Igiugig Village Council; Notice of Intent To File License Application, Filing of Draft Application, Request for Waivers of Integrated Licensing Process Regulations Necessary for Expedited Processing of a Hydrokinetic Pilot Project License Application, and Soliciting Comments, 24909-24910 [2015-10219]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 84 / Friday, May 1, 2015 / Notices
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
VerDate Sep<11>2014
18:14 Apr 30, 2015
Jkt 235001
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: May 13, 2015.
Dated: April 22, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–10222 Filed 4–30–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13511–002]
Igiugig Village Council; Notice of Intent
To File License Application, Filing of
Draft Application, Request for Waivers
of Integrated Licensing Process
Regulations Necessary for Expedited
Processing of a Hydrokinetic Pilot
Project License Application, and
Soliciting Comments
a. Type of Filing: Notice of Intent to
File a License Application for an
Original License for a Hydrokinetic Pilot
Project.
b. Project No.: 13511–002.
c. Date Filed: April 1, 2015.
d. Submitted By: Igiugig Village
Council (Igiugig).
e. Name of Project: Igiugig
Hydrokinetic Project.
f. Location: On the Kvichak River in
the Lake and Peninsula Borough, near
the town of Igiugig, Alaska.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Applicant Contact: Nathan
Johnson, Ocean Renewable Power
Company, 66 Pearl Street, Suite 301,
Portland, Maine 04101; (207) 772–7707.
i. FERC Contact: Dianne Rodman at
(202) 502–6077 or email at
dianne.rodman@ferc.gov.
j. Igiugig has filed with the
Commission: (1) A notice of intent (NOI)
to file an application for an original
license for a hydrokinetic pilot project
and a draft license application with
monitoring plans; (2) a request for
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
24909
waivers of the integrated licensing
process regulations necessary for
expedited processing of a hydrokinetic
pilot project license application; (3) a
proposed process plan and schedule; (4)
a request to be designated as the nonfederal representative for section 7 of
the Endangered Species Act (ESA)
consultation; and (5) a request to be
designated as the non-federal
representative for section 106
consultation under the National Historic
Preservation Act (NHPA) (collectively
the pre-filing materials).
k. With this notice, we are soliciting
comments on the pre-filing materials
listed in paragraph j above, including
the draft license application and
monitoring plans. All comments should
be sent to the address above in
paragraph h and filed with the
Commission. All comments may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. Any
individual or entity interested in
submitting comments on the pre-filing
materials must do so by May 23, 2015.
l. With this notice, we are approving
Igiugig’s request to be designated as the
non-federal representative for section 7
of the ESA and its request to initiate
consultation under section 106 of the
NHPA; and recommending that it begin
informal consultation with: (a) The U.S.
Fish and Wildlife Service and the
National Marine Fisheries Service as
required by section 7 of ESA; and (b) the
Alaska State Historic Preservation
Officer, as required by section 106 of the
NHPA and the implementing
regulations of the Advisory Council on
Historic Preservation at 36 CFR 800.2.
m. With this notice, we also are
asking federal, state, local, and tribal
agencies with jurisdiction and/or
expertise with respect to environmental
issues to cooperate with us in the
preparation of the environmental
E:\FR\FM\01MYN1.SGM
01MYN1
24910
Federal Register / Vol. 80, No. 84 / Friday, May 1, 2015 / Notices
mstockstill on DSK4VPTVN1PROD with NOTICES
document. Agencies who would like to
request cooperating status should follow
the instructions for filing comments
described in paragraph ‘‘k’’ above.
n. This notice does not constitute the
Commission’s approval of Igiugig’s
request to use the Pilot Project Licensing
Procedures. Upon its review of the
project’s overall characteristics relative
to the pilot project criteria, the draft
license application contents, and any
comments filed, the Commission will
determine whether there is adequate
information to conclude the pre-filing
process.
o. The proposed Igiugig Hydrokinetic
Project would consist of: (1) An instream 20- kilowatt (kW), 64-foot-long,
11-foot-high, 43-foot-wide pontoonmounted RivGen Power System Turbine
Generator Unit (TGU) in Phase 1; (2) an
additional in-stream 20-kW pontoonmounted TGU in Phase 2; (3) two
anchoring systems consisting of a
13,000-pound anchor, chain, shackles,
and 150 feet of mooring; (4) a 375-footlong, coated and weighted combined
power, data, and environmental
monitoring cable from the TGU for
Phase 1; and a 675-foot-long cable from
the TGU for Phase 2; (5) an existing 10foot-long by 8-foot-wide shore station
for housing project electronics and
controls; and (6) appurtenant facilities.
The project is estimated to have an
annual generation of 409,504 kilowatthours per year.
p. A copy of the draft license
application and all pre-filing materials
are available for review at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number (P–
13511), excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCONlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659.
q. Pre-filing process schedule. The
pre-filing process will be conducted
pursuant to the following tentative
schedule. Revisions to the schedule
below may be made based on staff’s
review of the draft application and any
comments received.
Milestone
Comments on pre-filing
materials due.
Issuance of meeting notice
(if needed).
Public meeting/technical
conference (if needed).
VerDate Sep<11>2014
Date
May 23, 2015.
June 7, 2015.
June 22, 2015.
18:14 Apr 30, 2015
Jkt 235001
r. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: April 23, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–10219 Filed 4–30–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13806–004]
5440 Hydro Inc.; Notice of Application
Accepted for Filing With the
Commission, Intent To Waive Scoping,
Soliciting Motions To Intervene and
Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Terms and Conditions, and
Recommendations, and Establishing
an Expedited Schedule for Processing
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Exemption
From Licensing.
b. Project No.: P–13806–004.
c. Date filed: July 28, 2014.
d. Applicant: 5440 Hydro Inc.
e. Name of Project: Brooklyn Dam
Hydroelectric Project.
f. Location: On the Upper
Ammonoosuc River, in the Town of
Northumberland, Coos County, New
Hampshire. The project would not
occupy lands of the United States.
g. Filed Pursuant to: Public Utility
Regulatory Policies Act of 1978, 16
U.S.C. 2705, 2708.
h. Applicant Contact: Lutz Loegters,
5440 Hydro Inc., 717 Atlantic Avenue,
Suite 1A, Boston, Massachusetts 02111,
(416) 643–6615.
i. FERC Contact: John Ramer, (202)
502–8969, john.ramer@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments, terms
and conditions, and recommendations:
Due to the small size and location of
this project and the close coordination
with state and federal agencies during
preparation of the application, the 60day timeframe in 18 CFR 4.34(b) is
shortened. Instead, motions to intervene
and protests, comments, terms and
conditions, and recommendations are
due 30 days from the issuance date of
this notice. All reply comments must be
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
filed with the Commission within 45
days from the issuance date of this
notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, comments, and
recommendations using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–13806–004.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. The Brooklyn Dam Hydroelectric
Project would consist of: (1) An existing
163-foot-long and 14-foot-high dam that
includes: (a) A 113-foot-long spillway
with a crest elevation 878.69 feet
National Geodetic Vertical Datum of
1929 (NGVD29); (b) 2.50-foot-high
flashboards with a crest elevation
881.23 feet NGVD29; and (c) a 50-footlong floodgate structure with four 6.9foot-wide, 10-foot-high floodgates; (2) an
existing 100-foot-long, 45-foot-wide
forebay with three 15.2-foot-wide, 15.5foot-high trashracks with 1.0-inch open
bar spacing; (3) an existing 40-foot-long,
15.78-foot-high tailrace training wall; (4)
an existing 9-foot-wide, 9-foot-high side
waste gate; (5) an existing 26-acre
impoundment having a gross storage
capacity of 52-acre-feet at elevation
881.23 feet NGVD29; (6) an existing 45foot-long, 48-foot-wide, and 23-foot-high
brick and concrete powerhouse that
would contain two proposed 300kilowatt (kW), Kaplan turbinegenerating units for a total installed
capacity of 600 kW; (7) an existing 48foot-long, 45-foot-wide tailrace; (8) a
proposed 400-foot-long 35.4-kilovolt
E:\FR\FM\01MYN1.SGM
01MYN1
Agencies
[Federal Register Volume 80, Number 84 (Friday, May 1, 2015)]
[Notices]
[Pages 24909-24910]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-10219]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13511-002]
Igiugig Village Council; Notice of Intent To File License
Application, Filing of Draft Application, Request for Waivers of
Integrated Licensing Process Regulations Necessary for Expedited
Processing of a Hydrokinetic Pilot Project License Application, and
Soliciting Comments
a. Type of Filing: Notice of Intent to File a License Application
for an Original License for a Hydrokinetic Pilot Project.
b. Project No.: 13511-002.
c. Date Filed: April 1, 2015.
d. Submitted By: Igiugig Village Council (Igiugig).
e. Name of Project: Igiugig Hydrokinetic Project.
f. Location: On the Kvichak River in the Lake and Peninsula
Borough, near the town of Igiugig, Alaska.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Applicant Contact: Nathan Johnson, Ocean Renewable Power
Company, 66 Pearl Street, Suite 301, Portland, Maine 04101; (207) 772-
7707.
i. FERC Contact: Dianne Rodman at (202) 502-6077 or email at
dianne.rodman@ferc.gov.
j. Igiugig has filed with the Commission: (1) A notice of intent
(NOI) to file an application for an original license for a hydrokinetic
pilot project and a draft license application with monitoring plans;
(2) a request for waivers of the integrated licensing process
regulations necessary for expedited processing of a hydrokinetic pilot
project license application; (3) a proposed process plan and schedule;
(4) a request to be designated as the non-federal representative for
section 7 of the Endangered Species Act (ESA) consultation; and (5) a
request to be designated as the non-federal representative for section
106 consultation under the National Historic Preservation Act (NHPA)
(collectively the pre-filing materials).
k. With this notice, we are soliciting comments on the pre-filing
materials listed in paragraph j above, including the draft license
application and monitoring plans. All comments should be sent to the
address above in paragraph h and filed with the Commission. All
comments may be filed electronically via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676,
or for TTY, (202) 502-8659. Although the Commission strongly encourages
electronic filing, documents may also be paper-filed. To paper-file,
mail an original and seven copies to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426. Any individual or entity interested in submitting comments on
the pre-filing materials must do so by May 23, 2015.
l. With this notice, we are approving Igiugig's request to be
designated as the non-federal representative for section 7 of the ESA
and its request to initiate consultation under section 106 of the NHPA;
and recommending that it begin informal consultation with: (a) The U.S.
Fish and Wildlife Service and the National Marine Fisheries Service as
required by section 7 of ESA; and (b) the Alaska State Historic
Preservation Officer, as required by section 106 of the NHPA and the
implementing regulations of the Advisory Council on Historic
Preservation at 36 CFR 800.2.
m. With this notice, we also are asking federal, state, local, and
tribal agencies with jurisdiction and/or expertise with respect to
environmental issues to cooperate with us in the preparation of the
environmental
[[Page 24910]]
document. Agencies who would like to request cooperating status should
follow the instructions for filing comments described in paragraph
``k'' above.
n. This notice does not constitute the Commission's approval of
Igiugig's request to use the Pilot Project Licensing Procedures. Upon
its review of the project's overall characteristics relative to the
pilot project criteria, the draft license application contents, and any
comments filed, the Commission will determine whether there is adequate
information to conclude the pre-filing process.
o. The proposed Igiugig Hydrokinetic Project would consist of: (1)
An in-stream 20- kilowatt (kW), 64-foot-long, 11-foot-high, 43-foot-
wide pontoon-mounted RivGen Power System Turbine Generator Unit (TGU)
in Phase 1; (2) an additional in-stream 20-kW pontoon-mounted TGU in
Phase 2; (3) two anchoring systems consisting of a 13,000-pound anchor,
chain, shackles, and 150 feet of mooring; (4) a 375-foot-long, coated
and weighted combined power, data, and environmental monitoring cable
from the TGU for Phase 1; and a 675-foot-long cable from the TGU for
Phase 2; (5) an existing 10-foot-long by 8-foot-wide shore station for
housing project electronics and controls; and (6) appurtenant
facilities. The project is estimated to have an annual generation of
409,504 kilowatt-hours per year.
p. A copy of the draft license application and all pre-filing
materials are available for review at the Commission in the Public
Reference Room or may be viewed on the Commission's Web site (https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket number (P-
13511), excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCONlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
(202) 502-8659.
q. Pre-filing process schedule. The pre-filing process will be
conducted pursuant to the following tentative schedule. Revisions to
the schedule below may be made based on staff's review of the draft
application and any comments received.
------------------------------------------------------------------------
Milestone Date
------------------------------------------------------------------------
Comments on pre-filing materials due... May 23, 2015.
Issuance of meeting notice (if needed). June 7, 2015.
Public meeting/technical conference (if June 22, 2015.
needed).
------------------------------------------------------------------------
r. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
Dated: April 23, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-10219 Filed 4-30-15; 8:45 am]
BILLING CODE 6717-01-P