Texas Eastern Transmission, LP; Notice of Intent To Prepare an Environmental Assessment for the Proposed Gulf Markets Expansion Project and Request for Comments on Environmental Issues, 19313-19315 [2015-08230]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 80, No. 69 / Friday, April 10, 2015 / Notices
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
Motions to intervene, protests and
comments may be filed electronically
via the internet in lieu of paper; see, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link. The
Commission strongly encourages
electronic filings.
Comment Date: April 23, 2015.
VerDate Sep<11>2014
20:09 Apr 09, 2015
Jkt 235001
Dated: April 2, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–08231 Filed 4–9–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–90–000]
Texas Eastern Transmission, LP;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Gulf Markets Expansion
Project and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Gulf Markets Expansion Project
(Project) involving construction and
operation of facilities by Texas Eastern
Transmission, LP (Texas Eastern) in
Lavaca County, Texas; St. Landry,
Pointe Coupee, and Beauregard
Parishes, Louisiana; Scioto, Ohio; Bath
County, Kentucky; Giles County,
Tennessee; and Monroe and Franklin
Counties, Mississippi. The Commission
will use this EA in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Please note that the
scoping period will close on May 4,
2015.
This notice is being sent to the
Commission’s current environmental
mailing list for this Project. State and
local government representatives should
notify their constituents of this
proposed Project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the Project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
19313
where compensation would be
determined in accordance with state
law.
Texas Eastern provided landowners
with a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What do I Need
to Know?’’ This fact sheet addresses a
number of typically-asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
Summary of the Proposed Project
The purpose of the Project would be
to provide 650,000 dekatherms per day
(Dth/d) of natural gas to the Gulf Coast
region of Louisiana and Texas from the
natural gas basins in the Northeast and
Texas. The Project would consist of the
following facility modifications:
• At the Wheelersburg Compressor
Station in Scioto County, Ohio to allow
for bi-directional compression on six,
existing 2,500 horsepower (HP)
compressor units;
• at the Owingsville Compressor
Station in Bath County, Kentucky to
allow for bi-directional compression;
• at the Mt. Pleasant Compressor
Station in Giles County, Tennessee to
allow for support of bi-directional
compression;
• at the Egypt Compressor Station in
Monroe County, Mississippi to allow for
support of bi-directional compression;
• at the existing launchers and
receivers at milepost (MP) 231.16, south
of the Union Church Compressor
Station in Franklin County, Mississippi
to allow for bi-directional in-line
inspection;
• at the Gillis County Compressor
Station in Beauregard Parish, Louisiana
to allow for bi-directional compression;
• at the existing Opelousas
Compressor Station in Saint Landry
Parish, Louisiana, to allow for bidirectional compression, and
installation of an additional 12,500 HP
electric-driven compressor unit;
• at two existing metering and
regulating (M&R) locations at Lottie and
New Roads Township in Pointe Coupee
Parish, Louisiana (M&R 71287 and M&R
71424) additions of gas chromatographs;
and
• at the new Provident City
Compressor Station in Lavaca County,
Texas, installation of a new 5,280 HP
compressor unit.
The general location of the project
facilities is shown in appendix 1.1
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
E:\FR\FM\10APN1.SGM
Continued
10APN1
19314
Federal Register / Vol. 80, No. 69 / Friday, April 10, 2015 / Notices
Land Requirements for Construction
The total land requirement for
construction and operation of the
Project is about 50 acres, of which 21
acres would be permanently affected by
the facilities operation.
The EA Process
mstockstill on DSK4VPTVN1PROD with NOTICES
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. The NEPA also requires us 2
to discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed Project under these general
headings:
• geology and soils;
• land use;
• water bodies, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
and
• public safety.
We will also evaluate reasonable
alternatives to the proposed Project or
portions of the Project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure your comments are
considered, please carefully follow the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
VerDate Sep<11>2014
20:09 Apr 09, 2015
Jkt 235001
instructions in the Public Participation
section of this notice.
With this notice, we are asking
agencies with jurisdiction and/or
special expertise with respect to
environmental issues to formally
cooperate with us in the preparation of
the EA.3 Agencies that would like to
request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with
applicable State Historic Preservation
Offices (SHPO), and to solicit their
views and those of other government
agencies, interested Native American
tribes, and the public on the Project’s
potential effects on historic properties.4
We will define the Project-specific Area
of Potential Effects (APE) in
consultation with the SHPOs as the
Project develops. On natural gas
projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
Project will document our findings on
the impacts on historic properties and
summarize the status on consultations
under section 106.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the Project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before May 4,
2015.
For your convenience, there are three
methods which you can use to submit
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Historic properties are
defined in those regulations as any prehistoric or
historic district, site, building, structure, or object
included in or eligible for inclusion in the National
Register for Historic Places.
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
your comments to the Commission. In
all instances please reference the Project
docket number (CP15–90–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert eFiling staff
available to assist you at (202) 502–8258
or efiling@ferc.gov.
(1) You may file your comments
electronically by using the eComment
feature, which is located on the
Commission’s Web site at www.ferc.gov
under the link to Documents and
Filings. An eComment is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Web site at www.ferc.gov
under the link to Documents and
Filings. With eFiling you can provide
comments in a variety of formats by
attaching them as a file with your
submission. New eFiling users must
first create an account by clicking on
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing;’’ or
(3) You may file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental groups and nongovernmental organizations; interested
Native American tribes; other interested
parties; and local libraries and
newspapers. This list also includes all
affected landowners (as defined in the
Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
Project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the Project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If the EA is published for distribution,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the compact disc version or would like
to remove your name from the mailing
E:\FR\FM\10APN1.SGM
10APN1
Federal Register / Vol. 80, No. 69 / Friday, April 10, 2015 / Notices
list, please return the attached
Information Request (appendix 2).
DEPARTMENT OF ENERGY
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are included in the User’s
Guide under the ‘‘e-filing’’ link on the
Commission’s Web site.
mstockstill on DSK4VPTVN1PROD with NOTICES
Additional Information
Additional information about the
Project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits, in the Docket Number
field (i.e., CP15–90). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets.
This can reduce the amount of time
you spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries and direct links to the
documents. Go to https://www.ferc.gov/
docs-filing/esubscription.asp
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: April 2, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–08230 Filed 4–9–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Becoming an Intervenor
Federal Energy Regulatory
Commission
[Docket No. ER15–1447–000]
[Project No. 349–173]
Martin Dam Hydroelectric Project;
Notice of Availability of the Final
Environmental Impact Statement for
the Martin Dam Hydroelectric Project
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380 (Order No.
486, 52 FR 47897), the Office of Energy
Projects has reviewed the application
for license for the Martin Dam
Hydroelectric Project (FERC No. 349),
located on the Tallapoosa River in
Tallapoosa, Coosa, and Elmore
Counties, Alabama, and has prepared a
Final Environmental Impact Statement
(final EIS) for the project. The project
occupies 1.39 acres of federal lands
administered by the U.S. Bureau of
Land Management.
The final EIS contains staff
evaluations of the applicant’s proposal
and the alternatives for relicensing the
Martin Dam Hydroelectric Project. The
final EIS documents the views of
governmental agencies, nongovernmental organizations, affected
Indian tribes, the public, the license
applicant, and Commission staff.
A copy of the final EIS is available for
review in the Commission’s Public
Reference Branch, Room 2A, located at
888 First Street NE., Washington, DC
20426. The final EIS also may be viewed
on the Commission’s Web site at
https://www.ferc.gov, using the ‘‘eLibrary’’ link. Enter the docket number,
excluding the last three digits, to access
the document. For assistance, contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY,
contact (202) 502–8659.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
For further information, please
contact Stephen Bowler at (202) 502–
6861 or at stephen.bowler@ferc.gov.
Dated: April 2, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–08232 Filed 4–9–15; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
20:09 Apr 09, 2015
Jkt 235001
19315
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
Mid-Georgia Cogen L.P.; Supplemental
Notice That Initial Market-Based Rate
Filing Includes Request for Blanket
Section 204 Authorization
This is a supplemental notice in the
above-referenced proceeding, of MidGeorgia Cogen L.P.’s application for
market-based rate authority, with an
accompanying rate schedule, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
§ 385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability is April 23,
2015.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
The filings in the above-referenced
proceeding(s) are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
E:\FR\FM\10APN1.SGM
10APN1
Agencies
[Federal Register Volume 80, Number 69 (Friday, April 10, 2015)]
[Notices]
[Pages 19313-19315]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-08230]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-90-000]
Texas Eastern Transmission, LP; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Gulf Markets Expansion
Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Gulf Markets Expansion Project
(Project) involving construction and operation of facilities by Texas
Eastern Transmission, LP (Texas Eastern) in Lavaca County, Texas; St.
Landry, Pointe Coupee, and Beauregard Parishes, Louisiana; Scioto,
Ohio; Bath County, Kentucky; Giles County, Tennessee; and Monroe and
Franklin Counties, Mississippi. The Commission will use this EA in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the Project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on May 4, 2015.
This notice is being sent to the Commission's current environmental
mailing list for this Project. State and local government
representatives should notify their constituents of this proposed
Project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the Project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
Texas Eastern provided landowners with a fact sheet prepared by the
FERC entitled ``An Interstate Natural Gas Facility On My Land? What do
I Need to Know?'' This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
The purpose of the Project would be to provide 650,000 dekatherms
per day (Dth/d) of natural gas to the Gulf Coast region of Louisiana
and Texas from the natural gas basins in the Northeast and Texas. The
Project would consist of the following facility modifications:
At the Wheelersburg Compressor Station in Scioto County,
Ohio to allow for bi-directional compression on six, existing 2,500
horsepower (HP) compressor units;
at the Owingsville Compressor Station in Bath County,
Kentucky to allow for bi-directional compression;
at the Mt. Pleasant Compressor Station in Giles County,
Tennessee to allow for support of bi-directional compression;
at the Egypt Compressor Station in Monroe County,
Mississippi to allow for support of bi-directional compression;
at the existing launchers and receivers at milepost (MP)
231.16, south of the Union Church Compressor Station in Franklin
County, Mississippi to allow for bi-directional in-line inspection;
at the Gillis County Compressor Station in Beauregard
Parish, Louisiana to allow for bi-directional compression;
at the existing Opelousas Compressor Station in Saint
Landry Parish, Louisiana, to allow for bi-directional compression, and
installation of an additional 12,500 HP electric-driven compressor
unit;
at two existing metering and regulating (M&R) locations at
Lottie and New Roads Township in Pointe Coupee Parish, Louisiana (M&R
71287 and M&R 71424) additions of gas chromatographs; and
at the new Provident City Compressor Station in Lavaca
County, Texas, installation of a new 5,280 HP compressor unit.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
[[Page 19314]]
Land Requirements for Construction
The total land requirement for construction and operation of the
Project is about 50 acres, of which 21 acres would be permanently
affected by the facilities operation.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. The NEPA also requires
us \2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed Project under these
general headings:
geology and soils;
land use;
water bodies, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species; and
public safety.
We will also evaluate reasonable alternatives to the proposed
Project or portions of the Project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure your comments are considered, please
carefully follow the instructions in the Public Participation section
of this notice.
With this notice, we are asking agencies with jurisdiction and/or
special expertise with respect to environmental issues to formally
cooperate with us in the preparation of the EA.\3\ Agencies that would
like to request cooperating agency status should follow the
instructions for filing comments provided under the Public
Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with applicable State Historic Preservation Offices (SHPO), and to
solicit their views and those of other government agencies, interested
Native American tribes, and the public on the Project's potential
effects on historic properties.\4\ We will define the Project-specific
Area of Potential Effects (APE) in consultation with the SHPOs as the
Project develops. On natural gas projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this Project will document our
findings on the impacts on historic properties and summarize the status
on consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Historic
properties are defined in those regulations as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register for Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send in your comments
so that they will be received in Washington, DC on or before May 4,
2015.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the Project docket number (CP15-90-000) with your submission.
The Commission encourages electronic filing of comments and has expert
eFiling staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's Web site at www.ferc.gov
under the link to Documents and Filings. An eComment is an easy method
for interested persons to submit brief, text-only comments on a
project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Web site at www.ferc.gov
under the link to Documents and Filings. With eFiling you can provide
comments in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making. A comment on a particular project is considered a ``Comment
on a Filing;'' or
(3) You may file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental groups and non-governmental organizations; interested
Native American tribes; other interested parties; and local libraries
and newspapers. This list also includes all affected landowners (as
defined in the Commission's regulations) who are potential right-of-way
grantors, whose property may be used temporarily for Project purposes,
or who own homes within certain distances of aboveground facilities,
and anyone who submits comments on the Project. We will update the
environmental mailing list as the analysis proceeds to ensure that we
send the information related to this environmental review to all
individuals, organizations, and government entities interested in and/
or potentially affected by the proposed project.
If the EA is published for distribution, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the compact
disc version or would like to remove your name from the mailing
[[Page 19315]]
list, please return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are
included in the User's Guide under the ``e-filing'' link on the
Commission's Web site.
Additional Information
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits, in the Docket Number field (i.e.,
CP15-90). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets.
This can reduce the amount of time you spend researching
proceedings by automatically providing you with notification of these
filings, document summaries and direct links to the documents. Go to
https://www.ferc.gov/docs-filing/esubscription.asp
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: April 2, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-08230 Filed 4-9-15; 8:45 am]