Tennessee Gas Pipeline Company, L.L.C.; Notice of Application, 21234-21235 [2015-08872]
Download as PDF
tkelley on DSK3SPTVN1PROD with NOTICES
21234
Federal Register / Vol. 80, No. 74 / Friday, April 17, 2015 / Notices
or via eMail stephen.veatch@
energytransfer.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
VerDate Sep<11>2014
19:08 Apr 16, 2015
Jkt 235001
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with he Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and ill not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link.
Comment Date: May 4, 2015.
Dated: April 13, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–08871 Filed 4–16–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–148–000]
Tennessee Gas Pipeline Company,
L.L.C.; Notice of Application
Take notice that on April 2, 2015,
Tennessee Gas Pipeline Company,
L.L.C. (Tennessee), 1001 Louisiana
Street, Houston, Texas 77002, filed an
application pursuant to section 7(c) of
the Natural Gas Act (NGA) requesting
authorization to construct and operate
its Susquehanna West Project (Project)
located in Pennsylvania. Tennessee
asserts that the proposed Project will
increase east-to-west delivery capacity
in the region by approximately 145,000
dekatherms per day. Tennessee states
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
that the Project involves: (i)
Approximately 8.1 miles of new 36-inch
diameter pipeline looping in Tioga
County, Pennsylvania; (ii) pipeline
modifications associated with the
pipeline loops; (iii) modification to
piping at three existing compressor
stations, which are Compressor Station
315, Compressor Station 317, and
Compressor Station 319; and (iv)
increase in horsepower at two of the
three existing compressor stations.
Tennessee estimates the cost of the
Project to be approximately $156.4
million, all as more fully set forth in the
application which is on file with the
Commission and open to public
inspection. The filing is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site web at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions concerning this
application may be directed to John E.
Griffin, Assistant General Counsel,
Tennessee Gas Pipeline Company,
L.L.C., 1001 Louisiana Street, Houston,
Texas 77002, phone: (713) 420–3624,
facsimile: (713) 420–1601, email: John_
Griffin2@kindermorgan.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice, the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
E:\FR\FM\17APN1.SGM
17APN1
tkelley on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 74 / Friday, April 17, 2015 / Notices
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
seven copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and seven copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
VerDate Sep<11>2014
19:08 Apr 16, 2015
Jkt 235001
NE., Washington, DC 20426. There is an
‘‘eSubscription’’ link on the Web site
that enables subscribers to receive email
notification when a document is added
to a subscribed docket(s).
Comment Date: May 4, 2015.
Dated: April 13, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–08872 Filed 4–16–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER15–1496–000]
2014 ESA Project Company, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of 2014
ESA Project Company, LLC’s
application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is May 4, 2015.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
21235
888 First Street NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: April 13, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–08874 Filed 4–16–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER15–1494–000]
Convergent Energy and Power LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of
Convergent Energy and Power LLC’s
application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is May 4, 2015.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
E:\FR\FM\17APN1.SGM
17APN1
Agencies
[Federal Register Volume 80, Number 74 (Friday, April 17, 2015)]
[Notices]
[Pages 21234-21235]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-08872]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-148-000]
Tennessee Gas Pipeline Company, L.L.C.; Notice of Application
Take notice that on April 2, 2015, Tennessee Gas Pipeline Company,
L.L.C. (Tennessee), 1001 Louisiana Street, Houston, Texas 77002, filed
an application pursuant to section 7(c) of the Natural Gas Act (NGA)
requesting authorization to construct and operate its Susquehanna West
Project (Project) located in Pennsylvania. Tennessee asserts that the
proposed Project will increase east-to-west delivery capacity in the
region by approximately 145,000 dekatherms per day. Tennessee states
that the Project involves: (i) Approximately 8.1 miles of new 36-inch
diameter pipeline looping in Tioga County, Pennsylvania; (ii) pipeline
modifications associated with the pipeline loops; (iii) modification to
piping at three existing compressor stations, which are Compressor
Station 315, Compressor Station 317, and Compressor Station 319; and
(iv) increase in horsepower at two of the three existing compressor
stations. Tennessee estimates the cost of the Project to be
approximately $156.4 million, all as more fully set forth in the
application which is on file with the Commission and open to public
inspection. The filing is available for review at the Commission in the
Public Reference Room or may be viewed on the Commission's Web site web
at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
Any questions concerning this application may be directed to John
E. Griffin, Assistant General Counsel, Tennessee Gas Pipeline Company,
L.L.C., 1001 Louisiana Street, Houston, Texas 77002, phone: (713) 420-
3624, facsimile: (713) 420-1601, email: John_Griffin2@kindermorgan.com.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice, the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal
[[Page 21235]]
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426, a motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit seven copies of filings made in the proceeding with the
Commission and must mail a copy to the applicant and to every other
party. Only parties to the proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and seven copies of the protest or intervention to
the Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. There is an ``eSubscription'' link on the Web
site that enables subscribers to receive email notification when a
document is added to a subscribed docket(s).
Comment Date: May 4, 2015.
Dated: April 13, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-08872 Filed 4-16-15; 8:45 am]