NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 52–012 and 52–013; NRC–
2008–0091]
Nuclear Innovation North America
LLC; South Texas Project, Units 3 and
4
Nuclear Regulatory
Commission.
ACTION: Combined license application;
availability.
AGENCY:
On September 20, 2007,
South Texas Project Nuclear Operating
Company (STPNOC) submitted to the
U.S. Nuclear Regulatory Commission
(NRC) an application for combined
licenses (COLs) for two additional units
(Units 3 and 4) at the South Texas
Project (STP) Electric Generating Station
site in Matagorda County near Bay City,
Texas. The NRC published a notice of
receipt and availability for this COL
application in the Federal Register on
December 5, 2007. In a letter dated
January 19, 2011, STPNOC notified the
NRC that, effective January 24, 2011,
Nuclear Innovation North America LLC
(NINA) became the lead applicant for
STP, Units 3 and 4. This notice is being
published to notify the public of the
availability of the COL application for
STP, Units 3 and 4.
DATES: The COL application is available
May 12, 2015.
ADDRESSES: Please refer to Docket ID
NRC–2008–0091 when contacting the
SUMMARY:
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0091. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it available in
ADAMS) is provided the first time that
a document is referenced. For the
convenience of the reader, the ADAMS
accession numbers are provided in a
table in the ‘‘Availability of Documents’’
section of this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Tom
Tai, telephone: 301–415–8484, email:
Tom.Tai@nrc.gov; or Luis Betancourt,
telephone: 301–415–6145, email:
Luis.Betancourt@nrc.gov. Both are staff
of the Office of New Reactors, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001.
On
September 20, 2007, the NRC received
a COL application from STPNOC, filed
pursuant to section 103 of the Atomic
Energy Act of 1954, as amended, and
part 52 of Title 10 of the Code of Federal
Regulations (10 CFR), ‘‘Licenses,
Certifications, and Approvals for
Nuclear Power Plants,’’ to construct and
operate two additional units (Units 3
and 4) at the STP Electric Generating
Station site in Matagorda County near
Bay City, Texas. The additional units
are based on the U.S. Advanced Boiling
Water Reactor design, which is certified
in 10 CFR part 52, appendix A. The
NRC published a notice of receipt and
availability for an application for a COL
in the Federal Register on December 5,
2007 (72 FR 68597). In a letter dated
January 19, 2011, STPNOC notified the
NRC that, effective January 24, 2011,
NINA became the lead applicant for
STP, Units 3 and 4. As such, NINA
assumed responsibility for the design,
construction and licensing of STP, Units
3 and 4. The application is currently
under review by the NRC.
An applicant may seek a COL in
accordance with subpart C of 10 CFR
part 52. The information submitted by
the applicant includes certain
administrative information, such as
financial qualifications submitted
pursuant to 10 CFR 52.77, as well as
technical information submitted
pursuant to 10 CFR 52.79. This notice
is being provided in accordance with
the requirements in 10 CFR 50.43(a)(3).
SUPPLEMENTARY INFORMATION:
Availability of Documents
The documents identified in the
following table are available to
interested persons through the ADAMS
Public Documents collection. A copy of
the COL application is also available for
public inspection at the NRC’s PDR and
at https://www.nrc.gov/reactors/newreactors/col.html.
ADAMS
Accession No.
mstockstill on DSK4VPTVN1PROD with NOTICES
Document
South Texas Project, Units 3 and 4, Combined License Application, Revision 0, September 20, 2007 .........................................
South Texas Project, Units 3 and 4, Supplement to Combined License Application ‘‘Safeguards Information,’’ Part 8, Revision
0, September 26, 2007.
South Texas Project, Units 3 and 4, Supplement to Combined License Application, Revision 0, October 15, 2007 .....................
South Texas Project, Units 3 and 4, Supplement to Combined License Application, Revision 0, October 18, 2007 .....................
South Texas Project, Units 3 and 4, Supplement to Combined License Application, Revision 0, November 13, 2007 .................
South Texas Project, Units 3 and 4, Supplement to Combined License Application, Revision 0, November 21, 2007 .................
South Texas Project, Units 3 and 4, Combined License Application, Revision 1, January 31, 2008 ..............................................
South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part
8, Revision 1, January 31, 2008.
South Texas Project, Units 3 and 4, Combined License Application, Revision 2, September 24, 2008 .........................................
South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part
8, Revision 2, September 24, 2008.
South Texas Project, Units 3 and 4, Submittal of Combined License Application, ‘‘Proprietary Information,’’ Part 10, Revision 2,
December 11, 2008.
South Texas Project, Units 3 and 4, Combined License Application, Revision 3, September 16, 2009 .........................................
VerDate Sep<11>2014
17:31 May 11, 2015
Jkt 235001
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
E:\FR\FM\12MYN1.SGM
12MYN1
ML072830407
ML072740461
ML072960352
ML072960489
ML073200992
ML073310616
ML080700399
ML080420090
ML082830938
ML082730700
ML083530131
ML092930393
Federal Register / Vol. 80, No. 91 / Tuesday, May 12, 2015 / Notices
ADAMS
Accession No.
Document
South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part
8, Revision 3, July 15, 2010.
South Texas Project, Units 3 and 4, Combined License Application, Revision 4, October 5, 2010 ................................................
South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part
8, Revision 4, February 3, 2011.
South Texas Project, Units 3 and 4, Update to Change in Lead Applicant, January 19, 2011 .......................................................
South Texas Project, Units 3 and 4, Combined License Application, Revision 5, January 26, 2011 ..............................................
South Texas Project, Units 3 and 4, Submittal of Supplement to Combined License Application ‘‘Safeguards Information,’’ Part
8, Revision 5, August 30, 2011.
South Texas Project, Units 3 and 4, Combined License Application, Revision 6, August 30, 2011 ...............................................
South Texas Project, Units 3 and 4, Combined License Application, Revision 7, February 1, 2012 ..............................................
South Texas Project, Units 3 and 4, Combined License Application, Revision 8, September 17, 2012 .........................................
South Texas Project, Units 3 and 4, Combined License Application, Revision 9, April 17, 2013 ...................................................
South Texas Project, Units 3 and 4, Combined License Application, Revision 10, October 29, 2013 ............................................
South Texas Project, Units 3 and 4, Combined License Application, Revision 11, October 21, 2014 ............................................
Dated at Rockville, Maryland, this 6th day
of May 2015.
For the Nuclear Regulatory Commission.
Samuel Lee,
Chief, Licensing Branch 2, Division of New
Reactor Licensing, Office of New Reactors.
[FR Doc. 2015–11549 Filed 5–11–15; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2013–0254]
Evaluation of a Proposed Risk
Management Regulatory Framework
Nuclear Regulatory
Commission.
ACTION: Draft white paper; request for
comment.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is seeking public
comment on a draft document entitled,
‘‘NRC Staff White Paper on Options for
Responding to the June 14, 2012
Chairman’s Tasking Memorandum on
‘Evaluating Options Proposed for a More
Holistic Risk-Informed, PerformanceBased Regulatory Approach’ ’’
(hereinafter referred to as NRC Staff
White Paper). The draft NRC Staff White
Paper discusses three items that the
NRC staff expects to present to the
Commission for its consideration:
Options for enhancing the risk
management approach used to ensure
nuclear power reactor safety; reevaluations of two ‘‘improvement
activities’’ from Fukushima Near-Term
Task Force Recommendation 1 that the
Commission deferred; and consideration
of an over-arching, agencywide policy
statement on using the risk management
approach to ensure safety and security.
DATES: Submit comments by June 11,
2015. Comments received after this date
will be considered if it is practical to do
so, but the NRC staff is able to assure
mstockstill on DSK4VPTVN1PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:31 May 11, 2015
Jkt 235001
consideration only for comments
received on or before this date.
Although the NRC staff will consider all
timely comments, the NRC does not
intend to prepare detailed comment
responses.
ADDRESSES: You may submit comment
by any of the following methods (unless
this document describes a different
method for submitting comments on a
specific subject):
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0254. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• Mail comments to: Cindy Bladey,
Office of Administration, Mail Stop:
OWFN–12–H08, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
For additional direction on obtaining
information and submitting comments,
see ‘‘Obtaining Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
FOR FURTHER INFORMATION CONTACT:
Richard F. Dudley, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
1116; email: Richard.Dudley@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and
Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC–2013–
0254 when contacting the NRC about
the availability of information for this
action. You may obtain publiclyavailable information related to this
action by any of the following methods:
PO 00000
Frm 00050
Fmt 4703
27191
Sfmt 4703
ML102010268
ML102861292
ML110400425
ML110250369
ML110340451
ML11243A171
ML11252A505
ML12048A714
ML12291A415
ML13115A094
ML13310A599
ML14307A876
• Federal rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0254.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in the SUPPLEMENTARY
INFORMATION section.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC–2013–
0254 in the subject line of your
comment submission.
The NRC cautions you not to include
identifying or contact information that
you do not want to be publicly
disclosed in your comment submission.
The NRC will post all comment
submissions at https://
www.regulations.gov as well as enter the
comment submissions into ADAMS.
The NRC does not routinely edit
comment submissions to remove
identifying or contact information.
If you are requesting or aggregating
comments from other persons for
submission to the NRC, then you should
inform those persons not to include
identifying or contact information that
they do not want to be publicly
disclosed in their comment submission.
E:\FR\FM\12MYN1.SGM
12MYN1
Agencies
[Federal Register Volume 80, Number 91 (Tuesday, May 12, 2015)]
[Notices]
[Pages 27190-27191]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-11549]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 52-012 and 52-013; NRC-2008-0091]
Nuclear Innovation North America LLC; South Texas Project, Units
3 and 4
AGENCY: Nuclear Regulatory Commission.
ACTION: Combined license application; availability.
-----------------------------------------------------------------------
SUMMARY: On September 20, 2007, South Texas Project Nuclear Operating
Company (STPNOC) submitted to the U.S. Nuclear Regulatory Commission
(NRC) an application for combined licenses (COLs) for two additional
units (Units 3 and 4) at the South Texas Project (STP) Electric
Generating Station site in Matagorda County near Bay City, Texas. The
NRC published a notice of receipt and availability for this COL
application in the Federal Register on December 5, 2007. In a letter
dated January 19, 2011, STPNOC notified the NRC that, effective January
24, 2011, Nuclear Innovation North America LLC (NINA) became the lead
applicant for STP, Units 3 and 4. This notice is being published to
notify the public of the availability of the COL application for STP,
Units 3 and 4.
DATES: The COL application is available May 12, 2015.
ADDRESSES: Please refer to Docket ID NRC-2008-0091 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2008-0091. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if it available in
ADAMS) is provided the first time that a document is referenced. For
the convenience of the reader, the ADAMS accession numbers are provided
in a table in the ``Availability of Documents'' section of this
document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Tom Tai, telephone: 301-415-8484,
email: Tom.Tai@nrc.gov; or Luis Betancourt, telephone: 301-415-6145,
email: Luis.Betancourt@nrc.gov. Both are staff of the Office of New
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001.
SUPPLEMENTARY INFORMATION: On September 20, 2007, the NRC received a
COL application from STPNOC, filed pursuant to section 103 of the
Atomic Energy Act of 1954, as amended, and part 52 of Title 10 of the
Code of Federal Regulations (10 CFR), ``Licenses, Certifications, and
Approvals for Nuclear Power Plants,'' to construct and operate two
additional units (Units 3 and 4) at the STP Electric Generating Station
site in Matagorda County near Bay City, Texas. The additional units are
based on the U.S. Advanced Boiling Water Reactor design, which is
certified in 10 CFR part 52, appendix A. The NRC published a notice of
receipt and availability for an application for a COL in the Federal
Register on December 5, 2007 (72 FR 68597). In a letter dated January
19, 2011, STPNOC notified the NRC that, effective January 24, 2011,
NINA became the lead applicant for STP, Units 3 and 4. As such, NINA
assumed responsibility for the design, construction and licensing of
STP, Units 3 and 4. The application is currently under review by the
NRC.
An applicant may seek a COL in accordance with subpart C of 10 CFR
part 52. The information submitted by the applicant includes certain
administrative information, such as financial qualifications submitted
pursuant to 10 CFR 52.77, as well as technical information submitted
pursuant to 10 CFR 52.79. This notice is being provided in accordance
with the requirements in 10 CFR 50.43(a)(3).
Availability of Documents
The documents identified in the following table are available to
interested persons through the ADAMS Public Documents collection. A
copy of the COL application is also available for public inspection at
the NRC's PDR and at https://www.nrc.gov/reactors/new-reactors/col.html.
------------------------------------------------------------------------
Document ADAMS Accession No.
------------------------------------------------------------------------
South Texas Project, Units 3 and 4, ML072830407
Combined License Application, Revision
0, September 20, 2007.
South Texas Project, Units 3 and 4, ML072740461
Supplement to Combined License
Application ``Safeguards Information,''
Part 8, Revision 0, September 26, 2007.
South Texas Project, Units 3 and 4, ML072960352
Supplement to Combined License
Application, Revision 0, October 15,
2007.
South Texas Project, Units 3 and 4, ML072960489
Supplement to Combined License
Application, Revision 0, October 18,
2007.
South Texas Project, Units 3 and 4, ML073200992
Supplement to Combined License
Application, Revision 0, November 13,
2007.
South Texas Project, Units 3 and 4, ML073310616
Supplement to Combined License
Application, Revision 0, November 21,
2007.
South Texas Project, Units 3 and 4, ML080700399
Combined License Application, Revision
1, January 31, 2008.
South Texas Project, Units 3 and 4, ML080420090
Submittal of Supplement to Combined
License Application ``Safeguards
Information,'' Part 8, Revision 1,
January 31, 2008.
South Texas Project, Units 3 and 4, ML082830938
Combined License Application, Revision
2, September 24, 2008.
South Texas Project, Units 3 and 4, ML082730700
Submittal of Supplement to Combined
License Application ``Safeguards
Information,'' Part 8, Revision 2,
September 24, 2008.
South Texas Project, Units 3 and 4, ML083530131
Submittal of Combined License
Application, ``Proprietary
Information,'' Part 10, Revision 2,
December 11, 2008.
South Texas Project, Units 3 and 4, ML092930393
Combined License Application, Revision
3, September 16, 2009.
[[Page 27191]]
South Texas Project, Units 3 and 4, ML102010268
Submittal of Supplement to Combined
License Application ``Safeguards
Information,'' Part 8, Revision 3, July
15, 2010.
South Texas Project, Units 3 and 4, ML102861292
Combined License Application, Revision
4, October 5, 2010.
South Texas Project, Units 3 and 4, ML110400425
Submittal of Supplement to Combined
License Application ``Safeguards
Information,'' Part 8, Revision 4,
February 3, 2011.
South Texas Project, Units 3 and 4, ML110250369
Update to Change in Lead Applicant,
January 19, 2011.
South Texas Project, Units 3 and 4, ML110340451
Combined License Application, Revision
5, January 26, 2011.
South Texas Project, Units 3 and 4, ML11243A171
Submittal of Supplement to Combined
License Application ``Safeguards
Information,'' Part 8, Revision 5,
August 30, 2011.
South Texas Project, Units 3 and 4, ML11252A505
Combined License Application, Revision
6, August 30, 2011.
South Texas Project, Units 3 and 4, ML12048A714
Combined License Application, Revision
7, February 1, 2012.
South Texas Project, Units 3 and 4, ML12291A415
Combined License Application, Revision
8, September 17, 2012.
South Texas Project, Units 3 and 4, ML13115A094
Combined License Application, Revision
9, April 17, 2013.
South Texas Project, Units 3 and 4, ML13310A599
Combined License Application, Revision
10, October 29, 2013.
South Texas Project, Units 3 and 4, ML14307A876
Combined License Application, Revision
11, October 21, 2014.
------------------------------------------------------------------------
Dated at Rockville, Maryland, this 6th day of May 2015.
For the Nuclear Regulatory Commission.
Samuel Lee,
Chief, Licensing Branch 2, Division of New Reactor Licensing, Office of
New Reactors.
[FR Doc. 2015-11549 Filed 5-11-15; 8:45 am]