261]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-11922]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-132-000]


Kern River Gas Transmission Company; Notice of Intent To Prepare 
an Environmental Assessment for the Proposed Summerlin Pipe Replacement 
Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Summerlin Pipe Replacement 
Project involving construction and operation of facilities by Kern 
River Gas Transmission Company (Kern River) in Clark County, Nevada. 
The Commission will use this EA in its decision-making process to 
determine whether the project is in the public convenience and 
necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before June 11, 2015.
    If you sent comments on this project to the Commission before the 
opening of this docket on March 26, 2015, you will need to file those 
comments in Docket

[[Page 28260]]

No. CP15-132-000 to ensure they are considered as part of this 
proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Kern River provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or efiling@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP15-132-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    Kern River proposes the Summerlin Pipe Replacement Project to 
replace a 1.56-mile-long segment of its existing 36-inch-diameter A-
line pipeline from milepost 543.63 to 545.19 in Clark County, Nevada. 
When originally constructed, this portion of the A-line was designed as 
pipeline located in a Class I location. This pipe segment must be 
upgraded with thicker-walled pipe to satisfy U.S. Department of 
Transportation safety regulations for a Class 3 location as a result of 
a planned residential development in the vicinity of the existing 
pipeline.
    In order to maintain delivery to Kern River's customers, the 
pipeline segment would remain in service until the new pipeline segment 
is constructed and placed into service, after which the old segment 
would be removed. Due to a crossover of two existing pipelines, the new 
pipeline segment would be installed at a 25-foot offset from another 
existing Kern River line (B-line) for 1.15 miles and at a 25-foot 
offset from the existing A-line for 0.41 mile. To allow for 
uninterrupted service during the project, Kern River would install a 
new 24-inch-diameter crossover valve near milepost 0 of the project by 
hot tapping the 36-inch-diameter A-line and installing crossover piping 
to the 24-inch-diameter B-line crossover piping. An existing 0.22-acre 
valve and pig \1\ launcher yard would be expanded by 0.37 acre to 
accommodate the new crossover valve and crossover piping. The general 
location of the project facilities is shown in appendix 1.\2\
---------------------------------------------------------------------------

    \1\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes.
    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

    Pipeline facilities are proposed to be installed and removed 
between October 2015 and December 2015. Kern River expects the new 
pipeline segment to be placed into service by December 29, 2015.

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 39.30 
acres of land, which includes 9.74 acres of permanent right-of-way, 
22.23 acres of construction right-of-way (i.e., additional temporary 
workspace, contractor staging yards), and 7.33 acres of access roads. 
Kern River proposes to use a 100-foot-wide construction right-of-way to 
install the replacement pipeline and remove the existing pipeline 
segment. Of the 31.97 acres used for construction along the pipeline 
route, 26.12 acres was previously disturbed by construction of the 
existing A-line and B-line.
    Following construction, Kern River would maintain 9.74 acres for 
permanent operation of the project's facilities with only 1.10 acres of 
new disturbance, accounting for overlapping rights-of-way with A-line 
and B-line and previously disturbed land. The remaining acreage used 
during construction would be restored according to Kern River's 
project-specific Reclamation Plan and revert to former uses.
    The proposed pipeline crosses 0.44 mile (9.22 acres) of land owned 
and managed by the Bureau of Land Management (BLM), 1.06 miles (27.34 
acres) of private property, and 0.06 mile (2.74 acres) owned by Clark 
County.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;

[[Page 28261]]

     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\4\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice. Currently, the BLM has 
expressed its intention to participate as a cooperating agency in the 
preparation of the EA to satisfy its NEPA responsibilities related to 
this project.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\5\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    We have already identified issues that we think deserve attention 
based on a preliminary review of the proposed facilities and the 
environmental information provided by Kern River, namely the impact on 
federally listed threatened and endangered species as well as BLM 
identified species. Other issues may be added based on your comments 
and our analysis.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies of the EA will be sent 
to the environmental mailing list for public review and comment. If you 
would prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP15-
132). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: May 12, 2015.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2015-11922 Filed 5-15-15; 8:45 am]
 BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.