Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To Prepare a Supplement Environmental Assessment for the Amended Rock Springs Expansion Project and Request for Comments on Environmental Issues, 23267-23269 [2015-09689]

Download as PDF Federal Register / Vol. 80, No. 80 / Monday, April 27, 2015 / Notices time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: April 21, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–09663 Filed 4–24–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–169–000] Rmajette on DSK2VPTVN1PROD with NOTICES Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To Prepare a Supplement Environmental Assessment for the Amended Rock Springs Expansion Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare a supplemental environmental assessment (EA) that will discuss the environmental impacts of the amendment to the Rock Springs Expansion Project (Project) involving construction and operation of facilities by Transcontinental Gas Pipe Line Company, LLC (Transco) in Lancaster County, Pennsylvania. The Commission will use this supplemental EA in its decision-making process to determine whether the amendment to the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the supplemental EA. Please note that the scoping period will close on May 20, 2015. You may submit comments in written form or verbally. Further details on how to submit written comments are in the Public Participation section of this notice. If you sent comments on this project to the Commission before the VerDate Sep<11>2014 14:41 Apr 24, 2015 Jkt 235001 opening of this docket on April 13, 2015 you will need to file those comments in Docket No. CP15–169–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list and includes landowners affected by the amended Project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the planned facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. Transco provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). Summary of the Project and Proposed Route Modification On March 19, 2015, FERC issued an Order Issuing Certificate (Order) to Transco authorizing the Rock Springs Expansion Project. The EA for the Project in Docket No. CP14–504–000 was issued on November 14, 2014. On March 19, 2015, Transco accepted the Order pursuant to section 157.20(a) of the Commission’s Regulations. The Project is an expansion of Transco’s existing pipeline system which will enable Transco to provide 192,000 dekatherms per day of incremental firm transportation capacity from Transco’s Station 210 Zone 6 Pool in Mercer County, New Jersey to Old Dominion Electric Cooperative’s approved Wildcat Point Generating Facility in Cecil County, Maryland. In this amendment, Transco proposes to modify the previously authorized pipeline route in Lancaster County, Pennsylvania. The proposed alignment modification occurs from milepost (MP) 7.60 to MP 8.29 (a total of 0.69 mile). PO 00000 Frm 00015 Fmt 4703 Sfmt 4703 23267 Transco is proposing to adjust the pipeline centerline alignment from the originally authorized property to the adjacent property to the east. The proposed minor route modification would not affect any new landowners, as the adjacent property owner owns other parcels on which the pipeline is sited. Additionally, the route modification would result in minor changes in workspace configurations on two other properties, including a reduction in permanent easement. The general location map of the project facilities is shown in appendix 1.1 Land Requirements for Construction No new workspace impacts would occur as a result of the proposed minor route modification. The minor route modification has been designed to result in no net gain of workspace required for Project construction. The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the supplemental EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the supplemental EA. We will consider all filed comments during the preparation of the supplemental EA. In the supplemental EA, we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • land use; • water resources, fisheries, and wetlands; • cultural resources; • vegetation and wildlife; • air quality and noise; • endangered and threatened species; 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of the appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\27APN1.SGM 27APN1 23268 Federal Register / Vol. 80, No. 80 / Monday, April 27, 2015 / Notices • public safety; and • cumulative impacts. We will also evaluate reasonable alternatives to the proposed route modification. The supplemental EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section beginning on page 5. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues related to this project to formally cooperate with us in the preparation of the supplemental EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act Rmajette on DSK2VPTVN1PROD with NOTICES In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our supplemental EA for this project will document our findings on the impacts on historic 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. VerDate Sep<11>2014 14:41 Apr 24, 2015 Jkt 235001 properties and summarize the status of consultations under section 106. Currently Identified Environmental Issues The change in land use impacts includes reductions of 0.37 acre of forest land and 0.07 acre of agricultural land, and increases of 0.39 acre of open land and 0.04 acre of commercial/industrial land. Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before May 20, 2015. For your convenience, there are three methods you can use to submit your comments to the Commission. In all instances, please reference the project docket number (CP15–169–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Environmental Mailing List The environmental mailing list includes landowners affected by the PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 route modification, federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. If we publish and distribute the supplemental EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the supplemental EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP15–169). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings E:\FR\FM\27APN1.SGM 27APN1 Federal Register / Vol. 80, No. 80 / Monday, April 27, 2015 / Notices by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: April 20, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–09689 Filed 4–24–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL15–60–000] Rmajette on DSK2VPTVN1PROD with NOTICES Bonneville Power Administration v. Puget Sound Energy, Inc.; Notice of Complaint Take notice that on April 20, 2015, pursuant to section 206 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.206 and sections 206 and 306 of the Federal Power Act, 16 U.S.C. 824(e) and 825(e), Bonneville Power Administration (Complainant) filed a formal complaint against Puget Sound Energy, Inc. (Respondent) alleging that the omission of the Respondent’s formula transmission rate under its jurisdictional open access transmission tariff to account for and reimburse Respondent’s transmission customers for prior period adjustments result in an unjust and unreasonable rate, as more fully explained in the complaint. The Complainant states that a copy of the complaint has been served on the Respondent. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission encourages electronic submission of protests and VerDate Sep<11>2014 14:41 Apr 24, 2015 Jkt 235001 interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for electronic review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on May 11, 2015. Dated: April 21, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–09664 Filed 4–24–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP15–162–000] Northern Natural Gas Company; Notice of Request Under Blanket Authorization Take notice that on April 10, 2015 Northern Natural Gas Company (Northern), 1111 South 103rd Street, Omaha, Nebraska 68124 filed a prior notice request pursuant to sections 157.205 and 157.208 of the Commission’s regulations under the Natural Gas Act for authorization to construct and operate certain facilities within Northern’s existing Kermit Compressor Station located near Kermit, Texas. Specifically, Northern proposes to: (i) Install and operate a new 15,900 horsepower compressor unit at the Kermit Compressor Station; and (ii) relocate approximately 200 feet of pipe to tie-in the new compressor. The project is referred to as the Permian II Expansion Project. Northern states that the proposed project will result in an incremental increase of 112,000 dekatherms per day, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 23269 Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this Application should be directed to Michael T. Loeffler, Senior Director, Certificates and External Affairs for Northern, 1111South 103rd Street, Omaha, Nebraska 68124, or by calling (402) 398–7103. Any person may, within 60 days after the issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention. Any person filing to intervene or the Commission’s staff may, pursuant to section 157.205 of the Commission’s Regulations under the NGA (18 CFR 157.205) file a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, E:\FR\FM\27APN1.SGM 27APN1

Agencies

[Federal Register Volume 80, Number 80 (Monday, April 27, 2015)]
[Notices]
[Pages 23267-23269]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-09689]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-169-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To 
Prepare a Supplement Environmental Assessment for the Amended Rock 
Springs Expansion Project and Request for Comments on Environmental 
Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare a supplemental environmental assessment (EA) 
that will discuss the environmental impacts of the amendment to the 
Rock Springs Expansion Project (Project) involving construction and 
operation of facilities by Transcontinental Gas Pipe Line Company, LLC 
(Transco) in Lancaster County, Pennsylvania. The Commission will use 
this supplemental EA in its decision-making process to determine 
whether the amendment to the project is in the public convenience and 
necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your comments should focus on the potential 
environmental effects, reasonable alternatives, and measures to avoid 
or lessen environmental impacts. Your input will help the Commission 
staff determine what issues they need to evaluate in the supplemental 
EA. Please note that the scoping period will close on May 20, 2015.
    You may submit comments in written form or verbally. Further 
details on how to submit written comments are in the Public 
Participation section of this notice. If you sent comments on this 
project to the Commission before the opening of this docket on April 
13, 2015 you will need to file those comments in Docket No. CP15-169-
000 to ensure they are considered as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list and includes landowners affected by the amended Project. 
State and local government representatives should notify their 
constituents of this proposed project and encourage them to comment on 
their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the planned facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Transco provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' This fact sheet addresses a number of typically-asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Summary of the Project and Proposed Route Modification

    On March 19, 2015, FERC issued an Order Issuing Certificate (Order) 
to Transco authorizing the Rock Springs Expansion Project. The EA for 
the Project in Docket No. CP14-504-000 was issued on November 14, 2014. 
On March 19, 2015, Transco accepted the Order pursuant to section 
157.20(a) of the Commission's Regulations. The Project is an expansion 
of Transco's existing pipeline system which will enable Transco to 
provide 192,000 dekatherms per day of incremental firm transportation 
capacity from Transco's Station 210 Zone 6 Pool in Mercer County, New 
Jersey to Old Dominion Electric Cooperative's approved Wildcat Point 
Generating Facility in Cecil County, Maryland.
    In this amendment, Transco proposes to modify the previously 
authorized pipeline route in Lancaster County, Pennsylvania. The 
proposed alignment modification occurs from milepost (MP) 7.60 to MP 
8.29 (a total of 0.69 mile). Transco is proposing to adjust the 
pipeline centerline alignment from the originally authorized property 
to the adjacent property to the east. The proposed minor route 
modification would not affect any new landowners, as the adjacent 
property owner owns other parcels on which the pipeline is sited. 
Additionally, the route modification would result in minor changes in 
workspace configurations on two other properties, including a reduction 
in permanent easement.
    The general location map of the project facilities is shown in 
appendix 1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    No new workspace impacts would occur as a result of the proposed 
minor route modification. The minor route modification has been 
designed to result in no net gain of workspace required for Project 
construction.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the supplemental EA on 
the important environmental issues. By this notice, the Commission 
requests public comments on the scope of the issues to address in the 
supplemental EA. We will consider all filed comments during the 
preparation of the supplemental EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the supplemental EA, we will discuss impacts that could occur as 
a result of the construction and operation of the proposed project 
under these general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;

[[Page 23268]]

     public safety; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed route 
modification.
    The supplemental EA will present our independent analysis of the 
issues. The EA will be available in the public record through eLibrary. 
Depending on the comments received during the scoping process, we may 
also publish and distribute the EA to the public for an allotted 
comment period. We will consider all comments on the EA before making 
our recommendations to the Commission. To ensure we have the 
opportunity to consider and address your comments, please carefully 
follow the instructions in the Public Participation section beginning 
on page 5.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues 
related to this project to formally cooperate with us in the 
preparation of the supplemental EA.\3\ Agencies that would like to 
request cooperating agency status should follow the instructions for 
filing comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our supplemental EA for this project will 
document our findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    The change in land use impacts includes reductions of 0.37 acre of 
forest land and 0.07 acre of agricultural land, and increases of 0.39 
acre of open land and 0.04 acre of commercial/industrial land.

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before May 
20, 2015.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
project docket number (CP15-169-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. This is an easy method for interested 
persons to submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Environmental Mailing List

    The environmental mailing list includes landowners affected by the 
route modification, federal, state, and local government 
representatives and agencies; elected officials; environmental and 
public interest groups; Native American Tribes; other interested 
parties; and local libraries and newspapers. This list also includes 
all affected landowners (as defined in the Commission's regulations) 
who are potential right-of-way grantors, whose property may be used 
temporarily for project purposes, or who own homes within certain 
distances of aboveground facilities, and anyone who submits comments on 
the project.
    If we publish and distribute the supplemental EA, copies will be 
sent to the environmental mailing list for public review and comment. 
If you would prefer to receive a paper copy of the document instead of 
the CD version or would like to remove your name from the mailing list, 
please return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the supplemental EA scoping process, 
you may want to become an ``intervenor'' which is an official party to 
the Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP15-
169). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings

[[Page 23269]]

by automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: April 20, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-09689 Filed 4-24-15; 8:45 am]
 BILLING CODE 6717-01-P